Professional Documents
Culture Documents
b.6.9 - Std. Specification Asphalt Road
b.6.9 - Std. Specification Asphalt Road
Rev No.
Issue Date
25/10/2008
Pages
21
Rev Description
Prepared
Checked
Approved
By
By
By
DK
SSP
MBR
21
Jacobs
Pages 2 of 21
HPCL, Mumbai
44LK5100
TABLE OF CONTENTS
1.0
PURPOSE
2.0
SCOPE OF WORK
3.0
TECHNICAL REQUIREMENTS
3.1
3.2
3.3
PREPARATION OF SUBGRADE
3.4
3.5
3.6
PREPARATION OF GRANULAR SUB BASE & BASE USING WATER BOUND MACADAM
3.6.1
3.6.2
GRANULAR BASE
3.7
3.8.a
BITUMINIOUS MACADAM
3.8.b
3.9
PREMIX CARPET
3.10
3.11
3.12
BITUMINOUS CONCRETE
3.13
Jacobs
HPCL, Mumbai
44LK5100
1.0
Pages 3 of 21
PURPOSE
The purpose of this document is to state the requirements of materials, workmanship,
plant & equipments, test & construction procedure to be followed carried out during the
asphalt road/ paving works.
2.0
SCOPE OF WORK
This specification covers the supply, preparation of sub base, base & top bituminous
courses, requirements of materials, necessary equipments, testing, transportation, etc., for
asphalt / paving works.
3.0
TECHNICAL REQUIREMENTS
All the materials & construction procedures adopted for asphalt road/paving works shall
conform to MORT & H specifications & IRC 37.
3.1
3.2
3.3
PREPARATION OF SUBGRADE
The preparation of subgrade includes all operations before the pavement structure to be
laid over it and compacted. Thus the preparation of subgrade would include site clearance,
grading (embankment or cut section) and compaction to desired density at optimum
moisture. The subgrade may be situated on embankment, excavation or at the existing
ground surface. In all cases the Contractor shall clear the site of all shrubs, roots and
grass or any vegetation and any other organic/non-organic impurities, minimum 150mm
thick topsoil to be removed. The exposed surface (subgrade) shall be consolidated
properly to obtain 90% of maximum laboratory dry density of soil. Any kind of underground
construction, which is existing in place & is an obstruction to the future construction
activities, shall be removed.
The grading operations shall be started thereafter so as to bring the profile of the subgrade to
designed grade and compaction where necessary. The original ground shall be leveled to
facilitate placement of first layer of embankment, scarified, mixed with water and then
compacted by rolling so as to achieve minimum specified dry density.
If the difference between the subgrade level (top of the subgrade on which pavement rests)
and ground level is less than 0.5m and the ground does not have 95% relative compaction
Jacobs
Pages 4 of 21
HPCL, Mumbai
44LK5100
with respect to the dry density as given in Table below, the ground shall be loosened upto a
SUBGRADE level 0.5m below the subgrade level, watered and compacted in layers in
accordance with MoRT&H Clause 3.4 to not less than 90% of dry density as given in Table
below.
Any unsuitable material occurring in the embankment foundation shall be removed and
shall be replaced by approved materials laid in layers to the required degree of
compaction, as directed by engineer.
Embankment or subgrade work shall proceed after the inspection by the Engineer for
satisfactory condition and approved.
COMPACTION REQUIREMENTS FOR EMBANKMENT AND
Type of work / material
2) Embankment
3) Expansive clays
a) Subgrade and 500mm portion just
below the subgrade
b) Remaining portion of
embankment
3.3.1
3.4
3.4.1
The fill material shall be granular, well graded compactable and possess good drainage
characteristics, and no swelling properties. It shall be free of vegetation, any organic matters
and other impurities. In extra ordinary circumstances expansive soil of acceptable free swell
index, generally less than 50 % may be used, however approval shall be sought from the
central engineering office on case to case basis. Use of expansive soil, as a fill material shall
be limited to a depth of at least 500 mm below the sub grade level. All relevant test, such as
optimum moisture content, maximum dry density, liquid limit , plastic index shall be carried
out as per IS 2720 to determine the suitability of the fill material.
