Professional Documents
Culture Documents
Contract Administration For Construction & Engineering Contracts - 1
Contract Administration For Construction & Engineering Contracts - 1
Presented by:
HSKS
9.00 a.m.
Registration
9.00 a.m.
10.30 a.m.
Session 1
10.30a.m.
10.45a.m.
Tea/Coffee Break
10.45 a.m.
12.30 noon
Session 2
12.30 noon
1.00 p.m.
Q & A Session
1.00 p.m.
2.00 p.m.
Lunch Break
2.00 p.m.
3.15 p.m.
Session 3
3.15 p.m.
3.30 p.m.
Tea/Coffee Break
3.30 p.m.
4.45 p.m.
Session 4
4.45 p.m.
5.00 p.m.
Q & A Session
End of Day 1
5.00 p.m.
HSKS
10.30 a.m.
Session 1
10.30a.m.
10.45a.m.
Tea/Coffee Break
10.45 a.m.
12.30 noon
Session 2
12.30 noon
1.00 p.m.
Q & A Session
1.00 p.m.
2.00 p.m.
Lunch Break
2.00 p.m.
3.15 p.m.
Session 3
3.15 p.m.
3.30 p.m.
Tea/Coffee Break
3.30 p.m.
4.45 p.m.
Session 4
4.45 p.m.
5.00 p.m.
Q & A Session
End of Course
5.00 p.m.
HSKS
CONTENTS
1.0
2.0
3.0
4.0
5.0
PAYMENTS/COMMERCIAL MATTERS
6.0
VARIATIONS/CHANGES
7.0
8.0
9.0
10.0
DEFECTS
11.0
HSKS
CONSTRUCTION/
ENGINEERING CONTRACTS:
INTRODUCTION
HSKS
1.0
GENERAL CONTRACTS
2.
ENGINEERING/CONSTRUCTION CONTRACTS
2.
MANAGEMENT TYPES
3.
4.
MISCELLANEOUS METHODS
HSKS
CONTRACT DEFINITIONS
2.
ELEMENTS OF CONTRACT
3.
4.
MISCELLANEOUS ISSUES
HSKS
SIMPLE
CONTRACTS
SPECIALITY
CONTRACTS
(DEED)
COLLATERAL
CONTRACTS
MATERIAL
& LABOUR
CONTRACTS
ORAL
CONTRACTS
LABOUR
CONTRACT
EXPRESS
CONTRACTS
GENERAL
CONTRACTS:
TYPES
MATERIAL SUPPLY
CONTRACT
MAIN CONTRACTS
INDEPENDENT
CONTRACTS
SUB-CONTRACTS
EMPLOYMENT
CONTRACTS
SUB-SUB
CONTRACTS
ENGINEERING/
CONSTRUCTION
CONTRACTS:
TYPES
TYPE OF CONTRACT
MESUREMENT
CONTRACTS
LUMP SUM
CONTRACTS
BASED ON
APPROXIMATE
QUANTITIES
COST PLUS
FIXED FEE
COST
REIMBURSEMENT
CONTRACTS
COST PLUS
PERCENTAGE
BASED ON A
SCHEDULE
COST PLUS
FLUCTUATING FEE
TARGET COST
VALUE COST
TRADITIONAL
GENERAL
CONTRACTTING
PACKAGE
DEAL TYPE
MANAGEMENT
TYPE
MANAGEMENT
CONTRACTING
CONSTRUCTION
MANAGEMENT
BUILD, OPERATE
& TRANSFER
ENGINEERING, PROCUREMENT,
CONSTRUCTION & COMMISSIONING
MISCELLANEOUS
METHODS
FAST
TRACKING
PARTNERING
TURNKEY
TURNKEY
1985
1990
1995
2000
95%
76%
31%
20%
2.0 MANAGEMENT
CONTRACTING
2%
3%
2%
1%
3.0 CONSTRUCTION
MANAGEMENT
1%
3%
9%
10%
2%
15%
52%
60%
2%
5%
8%
6.0 OTHER
MISCELLANEOUS
1%
1%
1%
HSKS
EMPLOYER
PROFESSIONAL
TEAM - DESIGN AND
CONTRACT ADMINISTRATION
1.
2.
3.
4.
Architect
Engineers - C&S, M&E
Quantity Surveyor
Other Specialist
MAIN CONTRACTOR
(MC)
DOMESTIC SUPPLIER
(DS)
SUBSUB-SUB
CONTRACTORS
Key
_______
_____
:
:
SUB--SUB SUPPLIERS
SUB
NOMINATED SUPLLIER
(NS)
SUBSUB-SUB
CONTRACTORS
SUBSUB-SUB SUPPLIERS
Contractual Link
Responsibility
HSKS
EMPLOYER
PROFESSIONAL
ADVISORS
1.
2.
3.
4.
Architect
Engineers - C&S, M&E
Quantity Surveyor
Other Specialist
1. Setting up Employers
Requirements
2. Auditing role during
construction
D & C CONTRACTOR
1.
2.
3.
4.
Architect
Engineers - C&S, M&E
Quantity Surveyor
Other Specialist
PROFESSIONAL
TEAM
:
:
SUBSUBSUPPLIER
1. Detailed Design
2. Construction supervision
SUBSUB-SUB
CONTRACTORS
Key
_______
_____
SUBSUBCONTRACTOR
SUBSUB-SUB SUPPLIERS
SUBSUB-SUB
CONTRACTORS
SUB--SUB SUPPLIERS
SUB
Contractual Link
Responsibility
HSKS
EMPLOYER
PROFESSIONAL TEAM
1.
2.
3.
4.
MANAGEMENT
CONTRACTOR
(MC)
Architect
Engineers - C&S, M&E
Quantity Surveyor
Other Specialist
TRADE
CONTRACTOR
TRADE
CONTRACTOR
TRADE
CONTRACTOR
Key
Responsibility
HSKS
EMPLOYER
PROFESSIONAL
TEAM
1.
2.
3.
4.
CONSTRUCTION
MANAGER (CM)
Architect
Engineers - C&S, M&E
Quantity Surveyor
Other Specialist
Key
_______
: Contractual Link
_____
: Responsibility
TRADE
CONTRACTORS
TRADE
CONTRACTORS
HSKS
*
1.0
DEFINATIONS
PER ANSON
*
*
*
*
2.0
CONTRACT -
CLEAR +
OFFER
UNQUALIFIED
ACCEPTANCE
+ CONSIDERATION =
CONTRACT
CONTRACT
(LEGAL
AGREEMENT)
FIRM OFFER/
PROPOSAL
+
UNQUALIFIED
ACCEPTANCE
+
CONSIDERATION
INTENTION TO CREATE
LEGAL RELATIONS
FREE CONSENT
CERTAINTY OF TERMS
LEGAL CAPACITY TO
CONTRACT
PHYSICAL/LEGAL
POSSIBILITY
DEFINITION/
MEANING
CHARACTERISTICS
MAIN TYPES
DISADVANTAGES
ADVANTAGES
FIG. 1-12 :
STANDARD
FORMS OF
CONTRACT
TYPES
PURPOSE
GOVERNMENT/
PUBLIC SECTOR
INTERNATIONAL
CONTRACTS
PRIVATE SECTOR
1. FIDIC Conditions
2. ICE Conditions
JKR / PWD
MISCELLANEOUS
3. IEEE Conditions
4. IMechE Conditions
5. JCT Conditions
CIVIL ENGINEERING
WORKS
BUILDING WORKS
M & E WORKS
IEM Conditions
IEM Conditions
- IEM.CE 2011
- IEM.CES 1/90
IEM.ME 1/94
COMMENCEMENT OF
CONTRACT AT SITE
HSKS
2.0
APPROACHES IN:
1.
2.
FORMALITIES:
1.
2.
CONDITIONS PRECEDENT
INSURANCES, PERFORMANCE BONDS, ETC.
SUBMITTALS :
1.
2.
3.
4.
5.
6.
CONSTRUCTION DRAWINGS
SHOP DRAWINGS
SAMPLES
QA AND QC DOCUMENTS
HEALTH AND SAFETY DOCUMENTS
METHOD STATEMENTS
TEMPORARY WORKS
MISCELLANEOUS ISSUES
HSKS
RELEVANT CASES
1. THE RADIO & GENERAL TRADING CO. SDN. BHD. V WYASS & FREYTAG (M)
SDN. BHD. [1998] 1 MLJ 346
2. LEC CONTRACTORS (M) SDN. BHD. V CASTLE INN SDN. BHD. & ANOR [2000]
3 MLJ 339
3. KLEINWORT BENSON LTD. V MALAYSIA MINING CORP. BHD [1989] 1 WLR 379
4. NANYANG INSURANCE CO. LTD. V SALBIAH & ANOR [1967] 1 MLJ 94
5. SURREY HEALTH
[1988] 42 BLR 25
BOROUGH
COUNCIL
LOVELL
CONSTRUCTION
BHD
9. YIP SHOU SHAN V SIN HEAP LEE MARUBENI SDN. BHD. [2002] 5
43, HC`
MLJ
HSKS
TAKING OVER OF
THE SITE
SITE POSSESSION
COMMENCEMENT
OF CONTRACT
COMMENCEMENT:
COMMON LABELS
COMMENCEMENT
OF OPERATIONS
ON SITE
COMMENCEMENT
OF CONTRACT
PERIOD
COMMENCEMENT
OF WORKS
PARENT COMPANY
GUARANTEE
INSURANCE
PERFORMANCE BOND
PROTECTION AGAINST
CONTRACTORS FAILURES:
COMMON MECHANISMS
LETTER OF COMFORT
STANDBY LETTER
OF CREDIT
LETTER OF AWARENESS
COMMON MECHANISMS/
INSTRUMENTS: TYPES
PURPOSE
Performance Bonds
Miscellaneous Types:
1.
