ASSIGNMENT

DASUN ISHARA MAHABADUGE

NG/HNDQS/09/42 |

Contractual procedure

1
Contractual procedures

Acknowledgement
I would like to express my deepest appreciation to all those who provided me the possibility to
complete this report. A special gratitude I give to my Contractual Procedure lecturer Major
(Eng.) Vajira Edirisinghe, whose contribution in stimulating suggestions and encouragement
helped me to finish the report successfully.
Furthermore I would like to thanks to Finance CO. LTD who gave the tender documents to
complete this assessment.

HND in QS

2
Contractual procedures

Contents
Task 01......................................................................................................................... 3
Introduction.................................................................................................................... 3
1.1 Parties involved.......................................................................................................... 4
Describe the roles and contractual responsibilities of the parties...................................................4
1.2 Process.................................................................................................................... 7
1.2 Procument selection..................................................................................................... 8
1.4 Contractual Arrangements........................................................................................... 10
Compare the main contractual arrangements of the contract......................................................10
1.5 Procument and Contractual issues.................................................................................. 12
1.5.2. Describe how those procurement issues are addressed using the form of contract of the contract. 14
1.5.3 Differentiate international methods of procurement, Outlining their advantages and disadvantages
................................................................................................................................. 18
1.6 Time, Cost and Quality Management.............................................................................. 26
1.6.1 Compare the projects planned programme schedule with the actual. Evaluate the implication of
begin ahead of the programme or behind the scheduled time for completion of the contract...............26
1.6.2 Compare the project costs in the context of pre-contract, tender and final account stages of the
contract....................................................................................................................... 28
1.6.3. Describe how quality is defined and the measures that are available within this contract to assume
its compliance............................................................................................................... 29
1.6.4. Analyze other clauses making reference to form of contract for their interpretation..................31
1.7 Other Stakeholders................................................................................................. 33
1.7.1 List the different organizations involved in the construction industry and evaluate the purpose and
activities of them on this contract....................................................................................... 33
1.7.2 Analyze the contractual differences between nominated and other types of contractors and evaluate
the forms of contracts regarding suppliers.............................................................................35
Task 2......................................................................................................................... 38
Describe the needs of clients in both public and private sectors...................................................38

HND in QS

3
Contractual procedures

Task 01
Introduction
Our project is the Proposed Housing Scheme at Seeduwa village Seeduwa. In this project these
are the basic details of the construction project.
Scope and duration of the project
Construction of house (9 calendar month)

The Location
Seeduwa

The principle parties involved


Client
ASST. General Manager
THE FINANCE CO.LTD,
REAL ESTATE DIVISION,
NO.97,
HYDRE PARKCORNR,
COLOMBO 2
Consultant
T.SENAKA PEIRIES A.IA. (S/L)
CHARTED ARCHITECT,
10A, MALLIKA MAWATHA,
TEMPLER ROAD, MT.LAVINIA

Contractor
HND in QS

4
Contractual procedures
CSK ENTERPRISES (PVT) LTD
236/4, JUBILEE POST,
KOTTE ROAD,
NUGUGODA

Initial contract sum


Rs. 2,122,789.83
Finale contract sum
Rs. 2,210,947.80
Procurement method
Traditional method

Form of contract - SBD 02

1.1 Parties involved


Describe the roles and contractual responsibilities of the parties
Client
Client is the primary part in this procedure. Since each venture is begins with a need of
undertaking. At the point when discussing the customers part. Principle attributes of his part are

Being in charge of the execution of the task from the underlying thought to usage

choosing the players required in all phases from outline through development to long
haul administration

HND in QS

5
Contractual procedures

Ensuring that the necessities of building clients/clients are met

Ensuring that the pertinent authorizations are secured (arranging and so forth) in
organization with the experts selected to the task

May likewise be agent and possible proprietor

It justifies saying that in various advantage trade develops the piece of client may in like manner
be part. Endeavors can have unmistakable accomplices and funders each of whom will have
various essentials for being required amid the time spent change and advancement. It may be
valuable to expressly consider the recommendations for the endeavor of who handle the parts of
"Client" and "Supervisor" at the improvement stage.
The client has a key part in the process since they will name directs, endorse work to happen,
agree costs and timetable and agent specialists to the endeavor. Some expects will have a
gathering affiliation or social event as the client however may encounter issues with the piece of
Employer as a result of its liabilities.
Range or structures toward the end of advancement, there ought to be a specific trade on who
will handle the Client and Employer parts in the midst of the system.
Consultant
Consultant is working in the organization board in the development. Consultant might be a
designer or an architect. Some expert groups have every one of them. Counting engineers
draftsmen cost advisor. There's an assertion amongst specialist and the proprietor which contains
obligations of the expert.
Consultant is the aide of the development venture. In the event that customer doesn't have much
involvement in development field. Specialist is the stand out he can trust. There are couple of
things a customer will anticipate from an expert.

Inspecting the contractual worker

Develop the configuration with temporary worker

HND in QS

6
Contractual procedures

Preparing the delicate records and other authoritative reports

Contract organization.

Contractor
Contractor is the person who manages a construction and the person who employs new workers.
Hes the one who controls the construction and the person who owns the constructing business.
There are such a large number of obligations of a contractor. He holds the responsibility of
finishing the work before the given time. So he needs to manage his laborers furthermore he is
the person who arranging how to bring out the task through all guidelines and directions. He
generally ought to consider about those laws and directions which relevant to development
ventures.
Quantity surveyor
The quantity surveyor is the individual in charge of making sense of exactly what a development
venture is going to cost. They have different parts as well, particularly ensuring that development
expenses and generation are overseen as effectively as could reasonably be expected.

Keep the project on time

Keep the project ongoing with the budget

Managing the all financial records of the site

Ensuring that development expenses and creation are overseen as proficiently as could
reasonably be expected

Site engineer
A site engineer is in charge of utilizing their structural building foundation to arrange and direct
different development endeavors in a wide range of territories of this field. They will apply civil
engineering standards to guarantee that structures are built in the most secure, sturdiest way.

