Substation Insulation Coordination Studies-Sparacino

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 42

InsulationCoordinationStudies

TheSelectionofInsulationStrength

March25,2014
AdamSparacino

MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

DefinitionofInsulationCoordination1
Insulation Coordination (IEEE)
The selection of insulation strength consistent with expected
overvoltages to obtain an acceptable risk of failure.
The procedure for insulation coordination consists of (a)
determination of the voltage stresses and (b) selection of the
insulation strength to achieve the desired probability of failure.
The voltage stresses can be reduced by the application of surge
protective devices, switching device insertion resistors and controlled
closing, shield wires, improved grounding, etc.

(1)IEEEStd 1313.11996IEEEStandardforInsulationCoordination Definitions,Principles,andRules.


MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

FourBasicConsiderations

Understanding Insulation Stresses


Understanding Insulation Strength
Designing Methods for Controlling Stresses
Designing Insulation Systems

MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

FourBasicConsiderations

Understanding Insulation Stresses


Understanding Insulation Strength
Designing Methods for Controlling Stresses
Designing Insulation Systems

MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

DefinitionofOvervoltages
Overvoltage
Abnormal voltage between two points of a system that is greater than
the highest value appearing between the same two points under
normal service conditions.2

Overvoltages are the primary metric for measuring and


quantifying power system transients and thus insulation
stress.

(2) IEEE Std C62.221991 IEEE Guide for the Application of MetalOxide Surge Arresters for AlternatingCurrent
Systems, 1991.
MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

VocabularyofVoltage

PeaklinegroundVoltage

RMSVoltagelineground=(Vpeak/2)

PeakVoltagelineground=VLL_rms2/3

MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

IllustrationofOvervoltages

MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

FourBasicConsiderations

Understanding Insulation Stresses


Understanding Insulation Strength
Designing Methods for Controlling Stresses
Designing Insulation Systems

MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

ElectricalInsulation
Insulation can be expressed as a dielectric with a function to
preserve the electrical integrity of the system.
The insulation can be internal (solid, liquid, or gaseous), which is
protected from the effects of atmospheric conditions (e.g.,
transformer windings, cables, gasinsulated substations, oil circuit
breakers, etc.).
The insulation can be external (in air), which is exposed to
atmospheric conditions (e.g., bushings, bus support insulators,
disconnect switches, line insulators, air itself [tower windows, phase
spacing], etc.).

MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

InsulationStrength
TypicalVoltTimeCurveforInsulationWithstand
StrengthforLiquidFilledTransformers

Source: IEEE Std 62.22-1997, IEEE Guide for the Application of Metal-Oxide Surge Arresters for AC Systems
MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

10

InsulationStrength
Example for Transformers Windings
Normal system operating voltage
345 kVLL_RMS (1.00 p.u.)

Maximum continuous operating voltage (MCOV)


362 kVLL_RMS (1.05 p.u.)

Basic switching impulse insulation level (BSL)


745/870/975 kVLN_Peak

Basic lightning impulse insulation level (BSL)


900/1050/1175 kVLN_Peak

Chopped wave withstand (CWW)


1035/1205/1350 kVLN_Peak

MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

11

FrequencyofDifferentEvents

10-20 minutes

seconds

Power System Control


& Dynamics

Power
Frequency

milliseconds

microseconds

Transients
& Surges

MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

12

FourBasicConsiderations
Understanding Insulation Stresses
Duty and Magnitude of applied voltage

Understanding Insulation Strength


Ability to withstand applied stress

Designing Methods for Controlling Stresses


Designing Insulation Systems

MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

13

PotentialOvervoltageMitigation
1. Surge Arresters

Need to be sized and located properly to clip overvoltages.

2. PreInsertion Resistors/Inductors

Need to be sized according to equipment being switched (only help


during breaker operation) to prevent excessive overvoltages from
being initiated.

3. SynchronousClose/Open Control

Need to use independent pole operated (IPO) breakers and program


controller based on equipment being switched (only help during
breaker operation) to prevent excessive overvoltages from being
initiated.

4. Surge Capacitors

Need to be sized and located to slow the front of incoming surges

MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

14

FourBasicConsiderations
Understanding Insulation Stresses
Duty and Magnitude of applied voltage

Understanding Insulation Strength


Ability to withstand applied stress

Designing Methods for Controlling Stresses


Designing Insulation Systems

MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

15

InsulationCoordinationProcess
1. Specify the equipment insulation strength, the BIL and BSL of
all equipment.
2. Specify the phaseground and phasephase clearances that
should be considered.
3. Specify the need for, location, rating, and number of surge
arresters.

MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

16

InsulationCoordinationStudies
1. Very Fast Transients (VFT) Analysis (nanoseconds time frame)

GIS disconnected switching.


Quantify the overvoltages throughout the substation.
Primary intent of determining location and number of surge arresters
within the substation.

2. Lightning Surge Analysis (microseconds time frame)

Quantify the overvoltages throughout the substation.


Primary intent of determining location and number of surge arresters
within the substation.

3. Switching Overvoltage Analysis (milliseconds time frame)

Quantify the overvoltages and surge arrester energy duties associated


with switching events and fault/clear operations.
Primary intent is to verify that transient overvoltage mitigating devices
(e.g., surge arresters, preinsertion resistors, synchronous close control)
are adequate to protect electrical equipment.
Capacitor, Shunt Reactor, Transformer, and Line Switching Studies.
MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

17

InsulationCoordinationStudies(cont.)
4. Temporary Overvoltage Analysis (seconds time frame)

Quantify the overvoltages and surge arrester energy duties as produced


by faults, resonance conditions, etc.
Primary intent is to verify conditions that cause problems within the
system and develop the necessary mitigation.
Fault/Clear, load rejection, ferroresonance studies.

5. Steady State Analysis (minutes to hours time frame)

Quantify voltage during various system configurations.


Power flow/stability studies.

MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

18

EXAMPLEAPPLICATION
STUDYFORINSULATIONCOORDINATION
LIGHTNINGSURGEANALYSIS

MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

19

500 kV LINE

Refer to Figure 2 for


details of line
terminations.

BML00

Refer to Figure 2 for


details of line
terminations.

BLU00

BML01

All lengths shown in meters.

BLU01

la = 30.70
lb = 25.66
lc = 21.76
la = 23.47
lb = 22.56
lc = 21.64

500 kV LINE

la = 21.19
lb = 20.74
lc = 23.64
la = 23.47
lb = 22.56
lc = 20.64

WEST500kVBUS
GWB06

la,b,c = 8.323

la,b,c = 19.59

G752W

G952W

CB

CB

G752E

la = 26.42
lb = 25.51
lc = 24.59

la = 9.518
lb = 8.603
lc = 7.689

G762W

G962W

CB

CB
G952E

CB

G762E

G772W

la = 12.47
lb = 11.55
lc = 10.64

EAST500kVBUS

CB

CB

G772E

G872E

GML00

la,b,c = 8.323

GEB06

la = 70.62
lb = 76.69
lc = 82.77

G972W

G872W

G4A00

DUMMYBUS(POSITIONFOR
FUTUREBREAKER)

XFMR

la,b,c = 5.634

CB

CB
G962E

la,b,c = 19.59

G3A00

la,b,c = 8.323

la = 26.42
lb = 25.51
lc = 24.59

G972E

GLU00

la,b,c = 8.323

la,b,c = 5.634
la = 70.15
lb = 76.25
lc = 82.30

B3A01

B4A01

B3A00

B4A00

Refer to Figure 3 for


details of XFMR
terminations.

MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

XFMR

Refer to Figure 3 for


details of XFMR
terminations.

20

ExampleforLine/XFMRTermination
500 kV Line

Line Trap1

To Transformer

Surge
Arrester

Gas-toAir
Bushing

CCVT

To GIS
Bay #6

Gas-to-Air
Bushing
550 kV GIS

350 MCM
Ground Lead
(38)

Surge
Arrester

Notes

To GIS
Bay
550 kV GIS

(1) Line traps only on phase A and C for 500 kV lines. In


EMTP model, phase B has a 2.53 m section of
conductor modeled in place of line trap.

350 MCM
Ground
Lead (38)

MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

21

DetailedAnalysis

ScreeningAnalysis

ApproachforEvaluationtheInsulationCoordinationof
the550kVGasInsulatedSubstation
Step 1:

A severe voltage surge was injected into the substation for


operating configurations to screen for maximum potential overvoltages.

Step 2:

The resulting overvoltages were compared to the Basic Lightning Impulse


Insulation Level (BIL) of the equipment and the protective margin1 for the
equipment was calculated.

Step 3:

If overvoltages resulted in less than a 20% protective margin in the initial


screening analysis for cases with the full system in or N1 contingencies, a more
detailed analysis was performed to identify the protective margins resulting from a
reasonable upper bounds lightning surge based on the configuration
of
the
substation and connected transmission lines.

various

For the detailed analysis, specific details of the transmission lines such as conductor
characteristics, shielding design, ground resistivity, keraunic level, etc. are considered to
determine a reasonable upper bounds to place on the lightning surge impinging on the
substation.

