Professional Documents
Culture Documents
McKay Consulting Incorporated v. Rockingham Memorial Hospital, 4th Cir. (2011)
McKay Consulting Incorporated v. Rockingham Memorial Hospital, 4th Cir. (2011)
No. 10-2038
Appeal from the United States District Court for the Western
District of Virginia, at Harrisonburg.
Glen E. Conrad, Chief
District Judge. (5:09-cv-00054-gec-bwc)
Argued:
Decided:
Before TRAXLER, Chief Judge, and AGEE and DIAZ, Circuit Judges.
Consulting,
award
Hospital
of
Inc.
summary
(RMH).
In
(McKay)
judgment
this
appeals
to
action
the
district
Rockingham
Memorial
based
on
diversity
I.
McKay
is
self-described
national
healthcare
Medicare.
McKay
researches
hospitals
that
could
to
provide
its
services
contingency
fee,
in
increase
Medicare
or
related
reimbursements
for
J.A. 347.
525
principal)
(emphasis
and
in
Brown
original).
met
with
Michael
Holsinger
on
McKay
June
3,
(McKays
2009
to
he
Holsinger
disclosed
whether
the
she
idea,
was
he
and
Brown
comfortable
repeatedly
going
forward
asked
and
verified that she wanted them to proceed and tell her about the
concept.
but contends a binding contract with RMH was formed at the June
3,
2009
meeting
based
on
her
oral
commitment
and
McKays
Although
explicitly
the
agreed
parties
disagree
to
terms
the
about
whether
proposed
by
Holsinger
McKay,
it
is
described
presentation,
it
McKay
in
detail.
disclosed
In
for
the
the
course
of
this
time
that
upon
first
likely
incur
several
million
dollars
in
reimbursement
Michael
McKay
then
to
met
whom
with
they
Michael
King,
explained
the
RMHs
Chief
Financial
Officer,
reimbursement
concept.
the
days
that
followed
the
meeting,
Michael
McKay
and
sent
written
agreement
that,
according
to
McKay,
Although McKay
now contends a firm, oral contract was made at the June 3, 2009
meeting with Holsinger, an e-mail between McKay and Brown that
clause,
the
proposed
written
In addition to a
contract
contained
the
the
twenty
percent
fee
was
too
high,
and
negotiate
an
already
agreed
upon
fee[,]
and
stated that [w]e are not attempting to change our agreement and
we ask that you do the same.
Invoking
diversity
J.A. 548.
jurisdiction,
McKay
filed
complaint
an
alleged
had
RMH
enforceable
entered
implied-in-fact
into
an
agreement
contract. 6
(either
McKay
orally
or
(2)
retain
as
McKay
if
its
it
chose
agent
to
to
pursue
perform
the
the
idea,
work
it
would
necessary
to
revenues
that
RMH
received
as
result
of
concluding
to
keep
that
McKays
the
parties
concept
had
an
confidential,
enforceable
the
district
court held that no reasonable jury could find that McKay and
RMH mutually assented to all of the essential terms outlined in
the
original
judgment
to
complaint.
RMH,
the
J.A.
district
2425.
court
In
held
granting
that
the
summary
record
evinces
no
meeting
agency
terms
conclude[d],
agency
the
asserted
as
terms
of
are
by
matter
not
minds
as
to
McKay.
of
law,
established
the
compensation
Moreover,
that
with
the
the
court
compensation
reasonable
and
and
certainty.
Id.
McKay
filed
timely
appeal
from
the
district
courts
II.
Whether
party
is
entitled
to
summary
Servs.,
Inc.,
320
F.3d
judgment
is
488,
491
reasonable
favorable
to
inferences
the
drawn
nonmoving
therefrom
party
(McKay,
in
in
the
this
light
case),
most
no
matter
is
before
us
in
diversity,
we
bound
by
the
are
III.
The district court based its grant of summary judgment upon
its primary holding that McKay and RMH failed to mutually assent
to the essential terms of the purported contract, those being
compensation
alternative
because
and
that
those
certainty.
agency.
there
terms
was
were
J.A. 2425.
The
no
not
district
contract
court
under
established
held
in
the
Virginia
law
with
reasonable
the
district
court
stated
its
decision
as
reasonable
certainty.
Accordingly,
single
analysis
A.
The Supreme Court of Virginia has consistently set forth as
necessary elements of contract formation that:
[T]he parties must have a distinct intention common to
both and without doubt or difference.
Until all
understand alike, there can be no assent, and,
therefore, no contract.
Both parties must assent to
the same thing in the same sense, and their minds must
9
also
Persinger
&
Co.
v.
Larrowe,
477
S.E.2d
506,
509
an
essential
Blackstock,
Inc.,
element
661
of
S.E.2d
all
contracts.
404,
409
Moorman
(Va. 2008)
v.
(internal
to
form
an
enforceable
agreement,
Virginia
courts
Virginia courts cannot make a new contract for the parties, but
must construe [the contracts] language as written.
Berry v.