3.4.2
The suitability of proposed fill material shall be tested to determine optimum moisture
content, However filling material shall have Liquid limit between 20-35 and Plasticity
index shall not be more than 12 & dry density shall be minimum 1.70gm/cc. The
material finer than 75 microns shall be limited to a max. of 35 % & clay percent within
fines shall be limited to 15 %. All these testing cost shall included in contractors scope.
Jacobs
HPCL, Mumbai
44LK5100
Pages 5 of 21
3.4.3
If top soil encountered is of clay or swelling in nature. The top soil removal guidance shall
be referred in site grading drawing and removed area shall be back filled with cohesivenon-swelling soil. The properties of such soil shall be as per Appendix-A attached here
with
3.4.4
Expansive clay exhibiting marked swell and shrinkage properties (free swelling index
exceeding 50 per cent when tested as per IS: 272 Part40) shall not be used as fill
material.
3.4.5
For non expansive sub-grade compaction shall be carried out to 95 % of lab dry density of
Optimum moisture content.
3.5
3.5.1
The fill shall be constructed in layers, each layer being compacted to the required density
before the next layer is laid. The compacted thickness shall be 200mm for each layer.
3.5.2
Compaction shall be carried out using 10 Mt static road roller. The Contractor shall
determine the number of passes of the roller required to achieve the required density by
first conducting trials over a test stretch. Vibrating roller of 80-100 KN static weight shall
be used if faster compaction is required. Precaution to be taken about adjacent property.
The compaction can be done using mechanical rammers or manual ramming in places
where road roller access is not possible as per directions of engineer.
The number of passes shall be reviewed and adjusted in consultation with the site
in-charge as required during the course of the work.
3.5.3
All lumps and clods in the fill material shall be broken before rolling. The top surface of
each layer shall be roughened before placing the subsequent layer to ensure proper
keying in between layers.
3.5.4
Prior to rolling, the moisture content of the material shall be brought to within +1 / -2% of
the optimum moisture content.
3.5.5
Each layer shall be compacted at least 95% of modified proctor density for embankment &
for subgrade and shall posses minimum dry density 1.70 gm/cc for subgrade &
embankment.
If the layer fails to meet required density, the failed part shall be reworked to achieve
the
specified density. In future any settlement occurs due to improper compaction,
Contractor shall rectify at his own cost. Minimum one test for every 500 sq.m. filling area
shall be conducted.
3.6
3.6.1
Granular sub-base
Sub-base to be prepared by filling supersaturated river sand/stone grit/murrum/granular
soil or mixture of all, in case of murrum & soil the liquid limit & plasticity index shall be less
than 20 & 6 respectively, complete as per drawing. The compaction shall be in layers to
get 98 % relative density after sprinkling required quantity of water. The consolidation shall
be done using 8-10 ton roller as per the camber required. Suitable thickness of Sub-base
shall be selected as per SOAK CBR VALUE available at site. The gradation and CBR
value of the material to be used for sub-base shall be as per Table 1A / 1B.
Jacobs
Pages 6 of 21
HPCL, Mumbai
44LK5100
Table 1A
Grading for Close Graded Granular Sub-base materials
IS Sieve Designation
75.0 mm
53.0 mm
26.5 mm
9.50 mm
4.75 mm
2.36 mm
0.425 mm
0.075 mm
CBR Value (Min)
Table 1B
Grading for Coarse Graded Granular Sub-base materials
IS Sieve Designation
75.0 mm
53.0 mm
26.5 mm
9.50 mm
4.75 mm
2.36 mm
0.425 mm
0.075 mm
CBR Value (Min)
15-35
25-45
< 10
30
< 10
25
< 10
20
Note : The material passing 425 micron (0.425 mm) sieve for all the three gradings when tested
according to IS : 2720 (Part 5) shall have liquid limit and plasticity index not more than 25
and 6 per cent respectively.