Supervising all workers and junior officers

Checking drawings and keep the work ongoing

Analyze the areas to apply engineering methods

Preparing record drawings and technical reports

HND in QS

7
Contractual procedures

Quality control

Project manager
The role of the project manager encompasses many activities including:

Planning and Defining Scope

Activity Planning and Sequencing

Resource Planning

Developing Schedules

Time Estimating

Cost Estimating

Developing a Budget

Documentation

Creating Charts and Schedules

Risk Analysis

1.2 Process
Determine the sequence of events of this contract from design to construction process to
meet the requirements of the client
Design / pre construction stage
Making a design Brief selecting the consultants
After get the prerequisites of the customer, Architecture must affirm the necessities before
outlining and next stride is recognizable proof of the acquisition strategy and its methods that
appropriate to the venture.
Design concept implementation of design brief
Planning of reasonable configuration - It implies as indicated by the customer's necessities
engineering will outline an applied outline of the building. Before entering the arrangement of
drawings must survey the acquisition course that chose one is reasonable for that.
Design development

HND in QS

8
Contractual procedures
Improvement of applied plan and changing the outline as indicated by the customer's
prerequisites done in this stage. Submitting set of compositional drawings is done in this Design
Development stage.
Technical design
Specialized drawings are produced by building drawings. Specialized drawings mean auxiliary
drawing of the building, plumbing arranges, electrical plans and fire wellbeing arranges.
Production information
In this stage must get approval from the municipal council and the other authorities.
Tender document
In this stage preparing the BOQ and other tender documents, selecting appropriate tender type
and calling for tenders are done.
Mobilization
This mean hand over the project to the particular client.

Construction stage
Construction stage has two main processes
1. Substructure
In the substructure following events are done in a sequence
Site investigation
Site clearance
Excavation
Formwork
Laying of foundation
2. Superstructure
In the superstructure following events are done
Form work
Structural frame
Walls
Installation of doors and windows
HND in QS

9
Contractual procedures

Installation of building services


Roof slab
Steel roof frame
Roofing
Ceiling
Roof plumbing

1.2 Procument selection


Analyze the Selection of procument method depending on different project variables of the
project
In the early stages of the project, the Client should be developing the Procurement Strategy for
the project in consultation with the PM and the Design Team. This decision requires to be made
in consideration of the objectives of the project, and will vary from project to project.
There are 3 types of procument routes in construction industry.
1. Traditional
2. Design and build
3. Turnkey
Risk distribution

HND in QS

10
Contractual procedures
Whilst investigating the most appropriate Procurement Strategy for the projects the Client must
consult with the PM and Design Team. They will have invaluable input and expertise to make in
making the final decision.
Different project variable
In the early stages of the project, the Client should be developing the Procurement Strategy for
the project in consultation with the PM and the Design Team. This decision requires to be made
in consideration of the objectives of the project. When the selecting a procument route there
some facts to consider. As following:

Project Size

Client Type

Time

Cost

Quality

Accountability

Certain of Project Objectives

Market Conditions

Risk.

Asset ownership.

Financing

In this project (Proposed Housing Scheme at Seeduwa Village Seeduwa) the client has selected
traditional procument route to complete the project. In this method client has to appoint a design
team and initiates with construction process.
The design is completed fully before the tender process commences. It affords the Client a great
deal of control over the quality, specification and cost, however the timescale is lengthened to
achieve the completion of the design, and the Client maintains the risk in terms of the
Consultants Design and any unforeseen items e.g. ground conditions, as well as failing to benefit

HND in QS

11
Contractual procedures
from the contractors input on build ability by appointing the Contractor once the design is
completed.
As the contractor has no responsibility for the design, the Client is responsible for any mistakes
or omissions in the design. Although, some risk is shared with the contractor the majority of risk
is taken on by Client and the success of Design Team and the contractor.
1.4 Contractual Arrangements
Compare the main contractual arrangements of the contract
Open Tendering
In open tendering anyone allows to submit a tender to supply required goods or services. That the
contract is being tendered generally an advert will be placed giving notice. To submit a tender
offering an equal opportunity to any organization. This sort of pre-qualification processes not the
same as selective tendering.
Selective Tendering
According to the Selective Tendering only invited suppliers can be submitted their tenders. There
is a pre- selected list which is called by the client. When the selected list preparing by the
particular client consider about the size nature and complexity required. They might then be
asked if they would be interested in tendering for the contact, and then based on the responses
received. Finally client will select a tender by considering the price and quality and negotiations
entered into.

Negotiated tenders
In negotiated tendering process client and consultant considered and decided which contractors
are the best suits for types of construction work. Trusted contractors invited to bid for
construction project by mail or direct contact. After get their bid determine contractors keenness
and possible contribution to the construction team. Negotiated tenders mostly use to maintenance
project or incomplete projects.
HND in QS

12
Contractual procedures
Serial tendering
This types of tender contractor using to submit costs for carrying out work usually not against a
particular project but against sample Bills of Quantity, Works Schedule, or price for a sample
structure in the knowledge that others of a similar nature will be undertaken. The rates given in
such documents will form the basis of costing for future work undertaken, which will be
measured and valued by both parties to the contract.
The most common types of construction contracts used in the construction industry include:
1. Unit price contract This contract type is based on anticipated quantities of items which are
counted in the project in addition to their unit prices. The final price of the project depends
upon the quantities required to carry out the work. Generally, this contract is suitable only
for construction and supplier projects which involve accurate identification of different
types of items, but not their numbers, in the contract documents.

2. Lump sum contract Under this contract type, the engineer or contractor agrees to perform
the specified and described project for a fixed price. This type of contract is also referred to
as a Fixed Price Contract and is very often used in engineering contracts. A Lump Sum or
Fixed Price contract is appropriate where scope and schedule of the project are defined
sufficiently thus allowing the contractor or engineer to estimate the costs of the project.

3. Cost plus contract The cost plus contract is an agreement which involves the buyers
consent to pay the complete cost for material and labor in addition to the amount for
contractor overhead and profit. This contract type is favored where the scope of work is
highly uncertain or indeterminate in addition to the types of labor, material, and equipment
being similarly uncertain in nature.

4. Incentive contracts The incentive contracts feature compensation based on the contracting
and/or engineering performance in accord with an agreed target schedule, quality, and
budget. Incentive contracts commonly fall into one of two common categories: Fixed Price
Incentive Contracts and Cost Reimbursement Incentive Contracts.
HND in QS

13
Contractual procedures
5. Percentage of construction contracts- This contract type is common for engineering
contracts. The compensation involved in these contracts is based on a percentage of the cost
of construction.
In this Proposed Housing Scheme at Seeduwa village Seeduwa Consultant is Mr.
T.SENAKA PEIRIES and Contractor CSK ENTERPRISES (PVT) LTD. Selective
tendering is the process used in this project.