(1) Protective Margin = [ BIL / Vmaximum_peak 1] x 100%

MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

22

LightningSurgeIncomingFrom500kVLine
PhasetoGroundVoltageofIncomingLightningSurge

MLFULL_halfSRC>MLSRCA(Type 1)

4000

Peak = 3264 kV (1.2 x 2720 kV CFO)


Time-to-peak = 0.5 microseconds.

Voltage (kV)

3000

2000
Lightning surge impinges
substation from 500 kV Line.

1000
Lightning surge initiated at
1.0 microseconds.

0
0

10
Time (us)
MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

15

20

23

LightningSurgeIncomingFrom500kVLine
HighestPhasetoGroundVoltageObservedinGIS

MLFULLB>G752WB(Type 1)

2000

GIS Basic Impulse Insulation Level (BIL) = 1550 kV

Voltage (kV)

1500
Protective Margin = 40%
([1550/1109 1] x 100%)

Peak overvoltage =
1109 kV.

1000

500

0
0

10
Time (us)
MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

15

20

24

EXAMPLEAPPLICATION
STUDYFORINSULATIONCOORDINATION
TRANSMISSIONLINESWITCHINGANALYSIS

MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

25

TransmissionLineSwitchingAnalysis
PotentialEquipmentConcerns
ExcessiveTransientOvervoltagesand
thePossibilityofaFlashoverDuring
EnergizingorReClosing
OvervoltagesExceedingGuidelines
UsedtoDevelopLineClearances
Transmission line is energized
(normal energizing or re-closing).

Applicable Criteria

BasicSwitchingImpulseLevel(BSL)
ProbabilityofFlashovers

PotentialMitigationTechniques

SynchronousCloseControl
PreInsertionResistors/Inductors
SurgeArresters
ShuntReactors

MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

26

StatisticalSwitchingMethodology

Source-Side Voltage
cycle window

Case simulated with


200-400 energizations
3 = cycle 2 = 2.08 ms
Each pole can close at anytime
within the cycle window centered
around the closing time (Tclose) for
each energization. Random closing
times based on a normal (Gaussian)
distribution
Tclose
Three poles closing
centered around closing
time (Tclose)

Sliding cycle window for pole


closing shifted over a half cycle
timeframe using a uniform
distribution

MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

27

ElectroGeometricLineModel
Example345kVTransmissionLine

14.5

ShieldWire:
Alumoweld7#8
Outsidediameter=0.385
RDC=2.40Ohm/mi

14.5

78
(63atmidpoint)
B

27

27

54
(24atmidpoint)
Center
Line

MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

PhaseConductor:
ACSRLapwing
2/cBundle18spacing
Outsidediameter=1.504
RDC=0.059Ohm/mi
Thick/Diam=0.375

LineLength(total)=85mi
Untransposed
Groundresistivity=37Ohmm

28

StatisticalSwitchingOvervoltageStrengthCharacteristics
andSOVdensitiesoftheline

MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

29

StatisticalDistr.OfOvervoltagesAlong500kVLinewith
NOSurgeArresters

StatisticalDistributionofOvervoltagesAlongLine
110%

Statistical
distributionbasedon
thecasepeak
methodfromIEEE
Std1313.21999.

ProbabilitytoExceedOvervoltage(%)

100%
Estimatedinsulation
withstandforthe
transmissionline:CFO=3.53
p.u.,f/CFO =5%.

90%
80%
70%

SendingEnd

60%

1/4Point

98%oftheovervoltagesalong
thelineare2.62p.u.(1070
kV).

50%
40%

1/2Point
3/4Point

Highestovervoltageatthe
remoteendoftheline=2.75
p.u.(1123kV).

30%
20%

RemoteEnd
ExampleCFO

E2isthevalueinwhichthe
overvoltagesexceed2%ofthe
switchingoperations.

10%
0%
1.00

1.50

2.00

2.50

3.00

3.50

4.00

PeakOvervoltage(PerUnitona500kVBase)
MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

30

StatisticalDistr.OfOvervoltagesAlong500kVLinewith
LineEndSurgeArresters

StatisticalDistributionofOvervoltagesAlongLine
110%

ProbabilitytoExceedOvervoltage(%)

100%
Estimatedinsulation
withstandforthe
transmissionline:CFO=3.53
p.u.,f/CFO =5%.

90%
80%

Statistical
distributionbasedon
thecasepeak
methodfromIEEE
Std1313.21999.

70%

SendingEnd

60%

1/4Point
98%oftheovervoltagesalong
thelineare2.16p.u.(882
kV).