1. Compensation
The
holding
most
that
compensation
vivid
proof
there
was
element
is
no
supporting
the
district
courts
meeting
the
minds
to
McKays
10
of
inability,
even
as
through
the
oral
the
course
parties
of
this
were
alleged
litigation,
to
McKay
have
agreed.
asserted
During
at
least
the
four
basis
for
June
3,
2009
contract,
McKay
contract
compensation
J.A. 546.
of
term
of
June
20%
4,
2009,
however,
the
additional
of
argues
the
The proposed
has
different
reimbursement.
different
iterations
of
J.A. 1160.
compensation
term
are
(implied
in
fact
McKay
(omitting
any
claim
of
11
adjustment
or
increased
reimbursement)
pleads
that
the
of
J.A. 27.
its
own
William
proffered
contract,
no
court
will
make
458
S.E.2d
568,
572
(Va. 1995)
(while
they
have
assumed,
Virginia
courts
nevertheless
cannot
settled
on
one
of
its
compensation
as
the
actual
multiple
contract
proposed
term
of
definitions
the
parties,
of
it
with
perhaps
other
categories
added
in?
Is
the
each
of
the
other
potential
adjustment,
additional
reimbursements
and
terms
of
reimbursement,
underscores
the
void
compensationor
in
increased
McKays
argument
question,
compensation
is
an
essential
contract
As a
In
respect
Womans
thereto.
Coll.,
Progressive
(Va. 1968)).
661
Const.
Dodge
S.E.2d
Co.
v.
v.
Trustees
801,
Thumm,
803
161
of
Randolph-Macon
(Va. 2008)
S.E.2d
(quoting
687,
691
13
2. Agency
The district court also correctly held that no contract was
formed between the parties because the essential term of agency
could
not
be
ascertained
with
reasonable
certainty.
[A]n
the
person
to
whom
it
is
to
be
rendered,
and
Mingo
Lime
&
Lumber
Co.,
10
S.E.2d
492,
494
the
Mullins
(Va. 1940)
(citation omitted).
McKay pled in its complaint that RMH agreed that if it
chose to implement McKays concept, it would [r]etain McKay as
its agent to perform the work necessary to implement McKays
idea.
J.A. 27.
argument,
McKay
could
not
J.A. 1395.
identify
the
Even through
scope
of
agency
in
the
light
most
favorable
to
McKay,
the agency
terms were so vague that the parties could not have mutually
assented to a contract.
convey
any
meaning
that
14
would
allow
the
parties
to
argues,
however,
that
RMHs
experience
with
other
the
parties
plaintiff-appellant
assented
to
30-31.
of
consultants
agency
McKays
the
to
term.
reliance
Br.
on
for
RMHs
address
Medicare
issues,
those
in
elusive.
the
it
is
clear
that
the
terms
here
are
shows
standard
practice
in
the
Medicare
reimbursement
relationship
with
RMH
would
merely
require
McKay
to
attorneys
and
experts
in
the
event
of
litigation.
initially
block
RMHs
application
to
change
status,
term
of
agency
is
simply
too
ill-defined
to
have
B.
In the absence of clear contract terms, McKay argues that
its purported contract is nonetheless enforceable because the
trier of fact could deduce and supply the terms of agreement.
McKay
cites
High
Knob,
Inc.
v.
Allen,
138
S.E.2d
49,
53
(Va. 1964) for the proposition that Virginia contract law does
not
favor
declaring
contracts
void
for
indefiniteness
and
courts
lack
authority
to
supply
Id.
However,
virtually
every
make contracts for the parties, and (2) courts will not permit
parties
to
be
released
from
the
obligations
which
they
have
language
circumstances.
used,
in
the
light
of
all
the
surrounding
Knob
was
developer
no
reference
residences
to
be
built
sold
Id. at 49-51.
that
was
on
made
the
to
certain
in
supplying
lots;
lots
however,
water
High
to
the
Knobs
51.
The
trial
court
found
that
McElroy,
High
Id.
Knobs
secretary, promised the buyers that High Knob had a water system
and would furnish a reasonable quantity of water to houses
constructed in the subdivision for a $200 hook-on fee; that this
was the only consideration to be paid for the water service; and
that this arrangement was one of the inducements to purchase the
lots.
Id.
Virginia
Supreme
Court
concluded
that
McElroys
was
simply
that
which
was
reasonably
necessary
for
Id. at 53-54.
water
refused
to
for
six
sign
the
months
before
written
cutting
water
it
contract
off
when
tendered
Allen
by
High
Knob.
The case at bar is a far cry from High Knob.
preceding
discussion
well
illustrates,
the
As the
circumstances
in
the
parties
made
an
agreement
as
to
the
essential
missing terms.
McKays solution, in the absence of either compensation or
agency terms necessary to form a valid contact, is essentially a
Price
is
Right
approach;
give
the
trier
of
fact
multiple
No principle of contract
Virginia
law simply does not permit finding a contract when the trier of
fact must determine one from among multiple choices presented by
a party for a term of compensation, then define what the chosen
term encompasses, and finally delineate the scope of agency sua
sponte.
Accordingly,
we
conclude
that
High
Knob
is
simply
not
IV.
On this record, no reasonable jury could find that the
parties mutually assented to the compensation and agency terms
set forth in the complaint.
19