Name of Work :- Design and Construction of RCC ESR of 120000 Lit. Capacity and 12.00 Mt. Ht.

at Village Shiyal under Adim Juth Program. F.Y. 2015-16


Ta. Bavla

Dist. Ahmedabad
Payment of Schedule for construction of RCC ESR

Sr.
no.

Stage of Work

1.
1.
2.
3.
4.

2
On Appruval designs and drawings
On completion of excavation
On Completion of Concreting of Foundation
On completion of Full Shaft and braces including staircase upto
bottom slab / dome level.
On completion of bottom slab or dome vertical wall or slant wall of
container without top slab or dome.
Top slab or dome staircase with RCC Cabin and door.
Prcurement and fixing of inlet, outlet, washout,overflow pipe, Valves,
Specials, Chambers, Lightingarresterconductor and Specials at Site.
Fixing above pipes,specials as directed.
Water Level indicator, painting of leters M.S. ladder pipe, railing and
all micelleneous items such as snowcem paint three coats etc.
(Completed with all respect) including water tightness test.

5.
6.
7.
8.
9.

Amt.
Admissible
Payment
3
2%
2%
8%
17%
21%
10%
15%
5%
20%
100%

Note:(1) 75% part rate shall be payable for concrete and plastering Items of Container until
satisfactory hydraulic testing for water tightness is performed as per tender condition.
Till the work shall be treated as incomplete.
(2) Contractor shall have tested the materials to be used in this work at his own cost.