2.
3.
Letters of Comfort
Standby Letters of Credit
Insurances
NATURE
Contractual performance of
Company within a corporate
group is underwritten by other
members of group
E.g. Subsidiary and Holding
Company
PARENT COMPANY
GUARANTEES
PROCEDURAL
REQUIREMENTS
USE
Owing to requirements of
applicable law e.g. company
law, etc.
Preliminary review
Contd.
Contn.
MISCELLANEOUS MECHANISMS/
INSTRUMENTS
PERFORMANCE BONDS
Reasons for
Typical contents
Legal effect of letter
DEFINITION
DEFINITION
Means of
guaranteeing to
the employer:
1. The
contractors
financial
viability and
2. Contractors
ability to
perform
obligations
under the
contract
Features of
local practice
Rules of
construction
and
enforcement
Reasons for
Comparison with letters of
comfort
Typical contents
Legal effect of letter
DURATION
DURATION OF
OF
LIABILITY
LIABILITY
TYPES
TYPES
STANDBY LETTER
OF CREDIT
LETTER OF AWARENESS
LETTER OF COMFORT
Normally stipulated in
bond. Types include:
1. Entire duration of
contract
2 Up to CPC Construction
Bond
3 CPC to Final
Certificate
Maintenance
Bond
Reasons for
Comparison with
Unconditional/On-Demand Bond
Obligations under
Legal effect of letter
PROCEDURAL
PROCEDURAL
REQUIREMENTS
FINANCIAL LIMITS
OF LIABILITY
Normally
stipulated in
Bond itself.
Normally 5-10%
Sometimes
higher
See use of
Indexed
Performance
Bonds
INSURANCE
Reasons for:
Legal effect of Insurance
Comparison with the other
mechanisms/instruments
NONPROVISION OF
OF
NON--PROVISION
BOND/GUARANTEE
RELEASE OF BOND
/GUARANTEE
Preliminary
review
Timing for
submission
Seven main
circumstances
Checks for
authenticity
Consequences of
failure to submit:
Check for
compliance with
formalities
Effect of
breaches of
terms and
conditions
1. Contract
provisions
2. Common law
rules
4 Up to date of
release stipulated
by guarantor
Voluntary assumption of
specified risk in return for an
agreed payment
CATEGORY I
CATEGORISATION
TYPES
DEFINITION
PURPOSES
Liability based
Loss based
Difference: basis of
compensation
CATEGORY II
PRINICPAL TYPES
Liability based
Loss based
Indemnification of insured
against damages payable to
3rd party
Examples:
Examples:
Management Corporation:
Common Types
1.
2.
3.
1.
2.
Contd.
FEATURES AND
CONDITIONS
PROCEDURAL
REQUIREMENTS
FAILURE TO INSURE
FAILURE TO INSURE
2 Common alternatives:
1. Before commencement of
work/contract; or
IMPORTANT
IMPORTANT
STANDARD
STANDARD
CONDITIONS
CONDITIONS
BASIS
BASIS OF
OF
CONTRACTING
CONTRACTING
Submission of
proposal
Issue of policy
Effect of :
1. Contracts of
uberrimae
fidei
2. Cover notes,
etc.
PARTIES
PARTIES
EFFECTING POLICY
POLICY
4. Following a loss
event
5. As to subrogation
6. On contribution
Various possibilities:
Typical parties:
1.
2.
3.
4.
3. As to risk
Employer
Contractor
Sub-contractors
Selected 3rd parties
Effect of cross
liability provisions
DURATION
DURATION
OF
OF POLICY
POLICY
COMMENCEMENT
COMMENCEMENT
OF
OF POLICY
POLICY
1. Named party
2. With insurable
interest
1. Condition precedent
to liability
2. During
work/construction
General rule:
Different formulae:
1. Date of
commencement of
contract; or
1. Up to issue of CPC
2. Date of
commencement of
work on site; or
3. Up to issue of Final
Certificate
3. Date of delivery of
material, etc.
2. Up to issue of CMGD
FINANCIAL
FINANCIAL LIMITS
LIMITS
OF
OF LIABILITY
LIABILITY
Guidelines for
estimating limits.
General rule on
deductibles/excess
clauses
4. Up to Final Certificate
plus fixed period
Normally stipulated
by employer in
tender/contract
Requirements
pertaining to extension
of period
TERMINATION
TERMINATION
OF
OF POLICY
POLICY
Three main methods:
1. Satisfaction of
conditions
precedent in
contract e.g. issue
of CPC, etc.
2. Termination of
policy by
breach/mutual
agreement
3. Lapse of insurance
period and/or
extension
PROVISIONS
FOR
MEANING
EXPRESS
Licence revocable by
Employer at any time
If not expressed, by
Or in Contract
Contractor entitled to
Sole/exclusive
possession
GENERAL
LEGAL POSITION
IMPLIED
No
EXCEPTIONS
TO GENERAL
PRINCIPLE
Express Stipulations
Case Law
POSSESSION
ON PIECEMEAL
BASIS?
LATEST LEGAL
POSITION
Sufficient degree
of possession/
access
To execute work
unimpeded
To be able to
perform work
FAILURE TO GIVE
POSSESSION
EXCEPTIONS
Law
GENERAL
PRINCIPLE
In Letter of
Acceptance
POSTPONEMENT
DEGREE
Express contract
stipulations permitting
postponement
GENERAL
LEGAL POSITION
EFFECT
General Position: No
Breach of Contract
Exceptions:
Entitles Contractor to
rescind Contract.
Contractor entitled to
loss occasioned
Contractor entitled to
EOT if expressly
permitted
contractually
Otherwise, LAD
cannot be imposed
a) Express
stipulations to
contrary
b) Where Common
Law applies
TIMING
On Date of Commencement
of Contract /
MATTERS
DEALT
PURPOS E
To officially handover
Possession of Site to
the Contractor
WHO
PREPARES ?
EXPLANATION
OF CONTRACT
REQUIREMENTS
LETTER OF
DELEGATION
OF POWERS
PARTICIPANTS
MINUTES
INTRODUCTION
OF PROJECT
MEMBERS
COPY OF
CONTRACT
DOCUMENTS
PRICED COPY
OF B.Q.
Contract Administrator
DISTRIBUTION/
CIRCULATION
To all parties
HANDOVER
OF VARIOUS
DOCUMENTS
SET OF
CONSTRUCTION
DRAWINGS
SET OUT
PROCEDURES
COVERING
Inspection of Work
Interim Valuations
Claim Procedures
WORK PROGRAMME
MISCELLANOUES
REPORTS
AND DOCUMENTS
METHOD STATEMENTS
DESIGN AND
CALCULATIONS FOR
TEMPORARY WORKS
QA/QC DOCUMENTS
MONITORING OF
WORK PROGRESS
HSKS
3.0
PROGRAMMING OF WORKS
PARTIES RESPONSIBLE:
1.
2.
3.
EMPLOYER
MAIN CONTRACTOR
CONTRACT ADMINISTRATOR
PROGRESS REPORTS
SITE RECORDS
MEETINGS:
1.
2.
3.
4.
SITE POSSESSION
PROGRESS/SITE
NSC COORDINATION
AD-HOC
MISCELLANEOUS ISSUES
HSKS
RELEVANT CASES
1.
2.
3.
4.
5.
71 BLR 1
6.
MORGAN BRANCH
HSKS
PRINCIPAL ACTIVITIES
IMPORTANT
MILESTONES FOR
EMPLOYER TO MEET
SEQUENCE OF
ACTIVITIES
WORK PROGRAMME:
PRINCIPAL CONTENTS
IMPORTANT
MILESTONES FOR
CONTRACTOR TO MEET
TIMING OF ACTIVITIES
IDENTIFICATION OF
CRITICAL ACTIVITIES
AND CRITICAL PATH
RESPONSIBILITY
Express Provisions
By Implication
METHOD OF
WORKING
BAR
CHARTS
FORM
MEANING
CONTENTS
Sequence and
Timing of Activities
Critical Milestones
FOR CONTRACT
ADMINISTRATOR
SEQUENCE OF
WORKING
CRITICAL PATH
ANALYSIS
PERT
PRIMIVERA/
MICROSOFT
PROJECT
PROJECT
PURPOSE
OPTIONS ON
SUBMISSION
PART OF
CONTRACT?
Approval
Rejection
Withholding of
Approval
ALTERATION/
REVISION
General
Policies
Mode of
Alternatives /
Revision
Effect of
Alternatives/
Revision
FOR
CONTRACTOR
MISCELLANEOUS
PART OF TENDER
SUBMISSION?
SUBMITTED AFTER
TENDER AWARD
MISCELLANEOUS
PURPOSES
PROGRESS MONITORING:
EMPLOYERS PURPOSES
TO PLAN AND
STREAMLINE FINANCIAL
ARRANGEMENTS
TO OBVIATE DEFAULT
TO TAKE NECESSARY
REMEDIAL MEASURES IF
DELAY OCCURS OR IF
EMPLOYER IS AT FAULT
TO WARN CONTRACTOR
TO TAKE REMEDIAL
MEASURES IN CASE
DELAY OCCURS
PURPOSE
DURATION
From Site
Possession
To Issue of Final
Certificate
Normally up to
Practical Completion
only
SITE
POSSESSION
MEETINGS
Primary Purposes
Secondary Purposes
METHODS
Use of Contractors
Work Programme
SITE PROGRESS
MEETINGS
SUBSUBCONTRACTORS
MEETING
Employer/ contract
administrator
Contractor
COORDINATION/
PROJECT
MANAGEMENT
MEETINGS
On regular basis
Normally monthly
Maybe
i. Weekly
ii. Fortnightly
iii. Quarterly, etc.
