LABOR ESTIMATE
1. CONCRETING OF PLAIN FLOORING:
2 MEN POUR 1.2 CU.M. CONCRETE/ DAY
2. CONCRETING OF REINF. FLOORING:
2 MEN POUR 0.84 CU.M. CONCRETE/ DAY
3. CONCRETING OF COLUMN AND BEAM:
2 MEN POUR 0.50 CU.M. CONCRETE/ DAY
4. FINISHING OF FLOORING (ROUGH)
2 MEN FINISHES 72 SQ.M./ DAY
5. FINISHING OF CHB JOINTS:
2 MEN FINISHES 420 PCS./DAY
6. PLASTERING OF CHB:
2 MEN PLASTERS 8 SQ.M./DAY
7. LAYING OF CHB:
2 MEN LAY 100 PCS./DAY
8. LAYING OF GLAZED TILE 4 X 4
2 MEN LAY 100 PCS./DAY
TYPE OF WORK
CAPABILITY
22 PCS.
b. CEMENT FINISH
28 SQ.M.
a. ERECTING FORMS
1.85 SQ.M
b. REMOVING FORMS
1.86 SQ.M.
MANHOURS
CARPENTER
LABORER
TOTAL
0.70
0.40
1.10
1.50
0.65
2.15
0.75
0.40
1.15
1.10
0.72
2.92
1.21
.90
1.99
1.35
0.90
2.25
7. COLUMNS
1.22
0.80
2.02
1.90
1.22
3.12
9. ELEVATED SLABS
1.15
1.16
2.31
0.70
0.90
1.60
(WORD SHORES)
10. ELEVATED SLABS
(ADJUSTED SHORES)
CONCRETING
MANHOURS
ITEMS
LABORER
CARPENTER
OPTR.
OILER
TOTAL
0.05
0.05
5.20
5.10
-CHUTE
0.75
- BUGGLES
0.98
0.05
0.80
0.98
5.10
-CHUTE
0.86
- BUGGLES
1.14
0.05
0.07
0.05
5.20
0.93
1.14
5.10
-CHUTE
0.90
- BUGGLES
1.48
0.05
0.05
0.07
5.20
0.97
1.48
5.10
0.05
0.05
-CHUTE
0.90
- BUGGLES
1.48
1.48
8.51
8.51
0.07
5.20
0.97
COLUMNS
-BY HAND
AND PULLEY
-PORTA LIFT
6.35
0.08
0.08
6.51
0.16
0.16
2.34
12.71
12.71
AND PULLEY
-PORTA LIFT
10.60
0.08
0.08
10.76
1.22
4.89
4.00
0.47
4.47
2.13
8.51
0.47
4.47
- RUBBED CONCRETE
4.00