3.6.2 Granular base
Granular base shall be made out of coarse aggregate crushed from hard rock or broken stone
metal and shall meet physical & chemical properties as per table-2 & table-3 respectively. The type
and sizes range of aggregates shall be as per grade listed in table-4.The interstice shall be filled
completely with murrum, liquid limit less than 20,plasticity index less than 6 and fraction passing
75 micron sieve shall not exceed 10%. In absence of murrum of the above characteristics
aggregate grit shall be used. The grading of screenings shall be Type A for grading 1 & 2, Type B
for grading 3 as per table 5, the layer to be compacted with 3 wheeled power rollers of 10 tonne.
Suitable thickness of Granular-base shall be selected as per SOAKED CBR VALUE available at
site. The work shall be carried out as specified in clause 404 of MORTH specification.
3.6.2.a
Screenings :Screening to fill voids in the coarse aggregate shall generally consist of the same
material as the coarse aggregate. However, where permitted, predominantly non-plastic
material such as moorum or gravel (other than rounded river borne material) may be
used for this purpose provided liquid limit and plasticity index of such material are below
20 and 6 respectively and fraction passing 75 micron sieve does not exceed 10 per cent.
Screening shall conform to the grading set forth in Table below.
The use of screening shall be omitted in the case of soft aggregates such as brick
metal, kankar, laterites, etc. as they are likely to get crushed to a certain extent under
rollers.
Jacobs
HPCL, Mumbai
44LK5100
Pages 7 of 21
Table 5
GRADING FOR SCREENINGS
Grading
Classification
A
Size of
Screening
13.2 mm
11.2 mm
IS Sieve
Designation
13.2 mm
11.2 mm
5.6 mm
180 micron
11.2 mm
5.6 mm
180 micron
Test method
Requirements
IS-2386 Part-4
40 % max
IS-2386/ IS-5640
30% max
Flakiness index
IS-2386
15% max
Elongation index
IS-2386
30%max
Sulphur content
Water absorption
Max 2%
Size Range
90 mm to 45 mm
63 mm to 45 mm
53 mm to 22.4 mm
IS Sieve Designation
125 mm
90
mm
63
mm
45
mm
22.4 mm
90
mm
63
mm
53
mm
45
mm
22.4 mm
63
mm
53
mm
45
mm
22.4 mm
11.2 mm
Note : Use of grading I shall be restricted to construction of sub-base course only. The
compacted thickness for a layer with Grading 1 shall be 100 mm while for layer
with other Gradings i.e. 2 and 3, it shall be 75 mm.
Jacobs
Pages 8 of 21
3.7
HPCL, Mumbai
44LK5100
3.8.a
BITUMINOUS MACADAM
The bituminous macadam should be laid in 50 mm thickness.
The base on which the bituminous macadam is to be placed shall be prepared, shaped &
compacted to required profile over which the prime coat & tack coat to be applied as described
in clause no. 3.6.
The bitumen to be used for bituminous macadam shall conform to IS 73 and shall be of 60/70
grade. The coarse aggregates to be used shall be clean, hard, durable & cubical shaped.
The fine aggregate shall be consist of crushed or naturally occurring material or combination
of two passing through 2.36 mm sieve & retained on 75 micron sieve. They shall be clean,
hard & durable.
The mix shall be as per table given below:COMPOSITION OF BITUMINOUS MACADAM
Mix designation nominal
Grading 2
19 mm
Aggregate size layer
Thickness IS Sieve(mm)
Cumulative % by weight of total aggregate
passing
26.5
19
13.2
4.75
2.36
0.3
0.075
100
90-100
56- 88
16-36
4-19
2-10
0-8
3.3-3.5
Anti-stripping agent
As per Appendix B
Jacobs
HPCL, Mumbai
44LK5100
Pages 9 of 21
The aggregates shall be proportioned & blended to produce a uniform mixture complying with
the requirement of the above table.
Mixing of aggregate & bitumen shall be in accordance with 3.8.1 Compaction shall be
continued till the density achieved is 95% of Marshal density and should be completed before
the temperature of mix falls below 90 C.