SITE
RECORDS
PROGRESS
MEETINGS
FREQUENCY/
NATURE OF
CHECKS
PARTIES
RESPONSIBLE
BASIS
ADAD-HOC
HOC
MEETINGS
DURATION
PURPOSE
OFFICIAL WORK
RECORDS
METHODS
OFFICIAL
PROGRESS
REPORTS
EVIDENTIAL VALUE
SITE
DIARY
SITE POSSESSION
MEETINGS
MISCELLANEOUS
MEETINGS
POST CONTRACT
AWARD STAGE:
PRINCIPAL TYPES
OF MEETINGS
AD-HOC
MEETINGS
SUB-CONTRACTORS
MEETINGS
SITE PROGRESS
MEETINGS
COORDINATION/
PROJECT
MANAGEMENT
MEETINGS
ENABLE
CONTRACTOR TO
PERMIT WORK
PROGRESS TO
Officially present
progress report
Be reviewed on
regular basis
Present problems
encountered
FINANCIAL ISSUES
3RD PARTY
ISSUES AFFECTING
CONTRACT
CONTRACT
ADMINISTRATOR
Chairs Meeting
Main participant
S.O./ Contract
Administrator
Main participant
DISTRIBUTION/
CIRCULATION
To all parties/
attendees
MISCELLANEOUS
ISSUES
MAIN
CONTRACTOR
PARTICIPANTS
MINUTES
WHO
PREPARES?
MISCELLANEOUS
ISSUES/
MATTERS DEALT
PURPOSE
TIMING
NSCs
CONSULTANTS
Observers Only
Participants if contract
administrator's assistants/
representatives
By invitation only
EMPLOYER
Observer only
ISSUES/
MATTERS DEALT
PURPOSE
TIMING
If necessary more
frequently
TO ENABLE SUBSUBCONTRACTOR TO
TO PERMIT
CONTRACTOR TO
Officially present
progress report to
Contractor
Present problems
encountered
PARTICIPANTS
MINUTES
WHO
PREPARES?
Main
Contractor
DISTRIBUTION/
CIRCULATION
To all parties/
attendees
NOMINATED
SUBSUBCONTRACTORS
DOMESTIC
SUBSUBCONTRACTORS
Chairs Meeting
OTHERS
(BY
INVITATION)
Employer
Third Parties
COORDINATION
MATTERS
SITE PROBLEMS
FINANCIAL ISSUES
Design
Possession
Payments
Authorities
Site Work
Access
V.O.s
Utilities Providers
Security
Claims
Others
MISCELLANEOUS
ISSUES
Contract
Administrator
CONVENORS
(AS APPLICABLE)
TIMING
AS AND WHEN
NECESSARY FROM
TIME TO TIME
The Employer
The Contractor
The Sub-Contractors
PURPOSE
USUALLY
DICTATED BY
CIRCUMSTANCES
EMERGENCY
ISSUES
TO DISCUSS
SPECIFIC ISSUES /
MATTERS
ADMINISTRATIVE
MATTERS
TECHNICAL
ISSUES
FINANCIAL
ISSUES
Site Issues
Payments
Design
Training
V.O.s
Construction/Installation
Maintenance
3rd
Claims
Testing and
Commissioning
As-Built Records
Defects
Party Issues
MISCELLANEOUS
ISSUES
PURPOSE
DURATION
Completion of works
Normally up to Practical
Completion only
PROVIDE NECESSARY
INFORMATION/ EVIDENCE
TO
EVALUATE
CONTRACTORS
CONTRACTOR
CLAIMS TO
REVIEW WORK
PROGRESS
Contractors Scope
Extension of Time
NSCs/DSCs Scope
Additional Work
Miscellaneous matters
EVIDENTIAL VALUE
METHODS
OFFICIAL
PROGRESS
REPORT
OFFICIAL WORK
RECORDS
PERMIT
DECISION MAKING
SITE DIARY
DULY SIGNED/
ENDORSED RECORDS
ACKNOWLEDGEMENT
OF RECEIPT RECORDS
TIMING OF
SUBMISSION
DAILY
WEEKLY
PURPOSE
PROCEDURAL
MATTERS
CONTENTS
USE OF
DESIGNATED
STAFF FOR
FORTNIGHTLY
Preparing
Maintaining
Submitting
RECORD OF
SITE INFORMATION
SITE WORK/
ACTIVITIES
FOR CONTRACT
ADMINISTRATION
RECORD
OF WORKERS
Planned
Skilled
Undertaken
Unskilled
SIGNING OR
ENDORSEMENT
By authorized
Person(s)
TIME OF
ENTRY
S.O/ Contract
Administrator
Daily
FOR BASIS
OF OFFICIAL
PROGRESS REPORT
RECORD OF
PLANT/MACHINER
Y
On site
WEATHER
CONDITIONS
SAFE
KEEPING
By S.O./Contract
administrator
Up to lapse of
period of
limitation
PROBLEMS
ENCOUNTERED
INSTRUCTIONS
Affecting work
Design
Received
Delaying site
operations
Site
Carried Out
Coordination
Outstanding
MISCELLANEOUS
Site/ Factory
Visits
Inspections
NATURE
DURATION
Preferably kept by
each and every site
personnel
From commencement of
work on site until
completion
Otherwise by
designated site
supervision team
member
Undertaken
ENTRIES ON
DAILY BASIS
SITE WORK/
ACTIVITIES
PROCEDURAL
MATTERS
CONTENTS
By designated
person
PROBLEMS
ENCOUNTERED
INSTRUCTIONS
As to Site Work
Issued to Contractors
Coordination
Carried out by
Contractor
PRESENTATION
ON REQUEST/
DEMAND
CHECKING /
ENDORSEMENT
By Employers
Representative/
Designated
person
Accuracy of
entries
RECORD OF
Contractors
defaults
/omissions
By Employer/
S.O./ any
interested party
MISCELLANEOUS
Site/ factory visits
Weather conditions
Disruption to site
activities
SAFE KEEPING/
CUSTODY
By S.O./ contract
administrator
Up to lapse of
period of
limitation
ATTACHMENTS
As-Built sketches,
drawings, diagrams,
etc.
As-erected/ AsInstalled Work/ plant,
etc.
SUPERVISION OF WORKS/
CONTRACT ADMINISTRATION
HSKS
4.0
1.0
2.0
SUPERVISION
FORMS
DURATION
LEVEL
LIABILITIES
3.0
ENSURE WORKS
SATISFACTORILY
COMPLETED WITHIN
ORIGINAL CONTRACT PERIOD
AND PRICE
CONTRACT
ADMINISTRATION:
PRIMARY PURPOSES
SUPERINTENDING
OFFICER/ S.O.
CONSTRUCTION
MANAGER
PROJECT DIRECTOR
EMPLOYERS
REPRESENTATIVE
CONTRACT
ADMINISTRATORS:
COMMON
DESIGNATIONS
ARCHITECT
ENGINEER
AS TO
RIGHTS/ DUTIES UNDER
THE CONTRACT
WITH IMPLIED/
OSTENSIBLE
AUTHORITY
WITH EXPRESS
AUTHORITY
AS TO MATTERS
OF COST
AS AN AGENT
OF THE EMPLOYER
AS TO OTHER
MATTERS
AS AN ADVISOR
TO THE EMPLOYER
CONTRACT
ADMINISTRATOR:
RANGE OF ROLES
PERFORMED
AS AN INDEPENDENT/
IMPARTIAL
ADJUDICATOR
AS AN INDEPENDENT
CONTRACTOR
WHERE SUCH
WORK
IS REQUIRED
POSTCONTRACT
FOR MAINLY
DESIGN/
DETAILING
WORK
AS TO DISPUTE
RESOLUTION
AS TO
CERTIFICATION
TERMS OF
REFERENCE OF
APPOINTMENT
CONDITIONS
OF CONTRACT
BEING
ADMINISTERED
IN-HOUSE EMPLOYEE
CONDITIONS
OF
ENGAGEMENT/
SERVICES
AGREEMENT
CONDITIONS OF
CONTRACT
BEING
ADMINISTERED
EXTERNAL BODY/PERSON
ARCHITECT
SPECIALIST
CONSULTANT
PROJECT MANAGER
CIVIL ENGINEER
CONTRACT ADMINISTRATORS
REPRESENTATIVES/ ASSISTANTS:
TYPICAL EXAMPLES
QUANTITY SURVEYOR
STRUCTURAL ENGINEER
MECHANICAL ENGINEER
ELECTRICAL ENGINEER
OVERALL SUPERVISION
PROGRESS MONITORING
ADMINISTRATION OF PAYMENTS
ISSUING INFORMATION,
DRAWINGS, DETAILS, ETC.