1.5 Procument and Contractual issues


1.5.1. Explain and evaluate the issues associated with procument and contractual
procedures of the contract.
Using procurement method it will speed up the delivery of the project by merging activities.
Procurement system is an organizational system that assigns specific authorities &
responsibilities to people & organization. It also defines the different elements in the
construction of a project. The procurement methods play a major role in defining as well as
shaping contractual and work relationships between parties involved.
In this project they used traditional procurement method & lump sum contract type proposed
housing scheme.
When considering about the procurement methods, so that the procurement types cover various
aspects such as,

How are the funds to be obtained

How is design to be carried out

How is construction/production to be arranged

Who is to have the managerial role to oversee or supervise the project

Who is to use the finished building/product

These aspects cant be controlled when we not manage the project. Before selecting an
appropriate procurement method the Clients must analyze their objectives of the project and

HND in QS

14
Contractual procedures
based on their needs the procurement choice might differ. So that issues can be arise when we
not manage these aspects.
Before arising the issues the parties who are involve in a project must be consider about the,

The nature of the project

The scope of the works

Measure of control by the Client

Accountability

Start and completion times

Assessment of risks
(Ashworth, 2013)

There are some sources can be identify to arise the issues in procurement methods.

project size
Small size projects are not really suited to the more elaborate forms of contractual
agreements, since such procedures are likely to be too difficult & not cost effective.

costs inclusive of the design


Open tendering will generally secure for the client the lowest possible price from a
contractor. This is the evidence that competition helps to reduce costs through efficiency
& lowers the price to the client.

time from brief to handover


The time available will also influence the type of construction technique which might
be used. The majority of the employers, once they have made the decision to build,
want the project to be completed as quickly as possible.

Accountability
Accountability is interlinked with finance and an emphasis on paying the smallest price
for the completed project. Accountability factors to be consider such as, contractor
selection, contractual procedure, value of money.

HND in QS

15
Contractual procedures

design, function and aesthetics

quality assurance

organization and responsibility

project complexity

Use of evaluate the issues in procurement & contractual procedure.

To establish a clear strategic direction

To deliver best value by reducing budget expenditure and providing more for less as
part of continuous review and improvement

Increase the proportion of the Councils spend against contracted and approved
suppliers

RISKS& ISSUES ASSOCIATED WITH PROCUREMENT


Claims and payments made on early accomplishments were bloated; the contractor
eventually abandoned the project
Unnecessary work items
Incorrect deductions of retention from progress payments due to failure to validate
conformance with project schedule
Advance payment not recouped or not fully recouped
Bidding Documents were not issued according to the required schedule
Contract awarded to a contractor who failed to pay taxes
Not allowed enough time for procurement procedures when developing project
Especially in this contract based on the measure & pay method so Payment is made for
quantities of work completed and measured during the month. These contracts are based
on drawings & prices. The contractor can claim additional payment for any changes in the
work content. So Tender price is usually increased by variations and claims.
HND in QS

16
Contractual procedures
1.5.2. Describe how those procurement issues are addressed using the form of contract of
the contract.
Contract management
The purpose of contract management is to ensure that all parties to the contract fully meet their
respective obligations as efficiently and effectively as possible, delivering the business and
operational outputs required from the contract and providing value for money. It also protects the
rights of the parties and ensures required performance when circumstances change.
The key clauses in any construction contract are those which impact on:
Time

Cost

Quality

The clients of the construction industry are primarily concerned with quality, time and cost and
yet the majority of construction projects are procured on the basis of only two of these
parameters, namely time and cost.
Time cost quality in traditional procurement method
Time/Certainty of Time

Not the fastest of methods.

Desirable to have all information at the tender stage.

Consider two stages or negotiated tendering.

Certainty of cost

Certainty in cost before commitment to build.

Clear accountability and cost monitoring at all stages.

Quality

Comprehensive design sets out quality standards Contractor is wholly responsible for
achieving quality on site

Under the terms of the particular contract, the construction manager was described as being the
only person on the project with access to all of the information and the various programmes. He
was the only available person who could make an accurate report to the Client at any one time,
of both the current status of the Project and the likely effects both on timing and on costs.

HND in QS

17
Contractual procedures
The contractor's main obligation under any construction contract is of course the construction
and completion of the works within the specified time for completion and in accordance with the
contract. Its other obligations under the Red and Yellow Books include:

Fitness for purpose ensuring that its design will meet the employer's requirements.

Design responsibility.

Carrying out the works in a proper and workmanlike manner with properly equipped
facilities and non-hazardous materials.

Providing those facilities and choosing those materials.

Responsibility for method of working.


The contractor also has an obligation to perform certain administrative and other functions to
facilitate performance, including providing information needed for the execution and completion
of the works and the issuing of notices including for events increasing cost or completion time.
The effective administration of a FIDIC construction contract is essential to ensure that time and
money claims are protected. It is important to write notices in clear and unequivocal terms do
not hint or insinuate. Keeping effective records will assist contractors and employers to prove
their entitlements and enable both parties to accurately ascertain their positions in the event that a
dispute arises.

Contractor's claims
A key obligation under the Red and Yellow Books is the requirement to serve notice in respect of
a claim for an extension of time or additional payment. The contractor must give notice of its
intention to claim as soon as possible and no later than 28 days after the contractor becomes
aware, or should have become aware, of an event. It must then submit its fully detailed claim
within 42 days of becoming aware of an event or circumstance that gives rise to a claim.
Variations and adjustments
Using the Red and Yellow Books, a variation for changes to the works can arise by:

An employer's instruction.

An employer's request for a proposal.

A contractor's 'value engineering' proposal.

HND in QS

18
Contractual procedures
Variations may have an adverse impact on the contract or on the guarantees in place for the
project, for example through a reduction in the safety or suitability of the works. This should be
monitored and flagged up immediately. A contractor could have liability even where it is simply
following the engineer's instructions.
A contractor is obliged to comply with the employer's request for a variation unless it cannot
readily obtain the necessary goods required for that variation.
Delay and extension of time
The contractor will be liable for damages if the actual completion date of the works occurs after
the agreed completion date unless the delay is caused by a matter for which an extension of time
is available and the contractor complies with the notice and other requirements under the
contract.
The contractor may be entitled to an extension of time where there is:

A variation or additional work instructed.

Exceptionally adverse weather.

Unforeseeable shortages in the availability of personnel or goods.

Delay caused by the employer.

A cause of delay under any other clause in the contract.

Unforeseeable delay caused by complying with public authority procedures.