3.8.b
Property
Cleanliness
Particle shape
Strength
Water absorption
Stripping
Durability
Table 6
Test
Grain size analysis
EI & FI (combined)
Aggregate Impact value
As per IS:2386 (Part 3)
IS : 6241 Stripping
Soundness
Sodium sulphate
Magnesium sulphate
Retained tensile strength
Los Angeles Test
Specifications
Max 5% passing 75 micron
Max 30%
Max 27%
Max 2%
Minimum retained coating 95%
Max 12%
Max 18%
Min 80%
Max 35%
Filler
Jacobs
Pages 10 of 21
HPCL, Mumbai
44LK5100
Filler shall consist of finely divided mineral matter such as rock dust, hydrated lime or cement
as approved by engineer. Grading requirement for filler
IS Sieve
(mm)
0.6
0.3
0.075
The filler shall be free from organic impurities and have a Plasticity Index not greater than 4.
The Plasticity Index requirement shall not apply if filler if cement or lime. When the coarse
aggregate is gravel, 2 percent of weight total aggregate, shall be Portland cement or hydrated
lime and the percentage of fine aggregate reduced accordingly. Cement or hydrated lime is
not required when the limestone aggregate is used. Where the aggregates fail to meet the
requirements of water sensitivity test (water absorption not more than 2%), then 2% by total
weight of aggregate, hydrated lime shall be added without additional cost.
Grading and Binder Content
When tested as per IS:2386, Part-I, combined grading should fall within in the limits given
below.
IS Sieve (mm)
37.5
26.5
19
13.2
4.75
2.36
0.3
Bitumen Grade (Pen)
Anti stripping agent
Bitumen Content %
Work of DBM shall not be done rainy, foggy or when the temperature is shed is less than 10
C.
Mixture Design
Requirement for the mixture
Apart from conformity with the grading and quality requirements for individual ingredients, the
mixture shall meet the requirements set out in Table 7.
Table 7
Requirements for Dense graded Bituminous Macadam
Minimum stability (kN at 60
9.0
C)
Minimum flow (mm)
2
Maximum flow (mm)
4
Compaction level (no. of
75 blows on each of the two
blows)
faces of the specimen
Percent air voids
36
Percent voids in mineral
See Table 8 below
aggregates (VMA)
Percent voids filled with
65-75
Bitumen (VFB)
\\nmumfil01\project\WIP\4401-5100\4401-5100_Civil\OSBL FACILITIES\Boilar house\standard specification\Specifications for Asphalt Road_1118.doc
Jacobs
HPCL, Mumbai
44LK5100
Pages 11 of 21
The requirements for minimum per cent voids in mineral aggregate ( VMA ) are set out in
Table 8
Table 8
Minimum Percent voids in Mineral aggregate ( VMA )
Nominal max.
Particle size (mm)
9.5
12.5
19.0
25.0
37.5
Notes : 1. The nominal maximum particle size is one size larger than the first sieve to retain
more than 10 per cent.
2. Interpolate minimum voids in the mineral aggregate ( VMA ) for design air voids
values between those listed.
Binder Content
The binder content shall be optimised to achieve the requirements of the mixture set out in
table 7 and the traffic volume specified in the contract. The Marshall method for determining
the optimum binder content shall be adopted as described in the Asphalt Institute Manual
MS-2, replacing the aggregates retained on the 26.5 mm sieve by the aggregates passing the
26.5 mm sieve and retained on the 22.4 mm sieve, where approved by the engineer.
Where 40mm dense bituminous macadam mixture is specified, the modified Marshall
method described in MS-2 shall be used. This method requires modified equipment and
procedure; particularly the minimum stability values in Table 7 shall be multiplied by 2.25 and
the minimum flow shall be 3mm.
Job mix formula
The contractor shall inform the Engineer in writing, at least 20 days before the start of the
work, of the job mix formula proposed for use in the works, and shall give the following
details:
i) Source and location of all materials
ii) Proportions of all materials expressed as follows where each is applicable
a)
Binder type, and percentage by weight of total mixture
b)
Coarse aggregate / fine aggregate / mineral filler as percentage by weight of
total aggregate including mineral filler
iii) A single definite percentage passing each sieve for the mixed aggregate
iv) The individual gradings of the individual aggregate fractions, and the proportion of each
in the combined grading.
v) The results of tests enumerated in Table 7 as obtained by the Contractor
vi) Where the mixer is a batch mixer, the individual weights of each type of aggregate and
binder per batch.
vii) Test results of physical characteristics of aggregates to be used
viii) Mixing temperature and compacting temperature
While establishing the job mix formula, the contractor shall ensure that it is based on a
correct and truly representative sample of the materials that will actually be used in the work
and that the mixture and its different ingredients satisfy the physical and strength
requirements of these specifications.