ORDERING VARIATIONS
ISSUING RELEVANT INSTRUCTIONS
INSPECTIONS OF WORKS
ADVISING EMPLOYER
CLOSING-OFF CONTRACT
FULL-TIME SUPERVISION
NOMINAL SUPERVISION
STANDING
SUPERVISION
FORMS OF SUPERVISION:
COMMON LABELS
PERIODIC SUPERVISION
CONSTANT SUPERVISION
PART-TIME SUPERVISION
TYPICAL
CLAUSES IN
AGREEMENTS
TYPICAL
PROVISIONS IN
BYBY-LAWS
Engineers Agreement:
NATURE
AND MEANING
Architects Agreement
1. Clause 5(4)(iv) Part II:
Architects (Scale of
Minimum Fees)
(Amendment) Rules 1992
2. Clause 9 Conditions of
Engagement of Architect
PURPOSES
1. To ensure contractor
carries out work in
accordance with contract.
2. To enable contract
administrator to discharge
his obligations to employer.
3. To enable contract
administrator to meet his
statutory obligations
LEVEL OF
SUPERVISION
REQUIRED
DURATION
Determining factors:
2. Applicable statutory
provisions e.g. By-Laws
1. Up to issue of Practical
Completion; or
3. Up to issue of Certificate of
Making Good Defects
Common practice is up to issue of
Certificate of Making Good
Defects
Typical examples:
1. Resident architect/engineer
2. Clerk-of-works.
3. Other relevant staff
Prevailing Forms:
1. Category I: Fulltime/Standing/ Constant
supervision
2. Up to application of certificate
for occupation; or
1. Conditions of engagement
2. Conditions of engagement
Determined by:
RESIDENT
SITE STAFF
Engagement:
Responsibilities of:
Legal Position:
1. Must be reasonable for
works involved
1. Contractual
2. In tort
3. Statutory
1. By employer; or
2. By contract administrator
LIABILITIES
Position of contract
administrators who are
professional engineers,
architects, etc.
1. RSS
2. Contract Administrator
CONTRACTUAL
LIABILITY
LEGAL KNOWLEDGE
AND PERSONAL DUTY
HEADS OF LIABILITIES
Three main categories:
1. Contractual
2. Tortious
3. Statutory
Nature of matters.
Characteristics:
Consequences of failure
DEFENCES
2. Concurrent/complementary
Prove no valid
express/implied contract
of engagement
STANDARD OF CARE
GENERAL POSITION
Contract of engagement:
1. Standard forms, or
2. Bespoke Forms
EFFECT OF BREACH
NEGLIGENCE
GENERAL POSITION
Common Forms:
1. Acts/omissions
2. Mis-statements
BASIC
ELEMENTS
DEFINITION
Laid down in
Donoghue v
Stevenson
Neighbourhood
principle
D owed P duty of
care
Application of the
Bolam Test
Consequence: P
suffered
loss/damage
Use of Reasonable
Man test
Use by Malaysian
Courts
Loss/damage
suffered not remote
Important elements:
1. Causation
2. Forseeability
STANDARD
OF CARE
Criterion: Objective
Less onerous
Proscribe use of
hindsight
See Eckersly v
Binnie & Partners
Per Hunter v
Henley
2. Fitness for
purpose
Only 3 types:
1. Deny existence of
duty of care
No liability to
contractor
Possible
exceptions:
See Para 5.9B5.
LIABILITY TO
3RD PARTIES
DEFENCES
1. There is a usual
and normal
practice
Use of standards
prevailing at time of
default
2 Categories:
1. Reasonable
skill & care
ESTABLISHING
LIABILITY
REASONABLE
SKILL & CARE
3. Show service
rendered meets
Bolam Test
No immunity to suit:
Sutcliffe v Thackrah
STATUTORY LIABILITY
LIABILITIES UNDER
DELEGATED
LEGISLATION
DIRECT
STATUTORY LIABILITY
GENERAL POSITION
PROFESSIONAL
LIABILITY
Various sub-heads:
Penalties/sanctions stipulated
in the By-Laws
Possible sanctions:
1. Fine
2. Suspension
3. Cancellation of
registration
PAYMENTS/
COMMERCIAL MATTERS
HSKS
5.0
PAYMENTS/COMMERCIAL MATTERS
PAYMENT TO SUBSUB-CONTRACTORS
BACK TO BACK
BACK PAYMENTS
RELEVANT CASES
GUNUNG BAYU SDN. BHD. V SYARIKAT PEMBINAAN PERLIS SDN. BHD. [1987] 2 MLJ 332
HAJI ABU KASSIM V TEGAP CONSTRUCTION SDN. BHD. [1981] 2 MLJ 149
KAH SENG CONSTRUCTION SDN. BHD. V SELSIN DEVELOPMENT SDN. BHD. [1997] 1 CLJ
SUPP 448
YONG MOK HIN V UNITED MALAY STATES SUGAR INDUSTRIES LTD. [1966] 2 MLJ 286
JALLCON (M) SDN. BHD. V NIKKON METAL (M) SDN. BHD. (No. 2) [2001] 5 MLJ 716, HC.
HSKS
QUANTUM/AMOUNT
SET-OFF/DEDUCTIONS
ENFORCEMENT/HONOURI
NG
TIMING
PERIODIC SCHEDULE
DURING CURRENCY
OF THE CONTRACT
OF WHOLE
CONTRACT SUM
STAGES/MILESTONE
PAYMENT
PHYSICAL WORKS
PERIODIC SCHEDULE
AFTER COMPLETION/
END OF CONTRACT
ADVANCE PAYMENT
FINANCIAL
OF PART OF
CONTRACT SUM
AFTER ISSUE
OF CPC
AFTER COMPLETION/
END OF CONTRACT
AFTER
ISSUE OF CPC
AFTER ISSUE OF
FINAL CERTIFICATE
MISCELLANEOUS/
METHODS
AFTER ISSUE OF
FINAL CERTIFICATE
START
Contract administrator to
resolve all preliminary issues
Yes
Yes
No
Yes
Have these
been formalized by all the
parties?
No
Contract administrator
to take necessary
action forthwith
Yes
Contract administrator to issue
formal record of issues agreed
upon by all relevant parties
No
Yes
Has he
executed any physical
work?
No
Yes
Has he
delivered materials to
site?
No
Contractor not
entitled to any
payment
Yes
Prima facie, contractor
may be entitled to payment
Contract administrator
not obliged to initiate
the progress payment
Establish if it is necessary
for the contractor to apply for
the required payment
No
FIG. 5-4: FLOWCHART ON GENERAL PROCEDURE FOR PROCESSING OF PAYMENTS (PART II)
HSKS
Contractor not
obliged to apply
No
Is it mandatory?
Yes
Contract administrator
obliged to initiate
process on his own
volition
Has
contractor complied with
requirements?
No
Contractor may
not be entitled to
payment until
he satisfies
pre -conditions
Yes
Contract administrator to proceed
with the next stage i.e. valuation
Has the
date of valuation been
reached?
No
Yes
Have the
relevant pre-conditions been
fulfilled?
No
Yes
No
Have the
parties involved been
identified?
Yes
Deficiencies/omissions
to be addressed
forthwith to enable
process to continue
No
Has the
method for valuation been
confirmed?
Yes
FIG. 5-5: FLOWCHART ON GENERAL PROCEDURE FOR PROCESSING OF PAYMENTS (PART III)
HSKS
Yes
Does the
contractor agree with the valuation?
No
Yes
Does he
sign off the
valuation report?
No
Valuation deemed to have
been accepted by the
contractor
No
Does he officially
register his protest with
valuers?
Yes
Do the valuers
consider the objections
protest?
Yes
Do they
agree with the
objections?
No
No
Yes
Valuers may revise/amend
the valuation as necessary
Does the
Contractor
protest to the
certifier?
No
Yes
FIG. 5-6: FLOWCHART ON GENERAL PROCEDURE FOR PROCESSING OF PAYMENTS (PART IV)
HSKS
Is the valuation
report complete, sufficient and
accurate?
No
Deficiencies/
omissions may
compromise the
certification
Yes
Certifier to take
objections into
consideration before
undertaking certification
Yes
Has the
contractor any valid grounds
for objecting?
No
Certifier not to consider
objections any further
Is the date
for certification
imminent?
Yes
No
Should in
his discretion a
certificate be
issued?
Yes
No
Yes
Certifier to proceed with the
necessary certification procedures
No
Yes
Have all
the stipulated pre-conditions been met?
No
Yes
Is the
subsequent Interim Certificate
due?
No
Yes
Have all
the relevant pre-conditions
been met?
No
Prima facie,
certificate cannot
be issued
Yes
Certifier to proceed with
preparation of Interim Certificate
Is there a
standard form of certificate prescribed?
Yes
Use the
standard form
as prescribed
No
Utilize the form
unless found
not suitable
Yes
FIG. 5-8: FLOWCHART ON GENERAL PROCEDURE FOR PROCESSING OF PAYMENTS (PART VI)
HSKS
Yes
No
Are
there any official
assignees?
Yes
Amount certified
for such parties
to be indicated
separately in certificate
No
No
Are
all procedural requirements met?
Yes
No
Are
all formal requirements
met?
Yes
Certificate may be
challenged as invalid and
unenforceable, if and
when issued
No
Is the signatory an
authorized person under the
contract?
Yes
Have all the
relevant checks for errors,
etc. been undertaken?
No
Yes
U
FIG. 5-9: FLOWCHART ON GENERAL PROCEDURE FOR PROCESSING OF PAYMENTS (PART VII)
HSKS
CA to rectify
deficiencies/errors
as soon as possible
Contract administrator to
issue relevant certificate
Is there a
certification period stipulated
in the contract?
No
Certificate to be issued
within a reasonable time
of application/ valuation
No
Yes
Prima facie, employer may
be in breach of contract.
