Professional Documents
Culture Documents
Denver International Airport Automated B PDF
Denver International Airport Automated B PDF
Denver International Airport Automated B PDF
Abstract
The purpose of this study is to critically analyse the Denver International
Airport Baggage Handling System project in order to detail the underlying
reasons for the perceived failures in the project and to provide
recommendations on how effective project management could have helped to
avoid the problems the project encountered.
A thorough analysis of the activities of the project from nature of project,
contracting, design, construction, testing, stakeholder management, risk
management, project controls, as well as the overall project leadership was
carried out and failure causal factors were identified. A recommendation was
also made on how the project should have been managed to ensure project
success. The analysis viewed the project from both project management and
project perspectives.
Student: @00380661
25-Feb-14
Number of words: 2558
Table of Contents
1.
1.1
2.
2.1
Introduction ................................................................................................................. 2
Project Failure .......................................................................................................... 2
Discussion .................................................................................................................... 3
Failure Modes of the Project .................................................................................... 6
3.
Conclusion ................................................................................................................. 10
4.
References ................................................................................................................. 11
Page 1 of 13
1. Introduction
Projects are increasingly considered strategic assets for many organisations today
(Dinsmore & Rocha, 2012) as such project management is occupying a progressively
central role (Morris, et al, 2011). Successful delivery of projects underpins the progress
and development of humanity (Morris, et al, 2011). The Denver International Airport
project was initiated to cater for the teaming air passengers at Denver city.
This report seeks to analyse the Denver Automatic Baggage System Project with the aim
to uncover the underlying reasons for its perceived failure. A thorough analysis of the
activities of the project was considered in order to identify the failure causal factors. A
recommendation was also made on how Denver automatic baggage system project should
have been managed to ensure project success.
The analysis viewed the project from both project management and project perspectives.
The project is said to be an all-round catastrophic colossal failure (Schlohs, 1996;
Neufville, 1994; Calleam Consulting Ltd, 2008); cost overruns, schedule delays, poor
quality of product, inability to meet stakeholder expectations and so on.
Big and complex projects fail at an alarming rate (Matta & Ashkenas, 2003). So was the
case with Denver baggage handling project. Most project failures term from failure to
identify and properly manage risks (Matta & Ashkenas, 2003).
Page 2 of 13
A project that has not delivered the required/expected quality, with the available
resources, on time, within budget and achieved expected benefits has failed (PMI (2013,
p.35).
However, that a project is not completed within budget and time does not make it a failed
project (Hallgren & Wilson, 2007). A project can still be a success even with the failing
of the project management if it can deliver its long term objectives (Munns & Bjeirmi,
1996). The Australian Sydney Opera house, for instance, came in 10 years late and about
1500% over budget but is considered an architectural achievement and perhaps a wonder
of the modern world (Hallgren & Wilson, 2007; Murray, 2004).
Its however important to note that a project must have either of two outcomes: its either it
succeeds or fails and that project managers have to understand that the chances of a
project getting into trouble are greater than those of getting out of it (Kleim, 2012).
2. Discussion
The Denver Airport Automatic Baggage Handling System Project that was supposed to
be a mega monumental achievement of a project and the worlds largest automated
airport baggage handling system turned out to be a colossal tragedy (Schlohs, 1996;
Neufville, 1994; Calleam Consulting Ltd, 2008).
Faced with the need for greater airport capacity, the city of Denver elected to construct a
new state of the art airport that would cement Denvers position as an air transportation
hub. Covering a land area of 140 km2, the airport was designed to handle more than 50m
passengers annually (Calleam Consulting Ltd, 2008; Neufville, 1994).
The construction started in 1989.
In 1991 Denver airport management suggested that an airport-wide integrated automated
baggage-handling system should be added to the project scope.