Approval of the job mix formula shall be based on independent testing by the Engineer for
which samples of all ingredients of the mix shall be furnished by the contractor as required by
the Engineer.
Jacobs
Pages 12 of 21
HPCL, Mumbai
44LK5100
The approved job mix formula shall remain effective unless and until a revised Job Mix
Formula is approved. Should a change in the source of minerals be proposed, a
new job mix formula shall be forwarded to the Engineer for approval before the placing of the
material .
Plant trials permissible variation in job mix formula
Once the laboratory job mix formula is approved, the contractor shall carryout plant trials at
the mixer to establish that the plant can be set up to produce a uniform mix conforming to the
approved job mix formula. The permissible variations of the individual percentages of the
various ingredients in the actual mix from the job mix formula to be used shall be within the
limits as specified in Table 9.
Table 9
Permissible Variations from the Job mix Formula
Description
Permissible Variation
Base / Binder course
Wearing course
Aggregate passing 19mm sieve or larger
8%
7%
Aggregate passing 13.2mm, 9.5mm
7%
6%
Aggregate passing 4.75mm
6%
5%
Aggregate passing 2.36mm, 1.18mm, 0.6mm
5%
4%
Aggregate passing 0.3mm, 0.15mm
4%
3%
Aggregate passing 0.075mm
2%
1.5%
Binder Content
0.3%
0.3%
Mixing temperature
10C
10C
Once the plant trials have demonstrated the capability of the plant, and the trials are
approved, the laying operation may commence.
Mixing and transportation of mix clause 3.8.1 shall apply.
Spreading of mix shall be by self propelled paver capable of laying in uniform thickness and
maintaining required levels. The temperature of mix at the time of laying shall not be less
than 120C.
Rolling shall continue till the density achieved is 98% of marshal density and shall be
completed before temperature of mix falls below 100C.
MANUFACTURING AND ROLLING TEMPERATURE
Bitumen
Penetration
35
65
90
3.9
Bitumen
Mixing ( C )
160 170
150 165
140 - 160
Aggregate
Mixing ( C )
160 175
150 170
140 165
Mixed Material
( C )
170 Max
165 Max
155 Max
Rolling ( C )
Laying ( C )
100 Min
90 Min
80 Min
130 Min
125 Min
115 Min
Premix Carpet
Tack coat as previous shall be applied of 0.3 Kg/sq.m. Over prepared (shaped) bituminous
macadam base as required by engineer in charge.
Binder for premix wearing course shall be straight run bitumen complying with IS:73The
Premix carpet of 20 mm compacted thickness shall comprise of bitumen of 60/70 grade &
small sized aggregate which shall be premixed & laid . The aggregates used shall have water
absorption limited to max. of 1 percent. The qty of materials required shall be as in table
given below:-
Jacobs
HPCL, Mumbai
44LK5100
Pages 13 of 21
0.18 cu.m.
0.09 cu.m.
0.27 cu.m. per 10 sq.m.
Hot mix plant of appropriate capacity shall be used for preparation of mix material. The hot mix
plant shall have a separate arrangement for heating aggregate. The temperature of 150o C to
o
O
O
160 C & that of aggregate in range of 155 C to 163 C provided the difference in
temperature between the binder & aggregate at no time exceeds 14O C. Mixing shall be
through to ensure that a homogenous mixture is obtained in which all particles of the
aggregates are coated uniformly & discharge temperature of mix shall be between 130O C &
O
160 C. The mix shall be immediately transported from mixer to the point of use in suitable
vehicles or hand barrows. The vehicles employed for transport shall be clean & the mix being
transported covered in transit if so directed by engineer.
Rolling of layers shall be carried out using 10 T capacity smooth wheeled road roller before the
O
temperature of the mix falls below 100 C. The roller wheels shall be kept damp to prevent the
premix from adhering to the wheels. In no case fuel/lubricating oil be used for this purpose.
