WORK METHOD STATEMENT

Title:
1.0

Anti-Termites Work

Page 1 of 3

OBJECTIVE
To outline the work method of construction to be adopted for the Anti-Termites.
Comprehensive Method of Statement for Anti-Termite will be provided by Specialized/
Subcontractor. Details of the procedures contained herein may be review and modified based
on site condition.

2.0

SCOPE
a) The contractor shall notify pest control operator 24 hours in advance that
anticipates concrete casting into the area to be treated.
b) Before area treated, the contractor shall ensure that all loose timber, wood
shaving, loose containing materials be removed from the said allocation area.
c) Pest control operator shall apply anti termite onto entire ground floor slab area
prior to concrete casting.
d) The area surrounding all sides of the column stumps extending to 1 meter below
the soil surfaces or to the top of pile cap.
e) Pest control operator shall applied 2 meter all-round the building prior to
concrete of the apron area.

3.0

RESOURCES
3.1

Materials
The chemical mix must be applied uniformly over the area to be treated at the
rate of 4-5 liters to 1m according to manufacturers specification. The area to be
chemically treated every 2 meters all around building perimeter prior concreting
of the apron area.
3.1.1
a)
b)

4.0

Submittal of Material
Sample of material will be submitted for approval
Material for test shall be done at site at any time

WORK METHODOLOGY
4.1

Chemical Preparation and Application


a) Pest control operator shall mixed the solution at site in the present of site
supervisor or client/clients representative according to manufacturers
specification and to apply the mixed solution onto the indicated allocation
area.

WORK METHOD STATEMENT


Title:

Anti-Termites Work

Page 2 of 3

b) Before soil treatment will be carried out, the ground water table will be
checked. Excavation of trial holes of more than 0.5 metres deep measured
from the level of the soil to be treated will be done. As required by DOE, no
treatment is to be carried out if the ground water table is 0.5 m or less below
of soil to be treated.
c) This chemical preparation shall be carried out within a kerbed area under a
roof with no outlet to the lake, open drains or public sewer. The waste water
containing the chemical shall not be discharged into the lake, septic tank or
open drain.
4.2

4.3

Time of Application
a)

Lean concrete shall be laid immediately


after chemical has been applied on the
hardcore as to avoid exposure to weather.

b)

Application of chemical should spray on


hard surfaces of hardcore or sand blinding
prior to concrete casting.

c)

After completion of applying chemical, PVC


sheet have to provide to cover up treated
area as to avoid exposure to sun heated
and rain wash in case occurred of
concreting may delay.

d)

Immediately after the soil treatment is


completed, the treated soil shall be
securely covered with black polyethylene
sheet. The layer of lean concrete shall be
cast on top of the sheet.

e)

After completion of applying chemical pest


control operator will let the site
supervisor/consultant to sign and certify on
the job sheet provided by pest control
operator.

Allocation Equipment
Pest control operator must be provided full range of equipment for the job.

4.4

Temporary Drainage
The provision of temporary drainage will be provided of adequate capacity
around the whole area to be treated within an outlet to a sump.

4.5

Sampling
The examination/quality control sampling.

4.6

Storage
WORK METHOD STATEMENT
Title:

Anti-Termites Work

Page 3 of 3

Pest control operator shall arranged owned transportation and delivery, storage
of material at site is not necessary.
4.7

Pest Control Operator


a)

4.8

Pest control operator (company) is not necessary to


register with CIDB but the technicians are trained by
CIDB and obtained recognized operators cards issued
by CIDB. Poison permit is issued not by DOE, but the
ministry of agriculture control the issuing poison
permit.

Warranty
a) Actual warranty is issued by Anti-termite contractor immediately upon P.R.
request subject to payment fully settled by the main contractor. The
warranty period is 10 years from CPC.
b) The treated subterranean termite be found affected the treated building
within warranty period by contractor anti termite to undertakes and
control at whatever method the company should deem fit free of charge.

4.9

4.10

Method of Applying Anti Termite Soil Treatment (4 Stages)


(a)

Spraying of surfaces of pile cap and ground beam trenches.

(b)

Spraying of surfaces below the floor-slab area after laying of hardcore


and prior to the final concreting stage.

(c)

Spraying of surfaces below apron / terraces and area within 2 meters


perimeter beyond the edge of external building wall unless adjoining
structures render this impossible.

(d)

Power spray at any soil surfaces or areas through which termite


infestation is likely to occur and as directed by client/clients
representative.

Method of Applying Anti Termite Soil Treatment (2 stages)

(a) Spraying of surfaces below the floor-slab area after laying of hardcore and
prior to the final concreting stage.
(b) Spraying of surfaces below apron / terraces and area within 2 meters
perimeter beyond the edge of external building wall unless adjoining
structure render this impossible.

(c) Power spray at any soil surface or areas through which termite infestation is
likely to occur and as directed by client/ clients representative.