The contractor must strictly comply with the notice requirements under the contract, including
giving all necessary information required in relation to the claim. Note that minutes of a meeting
or a contractor's progress report are unlikely to constitute proper notice.
The importance of record-keeping
Keeping adequate records is essential to:

Establish entitlements to money and time.

Defend subcontractor claims.

Comply with the contract's reporting obligations.


Decide at the outset how and what records should be kept, ensuring of course that this also
complies with the contract.

HND in QS

19
Contractual procedures
Compare with the procurement method used for this project & advice on changes which will
make the contract more efficient.
In this construction project parties are agreed to proceed with the lump sum contract in
traditional procurement method. The contractor undertakes to carry out a defined amount of
work in return for an agreed sum. This can be a fixed amount not subject to recalculation, in
which case there would be no opportunity for the employer to make variations. Lump sum
contracts might be less appropriate where speed is important, or where the nature of the works is
not well defined. Other forms of contract that might be more appropriate include measurement
contracts (used where the works can be described in reasonable detail, but the amount
cannot), cost reimbursement contracts (used where the nature of the works cannot be properly
defined at the outset, often used where an immediate start on site is required).
Disputes under FIDIC Red and Yellow Book contracts should be referred to a Dispute
Adjudication Board (DAB). A DAB can be created at the start of the project or when a dispute
occurs. It is an informal process which encourages party involvement and recognizes the need
for speed. The contracts provide that a DAB's decision will become final and binding 28 days
after it is issued if the parties do not give a notice of dissatisfaction.
Where a notice of dissatisfaction is given, the parties are obliged to attempt the amicable
settlement of their disputes.

1.5.3 Differentiate international methods of procurement, Outlining their advantages and


disadvantages
What is Procurement?
Procurement describes the merging of activities undertaken by the client to obtain a
building.
Procurement Methods Can be classified as:
1) Traditional procurement (Separated & corporate system)
2) Design & Build procurement (Integrated system)
3) Management procurement
Traditional Procurement Method
In the traditional approach, the employer accepts that design work will generally separate from
construction, consultants are appointed for design and cost control, and the contractor is
responsible for carrying out the works. This responsibility extends to all workmanship and
materials, and includes all work by subcontractors and suppliers. The contractor is usually

HND in QS

20
Contractual procedures
appointed by competitive tendering on complete information, but may if necessary be appointed
earlier by negotiation on the basis of partial or notional information.
There are three types of contract under the traditional procurement method:
1. Lump sum contracts - where the contract sum is determined before construction starts, and the
amount is entered in the agreement.
2. Measurement contracts where the contract sum is accurately known on completion and after
re-measurement to some agreed basis.
3. Cost reimbursement where the contract sum is arrived at on the basis of the actual costs of
labour, plant and materials, to which is added a fee to cover overheads and profit
Lump Sum Contract
The contractor undertakes to carry out a defined amount of work in return for an agreed sum.
This can be a fixed amount not subject to recalculation, in which case there would be no
opportunity for the employer to make variations. The sum is likely to be subject to limited
fluctuations, usually to cover tax etc changes not foreseeable at the time of tendering. The sum
may be subject to fluctuations in the cost of labour, plant and materials the so called
fluctuations provision. Recovery may be use of a formula, or by checking invoices.
Advantages

Less financial risk to Employer.

High financial risk to Contractor.

Minimum supervision related to quality & schedule.

Contractor is motivated for earlier completion and better performance.

Disadvantages

Changes are difficult and costly.

Design to be finalized prior to bidding.

Each project is unique.

Bidding is expensive & lengthy.

Contractor may include high uncertainty within each Schedule of Value item.

Measurement contracts

HND in QS

21
Contractual procedures
Measurement contracts are also referred to as re-measurement contracts. This is where the
work which the contractor undertakes to do cannot for some good reason be accurately measured
before tendering. The presumption is that it has been substantially designed, and that reasonably
accurate picture of the amount and quality of what is required is given to the tenderer. Probably
the most effective measurement contracts, involving least risk is to the employer, are those based
on drawings with approximate quantities.
Advantages

Early project start possible.

Flexibility, changes can be adopted as the project is carried out.

Complete design definition not required.

Suitable for competitive bidding.

Disadvantages

Final cost can be different from the contract sum

Can lead for conflict

Additional site staff needed for quality control

Cost reimbursement
These are sometimes referred to as Cost Plus contracts. The contractor undertakes to carryout
an indeterminate amount of work on the basis that they are paid the prime or actual cost of
labour, plant, and materials. In addition, the contractor receives an agreed fee to cover
management, overheads and profit.
Hybrids of the cost reimbursement contracts include:
Cost-plus percentage fee the fee charged is directly related to the prime cost. It is
usually a flat rate percentage, but it can also be on a sliding scale. However, the

HND in QS

22
Contractual procedures
contractor has no real incentive to work at maximum efficiency, and this variant is only
likely to be considered where the requirements are particularly indeterminate precontract.

Cost-plus fixed fee The fee to be charged is tendered by the contractor. This is
appropriate provided that the amount and type of work is largely foreseeable. The
contractor has an incentive to work efficiently so as to remain within the agreed fee.

Cost-plus fluctuating fee The fee varies in proportion to the difference between the
estimated cost and the actual prime cost. The assumption is that as the latter cost
increases, the contractors supposed inefficiency will result in a fee which decreases. This
approach depends upon there being a realistic chance of ascertaining the amount and type
of work at tender stage

Key points to consider with traditional procurement


A traditional lump sum contract requires the production of a complete set of documents
before tenders are invited. Adequate time must be allowed for this.
The traditional procurement method assumes that design will be appointed by
consultants, and it does not generally imply that the contractor has any design
obligations. If this is to be the case, express terms should be included in the contract.
As the employer appoints consultants to provide advice on all matters of design and cost,
they thereby retain total control over the design and quality required.

