Professional Documents
Culture Documents
Fabrication of Piping Systems
Fabrication of Piping Systems
Quality of the work is easier to manage & maintain in a controlled environment. High
accuracies on specified tolerances will avoid rework at site.
Prefabricated Spools are the perfect answer to severe skill & labor shortage. Users do not
have to mobilize significant work force for fabrication of spools on site.
Prefabricated Spools will take lesser fabrication / assembly time, thereby avoiding time &
cost overruns.
Prefabricated Spools will be serviced under the strict vigilance of Third Party Inspection
Agencies, ensuring 100% adherence to required quality standards.
Weld less Induction Bends (as permitted by the client) would entail complete avoiding of
welding pipe sections using SR elbows, thereby bringing in significant cost savings in
welding, radiography of welding joints & material requirements.
Fabricating spools off site means less slag, abrasive dust, smoke & other contaminants
which are unacceptable in highly hygienic food processing & other industries.
...
The main disadvantage of making Pipe Spools
Of course, the making of pipe spools has tremendous benefits, but the biggest drawback is that
the spools will not fit on site.
This can have several causes, but often it is a misinterpreted isometric by the contractor, or a
faulty dimensions on a isometric.
One small mistake can result in a lot of extra work because e.g. multiple pipe spools must be
modified. That often means that pressure tests must be done again, x-rays of the welds must be
done again etc. etc..
Remark(s) of the Author...
Check dimensions (on Site), (in Field) etc.
If you see that on your isometric(s), basically you can not fabricate the pipe spool(s).
The engineer / draftsman means, that the piping contractor must determine the correct
dimensions in the field.
At the time of contract negotiations, you as contractor must be very alert to this often underrated
"insignificant" comments.
If not, you will "have to bring money" for a job where you just want to earn money.
If these things in advance not properly negotiated, a (sometimes high) conflict between
engineering company and contractor will arise during the implementation period.
What do you think who will win?
Field fabrication & Installation of Piping spools
Field fabrication and installation is exactly what it means. The pipe is fabricated on-site, either
directly at the place where it is mounted, or in a temporary accommodation in the field.
A number of factors will determine whether it is profitable to fabricate pipe on site:
Type of project, size and scope of the project, pipe size and material, accessibility of the
equipment, surface treatment after fabrication, weather conditions, availability of qualified
personnel, time available to do the job, etc..
Only raw material (pipe, fittings, valves, etc.) need to be shipped to the site location. This
is much easier to handle and store than multi-plane configurations of pre-fabricated pipe.
More efficient opportunity to fab around unexpected obstacles (structural steel, duct,
cable tray, etc.)
Weather is arguably the biggest deterrent. If the facility under construction is not enclosed
then protection from the elements will have to be provided.
When welding has to be done in conditions that are not environmentally controlled then
pre-heating will be required if the ambient temperature (not the metal surface
temperature) is 0 F or below.
In a new facility, as opposed to having to route piping through an array of poorly located
existing pipe and equipment, field fabrication of buttwelded pipe is not as efficient and
cost effective as shop fabrication.
Concerns about safety and efficiency when working in a facility while it is in operation in
advance of a turnaround or to begin advance work on a plant expansion.
Generally speaking, threaded, socketweld, grooved, and other proprietary type joints that do not
require buttwelding are field fabricated and installed. Buttwelding of small (bore), NPS 1 and
less, are very often field fabricated and installed because of the added risk of damage during
transport, in pre-fabricated form, from the shop to the site.
Pipe rolling machine in Field Fabrication
In an existing plant in operation, the conditions are totally different as during construction of a
new plant.
In general, for all activities work permits are necessary. For activities with open flames (welding,
cutting etc.) and also for combustion engines, so called Hot-Permits are required.
The contractor often can not determine when a scheduled task can be performed, because it
depends on plant operators, who should or should not give permission for a particular job.
In short, in an existing plant in operation, high risks are present, and the contractor can probably
scheduled tasks do not always perform according to his planning.
In order to allow for these inevitable deviations between the drawing dimensions used to
fabricate the vessel, set the vessel, and install the pipe assembly, and the actual installed location
of the connecting points, a field closure piece, or two, will be required for that final adjustment.
The field closure piece is a designated section of the pipe assembly in which a field weld has
been indicated. The section with the field closure weld would be the length required to agree
with that indicated on the design drawing, plus an additional 100 to 150 mm (more or less
depending on fabricator's comfort level with the equipment locations). What this does is allow
the field to make the final determination in the adjustments when connecting to fixed equipment.
Field installation of Pipe Spools
...