In 1992 the automated baggage system was introduced against expert advice from Breier
Neidle Patrone Associates, the feasibility consultant, that the complexity of the system
makes it unfeasible (Calleam Consulting Ltd, 2008). 16 bidders were invited to bid. Only
Page 3 of 13
3 returned bids. Report indicated none could achieve the Oct 1993 deadline when the
airport will be opened. Management approached BAE; to expand the United Airlines
baggage handling system into an integrated system handling all 3 concourses, all airlines,
departing as well as arriving (Calleam Consulting Ltd, 2008)
The main objective of the automated baggage system was to reduce aircraft turnaround
time to as low as 30 minutes (Neufville, 1994) thereby enhancing efficient operations and
eliminating the time wasting manual conveyor and tug baggage handling and sorting
system (Goetz & Szyliowicz,, 1997).
This would, however, not be achieved as it became obvious in the course of executing
the project that the complexity of the system was underestimated (Schlohs, 1996;
Neufville, 1994; Calleam Consulting Ltd, 2008) and risks were not properly identified.
The airport was idle for 16 months with a cost impact of $1.1m per day as maintenance
charges (Calleam Consulting Ltd, 2008).
Duration in Years
Planned
Page 4 of 13
construction of the automated baggage handling system (Neufville, 1994). See charts
below.
Table 1- Cost of Denver International Airport (Dollars in millions)
Cost category
Airport planning, land, and construction
Capitalized interest
Bond discounts and issuance expense
Total costs to Denver Airport System
Costs to others
FAA facilities
United Airline's special facilities
Continental Airline's special facilities
Rental car facilities
Total costs to others
Cost
$3,214
919
136
$4,269
224
261
73
66
624
624
$4,893
Project Cost
(x$1000,000)
$300.00
$250.00
$200.00
$150.00
$100.00
$50.00
$-
Project Cost
Project Cost
Budgeted Cost
$193.00
$250.00
Page 5 of 13
missed another three opening dates in April and May 1994 under increasing pressure
from stakeholders.
By March 1995, the delay had resulted to additional $500 million (Neufville D. R.,
1994).
By August 1994, the Mayor of Denver had decided that a backup system of tug and cart
be implemented. BAE was charged liquidated damages of $12,000 per day for the delay.
The system was reduced from 3 concourses to 1. When it was tested, bags were crushed,
jammed on the track or thrown off the track. It was a monumental failure. Had it
succeeded the Denver Automated Baggage Handling System would have been the most
advanced airport baggage handling system in the world (Calleam Consulting Ltd, 2008).
The system was commissioned in 1995 only to be scrapped in 2005 due to unusual
expensive high cost of maintenance of $1.0m/month which was much higher than the
cost of a manual tug and trolley system (Schlohs, 1996; Neufville, 1994; Calleam
Consulting Ltd, 2008).
worker cancelling purchase orders for the filters for electricity without any knowledge
that the filters were part of the project. The filters ended up arriving later than they should
have; force-fitting the baggage handling system into the configuration of the already
constructed airport - the automatic baggage handling system had to be forced to fit in the
boundaries of the airport passenger buildings, the underground tunnel that connects the
concourses and the terminal.
To further compound issues, Walter Slinger, who was the systems de facto sponsor died
in October 1992 leaving the project without that required crucial leadership. His
successor lacked the technical know-how required to manage such project. Stakeholder
involvement was another failure mode. Denver initiated the DIA project without
involving major stakeholders like Continental and United airlines who collectively
contributed over 70% of passenger traffic at Stapleton airport. This was a major
contributor to the incessant changes to the project strategy when the airlines got involved
in the project (Neufville, 1994; Goetz &Szyliowicz,, 1997). There were no backup
systems that would serve as alternatives.
2.2 Recommended Project Management Best Practice
2.2.1
Change control
Changes are a constant in projects. Therefore project teams must be ready for them to
avoid surprises (Stare, 2010). It is, however, very important to examine other potential
risks that can arise if changes are approved before approving such changes (Thomsett,
2002).
Every project scope change comes with a ripple effect (Harding, 2012). Changes that
occur at engineering stage of a project only affect engineering cost. the later in a project
a scope change occurs the more impact in terms of both cost and potential schedule
delay (Harding, 2012).
Denver should have had a proper change management process that is robust enough to
control changes. That would have eliminated the complexity introduced by the various
changes that took place on the project.