HND in QS

23
Contractual procedures
The contractor depends heavily upon the necessary information and instructions from the
architect being issued on time. There is a risk of claims if they are delayed.
The employer decides which specialist firms the contractor is to use, although the
contractor may require certain safeguards relating to performance.
All matters of valuation and payment are the responsibility of the employers consultants.
If it is impossible to define precisely the quantity or nature of some of the work, it is still
possible to adopt a traditional method on the basis of approximate quantities, provisional
sums, or cost reimbursement. However, this is less than a perfect solution: the fuller and
more accurate the information, the nearer to the relative safety of the lump sum approach.
Traditional Procurement Method
Advantages

Disadvantages

Liability due to competitive selection

The process will take more time to


produce the full contract
documentation required

At the award of the contract price


certainty

Comparing to the other procurement


types, the overall project duration can
be longer

If there are any variations to the


contracts, they are comparatively
easy to organize and manage

The Contractor cannot input any


ideas into the design or in to the
planning of the project

Low Tender Price

Risk of design errors lies with the client

Design & Build procurement


Design and Build comes in various forms but is typified by the contractor taking both design
and construction responsibility. In integrated D&B contracting the contractor develops the design
and constructs the building based on a set of requirements provided by the employer. In contrast,
novated D&B contracting is closer to the traditional model in so far as the employer's design
team develops the design but is then novated to the contractor who takes the design
responsibility and then constructs the building. "Turnkey" or EPC contracts are a type of D&B
contract but Turnkey and D&B are not synonymous.
HND in QS

24
Contractual procedures
Design and construct methods offer certainty on the contract sum and bring cost benefits. The
close integration of design and construction methods and the relative freedom of the contractor to
use their purchasing power and market knowledge most effectively can provide a client with a
competitive price.
A number of variations of design and construct exist, which include

Direct in this case no competition is obtained in tenders. Some appraisal of the possible
competitors may be made before tendering but only one tender is obtained.

Competitive tenders are obtained from documents that are prepared to enable several
contractors to offer competition in designs and in prices.

Develop and construct consultants design the building required to a partial stage,
often referred to as scope design, then competitive tenders are obtained from a select
list of contractors to develop and complete the design and construct the building. The
amount of consultant design can vary depending on the clients needs.

Package deal this method is often used where the contractors competing will use a
significant part of their own or another proprietary building system or they will be
constructing variations of a repetitive theme. There is limited scope for innovation when
this method is used. Some contractors may offer to find a site, to sell, mortgage or lease
their product, obtain approvals etc. at a risk to themselves or at a charge to the client.

Novation sometimes referred to a design, novate and construct. This is where the
contractor takes over from the client a previous contract for the design work, completes
the design and constructs the work.

Key points to consider with design and construct procurement


In design and construct contracts, in theory, there is usually a single point of
responsibility. The employer therefore has the advantage of only on firm to deal with
and one firm to blame if things go wrong. In practice, the employers requirements are
detailed to the extent that the contractors design contribution, and liability, is diminished.
The employer lacks control over the detailed design; however, this might be acceptable
where broad lines of the scheme are satisfactory and the detail relatively less important.
HND in QS

25
Contractual procedures
Construction work can be started early as a great deal of detailed design can proceed in
parallel. However, it is mainly the contractor who benefits from this operational
flexibility.
Responsibility for completing on time rests wholly with the contractor. There should be
no risk of claims because of the allegations that information from the employer is late.
This obligation on the contractor to be responsible for the flow of their necessary
information is one of the most attractive features of design and construct.
There is greater certainty of cost, even to the extent that, if required, responsibility for
investigating site and subsoil conditions can be made entirely the contractors. Any
changes in the employers requirements can affect the contract sum, however, and are
likely to prove costly.
It is always advisable to ask for information about who the contractor intends using as a
designer. Adequate professional indemnity insurance should always be a requirement.
The employer should be advised to appoint consultants to provide advice on the
preparation of the requirements; it is important that adequate time is allowed for this to be
done adequately.
Design & Build procurement
Advantages
Advantage of dealing with one single
organization

Before construction begins, price


certainty can be obtained

HND in QS

Disadvantages
To the standard contracts that are
available, design responsibility is
limited

To the concept design and frequently


before the detailed designs are
complete, client is required to
commit towards them at an early
stage

26
Contractual procedures
The project time can be reduced due
to the overlapping of design and
construction activities

Clients reduced ability to control


design

Contractor can input his ideas in to


the design and planning and thereby
enhanced constructability for the
relevant project

Difficulty in evaluation

Use of a guaranteed maximum price


with a savings option split can
stimulate innovation and reduce time
and cost;

Client changes to project scope can be


expensive

Management procurement
Several variants of management procurement forms exist, which include;
Management contracting,
Construction management
Design and manage.
There are some subtle differences between these procurement methods. In the case of
management contracting, the contractor has direct contractual links with all the works
contractors and is responsible for all construction work. In construction management, a
contractor is paid a fee to professionally manage, develop a programmed and coordinate the
design and construction activities, and to facilitate collaboration to improve the projects
constructability.

Management contracting
The client appoints an independent professional team, and also a management contractor. Their
involvement at pre-construction stages will be as adviser to the team, and during construction
they will be responsible for executing the works using direct works contracts. With this type of
contract it is possible to make an early start on-site and achieve early completion. Because of its

HND in QS

27
Contractual procedures
flexibility, it allows the client to change the design during construction because drawings and
matters of detail can be adjusted and finalized as the work proceeds.
Construction management
The management contractor is selected after a careful selection process and is paid a
management fee. The basic difference is that works contracts, although arranged and
administered by the management contractor, are direct between the client and works contractor.
Design and manage
A design and manage strategy is similar to management contracting. Under a design and manage
contract, the contractor is paid a fee and assumes responsibility, not only for works contractors,
but also for the design team.
The common variations of design and manage are
Contractor a project design and management organization designs and manages the work,
generally for a fee and delivers the project by employing works contractors as its subcontractors
to design/or construct.
Consultant a project designer/manager is the clients agent, who designs and manages the
work, obtains subcontract tenders from works contractors who then each enter into a direct
contract with the client.
Management procurement
Advantages

Disadvantages

Reduced project duration

Client risk is high

Early involvement

Commitment prior to full design

Accommodates later design decision

Close time and information control


required

Flexibility for changes in design

Informed and proactive client is


required

Roles, risks and responsibilities for


all parties are clear

Client loses direct control of design


quality which is influenced by the
constructors

HND in QS

28
Contractual procedures

1.6 Time, Cost and Quality Management


1.6.1 Compare the projects planned programme schedule with the actual. Evaluate the
implication of begin ahead of the programme or behind the scheduled time for completion
of the contract.
Time, Cost and Quality

