Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 11

Cilacap Resid Fluid Catalytic

Doc.No. : RFCC-G-CS-PR-007
Rev. No. : 0

Cracking (RFCC) Project


Page No : 1 / 11

PT. PERTAMINA (Persero)


METHOD STATEMENT FOR BACKFILL AND COMPACTION

PROJECT

: CILACAP RESID FLUID CATALYTIC CRACKING


(RFCC) PROJECT

LOCATION

: PERTAMINA RU-IV, CILACAP, CENTRAL JAVA,


INDONESIA

OWNER

: PT. PERTAMINA (PERSERO)

CONTRACT NO.

: 15/C00000/2011-S2

Issued for Approval

Dec 7, 2012

NHK

YGK

IF/SDL

Rev.

Description

Date

Prepared
By

Checked
By

Approved
By

REVISION HISTORICAL SHEET


Rev.

Page/ Paragraf

Item

Description of Change

CONSORTIUM ADHI GS E & C

Cilacap Resid Fluid Catalytic Cracking (RFCC)


Project
PT. PERTAMINA (Persero)
METHOD STATEMENT FOR BACKFILL AND
COMPACTION

Doc.No. : RFCC-G-CS-PR-007

Rev. No. : 0

Page No : 2 / 11

INDEX
1. INTRODUCTION..(4/11)
2. METHOD OF WORK(5/11)
3. QA / QC .(9/11)
4. SAFETY ....(10/11)
CONSORTIUM ADHI GS E&C

Cilacap Resid Fluid Catalytic Cracking (RFCC)


Project
PT. PERTAMINA (Persero)
METHOD STATEMENT FOR BACKFILL AND
COMPACTION

Doc.No. : RFCC-G-CS-PR-007

Rev. No. : 0

Page No : 3 / 11

5. ATTACHMENT
- JOB SAFETY ANALYSIS

1. INTRODUCTION
This method statement describes the method, sequence of work at construction site for
backfill and compaction work.
Project Name

: Cilacap RFCC Project

Contractor

: GS E & C (GS Engineering & Construction)

Owner

: PT. Pertamina

This work procedure is a guidance to achieve a successful project completion with


acceptable quality, within specified schedule, and within a controllable budget for the
purpose of clients satisfaction. The following topics will be described / explained in this
work procedure.
To prevent uncontrollable discrepancy of work performance from this work procedure,
this procedure must be followed strictly. Any change or adapting action taken to
anticipate job site/work conditions, can only be performed under written notice /
instruction from Site Manager and approval of Client or Authorized Client Representative.

CONSORTIUM ADHI GS E&C

Cilacap Resid Fluid Catalytic Cracking (RFCC)


Project
PT. PERTAMINA (Persero)
METHOD STATEMENT FOR BACKFILL AND
COMPACTION

Doc.No. : RFCC-G-CS-PR-007

Rev. No. : 0

Page No : 4 / 11

2. METHOD OF WORK
2.1

Before the backfilling work is started, existing facilities and utilities shall be clearly
identified, removed or relocated where applicable and proper protection from dirt,

dust or damage during the work execution shall be undertaken.


2.2 Prior to excavation work, survey and lay outs shall be made to define and establish
the limit of the excavation work. Top and bottom excavation cuts shall be clearly
marked on the ground in accordance with the construction drawings. Excavations
shall be carried out to the widths, lengths and depths required and directed.
2.3 All fill material shall be approved excavated material, or imported material, free from
organic matter, rubbish or other deleterious matter.

CONSORTIUM ADHI GS E&C

Cilacap Resid Fluid Catalytic Cracking (RFCC)


Project
PT. PERTAMINA (Persero)
METHOD STATEMENT FOR BACKFILL AND
COMPACTION

Doc.No. : RFCC-G-CS-PR-007

Rev. No. : 0

Page No : 5 / 11

2.4 Soil spreading is done layer by layer and directly solidified until the surface or
desired elevation. The soil thickness layer should not be more than 30 cm, and after
solidified, the thickness will be 15-20 cm. things to consider before the
commencement of the work are:
- If there is mud or soft soil in the location, then it must be excavated or removed
before the work starts.
- Solidification must be conducted properly by using equipments such as vibro roller,
stamper, etc.
- Backfilling and solidification must not be conducted in heavy rain condition. Soil
drying will be done by making drainages so that soil will be free from puddle.

CONSORTIUM ADHI GS E&C

Cilacap Resid Fluid Catalytic Cracking (RFCC)


Project
PT. PERTAMINA (Persero)
METHOD STATEMENT FOR BACKFILL AND
COMPACTION

Doc.No. : RFCC-G-CS-PR-007

Rev. No. : 0

Page No : 6 / 11

Start backfill with excavator, layer by layer 30 cm

Soil changing

2.5 Soil solidification will be conducted by using solidifier devices per layer.

CONSORTIUM ADHI GS E&C

Cilacap Resid Fluid Catalytic Cracking (RFCC)


Project
PT. PERTAMINA (Persero)
METHOD STATEMENT FOR BACKFILL AND
COMPACTION

Doc.No. : RFCC-G-CS-PR-007

Rev. No. : 0

Page No : 7 / 11

2.5.1 If the solidification space is wide enough, vibro roller with 10 tons capacity is
used
2.5.2 If the solidification space is narrow, baby vibro roller or stamper will be used.
2.5.3 One layer for solidification is about 30 cm and the time is 4 x lines. Or until
reaches 95% dry density.
2.5.4 The cleaning on the all sides of cutting pile can be done. This is can be done
manually by hitting the ground.
2.5.5 The works continue until After the final trimming and the desired elevation is
already attained.