Page 7 of 13
2.2.2
A well-thought out project schedule allows time for items such as, permitting, safety
reviews, detailed design, tie-ins, bidding cycles, equipment deliveries, construction
durations, and so on (Harding, 2012). It also has to be logically sequenced to assure that
tasks that need to be completed before their successors are completed before moving to
the next task.
A good project plan would have ensured that:
Scope was clearly defined indicating what is in and out of the project (Maylor,
2010, p.70)
A Work Breakdown Structure prepared that would have being useful for resource
allocation and communication with project team and other stakeholders (Maylor,
2010, p.70)
A logical resource loaded schedule with critical path developed. This would have
guided Denver to construct the airport physical structures in a logical sequence
with the baggage handling system. That would have eliminated the unnecessary
costly reworks. The schedule would have also helped to ensure that designs are
completed before construction starts.
2.2.3
Stakeholders Management
the London Olympic 2012 where stakeholder engagement was one of the critical success
factors (Elson, 2013; Kintra, 2013; Caldwell et al, 2009).
2.2.4
Risk Management
Every project involves risks (Harding, 2012). Risks are uncertain events or conditions
that, if they occur, have positive or negative effect on project objectives (PMI, 2013).
Planned and systematically adopted risk management procedure is essential in keeping a
project on time and within budget with all requirements fulfilled (Iskanius, 2009).The
objective of risk management is to increase the probability and impact of positive events
and or decrease the probability of impact of negative events (PMI, 2013).
Denver should have carried out a risk management exercise at the beginning of the
project to identify potential risks and put together plans on how these risks would be
managed (Harding, 2012). (See Appendix 1 DIA ABS Risk Register). This would have
captured risks like electrical failure and the consequent delivery and installation of filters
and so on (Calleam Consulting Ltd, 2008).
2.2.5
Communication Management
Achieving projects success depends on people as people are the most critical project
management resource (Nauman & Khan, n.d).
Project leaders are decision makers and can overcome project potential change thereby
contributing significantly to project success (Atkinson, 1999).
Even Walter Slinger was not skilled enough to handle the project.
A good and skilled leadership should have been established to be able to handle even
political issues that affected the project.
Good leadership of the ODA and BAA was behind the success of the 2012 Olympic
Games and the Heathrow T5 projects (Brady & Davies, 2010; Kintrea, K & APM, 2013)
Page 9 of 13
2.2.7
Controlling cost
Cost is the universal and most highly visible performance metric for indicating project
success (Tichacek, R. L.2006).
Denver should have established project budget and had a system for monitoring and
controlling cost on the project.
2.2.8
Use of Experts
The management should have used industry expert organisations to execute the project.
Rejecting expert advices on major issues like the feasibility of implementing the
integrated baggage system, schedule, etc. was a big error.
3. Conclusion
According to Calleam Consulting Ltd, the Denver Baggage handling project is a classic
example of a project failure. As with so many other project failures Denver suffered
from:
Communication breakdowns
Poor designs
Majorly, Denver perished for lack of knowledge of the management team. Even Walter
Slinger was not that experienced on this kind of project. Moreover automated baggage
systems were relatively new, as such even BAE personnel have a diminutive knowledge
of what was involved.
Page 10 of 13
4. References
Page 11 of 13
12. Goetz & Szyliowicz,. (1997, July). Revisiting transportation planning and
decision making theory: The case of Denver International Airport. Retrieved
February 26, 2014,
http://www.sciencedirect.com/science/article/pii/S096585649600033X
13. Hallgren, M & Wilson, T. (2007). The nature and management of cirses in
construction projects: Projects-as-practice observations. International Journal of
Project Management. 26(2008), 830-838.
14. Harding, J. (2012). Avoiding Project Failures. Chemical Engineering. 2012
15. Kerzner, H., (2001). Project management: A systems approach to planning,
scheduling, and controlling (7th ed.). New York: John Wiley & Sons, Inc
16. Kintrea, K. & Association for Project Management (APM), 2013. Lessons Learnt
from the London 2012 Games Construction Project. Programme Management
17. Kliem, R. L. (2012). Managing Projects in Trouble: Achieving Turnaround and
Success. Project Management Journal, 44(1), 109 DOI: 10.1002/pmj
18. Maylor, H, 2010. (4th ed). Project Management. Prentice Hall pub.
19. Meyer, A. D.; Loch, C. and Pich, M. 2001. Uncertainty and Project Management.
Beyond the critical path mentality. Insead R&D
20. Nauman, S. & Khan, A. M. (n.d). Patterns of Leadership for Effective Project
Management. Journal of Quality and Technology Management
21. Morris, P. W. G.; Pinto, J. K. & Sderlund, J. (2011). The Oxford Handbook of
Project Management. Oxford University.