Time - Time, in development, is broke down to its littlest details. The measure of time required to
finish every last part of an undertaking is analyzed. When investigation has occurred, those
segments are separated significantly advance into the time required to do every assignment.
Clearly from every one of this we can assess the span of the venture and also the faculty and gear
required.
Cost - Resources dependably cost cash so the two are exchangeable from various perspectives.
When we discuss the expense of a task, we are discussing what should be connected or relegated
to working as far as cash and exertion with a specific end goal to get things going. This can be
assets like labor, hardware and materials. These could be claimed straightforwardly by the
manufacturer, or be as contractual workers and outer suppliers.
Quality There are numerous segments to quality anyway one especially imperative one is the
extent of an undertaking (frequently called the Scope of Work or Specifications). This is an
unmistakable, particular proclamation with respect to what has been consented to be
performed/accomplished in building your new home. At the end of the day - the agreement,
determinations and the drawings that we have singed.
Getting a task right is an exercise in careful control. Time, expense and quality tend to pull in
various headings, and all have diverse dangers, however a fruitful venture needs to strike the
right harmony between each of the three.
HND in QS

29
Contractual procedures
On building projects in particular, the three factors mean:
1.
2.
3.

The nature of the working for prompt practical needs, and use for the duration of its
life.
The time required for the working to be planned, manufactured, fitted out and
prepared for occupation.
The expense of the development, materials and all related costs incorporating cost
being used.

Accomplishing the right adjust of value, time and cost for the task is critical to the achievement
of the undertaking. The harmony between these three components will shift as indicated by the
specific necessities of the venture, and their effect on each other will be pretty much as
interesting to the task's circumstances.
As the task group, they should remember a thought of the different situations that could emerge
if time, quality or expense were to be organized over the other two. Should the need emerge;
these situations would then be investigated further.
At the point when discussing this anticipate proposed housing scheme for the client Finance
Co .Ltd for is a task of CSK enterprises PVT Ltd who is a decent organization for building
developments, Repairs and upkeep.
Fixed price contract
The altered value contract is a lawful understanding between the venture association and a
substance to give products or administrations to the undertaking at a concurred on cost. The
agreement ordinarily points of interest the nature of the products or administrations, the planning
expected to bolster the undertaking, and the cost for conveying merchandise or administrations.
There are a few varieties of the settled value contract. For items and merchandise and
administrations where the extent of work is clear and not liable to change, the altered value
contract offers an anticipated expense. The obligation regarding overseeing
1.6.2 Compare the project costs in the context of pre-contract, tender and final account
stages of the contract.
In the event that we not have a decent spending plan, boss can't pass judgment on contract
proposition, spending plan will constantly helpful for boss for getting a thought regarding the
development and oversee cash furthermore it will imperative for temporary worker for deal with
their benefit and everything.

HND in QS

30
Contractual procedures

Along these lines, project spending plan is constantly acquainted with undertaking extension,
plan and the expense of the task.
Setting a doubtful spending plan can mean task fizzles, is sick fitting or wasteful. Development
parties need to guarantee to oversee venture costs deliberately. The money related requirements
may change amid an undertaking ensure venture group continue top of the accounts at all
phases of configuration advancement.
Parties they should set a blueprint spending plan, use cost benchmarks to set up beginning
costing, make note of variables and comprehend the ramifications of capital expenses. At that
point can oversee venture cost so effectively. By drawing together data from over the
development business, cost benchmarks build up run of the mill costs per square meter. These are
upgraded every year to reflect changes in expenses. Taken a toll benchmarks are valuable from
the get-go to decide the possible expense of the task you are arranging.
In this development CSK enterprises have officially arranged the task spending plan in
preliminaries as site leeway to entire the fittings and completions to the house.

1.6.3. Describe how quality is defined and the measures that are available within this
contract to assume its compliance.
How quality is defined and measures
The measures those are available within this contract to assume its compliance.

Functionality
Impact
Building quality

HND in QS

31
Contractual procedures
What is functionality?
A clear understanding of the functional and physical requirements of a project is essential to
ensuring its success. A client's intent to develop a project is derived from a need, a purpose or
mission, and a desired result.

There are 3 main type in functionality

Space
Access
Uses

What is impact?
Construction has long been recognized as one of the most resource-hungry and therefore least
sustainable industries in the world. However we continue to depend on buildings of all kinds
homes, offices, hospitals, shops, cultural centers and more. Despite increasing awareness of the
need to develop a more sustainable approach within the construction industry, this proved
difficult without a reliable method of evaluating and comparing the environmental impacts of
different construction materials.
There are 4 main type of impact

Urban and social integration


Internal environment
Form & material
Character & innovation

What is building quality?


Construction projects are a balance between cost, time and quality. It is possible to have high
quality and low cost, but at the expense of time, and conversely to have high quality and a fast
project, but at a cost. If both time and money are restricted, then quality is likely to suffer. High
quality is not always the primary objective for the client; time or cost may be more important. It
is only realistic to specify a very high standard of quality if the budget is available to achieve that
standard.
There are 3 main type of building quality

Performance
Engineering
Construction

HND in QS

32
Contractual procedures
How time, cost and quality have been balanced in the contract.
Time, quality and cost

How time, cost and quality balance in the contract

HND in QS

33
Contractual procedures

Quality
The quality of the building for immediate functional needs, and use throughout its life
Time
The time needed for the building to be designed, built, fitted out and ready for occupation
Cost
The cost of the construction, materials and all related expenses including cost in use
1.6.4. Analyze other clauses making reference to form of contract for their interpretation.
The key to the success of the project is achieving the right balance of time, cost and quality. The
balance between these three factors will vary according to the particular requirements of the
project and their impact on each other will be just as unique to the projects circumstances.

HND in QS

34
Contractual procedures

As the client of the project he will need to keep in mind an idea of the various scenarios that
could arise if time, quality or cost were to be prioritized over the other two. Should the need
arise, these scenarios would then be explored further and with others in the project team if
appropriate in order to arrive at informed decisions based on reasoned weighing of the relative
risk involved.
For instance, client may have to think the project will complete the particular deadline or is it
more worthwhile in the case of the project to adopt a longer programed in order to save on cost
or improve in quality? Remember that missed deadlines can sometimes add to contractor costs,
and may mean client have to compromise in the cost of materials, which will in turn affect
quality.

Good project and delivery teams must support to client in any balancing of time, quality and
cost. A good design team should be able to work within a reasonable, set budget the discipline of
limited budget can actually stimulate creativity and innovation. And sound financial management
often goes hand in hand with delivering a high quality project to deadline.
In assessing the cost of a project, must consider the costs over the entire life of the building
rather than just the design and construction costs. This is known as whole life costing. A
successful building project will attempt to meet the needs of a building over is entire lifetime.