Contractor may take
appropriate action for
employers breach
No
Is certificate
issued within the said
period?
Yes
Contractor to
be furnished with
original copy
No
Is the recipient
of the original copy
stipulated?
Yes
Is the certificate
issued to the stipulated
person?
Yes
Are copies
issued to the relevant
parties?
No
Yes
No
Is the service
of certificate formally
evidenced?
Yes
AA
AB
FIG. 5-10: FLOWCHART ON GENERAL PROCEDURE FOR PROCESSING OF PAYMENTS (PART VIII)
HSKS
AA
AB
Do the
recipients formally
acknowledge receipt of
document?
No
Omission to
acknowledge may
lead to future evidential
problems
Yes
No
Contractor
may present
certificate within
a reasonable
period of receipt
Contract administrator
to procure said
acknowledgements as
soon as possible
Is presentation
of certificate stipulated in the
contract?
Yes
No
Is there a
period stipulated for the
presentation?
Yes
Is presentation
formally effected within this
period?
No
Yes
Does employer
formally acknowledges receipt
of the certificate from
contractor?
No
Yes
Employer to review
certificate for validity
AC
AD
AE
Contractor to procure
said acknowledgement
as soon as possible
AF
FIG. 5-11: FLOWCHART ON GENERAL PROCEDURE FOR PROCESSING OF PAYMENTS (PART IX)
HSKS
AC
AD
AE
Are
there grounds for
challenging validity of
certificate?
AF
Yes
No
Employer to proceed with honouring
certificate issued/ presented (as
applicable)
No
Employer must
pay amount
as certified
to the contractor
No
Are these
expressly permitted by the
contract?
Yes
Has the
amount certified less the setoffs/ deduction been
established?
Yes
Has the final
sum due been paid to the
contractor?
No
No
Yes
Has this been done in the
stipulated honouring
period?
No
Employer culpable
of breach of contract.
Contractor to take
appropriate action.
Yes
STOP
INTEREST ON THE
UNPAID AMOUNT
DEFAULT IN PAYMENT:
TYPICAL CONTRACTUAL
REMEDIES
RIGHT TO DETERMINE
EMPLOYMENT UNDER
CONTRACT
INTERIM CERTIFICATES:
TYPICAL CHALLENGES
CONTINGENT PAYMENT
PAYMENT TO SUB-CONTRACTORS:
PRINCIPAL METHODS
START
Sub-Contractor
(SC) forwards details of amount
claimed to Main Contractor (MC) officially
Is it within
the prescribed time
limits?
Yes
No
Does the
MC accept the
submission?
Yes
MC to include
SCs details in his claim
CA to issue interim
payment certificate to MC
Establish if there is a
Contingent Payment Type II
clause in the sub-contract
FIG. 5-16: FLOWCHART ON GENERAL PROCEDURE FOR TYPE II CONTINGENT PAYMENT (PART I)
HSKS
A
Is there
such a clause in the
contract?
No
Yes
Is the
period for payment
stated?
No
Yes
Yes
Does the MC
pay the SC within the
said period?
No
SC to pursue the remedies
available under the contract
Are there
any contractual remedies
available?
Yes
Yes
No
Is there
an arbitration
agreement?
No
SC to pursue his common
law remedies if necessary
STOP
CONTRACT SUM
ANALYSIS
PURPOSE
DRAFTING
Normally by
Contractor
Samples may be
given by Employer
in Employers
Requirements
GENERAL
POSITION
MEASUREMENT
QUANTITIES
STRUCTURE
Given in some Forms
e.g. JCT 98, PWD
Form DB/T, etc.
Required for:
1. Overall Works
2. Sections or
Phases
EXPRESS
PROVISIONS
Included in most
Standard Forms
GENERAL
POSITION
As based on
Lump Sum and
due to nature of
contract
SITUATIONS
WHERE USED
Changes/V.O.s
Unforeseen
Conditions
No requirement
for measurement
ERRORS/
OMISSIONS
ACCURACY
Effect of
measurement
expressly
stipulated in
some forms
Mostly deals with
patent errors
PREPARATION
Risk on Contractor
Contractor responsible
If Employer prepares,
risk for errors/omissions
normally passed on to
Contractor
FINAL ADJUSTMENTS TO
THE CONTRACT SUM
APPROVED VARIATIONS
TO THE CONTRACT
MISCELLANEOUS
ADJUSTMENTS
APPROVED
CONTRACTORS CLAIMS
ADJUSTMENT TO THE
CONTRACT SUM: TYPICAL
HEADS/ITEMS
VARIATIONS/CHANGES
HSKS
6.0
VARIATIONS/CHANGES
ISSUES AS TO VALIDITY
LIMITATIONS OF VARIATIONS
RELEVANT CASES
*
COMMISSIONER FOR MAIN ROADS V REED & STUART PTY LTD. & ANOR [1974] A.L.J.R.
461
ANTARA ELEKTRIK SDN. BHD. V BELL & ORDER BHD [2002] 3 MLJ 321, HC.
HSKS
VARIATIONS
FACTORS DETERMINING
A VALID V.O.
TYPES
ADDITION
OMISSION
HYBRID
LEGAL NATURE OF
PROPOSED CHANGE
FORMALITIES
ISSUE BY
DESIGNATED
OFFICER
PROCEDURAL
REQUIREMENTS
EXPRESS CONTRACT
CONDITIONS
APPLICABLE
APPLICABLE
COMMON
LAW RULES
CHANGE TO BE IN RELATION
TO SCOPE OF THE WORK
INCREASE/
DECREASE
QUANTITY OF
WORK
OMIT
WORK
EXECUTE
ADDITIONAL WORK
OF ANY KIND
CHANGE
CHARACTER OF
WORK
VARIATIONS:
TYPICAL
EXAMPLES
CHANGE
SEQUENCE OF
WORK
CHANGE QUALITY
OF WORK
CHANGE TIMING
OF WORK
ACTIVITIES
CHANGE
KIND OF WORK
CHANGE
DIMENSIONS OF
WORK
CHANGE LEVELS
OF WORK
CHANGE POSITION
OF WORK
OMISSIONS
ADDITIONS
HYBRID
ACCORDING TO NATURE
OF THE CHANGE
NSC
CONTRACTOR
TIME IMPLICATIONS
CONTRACT
ADMINISTRATOR
EMPLOYER
ACCORDING TO IDENTIT Y
OF INITIATOR OF CHANGE
COMBINATION
OF BOTH
FINANCIAL
CONSIDERATIONS
ACCORDING TO
CONSEQUENCES/EFFECT
OF THE CHANGE
TYPES OF VARIATIONS:
MAIN METHODS OF CLASSIFICATION
CHANGES IN
EMPLOYERS
REQUIREMENTS
INTEFERENCE
BY EMPLOYER
MALADMINISTRATION
OF CONTRACT
DEFECTIVE
DRAWINGS
DEFECTIVE
SPECIFICATIONS
DEFECTIVE
CONTRACT
DOCUMENTS
ITEMS
CONSTITUTING
VARIATIONS
WRONG/
NEGLIGENT ADVICE
FROM CONTRACT
ADMINISTRATOR
DIFFERENCES
BETWEEN BILLED
AND ACTUAL
QUANTITIES
CHANGES DUE
TO STATUTORY/
LEGISLATIVE
CHANGES
LEGAL POSITION
CONTRACTS
BASED ON
BILL OF QUANTITIES
1. Rule: All items intended to be
executed by Contractor must
be provided for in the
Contract.
2. All items not provided for in
Contract are extras.
3. Literal interpretation/ strict
construction.
CONTRACTS BASED ON
DRAWINGS
AND SPECIFICATIONS
1. Rule: Contract requires:
a) Not only work set out in
drawings and/or
specifications
b) But also all work incidental or
necessarily required whether
set out in the drawings and/or
described in specifications or
not
VARIATION TEST
PER RE:
THERE MUST BE AN
INSTRUCTION
INSTRUCTION TO BE ISSUED BY
CONTRACT ADMINISTRATOR OR
BY AUTHORISED PERSON
EXISTENCE OF EXPRESS
CONTRACTUAL PROVISION
PERMITING VARIATION OF WORK
UNDER THE CONTRACT
LIMITATIONS TO VARIATIONS
LEGAL POSITION
EXERCISE OF POWER
BY CONTRACT
ADMINISTRATOR
1.
2.
If effect of omission is
to give omitted work to
3rd Parties: Invalid
Omission
CARDINAL CHANGES
SCOPE OF WORK
1.
2.
2.
TESTS
If effect of variation is to
substantially change
scope of work (Cardinal
Change): Invalid
Variation
DEFINITION
1.
NATURE
3. Functionally is it similar
to the intended work or
some other work
required by the
Contract?
EFFECTS
1. General Rule:
Invalid
2. Contractor cannot
be compelled to
carry it out
3. If compelled,
breach of contract
4. If Contractor
carries out work,
Contract rates not
applicable
FORM
TYPES
1.
1.
A Single change
2.
Financial Changes
2.
A large number of
otherwise small permissible
changes.
Constitutes a fundamental
change in the scope of the
Contract
FORMULA VALID
AND APPLICABLE
A CARDINAL
CARDINAL CHANGE
i.e. FUNDAMENTALLY
ALTERS CONTRACT
ABSENCE OF EXPRESS
FORMULA IN CONTRACT
EXISTENCE OF EXPRESS
FORMULA IN CONTRACT
NOT A CARDINAL
CARDINAL CHANGE i.e.
