Professional Documents
Culture Documents
Eoi For Caustic Sodaplant
Eoi For Caustic Sodaplant
Eoi For Caustic Sodaplant
General Information
1.1
Company profile and location of the plant: NALCO was incorporated in 1981 following a major investment decision
by the Government of India to exploit a part of the Bauxite deposit
discovered in the East coast of India.
NALCO is operating a multi-location Bauxite Mines-Alumina -Aluminium
complex along with a Captive Power Plant, in the State of Orissa, India.
A major expansion programme (1st phase) was started in 1997/1998 and
the same has already been completed. Currently the organization is in
the midst of Phase-2 expansion.
The plant capacity and location of various units of the complex after
Phase-1 expansion and current expansion are as under:
Unit
Location
Current
Capacities
4.8 MTPY
Bauxite
Mines
Alumina
Refinery
Aluminium
Smelter
Captive
Power Plant
Panchpatmali,
Distt:Koraput,Orissa
Damanjodi,
1.575 MTPY
Distt:Koraput,Orissa
Angul,
0.345 MTPY
Distt,Angul,Orissa
Angul,
960 MW
Distt,. Angul, Orissa
Capacities after
expansion
6.3 MTPY
2.1 MTPY
0.460MTPY
1200 MW
Specialty Hydrate/Alumina
(Alumina Chemicals)
Aluminium Metal
Ingots
Sows
Billets
Wirerods
Alloy wire rods
Cast strips
5 Rolled Product
Aluminium Flat Rolled Products
1.2
Particulars
Paid-up Share Capital
As at
March 2007
664
Net Worth
7906
Sales Turnover
6517
2381
General
The company is listed on National Stock Exchange of India . The
registered office is located at Nalco Bhawan, P/1, Nayapalli,
Bhubaneswar-751013, Orissa, India. It is certified for ISO 9001: 2000,
ISO 14001 and OHSAS 18001. It has won several awards for
Environmental performance including the most coveted, Indira Gandhi
Paryavaran Puraskar- 2000, Pollution Control Excellence Award-2000,
and CII, Orissa, Environment Safety & Health Management Award2005.The Company has also won CAPEXIL Highest Export Award
continuously since 1988,the EEPC Export award, FIEO Niryat Shree
Award and many other awards for excellence in export performance.
1.3
Background
NALCO have decided to establish a Caustic Soda plant for producing
caustic soda to be used for our Alumina Plant at Damanjodi. The project
had been envisaged based on availability of Brine(salt) from coastal
Orissa and Andhra Pradesh.
It is proposed to locate this project in the vicinity of Alumina Refinery at
Damanjodi,Orissa. NALCO wants to set up a grass root plant for
production of caustic soda as well as want to have a flexibility of
producing and marketing different chlorine derivatives.
NALCO appointed M/s Lurgi India Ltd for preparation of Deatailed
Feasibility Report (DFR) for a 150,000 TPA Caustic Soda Plant at
Damanjodi,which consists of the following reports:
Market Survey Report.
Site Selection Report
Technology Selection report
Capacity Selection report
Detailed Feasibility Report
In this report process configuration of proposed plant has been
established based on feed stock availability, market analysis, site
selection, desired product pattern and the requirement of utilities,
chemicals and catalysts worked out. The report covers the description of
the projects and infrastructure facilities. The capital cost of the project
has been estimated and presented along with the financial analysis in
the report. The demand and supply forecasts presented in the report are
based on the information provided by M/s Nandini Chemicals, marketing
consultant engaged by Lurgi India. Plot plan for the project has been
included in this report.
1.5
Uhde
PPG BIZEC
Tokuyama Soda
Krebskosmo MZB
De Nora
OxyTech
1.6
Project Description
The proposed facilities comprise the following:
Process Unit
Caustic Soda Plant of 120,000 TPY capacity:
Consisting of salt handling, brine purification and filtration unit,
electrolysis unit, chlorine and hydrogen handling facilities,
Hypo unit
Hcl unit
Stable Bleaching powder Unit
.
Utility Facilities
Power requirement will be met from grid.
Offsite Facilities
The proposed offsite facility consisting of:
Storage Facility for Salt and other chemicals,
Caustic Soda (48%), Sodium hypo chlorite
tank, Hydrochloric Acid (33%), Bleaching tank
Sulphuric Acid (70%), Sulphuric Acid (98%)
Fire Fighting System
Lying of piping from port to plant area.
