Professional Documents
Culture Documents
North Carolina Utilities Comm v. FERC, 4th Cir. (2014)
North Carolina Utilities Comm v. FERC, 4th Cir. (2014)
No. 12-1881
Argued:
Decided:
(ER08-
to
Virginia
Electric
Power
Company
d/b/a
Dominion
we affirm.
I.
We
begin
with
brief
description
of
FERCs
statutory
and
conditions
of
interstate
electric
transmission
(EPAct)
to
create
national
energy
the
reliability
of
the
focused
on
policy
In response to concerns
countrys
aging
transmission
incentive-based
rate
3
treatments
for
qualifying
projects
to
spur
infrastructure
investment.
16
U.S.C.
824s(c). 1
After
notice
and
comment,
FERC
adopted
final
rule
under
219.
Promoting
Transmission
Investment
Through Pricing Reform, Order No. 679, FERC Stats. & Regs.
31,222, at P 326 (2006), order on reh'g, Order No. 679-A, FERC
Stats. & Regs. 31,236 (2007), order on reh'g, Order No. 679-B,
119 FERC 61,062 (2007); codified at 18 C.F.R. 35.35 (Orders
No. 679, 679-A, & 679-B).
project.
nexus
Id. 48.
between
the
requested
incentive
and
the
rebuttable
presumption
that
its
infrastructure
project
will
resulted
from
regional
planning
process
that
included
is
met--is
more
challenging.
utility
must
Order
FERC 61,084 (2007), FERC held that a project meets the nexus
test
if
it
is
determination,
(1)
the
increase
not
FERC
projects
in
reliability
considers
scope
transfer
or
routine.
all
54.
relevant
measured
capability;
reduced
Id.
in
(2)
congestion
To
make
factors
dollar
this
including:
investment
or
its
impact
on
regional
costs;
and
(3)
project
Id. 52.
FERC also
not
routine
reliability.
because
of
their
impact
on
regional
Id. 58. 2
aggregate
to
determine
sufficient
whether
the
nexus
test
was
met.
and
support
to
allow
the
application,
FERC
sought
to
ensure
that
the
package
of
Id.
single application.
meet
the
nexus
test
for
each
individual
61,273, at 45.
project.
PJM
Id.
C.
Finally, under the third prong of the Order No. 679 test, a
utility must demonstrate that its resulting rates are just and
reasonable under 219(d).
Id. 77.
A utility
the
three
prongs
of
Order
No.
679s
test
to
II.
A.
On July 1, 2008, VEPCO, a member of PJM Interconnection LLC
(PJM), 4 sought incentives for eleven transmission projects with
a total estimated cost of $877 million.
VEPCO
notice
other
of
VEPCOs
parties
moved
filing
to
was
published,
intervene.
NCUC
NCUC
originally
and
On
The
Lexington
Tie
Project,
Idylwood-to-Arlington
fifth,
the
Proactive
Transformer
Replacement
Project
adder.
We
briefly
describe
each
challenged
project
before
Lexington
Reconductor
(RTEP)
are
Tie
PJM
projects.
Project
Regional
The
RTEP
and
Idylwood-Arlington
Transmission
is
the
Expansion
product
of
Plan
long-term
conductors.
As
RTEP
projects,
and
the
construction
of
new
transmission
underground
million.
involve
transmission
line
at
an
estimated
cost
of
$120
twelve-mile
transmission
line,
two
of
which
would
be
increase
reliability. 5
NCUC
protested
the
grant
of
Under prong one, VEPCO argued that its PTRP would increase
regional
reliability
transformer failure.
by
significantly
reducing
the
risk
of
10
would
be
decrease
of
between
PJMs
PRA
actually
determined
33%
to
66%
in
that
VEPCOs
current
than
result,
the
PJM
transformer
required
did
not
network
number
of
spare
recommend
in
its
any
planning
transformers.
upgrades
process.
As
to
VEPCOs
NCUC
argued,
therefore, that VEPCO should not be able to rely upon the PRA to
support its application for an incentive.
FERC
found
that
VEPCO
carried
its
prong-one
burden
of
project,
there
was
risk
of
outages
for
customers
in
FERC
Id. 38.
11
b.
Under prong two of the Order No. 679 test, VEPCO presented
evidence
that
each
of
its
projects
was
non-routine
under
Lexington
Tie
Project
merited
incentive
treatment,
interface
identified
the
the
construction
substation
construction.
nexus
in
test
be
Eastern
risks,
taken
Interconnection.
including
out
of
the
service
VEPCO
also
requirement
that
temporarily
during
it
faced
significant
local
opposition.
rejected
NCUCs
Lexington
Tie
Idylwood
Baltimore
Gas.