CONSORTIUM ADHI GS E&C

Cilacap Resid Fluid Catalytic Cracking (RFCC)


Project
PT. PERTAMINA (Persero)
METHOD STATEMENT FOR BACKFILL AND
COMPACTION

Doc.No. : RFCC-G-CS-PR-007

Rev. No. : 0

Page No : 8 / 11

3. QA / QC
Site QA/QC Manager under the direction of Site Manager and Construction
Manager is responsible for supervision of Site Quality Assurance and Quality
Control activities and coordinates project quality control efforts to ensure the
desired results.
QC Engineer and Inspectors will be working under direction of QA/QC
Manager.
Site QA/QC Engineer & Inspector shall be responsible for the followings:
1) Monitors and controls implementation of Site inspection policies and
procedures.
2) Reviews individual inspection / testing procedure for each category of
work, prepared by engineer in charge or Subcontractor to ensure all
requisitions, project specification and codes are satisfied.

CONSORTIUM ADHI GS E&C

Cilacap Resid Fluid Catalytic Cracking (RFCC)


Project
PT. PERTAMINA (Persero)
METHOD STATEMENT FOR BACKFILL AND
COMPACTION

Doc.No. : RFCC-G-CS-PR-007

Rev. No. : 0

Page No : 9 / 11

3) Verifies inspection / testing results and documentation and issue


inspection reports to PERTAMINA.
4) Holds

Inspection

Meeting

between

PERTAMINA,

other

parties

and

CONTRACTOR regarding inspection and quality control activities.


5) Attends

kick-off

meeting

with

Subcontractors,

PERTAMINA

and

CONTRACTOR inspector / engineers of each discipline to review inspection


policy and procedures and to discuss detail procedure including inspection
/ test items to be witnessed by PERTAMINA.
6) Attends or has his representative attend for all inspection / testing,
confirm the record and ensure the test results obtain the signature of
acceptance from PERTAMINA.

7) Maintains close contact with PERTAMINA:

To solicit and study PERTAMINA comments and opinions on quality


control implementation.

To jointly study and resolve any problems related to inspection matters


and procedures applied.

8) Sets up a documentation filing system including filing original documents


and controls all documents of inspection and quality control.
9) Monitors and controls quality control activities to confirm that they comply
with the specified procedure.

CONSORTIUM ADHI GS E&C

Cilacap Resid Fluid Catalytic Cracking (RFCC)


Project
PT. PERTAMINA (Persero)
METHOD STATEMENT FOR BACKFILL AND
COMPACTION
10)

Doc.No. : RFCC-G-CS-PR-007

Rev. No. : 0

Page No : 10 / 11

Supports Site and Construction Managers activities for quality control

matters by:

Obtaining PERTAMINA ideas, by evaluating the specified procedures.

Demarcate inspection activities between QC group and Construction


group.

Advising or being consulted by QC Engineer or QC Inspector on quality


control procedures, methods and application.

Interpreting

codes,

standards,

specifications

and

government

regulations.
11)

Holds Inspection Meeting between CONTRACTOR and Subcontractor to

emphasize procedures, progress or other inspection and test matters.


12)

Reviews and submits Daily Inspection Schedule and Weekly Inspection

Schedule for specified items to PERTAMINA.

4. SAFETY
4.1 Before began to working at site, all worker joint TBM at site, the complete works
force will receive a toolbox meeting, TBM at site consists planning, review for main
civil work, and safety matter.
4.2 Excavation permit where required shall be obtained by the Site Engineer and or
Safety Officer based on the following: a) location of the excavation, b) proximity of
CONSORTIUM ADHI GS E&C

Cilacap Resid Fluid Catalytic Cracking (RFCC)


Project
PT. PERTAMINA (Persero)
METHOD STATEMENT FOR BACKFILL AND
COMPACTION

Doc.No. : RFCC-G-CS-PR-007

Rev. No. : 0

Page No : 11 / 11

known existing underground services, c) proximity to existing overhead services,


and d) proximity of existing structure that may be affected by the excavation,
ground conditions and known risk contamination.
4.3 The use or restriction of the machine or hand tools will be monitored all the time by
the foreman concerned personally, and put safety tag from GS E&C safety
4.4

department.
Prior to commence any backfill work and if applicable and required, hard
barricades, signs and warning lights shall be arranged and assembled at the area
of excavation. Likewise suitable steps for safe access for workers and for inspection

purpose shall be provided.


4.5 The Site Engineer and or Safety Officer shall inspect excavations after every
rainstorm or other hazard-increasing occurrence. Protection against slide or caveins by the use of sand bag & plastic sheets as cover shall be increased if and when
required.
4.6 Banksman or signal man must stand by at site for one equipment.
4.7 Toilet facility , shelter / rest area and water must be provide at site.

CONSORTIUM ADHI GS E&C

You might also like