HND in QS

35
Contractual procedures
1.7 Other Stakeholders
1.7.1 List the different organizations involved in the construction industry and evaluate the
purpose and activities of them on this contract.
In a development project there are a few gatherings required in the finishing of the task. These
gatherings can be from either general society area or the private segment. The key gatherings are
the customer, temporary worker and specialist.
Customer is the individual who is at first contributing the cash to give the contractual worker to
fire up all the work and if the customer is neglecting to give cash the specialist may give the cash
or the temporary worker will pay the cash to begin the task and get them from the customer
before long. These are the underlying partners.
A task can't continue without satisfactory financing, and the expense of giving sufficient
financing can be entirely vast. Hence thoughtfulness regarding venture account is an imperative
of task administration perspectives. Account is additionally a worry to alternate associations
required in a task, for example, the general contractual worker and material suppliers. Unless a
proprietor promptly and totally takes care of the expenses brought about by every member these
associations face financing issues of their own. At the point when discussing each development
as a primary partners there have customer who chiefly speak to their cash to the development,
temporary worker and the advisor.
For a development organization as another partner's private or open banks and insurance
agencies they will give the cash or credits to continue the development.
At the point when an undertaking is recompensed, the general population and private gatherings
make another privately owned business to oversee and trade stores for the venture. These assets
are utilized to start and run the venture. For a development venture after the building is
completely operational if the privately owned businesses made an assertions for the upkeep of
the working over a period.
Finally according to our project the other stake holders are privet bank sector insurance
companies and the end users of it the general users the public people who annually pays tax
and indirectly they are also stakeholders because the money that government spend is
collected by the taxes that the people pays.

HND in QS

36
Contractual procedures
Municipal Council
Taking permit and consent for the development, taking endorsements to the arrangements must
do through Municipal Council. Additionally municipal chamber gathering the development
wastage from the site.
National Water Board (NWSDB)
In this agreement took water supply through NWSDB to the entire building.
Ceylon Electricity Board (CEB)
CEB will disseminate the power to the Whole building
Sri Lanka Telecom (SLT)
For telecom administration customer professed to utilize SLT
Banks and Insurance Cooperation
Regularly after culmination of the building ordinarily building will protect in some protection
participation if any flame or any normal peril brought on to the building it will guarantee it.
Additionally banks likewise including with the building development so typically customers
taking advances from a bank and contributing so bank additionally including with this.
Law firms
In the event that any lawful circumstances happened Law firms are required.

HND in QS

37
Contractual procedures
1.7.2 Analyze the contractual differences between nominated and other types of contractors
and evaluate the forms of contracts regarding suppliers.
Domestic sub-contractor
Nominated sub-contractor
Named sub-contractor
Domestic Sub-Contractor

A Domestic Sub-contractual worker is chosen and connected with straightforwardly by


the fundamental temporary worker to do a specific exchange, this will mostly incorporate
standard exchanges, for example, bricklayers, roofers, ground specialists, handymen,
electrical and plasterers. They might be work just or supply and alter. In all cases they
should be endorsed by the designer. The modeler has the full power to dismiss any
subcontractor asked for by the temporary worker. The agreement does not perceive the
principle temporary workers own subcontractors any work completed by these is taken as
though it were done by the primary contractual worker.
Nominated Sub-Contractor
A Nominated subcontractor is picked by the designer customer or specialist to do certain
parts of the work. They are designated on the consumption of a PS or PC entirety
incorporated into the agreement bills. The selected subcontractor goes into an agreement
with the primary contractual worker yet there might be a security guarantee between the
designated subcontractor and the customer. The principle temporary worker has no
obligation to convey our work that is planned to be done by a designated subcontractor
Named Sub-Contractor
A named sub-contractual worker will regularly be looked over a rundown of
subcontractors gave by the draftsman. The modeler may furnish the temporary worker
with a rundown of no less than three subcontractors to browse for doing specific parts
under the JCT 05 standard or moderate building contracts. The fundamental temporary
worker may with endorsement from the planner add subcontractors to the rundown. In
spite of the fact that the subcontractor is named they are a local subcontractor under the
agreement.
Difference between Nominated Sub-Contractor and Domestic Sub-Contractor
HND in QS

38
Contractual procedures

Assigned sub-contractual worker somebody the Employer has told the temporary worker
he should utilize. The customer will have generally arranged the terms and cost and
entered a PC total into the delicate Bill of Quantities, which you include attendances,
benefit and so forth to again normally in a different Bill thing. There are frequently sure
commitments that the Employer stays in charge of, for example, program, yet this totally
relies on upon what is composed in the agreement.
Local or direct are presumably the same thing as an illustration a sub-contractual worker
the principle temporary worker utilizes without reference to the Employer with respect
terms and cost. There might be particular conditions for their job, for example, Employer
endorsement and the fuse of particular terms required under the principle contract. The
fundamental contractual worker assumes full liability for the execution of a residential
sub-temporary worker and includes benefit and so forth to the rates of work that the subcontract based worker completes similarly as whatever other rate.

Contrast between Nominated Sub-Contractor and Named Sub-Contractor

Named sub-contractual worker delegated by the customer and named sub-temporary workers
principally designated by the significant contractual worker.

Named sub-contractual worker primarily contracts with the fundamental temporary worker to
supply or alter any materials or products or execute work framing part of the primary contract.
Be that as it may, named sub-contractual worker is delegated for unique works like pipes,
electrical, and so forth for named subcontractor's installments will done by the significant
temporary worker and selected sub contractual worker's installments will done by the customers
straightly.
Forms of contracts regarding suppliers
Fixed price contract
The altered value contract is a lawful understanding between the venture association and a
substance to give products or administrations to the undertaking at a concurred on cost. The
agreement ordinarily points of interest the nature of the products or administrations, the planning
expected to bolster the undertaking, and the cost for conveying merchandise or administrations.
There are a few varieties of the settled value contract. For items and merchandise and
HND in QS