Lexington
Tie
and
As
and
RTEP
arguments,
Projects
projects,
Idylwood
were
FERC
Projects
12
finding
that
non-routine
concluded,
would
both
enhance
the
under
both
the
regional
reliability.
additional
Id.
arguments
100.
that
Further,
these
FERC
projects
credited
were
VEPCOs
non-routine
to
construct
the
Garrisonville
line
and
part
of
the
responded
these
projects
were
not
economically
ground
Virginia
at
lower
Commission
had
cost.
NCUC
approved
pointed
entirely
out
that
the
above-ground
not
be
required
to
subsidize
the
incremental
cost
of
underground construction.
In
light
of
the
on-going
local
opposition
to
these
build
underground
did
not
disqualify
these
projects
from
incentive treatment and that VEPCO satisfied the nexus test for
the full price of both projects.
iii.
Finally, VEPCO argued that the PTRP was non-routine because
its
proactive
required
deviated
coordination
necessitated
capital.
should
approach
across
significant
from
the
industry
multiple
investment
in
standard,
substations,
skilled
labor
and
and
qualify
for
incentive
treatment
because
VEPCOs
rejected
NCUCs
argument
in
this
regard
as
well,
concluding that the fact that this project was not included in
PJMs
RTEP
was
incentives.
insufficient
Id.
72.
to
disqualify
Overall,
FERC
it
from
held
that
meriting
VEPCOs
Id. 48.
Id.
its
request
for
rehearing,
NCUC
reiterated
its
identified
other
errors
in
14
FERCs
order
as
well.
In
particular,
it
contended
FERC
misunderstood
the
PTRPs
scope
reasons
oral
that
argument,
remain
FERC
unsatisfactorily
failed
to
issue
explained
its
Order
even
Denying
Rehearing until almost four years after its initial order on May
22, 2012.
argued
that
if
similar
request
incentives
were
in
light
of
the
Commissions
evolving
policy
with
Id.
Id. 11.
Id. 12.
regulatory
that
uncertainty
would
from
shifting
an
earlier position four years after the fact could deter reliance
15
on
219
confirm
incentives
the
additional
grant
more
of
arguments
broadly.
VEPCOs
raised
Id.
incentives,
FERC
on
rehearing
proceeded
finding
failed
that
to
to
the
provide
III.
We
will
affirm
FERCs
conclusions
unless
they
are
T-Mobile
Ne. LCC v. City Council of Newport News, Va., 674 F.3d 380, 385
(4th Cir. 2012).
Coal Co., 556 F.3d 177, 192 (4th Cir. 2009) (citing Balt. Gas &
Elec.
Co.
v.
Natural
Res.
Def.
Council,
462
U.S.
87,
103
(1983)).
IV.
NCUC
makes
two
primary
arguments
on
appeal.
First,
it
Second,
We address
however,
we
must
determine
whether
we
have
Commission
shall
be
considered
by
the
court
unless
such
17
764,
requirement
exhaustion
773-74
(D.C.
strictly
of
based
Cir.
1985).
on
administrative
the
We
interpret
time-honored
remedies.
Consol.
this
doctrine
Gas
of
Supply
Corp. v. FERC, 611 F.2d 951, 959 (4th Cir. 1979) (quoting Fed.
Power Commn v. Colo. Interstate Gas Co., 348 U.S. 492, 500
(1955)).
It is hardly surprising that NCUC did not argue in its
September
28,
2008
reevaluate
VEPCOs
rehearing
incentives
petition
under
the
that
2010
FERC
should
policy
change.
Given that NCUC filed its petition two years before FERC issued
PJM and Okla. Gas, absent extraordinary prescience it could not
have done so.
To
FERC, 877 F.2d 1066, 1072 (D.C. Cir. 1989) (quoting Boston Gas
Co. v. FERC, 575 F.2d 975, 978 (1st Cir. 1978)).
Gas,
for
discounted
example,
rate
FERC
initially
agreement
under
rejected
the
the
Natural
Gas
In Columbia
petitioners
Act
(NGA)
Id.
jurisdiction
to
evaluate
the
parties
challenge
to
FERCs
the
outcome
and
FERC
had
not
yet
revealed
here,
the
conclusions
of
the
its
new
Id.