Excess use of water also shall be avoided. Joints along & transverse to the surfacing laid &
compacted earlier shall be cut vertically to their full depth so as to expose fresh surface which
shall be painted with a thin coat of appropriate binder before the new mix is placed against it.
Excessive rolling should be avoided.
3.10
Jacobs
Pages 14 of 21
HPCL, Mumbai
44LK5100
The mix shall be immediately transported from mixing plant to the point of use & spread
uniformly on the premix surface. Rolling shall be done using 10 T capacity smooth wheeled
road roller until the premix material is sealed completely. Excessive rolling should be avoided
Opening to traffic - The finished road surface shall be opened to traffic after minimum 24
hours period.
3.11
Cumulative % by wt. Of
total aggregate passing
100
90 100
35 51
24 39
15 30
9 19
38
Min. 5.0
65
TABLE 9
Property
Polishing
Water sensitivity
Test
Polished stone value
Retained Tensile strength
Specifications
Min. 55
Min. 80%
Jacobs
HPCL, Mumbai
44LK5100
Pages 15 of 21
8.2
2
4
75 blows on each of the two faces of the
specimen
35
See table 8 above
65 78
BITUMINOUS CONCRETE
Scope
This clause specifies the construction of Bituminous Concrete, for use in wearing and profile
corrective courses. This work shall consist of construction in a single or multiple layers of
bituminous concrete on a previously prepared bituminous bound surface. A single layers shall
be 25mm to 100mm in thickness. Bituminous concrete shall be done as per clause 509 of
MORTH specification.
Materials
Bitumen
The bitumen shall be paving bitumen of penetration grade complying to IS:73 and of the
penetration indicated in Table 11.
Coarse Aggregates
The coarse aggregates shall be generally as specified in Clause for DBM, except that the
aggregates shall specify the physical requirements of Table 10.
Fine Aggregates
The fine aggregates shall be all as specified in Clause for DBM.
Filler
Filler shall be generally as specified in clause for DBM, where the aggregates fail to meet the
requirements of the water sensitivity test in Table 10 then 2 per cent by total weight of
aggregate, of hydrated limit shall be added without additional cost.
Aggregate grading and binder content
When tested in accordance with IS:2386 Part 1 ( wet grading method ), the combined grading
of the coarse and fine aggregates and added filler shall fall within the limits shown in Table 11
for grading 1 or 2 as specified in the contract.
Jacobs
Pages 16 of 21
HPCL, Mumbai
44LK5100
Mixture Design
Requirements for the mixture
Apart from conformity with the grading and quality requirements for individual ingredients, the
mixture shall meet the requirements set out in Table 12.
The requirements for minimum per cent voids in mineral aggregate (VMA) are set out in
Table 8.
Binder Content
The binder content shall be optimised to achieve the requirements of the mixture set out in
Table 12 and the traffic volume as specified in the contract. The Marshall method for
determining the optimum binder content shall be adopted as described in the Asphalt Institute
Manual MS-2, replacing the aggregates retained on the 26.5mm sieve and retained on the
22.4mm sieve, where approved by the Engineer.
Job mix formula
The procedure for formulating the job mix formula shall be generally as specified in clause
for DBM and the results of tests enumerated in Table 12 as obtained by the Contractors.
Preparation of base
The surface on which the bituminous concrete is to be laid shall be prepared in accordance
with clause 501 and 902 of MORTH specs. as appropriate, or as directed by the Engineer.
The surface shall be thoroughly swept clean by mechanical broom and dust removed by
compressed air. In locations where a mechanical broom cannot access, other approved
methods shall be used as directed by the Engineer.
Table 10 Physical requirements for Coarse aggregate for
Bituminous Concrete pavement layers
Property
Cleanliness (dust)
Test
Grain size analysis (1)
Particle shape
Strength*
Polishing
Durability
Water absorption
Stripping
Water Sensitivity**
Specification
Max 5% passing
0.075mm sieve
Max 30% (Combined) (2)
Max 30%
Max 24%
Min 55
Max 12%
Max 18%
Max 2%
Minimum retained
Coating 95%
Min 80%
Notes
1) IS:2386 Part 1
6) IS:2386 Part 5
2) IS:2386 Part 1
7) IS:2386 Part 3
( the elongation test to be done only on non-flaky aggregates in the sample )
3) IS:2386 Part 4*
8) AASHTO T283**
4) IS:2386 Part 4*
IS : 6241
5) BS:812 Part 114
* Aggregate may satisfy requirements of either of those two tests
** The water sensitivity test is only required if the minimum retained coating in the stripping
test is less than 95%.