DOES NOT FUNDAMENTALLY
ALTER CONTRACT
No right of election
Additions
Omissions
FINANCIAL EFFECTS
Extension of time to
Contract Period, etc.
TIME EFFECTS
VALUATION OF VARIATIONS:
COMMON COMPUTATIONAL METHODS
On a cost-reimbursible basis
MISCELLANEOUS
METHODS
WHERE NO RATES/
PRICES IN CONTRACT
Use of Negotiated/Agreed
Rates
Use of Negotiated/Agreed
Rates
START
Establish if the conditions
precedent have been satisfied
Has measurement
stage been satisfactorily
completed?
No
Yes
Has the valuation
stage been satisfactorily
completed?
No
Yes
Contract administrator to prepare
certificate of variation of works
No
Is there a
contract provision prescribing
the same?
Yes
Yes
Are its
requirements clear and
complete?
No
Have the
requirements been agreed to by
the parties?
No
Yes
Have the
requirements been complied
with?
No
Yes
Have the
particulars been completely and
properly filled in?
No
Yes
Is the
V.O./instruction
attached?
No
Yes
Are the
measurement and valuation
details endorsed?
No
Omissions/deficiencies
may render certificate
invalid
No
Contract administrator
to address omissions
/deficiencies forthwith
Yes
Has the certificate
been checked for sufficiency and
accuracy?
Yes
No
Has it been
signed by the authorized
person?
Yes
FIG. 6-14:
No
Has it been
prepared within a
reasonable/ prescribed period of
completion of measurement
and valuation?
Yes
Contract administrator to
issue certificate to the contractor
No
Is the
certificate sufficient and
accurate?
Yes
No
Has it been
signed by the authorized
person?
Yes
Prima facie,
certificate is invalid
No
Does it
comply with any prescribed
requirements?
Yes
Does the
contractor agree with the
content?
Yes
Contractor
to formally signify
acceptance
No
Does he notify
the contract administrator officially
of his dissent?
No
Yes
Are the
full particulars/details
given?
No
Yes
Contractor obliged
to give notice
within reasonable
period only
No
Is there a
period stipulated for the giving of
the notice?
Yes
Has the
contractor met the time
requirements?
No
Contractor deemed
to have accepted
the measurement
and valuation
Yes
Contract administrator
to review contractors notice
and make decision
FIG. 6-16:
Yes
Is the
notice sufficient and
accurate?
No
No
No
Yes
Is the contractors stand
reasonable?
Yes
No
Is there any
reason not to reject the contractors
application?
Yes
Contract
administrator to
undertake necessary
amendments/
revisions
No
Does the
contractor wish to proceed with
dispute resolution?
Yes
Contractor to give
necessary notice. Contract
administrator to use valuation
set out in the interim period
No
STOP
FIG. 6-17: FLOWCHART ON THE GENERAL PROCEDURE FOR CERTIFICATION OF VALUATION (PART V)
HSKS
EXPRESS
STIPULATIONS
EMPLOYER
EMPLOYERS
RIGHT TO VARY
CONTRACTOR
CONTRACTORS
RIGHT TO VARY
In most Standard
Forms
Stipulate Extent,
Procedure, etc.
EXPRESS
EXPRESS
PROVISIONS
PROVISIONS
Enshrined in
all Standard
Forms
NEED
NEED FOR
FOR
CONSULTATION
CONTRACTOR
CONTRACTORS
S
RESPONSIBILITY
Prior to ordering
V.O.
Get Contractors
view on effect of
V.O. on
programme
Be pro-active
Permitted expressly
in most Standard
Forms
Due to:
1. Value
engineering
2. Buidability
3. Safety
4. Legal/Physical
impossibility
VARIATIONS
IN WRITING
EFFECT OF
PROCEDURE
Formal V.O.
Instruction from
E.R./P.D. condition
precedent to recovery
of payment
Permissible if only
expressly allowed
by contract
Some Standard
Forms do allow e.g.
ICE, FIDIC, etc.
Others are silent
e.g. JKR, etc.
Failure of Contractor
to observe procedure/
formalities may
compromise recovery
Not to unreasonably
withhold consent, etc.
NECESSITY
NECESSITY FOR
FOR
WRITTEN
WRITTEN
INSTRUCTIONS
INSTRUCTIONS
CONTRACT
CONTRACT
PROVISIONS
PROVISIONS
VARIATIONS
IN DLP/DCP
RECOVERY
RECOVERY WITHOUT
WITHOUT
INSTRUCTIONS
INSTRUCTIONS
ORAL INSTRUCTIONS
Generally no
Situations where permitted:
1. If contract expressly allows
2. Under Waiver/Estoppel
3. Under concept of
Constructive Change
FIG. 6-18: VARIATIONS PRINCIPAL REQUIREMENTS FOR PACKAGE DEAL TYPE OF CONTRACT
HSKS
DELAY AND
EXTENSION OF TIME
HSKS
7.0
ACCELERATION OF WORKS
MISCELLANEOUS ISSUES
RELEVANT CASES
*
PEAK CONSTRUCTION (LIVERPOOL) LTD. V MCKINNEY FOUNDATION LTD. [1970] 1 BLR 114
SYARIKAT TAN KIM BENG DAN RAKAN-RAKAN V PULAI JAYA SDN. BHD. [1992] 1 MLJ 42
HSKS
BY EMPLOYER
(ACTS OF PREVENTION)
BY CONTRACTOR
INSTRUCT CONTRACTOR
TO ACCELERATE WORKS
GRANT OF
EXTENSION OF TIME
Only if contract expressly permits
1.
Extended Preliminaries
2.
DUE TO
NEUTRAL EVENTS
DUE TO CONTRACTOR
CONTRACTORS
OWN ACTS AND/OR OR
OMISSIONS
Contractor culpable
DUE TO CONTRACTOR
CONTRACTORS
SUBSUB-CONTRACTORS/
SUPPLIERS
FORCE MAJEURE
EXCEPTIONALLY INCLEMENT WEATHER
CIVIL COMMOTION, STRIKES, LOCK-OUT, ETC.
LOSS OR DAMAGE TO THE WORKS OCCASIONED BY SPECIFIED PERILS
CONTRACTORS INABILITY TO SECURE LABOUR, GOODS, MATERIALS, ETC.
CARRYING OUT OF WORK BY STATUTORY UNDERTAKERS
EXERCISE BY GOVERNMENT OF ANY POWER WHICH DIRECTLY AFFECTS THE WORKS
DEFERMENT/POSTPONEMENT
IN GIVING SITE POSSESSION
OTHER ACTS OF PREVENTION
EXPRESSLY PERMITTED BY
THE CONDITIONS OF
CONTRACT
LATE SUPPLY OF
INFORMATION, DRAWINGS,
INSTRUCTIONS, ETC.
ACTS OF PREVENTION:
TYPICAL EXAMPLES
COMPLIANCE WITH
CONTRACT
ADMINISTRATORS
INSTRUCTIONS, DIRECTIONS,
ETC.
FORCE MAJEURE
DELAYS BY NOMINATED SUBCONTRACTORS/SUPPLIERS
FOR THE SAID NEUTRAL
EVENTS
EXCEPTIONALLY INCLEMENT/
ADVERSE WEATHER
NEUTRAL EVENTS:
TYPICAL EXAMPLES
CONTRACTORS IN ABILITY
TO SECURE LABOUR, GOOD,
MATERIALS AND/OR OTHER
RESOURCES
LOSS/DAMAGE TO THE WORKS
OCCASIONED BY SPECIFIED
PERILS
OR CONTINGENCIES
APPROPRIATE
CONTRACT
REFERENCES TO SUCH
EVENT OF DELAY
SCHEDULING
DOCUMENTATION
DETAILS OF EFFECT OF
DELAY ON WORK
PROGRAMME
APPLICATION FOR
EXTENSION OF TIME:
TYPICAL CONTENTS
ESTIMATE OF THE
EXTENSION OF TIME
REQUIRED
ESTIMATED LENGTH
OF THE DELAY
STEPS TAKEN/PROPOSED
TO MINIMIZE/AVOID DELAY
EXTENSION OF TIME
APPLICATION: TYPICAL
SOURCES OF INFORMATION
START
Is progress
delayed or is likely to be
delayed?
No
Yes
Does the
delaying event constitute
one of the relevant events /grounds
under the provisions of the
contract?
No
Yes
Initiate notification
of the delay procedure
Is the
notice given in writing?
No
Yes
Is the notice
given within the period expressly
stipulated?
No
Yes
No
Yes
Proceed with the
application of the extension
of time process
Is the
notice a condition
precedent?
Yes
Has an
extension been
granted by the contract
administrator?
No
FIG. 7-7: FLOWCHART ON THE GENERAL PROCEDURE FOR CLAIMING EXTENSION OF TIME (PART I)
HSKS
Is the
application given in
writing?
No
Yes
Is the
application made within
the period expressly
stipulated?
No
Yes
Contract Administrator to
check application made
Is the application
complete/sufficient and
accurate?
Is the
application a condition
precedent?
Yes
No
Yes
No
Yes
Has an
extension been
granted by the contract
administrator?
No
Is the
requirement as to
sufficiency, etc. a condition
precedent?
Yes
No
No
No
Has the
contract administrator
requested for information,
details, etc.?