Environment
The environment is only a factor when work has to be done in an open-air structure or other
outdoor installation (tank farm, pipeline, pipe rack or yard piping, etc.). Working in an open air
structure will require protection from the elements (rain, snow, wind, cold, etc.). There may
additionally be a requirement to work in elevated areas on scaffolding and otherwise. All of this
can have a potential impact on safety and efficiency.
Pipe rack installation consists mainly of straight runs of pipe, and will not necessarily have a
requirement or need for pre-fabrication. That is, unless it is pre-fabricated as modular skid units.
Depending on the project it could be cost effective on an overall strategic basis to modularize the
pipe rack, steel and all.
The big advantage to shop fabrication is the controlled environment in which it's done. This
includes the Quality Control aspect, better equipment (generally speaking), a routine
methodology of how a piece of work progresses through the shop, and better control, through a
developed routine, of required documentation.
Minimum Length & Spacing - Welded Nozzles Minimum Length & Spacing without Reninforcement
Center of Nozzle
O.D. of Run
to
to
End of Run
End of Nozzle
A
B
2
114
76
3
127
89
4
152
102
5
178
114
6
203
127
8
254
152
10
305
178
12
356
203
14
381
216
16
432
229
18
483
254
20
533
279
24
610
305
Table 1 - 3
Minimum Length & Spacing with Reninforcement
NPS
of
Nozzle
NPS
of
Center of Nozzle
to
O.D. of Run
to
O.D. to O.D.
of Nozzle
C
76
89
102
114
127
152
178
203
216
229
254
279
305
O.D. to O.D.
of Nozzle
End of Run
End of Nozzle
A
B
2
152
114
3
178
127
4
203
140
5
241
152
6
279
165
8
356
203
10
432
241
12
508
279
14
559
305
16
635
330
18
711
356
20
787
381
24
914
406
Table 2 - 3
Minimum Length & Spacing Integrally Reinforced
Nozzle
NPS
of
Nozzle
2
3
4
5
6
8
10
12
14
16
18
20
Center of Nozzle
to
End of Run
A
140
152
178
203
254
305
356
406
432
483
533
584
O.D. of Run
to
End of Nozzle
B
MFR
Standard
C
152
178
203
241
279
356
432
508
559
635
711
787
914
O.D. to O.D.
of Nozzle
C
76
76
89
102
127
152
178
216
229
254
279
305
24
660
Table 3 - 3
356
Notes:
1. MFR = Manufacturer
2. All nozzle welds should be checked for compliance with the applicable code
requirements.
3. It is preferred that multiple branch openings of in-line nozzles be spaced so that their
reinforcement zones do not overlap. If closer specing is necessary, the reinforcement
requirements of the applicable construction code shall be met.
4. Some configurations of integrally reinforced nozzles in combination with certain header
sizes may present a problem in the radiographic examination of the attachment weld due
to inability to meet the geometric unsharpness requirements of the construction code.
5. Where attachments such as flanges, fittings valve and pipe insulation are involved,
minimum dimensions tabulated may have to be increased to allow for required
clearances.
6. In special cases, it may be possible to reduce the dimensions given in the tables. Such
design should then be submitted to the fabricator for individual considerations, as close
spacing may involve additional shop operation to prevent, or correct distortion.
7. Integrally reinforced nozzles are considered to be the commercially available types.
8. In cases of different nozzle diameters, dimension C, should be determinded on the basis
of the larger of the two of adjacted nozzles.
Certain materials and combinations of nozzle and header pipe size and wall thickness together
with multiple branch openings welded to a header may result in distortion of the header pipe.
In most piping systems there are components such as valves, castings, heavier header sections,
and equipment nozzles which are welded to the pipe.
In such instances the heavier sections are machined to match the lighter pipe wall and the
excess thickness tapered both internally and externally to form a transition zone.
Limits imposed by the various codes for this transition zone are fairly uniform.
The external surface of the heavier component is tapered at an angle of 30 maximum for a
minimum length equal to 1 times the pipe minimum wall thickness and then at 45 for a
minimum of 1 times the pipe minimum wall.
Internally, either a straight bore followed by a 30 slope or a taper bore at a maximum slope of 1
to 4 for a minimum distance of 2 times the pipe minimum wall are required.
The surface of the weld can also be tapered to accommodate differing thickness. This taper
should not exceed 30. It may be necessary to deposit weld metal to assure that these limits are
not violated.
Below some tables with acceptable design for unequal wall thicknesses acc to ASME B31.8
Internal Offset
External Offset
Combination Offset
NOTE:
(1) No minimum when materials joined have equal specified minimum yield strengths.