Jacobs
HPCL, Mumbai
44LK5100
Pages 17 of 21
1
2
19mm
13mm
50 65mm
30 45mm
Cumulative % by weight of total aggregate passing
100
79 100
59 79
52 72
35 55
28 44
20 34
15 27
10 20
5 13
28
5.0 6.0
100
79 100
70 88
53 71
42 58
34 48
26 38
18 28
12 20
4 10
5.0 7.0
65
65
Notes 1. The combines aggregate grading shall not vary from the low limit on one sieve to
the high limit on the adjacent sieve.
2. Determined by the Marshall method.
Table 12 Requirement for Bituminous Pavement Layers
Minimum stability ( kN at 60 deg. C )
Minimum flow ( mm )
Max. flow ( mm )
Compaction level ( no. of blows )
Percent air voids
Percent voids in mineral aggregates (VMA)
Percent voids filled with Bitumen (VFB)
Loss of stability on immersion in water at 60
deg. C ( ASTM D 1075 )
3.13
9.0
2
4
75 blows on each of the two faces of the
specimen
36
See table 8
65 75
Minimum 75 percent Retained strength
Jacobs
Pages 18 of 21
HPCL, Mumbai
44LK5100
the surface shall be allowed to cure overnight. Any unevenness noticed on the surface
shall be filled with screenings or binding material shall be lightly sprinkled with water &
rolled. No traffic shall be allowed till the WBM sets & dries out & then the bituminous
surfacing layers are laid. Levels shall be taken before & after laying layers.
2.0 Rolling :Rolling in case of road should commence from the edges/sides & proceeds to the center,
parallel to the centerline of the road, the overlap recommended being 1/3 of width of
drum. But in case of paving will depend on the camber needed.
3.0 Plants & Equipments:Required
Plant & Equipment like bitumen distributor, bitumen heating device
(mechanical sprayer or mechanical blower) , aggregate spreader( whirl spreader/vane
spreader/hopper spreader/self propelled spreader),roller for compaction, Template for
checking desired profile. Mixing of aggregate & bitumen shall be done in a central plant
or travelling plant taking care that the aggregate & bitumen for premix & seal coat has
been properly mixed prior to laying.
4.0 Weather precaution:The laying of layers shall be done in dry & clear weather. The laying of bitumen layers
shall be avoided in very hot climate.
5.0 Prime and Tack Coat:Prime coat shall be spray applied on all granular layers as per the details given in the
document before laying of any bituminous layers. Thereafter a tack coat as detailed shall
be applied before laying of subsequent bituminous layer.
Tack coat shall be spray applied to all bituminous surfaces, whenever the time taken to
lay the subsequent bituminous layer is more than 24 hours.
Jacobs
HPCL, Mumbai
44LK5100
Pages 19 of 21
APPENDIX- A
VERY BROAD SPECIFICATION FOR SOIL TO BE CONSIDERED AS CNS
MATERAIL
Sr.
No.
1
4
5
Property
Grain Size analysis
(i)
Clay
(ii)
Silt
(iii) Sand
(iv) Gravel
Consistency limits
(i)
Liquid limit
(ii)
Plastic limit
(iii) Plasticity index
(iv) Shrinkage limit
a) Swelling pressure when compacted to maximum dry
density corresponding to standard Proctor
compaction with zero initial compaction moisture
constant, for no volume change condition.
b) Swelling pressure when compacted to maximum dry
density corresponding to standard Proctor
compaction and initial compaction moisture
corresponding to optimum moisture content for no
volume change condition.
Clay minerals
Shear strength of compacted sample compacted to
maximum dry density correspond to standard Proctor
compaction and initial moisture content corresponding
to optimum moisture content, but sample tested on
saturation.