Yes
Prima facie no
extension of time
can be granted
Yes
Contract Administrator to
proceed with further assessment
for the possible grant of
extension of time
Return to contractor
for resubmission
or reject application
as appropriate
STOP
FIG. 7-8: FLOWCHART ON THE GENERAL PROCEDURE FOR CLAIMING EXTENSION OF TIME (PART II)
HSKS
NATURE OF
APPLICATION
EXPRESS CONTRACT
PROVISIONS
REQUIREMENT
REQUIREMENT
TIMING OF
NOTIFICATION
Expressly stipulated
in conditions of
contract of contract;
or
Implied by law
2 broad steps:
VARIATIONS
VARIATIONS
1. Whether notification/application
is a condition precedent to
entitlement
Either a:
1. Notification of
the delay; and
1. Single exercise,
or
2. Making the
application
2. Two separate
processes
Depends upon
express/ implied
requirements
CONTENTS OF
THE NOTICE
CATEGORIZATION
CATEGORIZATION
FORM OF
THE NOTICE
3. Application to acts of
prevention/neutral events
EXPRESS
EXPRESS REQUIREMENTS
REQUIREMENTS
TYPES
TYPES OF
OF WRITTEN
WRITTEN NOTICES
NOTICES
/NOTICES
/NOTICES IN
IN WRITING
WRITING
Correspondence
Facsimile transmissions
1. Written notice or
2. Notice in writing
EVIDENTIAL VALUE
EVIDENTIAL
GENERAL RULE
FORM OF
THE APPLICATION
TIMING OF
THE APPLICATION
EXPRESS
REQUIREMENT
Formulae include:
1. Specific time
periods
2. Within a reasonable
period
Preferably to be in writing
GENERAL RULE
CONTENTS OF
THE APPLICATION
Dictated by express stipulations in
contract
Otherwise by necessary implication.
Typical list includes:
1.
Cause of delay
2.
Appropriate contract
reference
3.
4.
5.
Steps taken to
mitigate/prevent delay
6.
Scheduling documentation
7.
Miscellaneous details,
records, documents, etc.
FIG. 7-10 : PROCEDURES FOR CLAIMING EXTENSION OF TIME AN OVERVIEW (PART II)
HSKS
DETERMINING
DETERMINING FACTORS
FACTORS
CONSEQUENCES
CONSEQUENCES WHERE
WHERE
PROVISION
PROVISION IS
IS NOT
NOT A
A
CONDITION
CONDITION PRECEDENT
PRECEDENT
CONSEQUENCES
CONSEQUENCES WHERE
WHERE
PROVISION IS
IS A
A CONDITION
CONDITION
PRECEDENT
PRECEDENT
BASIS
BASIS OF
OF
REQUIREMENT
REQUIREMENT
FAILURE
FAILURE TO
TO RESPOND
RESPOND
AFTER
AFTER EXTENSION
EXTENSION
PRINCIPAL
PRINCIPAL SOURCES
SOURCES
FIG. 7-11 : PROCEDURES FOR CLAIMING EXTENSION OF TIME AN OVERVIEW (PART III)
HSKS
EXPRESS
CONTRACT
PROVISIONS
GENERAL
TO WHOM
OWED
THE CONTRACT
ADMINISTRATORS DUTY
ADMINISTRATOR
OF CARE
DERELICTION
DERELICTION
OF
OF DUTY:
DUTY:
CONSEQUENCES
CONSEQUENCES
DUTY
DUTY TO
TO
EMPLOYER
To Employer
To Contractor
To Nominated Subcontractors/Suppliers
PRELIMINARY
PROCEDURES
May compromise
employers position
Contract administrator
liable to actions in:
1. Breach of contract
2. Tort of negligence
PRELIMINARY
PRELIMINARY CHECKS
CHECKS
TO ESTABLISH
MATTERS
SUCH
MATTERS SUCH AS
AS
WHO UNDERTAKES
WHO
ADDITIONAL
ADDITIONAL DUTY
DUTY
NATURE
NATURE OF
OF ROLE
ROLE
As an independent adjudicator
Decision making function
Must act fairly, reasonably and
impartially
POST APPLICATION
PROCEDURES
Verification of occurrence
of delay
Sufficiency, accuracy,
relevancy, etc.
Compliance with preconditions, procedural
requirements, etc.
Assessment of evidential
value
Assessment whether delay
in principle entitles
contractor to extension
INSUFFICIENT
INSUFFICIENT
INFORMATION: OPTIONS
AVAILABLE
AVAILABLE TO
TO CONTRACT
CONTRACT
ADMINISTRATOR
ADMINISTRATOR
Request contractor to
submit more details, etc. or
If delaying event of a
continuing nature:
1. Proceed with interim
assessment
2. Grant an interim
extension
THE ASSESSMENT
PROCESS
BASIS OF ASSESSMENT
Basic principles
Overriding requirements:
Satisfaction of:
1. Reasonableness Test
2. Fairness Test
3. Procedural requirements
MISCELLANEOUS
ISSUES
Multiple extensions
Concluding decision:
Important exceptions
1. Contractor not to be culpable
2. Contractor to mitigate/prevent
delay
TIMING FOR
GRANTING EXTENSION
1. Rejection of claim; or
2. Grant of extension of time
PRINCIPAL ISSUES
PRINCIPAL
Express stipulations as to
time period for granting
Prospective/Retrospective
granting of extension
TIME
TIME PERIOD
PERIOD
FACTORS
FACTORS DICTATING
DICTATING
PROSPECTIVE/
PROSPECTIVE/
RETROSPECTIVE GRANTING
GRANTING
OF
OF EXTENSION
EXTENSION
Various formulae:
Where implied
Courts approach:
Circumstances where
retrospective granting permitted
OTHER MATERIAL
BREACHES
CERTIFICATE NOT IN
CORRECT FORM
CONTRACTUAL
PROCEDURES NOT
FOLLOWED
CERTIFICATE GIVEN
BY UNAUTHORIZED
PERSON
CHALLENGING CERTIFICATE
OF EXTENSION OF TIME:
COMMON GROUNDS
CERTIFICATE NOT
GIVEN FAIRLY
NO NAMED
CERTIFIER
DECISIONS IMPROPERLY
DELEGATED
EXPRESS
CONTRACTUAL
PROVISIONS
GENERAL
REQUIREMENTS
PAM
PAM 1998
1998
SUB
SUB---CONTRACT
CONTRACT
FORM
FORM
GENERAL
PROCEDURAL
REQUIREMENTS
GENERAL
CONTRACTUAL
POSITION
Extension of time under contract can
only be validly granted if:
PUTRAJAYA
PUTRAJAYA
CONDITIONS OF
OF
NOMINATED
SUB-NOMINATED SUBCONTRACT
CONTRACT
IEM.CES.1/90 FORM
IEM.CES.1/90
6. Contract administrator
communicates decision to
contractor
7. Contractor informs subcontractor
8. Receipt and acknowledgement
NON-COMPLETION
AND DAMAGES
HSKS
8.0
CONTRACTUAL FORMULAE
RIGHTS TO IMPOSE
CHALLENGES
MALAYSIAN POSITION
RELEVANT CASES
*
DUNLOP PNEUMATIC TYRE CO. LTD. V NEW GARAGE & MOTOR COMPANY LTD. [1915]
AC 79
LION ENGINEERING SDN. BHD. V PAUCHUAN DEVELOPMENT SDN. BHD. [1997] 4 AMR
3315
HSKS
SELVA KUMAR A/L MURUGIAH V THIAGARAJAH A/L RETNASAMY [1995] 1 MLJ 817
REALVEST PROPERTIES SDN. BHD. V THE COOPERATIVE CENTRAL BANK LTD. (Under
Receivership) [1996] 2 AMR 2292, FC.
SAKINAS SDN. BHD. V SIEW YIK HAU & ANOR [2002] 5 MLJ 497, HC.
ARAB MALAYSIAN CORP. BUILDERS SDN. BHD. & ANOR V ASM DEVELOPMENT SDN. BHD.
[1998] 6 MLJ 136, HC.
HSKS
RECOVERY/PAYMENT
TRIGGERED BY OCCURRENCE
OF SPECIFIED DEFAULT/BREACH
LIQUIDATED DAMAGES:
PRINCIPAL CHARACTERISTICS
BASIC
CHARACTERISTICS
DEFINITION
Per Eggleston
1.
2.
3.
4.
GENERAL
Common view
Common view
Sum of money
agreed/fixed in
advance by parties
Reiteration in Philips
Hong Kong Ltd. v AG
of Hong Kong.
Disadvantages to:
Sum is a genuine
pre-estimate of
likely loss
Distinct difference
1. Employer
2. Contractor
Advantages to:
3. Sub-contractor
1. Employer
2. Contractor
Sum is stipulated in
the contract
3. Sub-contractor
Recovery of sum is
triggered by
contractors breach
e.g. non-completion
DISTINGUISHING
BETWEEN THE
TWO TERMS
PENALTY: DEFINITION
Use of terms
interchangeably
DISADVANTAGES
ADVANTAGES
LIQUIDATED
DAMAGES AND
PENALTIES
DISTINGUISHED
Depends on construction
afforded to term by the
courts
EXAMPLES OF
PENALTY CLAUSES
LEGAL EFFECTS
OF PENALTIES
THE EXPRESS
LIQUIDATED DAMAGES
CLAUSE IS VALID AND
ENFORCEABLE
IMPOSITION OF
LIQUIDATED DAMAGES:
TYPICAL PRE-CONDITIONS
SPECIFIED
CONTRACTUAL
PROCEDURES HAVE
BEEN STRICTLY
COMPLIED WITH
DETAILS ON LIQUIDATED
DAMAGES CLEARLY AND
PROPERLY FILLED IN
DEFINITE DATE FIXED
CONTRACTUALLY FROM WHICH
DAMAGES CAN RUN
MISCELLANEOUS
PRE-CONDITIONS
THE CONTRACT
ADMINISTRATOR SHALL
DETERMINE AND ISSUE
ANY EXTENSIONS OF
TIME DUE TO
CONTRACT
DEDUCTION OF
LIQUIDATED DAMAGES:
COMMON CONDITIONS
PRECEDENTS USED
FIG. 8-4 :
THE CONTRACT
ADMINISTRATOR SHALL
CERTIFY THAT NO
FURTHER EXTENSIONS
OF TIME ARE DUE TO
CONTRACTOR
DEFINITION
GENERAL PROCEDURE
BASIC STEPS
FIG. 8-5 :
Triggering event:
failure of
contractor to
complete on time
Crucial to
enforceability
of provision
and recovery of
LAD
DETERMINE
IF RELEVANT
CERTIFICATES/
NOTICES HAVE
BEEN ISSUED
DETERMINE IF
EMPLOYER HAS
WAIVED HIS
RIGHTS TO LAD
ESTABLISH
EXISTENCE AND
VALIDITY OF
LAD CLAUSE
ESTABLISH
DEFAULT OF
CONTRACTOR
2 forms of waiver:
1. Express
2. Implied
Was there
consideration in
return?