22. Tichacek, R. L. (2006). Effective Cost Management Back to Basics. Cost
Engineering. 48(3)
23. Thomsett, R. (2002). Radical project management. Prentice Hall PTR, Upper
Saddle River
24. Schloh, M. (1996). Analysis of the Denver International Airport baggage system.
Retrieved 25th February, 2014, from
http://www5.in.tum.de/~huckle/schloh_DIA.pdf
25. Scott, J. Shwant, S. & Sheryl, L. (2006). A case Study of Project and Stakeholder
Management Failures: Lessons Learnt. Project Management Journal. 37(5). 2635.
26. Stare, A. (2010). Comprehensive management of project change. Economic and
business review. 12(3) 195210.
27. PMI, 2013. PMBOK 5th ed. PMI Pub
Page 12 of 13
28. Neufville, R. de. 1994. "The Baggage System at Denver: Prospects and Lessons."
Journal of Air Transport Management. 1(4): 229-236.
Page 13 of 13
Risk ID
No.
Risk Category
DIA - XYZ
Risk Description
Risk Analysis
RAM
RISK H/M/L
Risk Owner/
Manager
Risk Response
Strategy
Mitigation Plan
5C
PM
Mitigate
Architecture and
Design complexity
Design Issues
5C
PM
Mitigate
5C
PM
Mitigate
Underestimation of budget
5C
PM
Mitigate
5C
PM
Mitigate
5C
PM
Mitigate
No direction
5C
PM
Mitigate
Understimation of project
complexity
Understimation of project
complexity
5C
PM
Mitigate
5C
PM
Mitigate
5C
PM
Mitigate
5C
PM
Mitigate
Schedule
Budget
Change Control
Strategy
Complexity
Political Risks
10
Stakeholders
Management
11
Electric Power
Failure
12
Traffic Isssues
13
Communication
High
Medium
Low
5C
PM
Mitigate
Lack of or ineffective
communication
5C
PM
Mitigate
Avoid:
Accept:
Mitigate:
Transfer:
Integrity
Assurance/Monitoring &
Control
CONSEQUENCES
INCREASING SEVERITY
Category
People
Asset / Production
Environment
Reputation
Community Relation
Security
No injury or health
effect
No damage
No effect
No impact
No impact
No impact
No change in cost
Slight damage
(10k$ & no disruption
to operation)
Slight effect
(within fence, no
exceedance)
Incidental problem
with community
relations resolved with
compensation
Minor damage
(10k$ - 100k$ & brief
disruption)
Minor effect
(temporary
containment. Slight
exceedance)
Limited impact
(Eg. local / public
media)
Moderate damage
(0.1 - 1.0M$ & partial
shutdown)
Permanent Total
Major damage
Disability (PTD) or up (1.0 - 10.0M$ & partial
to 3 fatalities
operation loss)
Moderate effect
Considerable impact
(recoverable
(Eg. region / state /
environmental loss /
public media)
repeated exceedance)
Major effect
(severe damage
recoverable /
extended
exceedance)
Massive effect
Extensive damage
(widespread chronic
(>10M$ & substantial
effects / constant high
operation loss)
exceedance)
Major Impact
(Eg. extensive
adverse media)
Massive impact
(Eg. extensive
adverse media)
Re-instatement of no
go areas
Several days of
blockade of local
facilities, legal
litigations)
Severe damage to
environment reported
in the media
Impossible to operate
without major military
support
Slight
Minor
Moderate
Significant
Extensive
Heard of in the
Aviation Industry
NEGLIGIBLE
LOW
MEDIUM
HIGH
Mission
NEGLI