(a)
From unconfined compression.
(b) From consolidated undrained direct shear test.
Very Broad
Specification Range
15-25%
35-50%
30-40%
10%
30-50%
20-25%
10-25%
15% and above
Less than 0.1 Kg/cm
(10 KN/m)
Less than 0.05
Kg/cm
(5 KN/m)
Preferable Kaolinite
and illite.
Cu = 0.15-0.35 kg/cm
(15 to35 kN/m)
Jacobs
Pages 20 of 21
HPCL, Mumbai
44LK5100
APPENDIX B
ANTI-STRIPPING AGENTS USED FOR BITUMINOUS
MATERIAL AND MIXES
1.0
Scope
1.1
2.0
Anti-stripping agents are used for bituminous materials and mixes to ensure adhesion
between aggregates (hydrophilic in nature) and bitumen, even under submergence in
water. Prior approval of the Engineer shall be taken in respect of both qualitative and
quantitative use of a particular product.
Materials
2.1
The anti-stripping agents shall be fatty acid amines having a long hydrocarbon chain.
2.2
Physical and chemical Requirement : The anti-stripping agents shall conform to the
physical and chemical requirements as detailed in Table below.
SPECIFICATION FOR ANTI-STRIPPING COMPOUND
Sr.
No.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
2.3
3.0
Test
Appearance
Odor
Specific gravity 27C
Pour point C Maximum
Flash point (COC) Minimum
Water Content per cent Vol.
Maximum
Solubility in diesel oil (HDO or LDO) in
the ratio of 2.98 at 50C
Total base value mg KOH/g minimum
Nitrogen content per cent Wt.
minimum
Stripping value with bitumen
containing 1 per cent Wt. antistripping compound at 40C 24 hours
Under water coating test
Thermal stability at 163C 5 hours
Boiling water test per cent minimum
coating
Retained Marshall Stability per cent
minimum
Method
Visual
Smelling
IS : 1202 1978
IS : 1448
IS : 1448
IS : 1448
Limit
Liquid / Solid
Agreeable
0.860 1.03
42
150
1.0
Complete
IS : 6241 As given
at the end of
Appendix
- do - do -
No stripping
ASTM D 3625
200
7.0
Complete coating
Should not lose its
efficacy
95
75
Additive Dosage : The dosage shall be determined depending on the nature (stripping
value) of the aggregate and the size of aggregate. While the recommended minimum
Jacobs
HPCL, Mumbai
44LK5100
Pages 21 of 21
dose of anti-stripping agent for sprayed work is given in Table below, the actual dosage
shall be determined in the laboratory as directed by the Engineer.
TENTATIVE RECOMMENDED MINIMUM DOSE OF ANTI-STRIPPING AGENT
FOR SPRAYED WORK
Aggregate
stripping
value
0 - 25
25 50
50 - 100
3.2
4.0
Additive Dosage : The dosage shall be determined depending on the nature ( stripping
value ) of the aggregate and the percent voids in the mix. While the recommended
minimum doses for different types of bituminous premix materials in terms of voids
content given in Table below, the actual dosage shall be determined in the laboratory as
directed by the Engineer.
TENTATIVE RECOMMENDED MINIMUM DOSE OF ANTI-STRIPPING
COMPOUND IN BITUMEN PREMIX WORKS
Stripping value of
aggregate
0 25
25 50
50 100
4.2
Mixing Procedure During Construction : The required dose of the anti-stripping agent
shall be poured into the hot bitumen tank and allowed 15 to 30 minutes of circulation or
stirred to ensure a homogeneous mix. It is necessary to use a stable anti-stripping agent
or increase the dose according to expected degradation. Alternatively, the correct dose
shall be injected into the bitumen line by means of pump. The agent is fed into the
bitumen first before it is sprayed on the aggregate in the mix; thus, no separate mixing
time for mixing the agent with bitumen is required. In rolled asphalt and bitumen mastic
surfacing works, precoated chippings are pressed into the hard surface while the mix is
still hot to make the newly laid surface skid resistant. These chippings shall be precoated
with bitumen treated with anti-stripping compound.