39
Contractual procedures
administrations where the extent of work is clear and not liable to change, the altered value
contract offers an anticipated expense. The obligation regarding overseeing
The work to address the issues of the venture is centered around the temporary worker. The task
group tracks the quality and timetable advancement to guarantee the contractual workers will
meet the venture needs.
Unit value contract
In a unit value get, the work to be performed is broken into different parts, typically by
development exchange. This agreement sort depends on expected amounts of things which are
included the undertaking notwithstanding their unit costs. The last cost of the task relies on the
amounts required to do the work. For instance painting is regularly done on a square foot
premise. Unit value contracts are from time to time utilized for a whole real development extend
yet they are oftentimes utilized for concurrences with subcontractors which include exact
recognizable proof of various sorts of things, yet not their numbers in the agreement archives.
They are likewise frequently utilized for support and repair work.
Cost plus contract
The expense in addition to contract is an assertion which includes the purchaser's agree to pay
the complete expense for material and work notwithstanding the sum for temporary worker
overhead and benefit. This agreement sort is favored where the extent of work is exceptionally
questionable or vague notwithstanding the sorts of work, material, and gear being comparably
dubious in nature. Here, the temporary worker's benefit is set at an altered sum. In the event that
genuine expenses are lower than the assessment, the proprietor keeps the reserve funds. On the
off chance that genuine expenses are higher than the assessment, the proprietor must pay the
extra sum. The upside of an expense in addition to contract is that as a rule the task will bring
about the building that was imagined regardless of the possibility that costs run high. The
developer is less inclined to compromise or contend for less costly materials.
Incentive contract

Motivation contracts are frequently utilized when there is some vulnerability in the expense of
the work, distinction when an item is being worked to one of a kind details, and does not use offthe-rack segments. This is regular in contracts including test programs or new innovation or
procedures. Taken a toll based impetus contracts set up an objective value, target benefit and a
most extreme expense. A recipe is incorporated to designate any invade of the objective expense
between the purchaser and temporary worker. Once the greatest expense has been achieved, the
contractual worker subtracts any extra invades from his benefit, or charge.

HND in QS

40
Contractual procedures
Task 2
Describe the needs of clients in both public and private sectors.
Client
Every construction project begins with a bright idea from a client
that is then elaborated on and executed by a team of designers,
architects, quantity surveyors and the engineers. Only once
individual objectives, goals and parameters are defined can the
project commences. Key to managing a diverse team of service
providers successfully is to be upfront with them regarding the variable priorities and
expectations of the respective client. Understanding that every client is unique will guide the
approach of all participants before any ground is broken.
There are 2 main types of clients.
1. Public clients
2. Private clients
Public clients
Public client base includes Central Government, Local Authorities, The National Health Service,
Police Stations, Transport, Colleges/Universities, Chemists/Pharmacies, and Doctor
Surgery/Health Centers.
Public limited companies
A public limited company, such as a bank, is one that trades on the stock exchange and is owned
by its shareholders. A bank could have hundreds of branches that all need to be maintained and
looked after and upgraded by refurbishment from time to time.
It is also likely to have a large headquarters in a major city, which will need similar work doing.
The Government the Government can issue work at three different levels: through local councils,
devolved administrations (Welsh Assembly and Scottish Parliament), and central government.
Local councils have duties to construct and maintain services. They can issue work such as the
following: constructing schools maintaining highways replacing window maintaining houses
carrying out building works on council properties. Devolved administrations can instruct major
capital works such as the new parliament buildings or infrastructure works.

HND in QS

41
Contractual procedures
Central government departments, such as the Ministry of Defense (MOD), or bodies such as the
Highways Agency or National Health Service, purchase a great deal of construction services,
usually using intermediate companies who specialize in managing large building projects.
Client Needs in Constructions
In Order to ensure a successful choice of building procurement system (constructions) the clients
brief must be clear, comprehensive and contain Accountability (Public sector), Quality at the
right place and right price. Speedy constructions, new designed building, maximum tax benefits
Government
The Government can issue work at three different levels: through local councils, devolved
administrations (Welsh Assembly and Scottish Parliament), and central government. Local
councils have duties to construct and maintain services. They can issue work such as the
following.

constructing schools

maintaining highways

replacing windows

maintaining houses

carrying out building works on council properties


Devolved administrations can instruct major capital works such as the new parliament buildings
or infrastructure works. Central government departments, such as the Ministry of Defense
(MOD), or bodies such as the Highways Agency or National Health Service, purchase a great
deal of construction services, usually using intermediate companies who specialize in managing
large building projects.
Private clients
Private sector client base includes Banks and Building Societies, Airports, Railways, Retail
Establishments, Embassies, Supermarkets, Ticket Offices, Customer Service Desks, Bakers,
Butchers, Shoe Shops, International Distributors. Private clients are sole traders or domestic
clients who would like to have a house building altered, extended or maintained. They enter into
private agreements with a builder to undertake the work.
The private sector is the part of the economy that is not state controlled, and is run by individuals
and companies for profit. The private sector encompasses all for-profit businesses that are not
owned or operated by the government
Commercial
HND in QS

42
Contractual procedures
A commercial client is a factory or business that needs to undertake building works in order to
produce a product or process. For example, a fast food company needs an outlet to sell its
products from. The outlet usually has to be built quickly, and to be maintenance-free and
adaptable. Small industrial factory units are commercial buildings that provide products and
services. Commercial client would similarly have to follow environmental and safety regulations
regarding planning and building. Their cost of construction pays by their own money or business
money.
Our client
Our client is private client. When we are doing any construction project it will better thing.

No need to wait until providing money as government project.

We dont want get approvals from different department as government project.

When decision making private client is the major person.

Can do our job well as our own ideas.

As contractors we have very good working environment with private clients.

And also we no need to afraid about project delays with political reasons as government
projects.

Conclusion
There are so many parties involved in a construction project. We mentioned the roles &
responsibilities of the contractor, consultant, Project manager, Quantity surveyor, Civil Engineer.
Then we described the sequence of events of a construction project from design to construction.
Before start the construction we have to select the suitable procurement method. This contract is
based on the traditional procurement method.
There are so many contractual arrangements in a contract. We explained those contractual
arrangements according to this project.
When doing the contract according to the traditional method we could identify some problems
such as Claims and payments made on early accomplishments were bloated; the contractor
eventually abandoned the project, unnecessary work items, incorrect deductions of retention

HND in QS

43
Contractual procedures
from progress payments due to failure to validate conformance with project schedule. To avoid
those issues we proposed some changes to the contract.
Then we compare the project costs in the context of pre contract, tender and final account
Stages of the contract as well as Compare the projects planned programme schedule with the
actual. After that we described how quality is defined and the measures that are available within
this contract to assume its compliance. Analyze other clauses making reference to form of
contract for their interpretation.
Then we explained the different organizations involved in a construction industry& also
explained their services. Then we described the contractual difference between nominated &
other type of contractors.
Finally we discussed needs of clients in both public and private sectors& give effective
judgments based on this housing scheme project.