CALCULATION OF BASE SHEAR (UBC-1997)

Location : Rancakusumba Substation


Seismic Zone Factor
Building inportance Factor
Soil Profile Type
Response Modification Factor
Acceleration-Dependent Seismic Coefficient
Velocity Dependent Seismic Coefficient
Total Of Building in Meter
Elastic Fundamental Period of Vibration
=0.0488 (_ )^(3/4)

Z
I
SD
R
Ca
Cv
hn
T

0.075
1.000
SD
5.500
0.120
0.180
38.280
0.751

Total Base Shear


=0.11 _

=0.11 _
=(_ )/
=( 2.5 _ )/

<

=(_ )/

<

=( 2.5 _ )/

0.013
0.044
0.055

Special Occupancy Structure


Stiff Soil Profile

2.5 _ )/

W
W
W