Testing & Commissioning/ Pre Opening Preparations: Operation
Testing & Commissioning/ Pre Opening Preparations: Operation
OPERATION:
Reports:
1. Terminology in Car Park's Name
"Main Car Park" into "Long Term Car Park"
"Taxi Park" into "Employee Car Park" etc.
2. Contact Details on ticket & Reports: PMO (Parking Management Office) Contact nos.
3. Activation of USB/Flash Drive for reports
4. No Plate no. on Tickets
5. Number plate Mismatch
6. No pop up on alarms/Alarms
7. Existing Reports Terminologies
Occupancy Report: "Min", "Max" & "Cnt";
Sum Report Events: "Undefined barrier arm position", "Not present in facility", "Event
Cancellation (special user status code)", "Ticket not transp. from tray to presenter";
Summary Turnover Movement: "Passages Locked", "Passing when locked" &
"Transactions w/o magnetic card"
Attendance report: Can we generate Attendance Report for from existing system?
8. Other Reports:
Attendance report for Car Park
Usage summary of Long Range Cards
Parking System Testing:
Testing of Parking Equipment: Barrier, ANPR, Intercom, Long Range Reader, Bar Code
Reader etc.)
Testing of Operational Issues: Parking Swindler, Tail Gating, Loop Detection, ANPR
Accuracy, ANPR Integration etc.
Finance System Access to update Foreign currency exchange rates (with the help of IT, if
needed)