50%

1/2Point
3/4Point

40%

RemoteEnd
30%

ExampleCFO

20%

Highestovervoltagealongthe
line=2.21p.u.(902kV).

E2isthevalueinwhichthe
overvoltagesexceed2%ofthe
switchingoperations.

10%
0%
1.00

1.50

2.00

2.50

3.00

3.50

4.00

PeakOvervoltage(PerUnitona500kVBase)
MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

31

EXAMPLEAPPLICATION
STUDYFORINSULATIONCOORDINATION
SHUNTCAPACITORSWITCHINGANALYSIS

MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

32

ShuntCapacitorSwitchingAnalysis

Capacitor bank is energized and


transient inrush currents flow
through capacitor bank breaker
and voltage surges propagate
into the system.

PotentialEquipmentConcerns
ContactWearfromExcessiveInrush
CurrentDuty
ExcessiveTransientOvervoltages
InducedVoltagesandCurrentsin
ControlCircuits
StepandTouchPotentialsDuring
Switching
ApplicableCriteria

ANSI/IEEEInrushCurrentLimits

BasicSwitchingImpulseLevel(BSL)

BreakerCapabilityBeyondStandards

IEEEStd 80forgrounding
PotentialMitigationTechniques

CurrentLimitingReactors

SynchronousCloseControl

PreInsertionResistors/Inductors

SurgeArresters
MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

33

CapacitorBankReStrike
DuringDeEnergization
CurrentThroughSwitchingDevice
Highfrequency
currentis
interrupted

Firstrestrike
occursand
currentisre
established

Secondrestrikeoccursand
currentisreestablished

VoltageonEachSideofSwitchingDevice
Peakovervoltage
from1st restrike

Voltageonsystem
sideofswitching
device

Currentis
interrupted
Voltageoncapacitor
banksideof
switchingdevice(DC
trappedcharge)
Peakovervoltage
from2nd restrike

MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

34

VoltageMagnification
When a shunt capacitor bank is energized with a nearby
capacitor at a lower voltage, the potential for voltage
magnification may exist when the following condition is true:
1

Furthermore,whenC1>>C2,andL1<<L2 theconditioncanbe
exaggerated

MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

35

VoltageMagnification(Cont.)
Example 4.39 p.u. overvoltage at LV
bus when capacitor bank is switched.

Example 1.95 p.u. overvoltage at HV


bus when capacitor bank is switched.

MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

36

EXAMPLEAPPLICATION
STUDYFORINSULATIONCOORDINATION
SHUNTREACTORSWITCHINGANALYSIS

MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

37

ShuntReactorSwitchingAnalysis
PotentialEquipmentConcerns

Shunt reactor is energized and


inrush current flows through the
system and circuit breaker.

ExcessiveInrushCurrentsfrom
Energizing
TransientandTemporaryOvervoltages
fromResonanceConditions
GenerationofHarmonics
ResonancefromParallelLines

ApplicableCriteria

EquipmentInsulationLevels
VoltageSag/DipCriteria
HarmonicDistortion

PotentialMitigationTechniques

SynchronousCloseControl
SurgeArresters
AppropriateRelaySettings
OperationalLimitations

MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

38

ResonanceOvervoltages

345kVSubstation

345kVSubstation
VoltageMeasuredonEnergizedLine

Lineinservice
(breakersclosed
atbothends)

Lineoutofservice
(breakersopenat
bothends)

345kVSubstation

345kVSubstation

MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

39

ResonanceOvervoltages

Line breakers open to


trip the line at 200 ms.

Peak overvoltage
= 2.94 p.u.

It is anticipated that the line equipment


would be capable of withstanding at
least 1.5 p.u. for 100 ms.

Anticipated temporary overvoltage


(TOV) capability (1.5 p.u. for 100 ms).

The shunt reactors should be tripped


within 550 ms of the line breakers
tripping to avoid excessive
overvoltages for this case.

MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

40

Summary
Insulation Coordination is the selection of insulation strength.
Determine maximum insulation stress.
Determine the minimum insulation strength with margin taking into
account stress reducers (surge arresters, preinsertion resistors,
synchronous close control, etc.) that can withstand the maximum
stress.

Studies help in quantifying the maximum anticipated stress


and determining the rating/location of overvoltage mitigating
devices.
A key component of insulation coordination is pairing the
correct strength to the correct stress.
As a rule of thumb, the shorter the time the overvoltage is applied to
the insulation the greater the magnitude of overvoltage the insulation
can withstand before failure.

MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

41

THANKYOUFORYOUATTENTION

MITSUBISHIELECTRICPOWERPRODUCTS,INC.
POWERSYSTEMENGINEERINGSERVICES

42

You might also like