May
22,
2012
Rehearing Order and the August 29, 2008 Incentives Order were
identical.
In
both,
FERC
determined
that
VEPCO
merited
The
only new analysis FERC provided in its Rehearing Order was its
decision not to reopen the case to apply the 2010 policy change.
NCUC had no way to anticipate that FERC would consider whether
to grant rehearing to apply its changed approach to the nexus
19
test. 7
response
to
its
initial
petition,
we
have
little
difficulty
petition. 8
rehearing
Having
found
that
we
have
an
agency
announces
new
policy
while
case
is
rehearing
is
committed,
in
the
first
instance,
to
the
F.2d 1358, 1364 (4th Cir. 1983) (quoting NLRB v. Food Store Emp.
Union, 417 U.S. 1, 10 n.10 (1974)).
In
reviewing
reliance interests.
that
discretion,
we
consider
the
parties
20
standard
cautions
against
retroactive
application.
Id.
to
the
Rehearing
Order
where
FERC
stated
that
NCUC
its
projects
in
the
Id. 45.
aggregate,
Instead of assessing
FERC
would
require
Id.
the
aggregate
to
the
21
eleven
projects
in
VEPCOs
application.
whether
entitled
to
grant
to
rehearing
consider
here.
the
Agencies
broader
are
regulatory
See id.
Tie,
Idylwood,
Garrisonville,
and
Pleasant
View
the
merited
incentive
evidence.
reweigh
Proactive
Transformer
treatment
Replacement
is
not
Project
supported
by
(PTRP)
substantial
evidence.
We
determine
only
whether
FERC
22
for
its
action
including
rational
connection
Motor Vehicle
Mfrs. Assn v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 43
(1983) (quoting Burlington Truck Lines v. United States, 371
U.S. 156, 168 (1962)).
1.
NCUC argues the Lexington Tie and Idylwood Projects fail to
meet the nexus requirement because their pre-incentive ROE was
sufficient to attract investment.
of these projects and the fact that they were already underway
when the incentives issued, NCUC contends, VEPCO failed to show
that
the
incentives
decisions.
would
materially
affect
its
investment
We disagree.
In Order No. 679-B, FERC stated that there was no size cutoff
for
projects
when
determining
Id. 18.
eligibility
for
incentives
Id.
Moreover, as we
counter
to
Congresss
directive
to
drive
money
into
Id.
for
incentives
given
that
based
they
construction.
on
could
projects
help
that
attract
are
already
financing
or
underway,
accelerate
both
substantial
projects
satisfy
evidence.
the
Both
nexus
the
test
Lexington
is
supported
Tie
and
by
Idylwood
They resulted
elevation
and
the
use
of
new
technology.
See
Therefore, we affirm.
2.
fail
to
meet
the
nexus
test
because
they
The
basis
of
this
alternative--namely,
construction--exists
contention
above
for
is
ground
both
are
16 U.S.C.
that
rather
utility
not
lines.
less
than
We
approach
to
project.
To
the
contrary,
FERC
expressly rejected a requirement that utilities provide a costbenefit analysis, concluding that consumers would be adequately
24
three-prong
test
for
incentives
in
its
view,
Order No.
679-A 3.
In some respects, it appears NCUC is asking us to determine
whether
Order
No.
679
is
permissible
219].
construction
of
familiar
FERCs
Chevron
grant
of
test,
we
simply
incentives
to
VEPCO
will
for
determine
these
whether
projects
was
local
reliability.
opposition,
and
their
impact
on
regional
We affirm.
3.
NCUCs
granted
for
It
argues
that
final
challenge
FERCs
decision
is
is
to
not
the
incentive
supported
by
substantial
In fact,
course,
has
an
outsized
impact
on
the
projects
scope.
exhibit
transformers.
remand
for
that
listed
each
FERC
to
correct
of
the
thirty-two
targeted
its
error
and
reevaluate
PTRPs
of
additional
challenge--that
the
PRA--asks
PJMs
us
to
FERC
misunderstood
reweigh
the
the
evidence.
VEPCO used the PRA preformed by PJM as a starting point for its
10
26
to
replace.
FERC
determined
the
PTRP
would
Further, FERC
with
however
these
findings.
This
analysis
is
more
than
V.
In sum, we hold that in this case, FERC properly exercised
its
broad
change
in
discretion
its
in
declining
Rehearing
Order
to
and
apply
in
the
2010
evaluating
policy
VEPCOs
27