1.7
Project Schedule
A project execution plan was developed based on Lurgi's experience
and Licensors information or similar type of plant & considering the local
conditions. The Project Execution Plan is based on a phased approach
to the project.
The project is scheduled for commissioned within 24 months from
the selection of licensor including commissioning of 2 months or
28 months from the date of Project Zero date.
1.8
Capital Cost
The estimated investment cost for the proposed Caustic Soda Plant
(120,000 TPA) at Damanjodi on stand alone basis is Rs. 500 Crores
(INR 5 billion) with a foreign exchange component of Rs.110 Crores
(INR1.1 billion) as of April, 2007 price level and does not include
any future escalation. The above total project cost inc ludes a provision
of Rs. 40 Crores (INR400million) towards financial cost and Rs.16
Crores (INR160 million) towards margin money.
The cost estimates assumed to have the accuracy of level of +/10%.
1.9
Economic Analysis
The internal rate of return (IRR) on investment has been worked out.
Considering the project will start production from 2010-11 and using the
caustic soda for NALCOs own plant.
Salt
: 1,000 Rs/ ton
Caustic Soda (lye) : 14,000 Rs/ton
HCL
: 3,250 Rs/ton
Chlorine
: 6,000 Rs/ton
Stable Bleaching Powder: 13,600 Rs/ton
Electricity
:3.50 Rs/Kwh(from Grid)
Sensitivity Analysis
Sensitivity analysis (before tax) is carried out for increase and reduction of
10% in sales price, operating cost and project cost.
For 120,000 TPA Caustic Soda (stand alone) Plant
Variation
-10%
+10%
Project Cost
Product Price
Operating Cost
IRR on
Equity%
IRR on
Capital %
IRR
on IRR on IRR on
Equity %
Capital% Equity %
IRR on
Capital %
16.87
12.22
14.61
11.88
5.40
22.83
16.65
9.22
7.45
17.91
20.53
7.97
Synthetic Rutile
Considering the project cost between the EDC / VCM / PVC plants
separately, the cost for the EDC plant is much lesser than for the VCM /
PVC plants. Presently the PVC manufacturers are purchasing EDC from
abroad. The EDC produced can be easily sold in the Indian market.
Though setting up a Synthetic rutile plant is as profitable but the project
cost for synthetic rutile is almost double that of the EDC plant. Hence
EDC plant as chlorine derivative is selected.
Regarding capacity Caustic soda plant with 150,000 TPA along with
Ethylene Di Chloride plant of 100,000 TPA is best suited, as all chlorine
can be used totally for production of EDC.
The preliminary feasibility report also carried out for caustic soda
plant with one of the derivative plant by using produced chlorine.
PART-2
2.0
2.1.1 Land required on sub -lease basis for setting up of the Caustic Soda
Plant, railway siding, laboratory, office, loading& storing facilities etc.
2.1.2
QUALIFICATION CRITERIA
3.1
3.1.3 The Net worth of Firms should be positive as per the last audited
Balance Sheet.
4.0
JOINT VENTURE
If required by the interested Firm, NALCO may consider equity
participation in the proposed project up to 40%.
5.0
PREPARATION/SUBMISSION OF EOI
EOI outline requirements: The interested Firms are invited to furnish a
proposal in a format as outlined below in order to achieve the objective
of maintaining uniform proposal structure from all the Firms:
CHAPTER-I
CHAPTER-II
ORGANIZATION PROFILE
CHAPTER-III
CHAPTER-IV
CHAPTER-V
CHAPTER-VI
6.0
SUBMISSION OF EOI
Firms are expected to prepare EOI in accordance with requirement vide
Clause 3.0 and 4.0.The proposal along with all information and requisite
documents should be delivered at the following address latest by 31st
August, 2007.
N.Ravi
Senior Manager (BD)
National Aluminium Company Limited
Nalco Bhawan
P/1 ,Nayapalli
Bhubaneswar-751 013.
Place:Bhubaneswar
Date: 19.07.2007
N. Ravi
Sr.Manager (BD)
Telephone: 0674-2300789
Telefax:
0674-2300612
Mobile: +91-9437019892
E-mail: NRavi@nalcoindia.co.in