EMPLOYER
RECOVERS THE
LIQUIDATED
DAMAGES
Conditions precedent
Decision as to recovery
Timing
POST LAD
DEDUCTION
PROCEDURES
Effect of further
E.O.T.
EXPRESS CONTRACTUAL
PROVISIONS
GENERAL POSITION
1.
2.
Liquidated damages, or
Unliquidated/general damages
EFFECT OF
NSCS DEFAULT
DAMAGES FOR
BREACH OF CONTRACT
EXPRESS
CONTRACTUAL FORMULA
Governing Provision: S 74
Contracts Act 1950 (Rev. 1974) Compensation for loss or damage
caused by breach of contract
Rate
Scope of coverage
Maximum limit
Pre-conditions, etc.
GENERAL
OBSERVATIONS
LIQUIDATED DAMAGES:
TYPICAL GROUNDS FOR
CHALLENGING
EFFECT OF SELVAKUMAR V
THIAGARAJAH [1995]
CIRCUMVENTING SELVAKUMAR
V THIAGARAJAH
UNDER DOCTRINE
OF FREEDOM TO
CONTRACT
1. Parties of equal bargaining strength.
2. Free to agree on any terms between
themselves.
3. Philips HK Ltd. v AG of Hong Kong.
MUTUAL
AGREEMENT
CLAUSE 22.2:
PAM CONTRACT 2006
START
Is the
contractor liable to pay
LAD?
No
Yes
Have all
the conditions precedents
been fulfilled?
No
Yes
Employer can proceed to
recover simpliciter the sum
fixed in the contract as LAD
Does the
contractor challenge the
employers deduction of the
LAD?
No
Yes
Is there an
express clause circumventing
rule in Selvakumar
Thiagarajah?
Yes
No
Matter to be resolved
through arbitration/litigation
Is
employer able to
prove damages as
required?
No
Yes
Are the
damages more than the sum stipulated in the
contract
as LAD?
Yes
No
STOP
COMPLETION AND
HANDING-OVER
HSKS
9.0
CONDITIONS PRECEDENT
CHALLENGES TO CPC
RELEVANT CASES
H.W. NEVILL (SUNBLEST) LTD. V WILLIAM PRESS & SONS LTD. [1981] 20 BLR 78
EMSON EASTERN (IN RECEIVERSHIP) V EME DEVELOPMENTS LTD. [1991] 55 BLR 114
HSKS
CONTRACT ADMINISTRATOR
HAS DISCRETION TO ISSUE
C.P.C. WHERE MINOR WORKS
ARE LEFT TO BE DONE ON A DE
MINIMIS BASIS
FUNCTIONAL TEST
MISCELLANEOUS TESTS
COMPLETENESS TEST
ESTABLISHING PRACTICAL
COMPLETION:
PRINICPAL TESTS
AUTHORITIES TEST
SAFETY TEST
INCONVENIENCE TEST
OBLIGATION TO INSURE
FOR EACH SECTION
ENDS WITH CPC
(DEPENDING ON
CONTRACT PROVISION)
CERTIFICATE OF PRACTICAL
COMPLETION FOR EACH SECTION
SEPARATE EXTENSION
OF TIME CERTIFICATION
FOR EACH SECTION
SECTIONAL COMPLETION:
PRINICPAL ISSUES/EFFECTS
RELEASE OF ONE
MOIETY OF RETENTION
SUM FOR EACH SECTION
SEPARATE LIQUIDATED
AND ASCERTAINED
DAMAGES FOR EACH
SECTION
SEPARATE DEFECT LIABILITY
PERIOD FOR EACH SECTION
RELEASE OF
PERFORMANCE BOND
AND FINAL PAYMENT
UNAFFECTED
ISSUE OF CERTIFICATE OF
PARTIAL OCCUPATION OF
RELEVANT PART WITHIN
STIPULATED PERIOD
COMMENCEMENT OF
DEFECT LIABILITY
PERIOD FOR RELEVANT
PART ON DATE OF
POSSESSION/
OCCUPATION
PARTIAL POSSESION/
OCCUPATION:
PRINICPAL ISSUES/EFFECTS
CESSATION/REDUCTION
OF INSURANCES
CORRESPONDINGLY (IF
EXPRESSLY PERMITTED)
PROPORTIONING DOWN
OF LIQUIDATED AND
ASCERTAINED DAMAGES
RELEASE OF A PROPORTION OF
FIRST HALF OF RETENTION SUM IN
RESPECT OF RELEVANT PART
WITHIN STIPULATED PERIOD
LITERAL MEANING/
INTERPRETATION
SECTIONAL
COMPLETION
PRACTICAL
COMPLETION
Strict View
Envisages completion in
sections/ stages/phases
Connotates a state of
readiness for use or
occupation by Employer
Intention must be
agreed/expressed at time of
contracting.
Formalized by issue of
Certificate of Practical
Completion (CPC) or Taking
Over Certificate (TOC)
a) Each Section
b) The Completion dates
c) The Corresponding LAD
PARTIAL
POSSESSION
Situation where Employer takes
over/resumes possession of:
a)Whole works, or
b)
Part of works
before Contract Completion Date
Pre-Conditions:
a)With consent of Contractor
b)
Consent not to be
unreasonably withheld
Procedural aspects:
a)Issue of Certificate of Partial
Occupation (CPO) within 7
days of possession.
b)
Certificate to identify:
i) Relevant part possessed
ii) Its estimated value
c) Liquidated and
Ascertained Damages
(LAD)
d)
LAD rate reduced prorata for unoccupied
part/portion
TYPES
PURPOSE
PRELIMINARY
Normally undertaken
by Contractor on his
own.
Is a necessary prelude
to the Final Tests
FINAL
Normally undertaken by
either:
As a pre-condition to issue of
CPC
As a pre-condition to
certification by Independent 3rd
Party Specialist.
FAILURES
RESPONSIBILITY
a) Contractor in the
presence of
Contract
Administrator (or)
b) Independent 3rd
Party Specialists
CONTRACT
ADMINISTRATOR
CONTRACTOR
INDEPENDANT TESTER
Default/negligence in
certification does not relieve
Contractors obligations.\
GENERAL
GENERAL
POSITION
TIMING
TIMING FOR
FOR
SUBMISSION
Type/Nature
Contents
Quantity
Timing for
Submission
b)Errors/
inaccuracies
Professionals to update
OPERATION &
MAINTENANCE MANUALS/
MANUALS/
MAINTENANCE
HANDBOOKS
ASAS--BUILT/
BUILT/
ASAS--CONSTRUCTED/
CONSTRUCTED/
ASAS-INSTALLED DRAWINGS
ACCURACY
ACCURACY
Contractors
responsibility at least
during Limitation Period
for:
a) Before TOC
b) After TOC
c) Before Performance
Certificate
UPDATING
TYPES/
TYPES/ NATURE
NATURE
Primary responsibility
for errors, omissions,
etc.
Especially so for
signing-off/
endorsing Qualified
Person.
MISCELLANEOUS
RECORDS/ DOCUMENTS
RECORDS/
RECORDS
RECORDS OF
OF FINAL
FINAL
MEASUREMENT
MEASUREMENT
Undertaken by Contract
Administrator jointly with
Contractor.
PROFESSIONAL
PROFESSIONALS
S
RESPONSBILITY
RESPONSBILITY
CONTRACTOR
CONTRACTOR S
S
RESPONSBILITY
RESPONSBILITY
IDENTIFICATION OF PATENT
DEFECTS
& OUTSTANDING WORKS
ISSUE OF RELEVANT
COMPLETION CERTIFICATE
HANDOVER OF APPROVALS/
CLEARANCES FROM
STATUTORY AUTHORITIES
HANDOVER OF ALL
NECESSARY SPARES
COMPLETION
OF TESTING &
COMMISSIONING
TAKING OVER:
TYPICAL PRECONDITIONS
TRAINING OF
EMPLOYERS OPERATION
& MAINTENANCE PERSONNEL
HANDOVER OF
ALL AS-BUILT DOCUMENTS/
RECORDS
HANDOVER OF
ALL NECESSARY TOOLS
HANDOVER OF ALL
KEYS
IDENTIFICATION OF
THE SEQUENCE OF
TAKING-OVER
TAKING OVER OF
COMPLETED WORKS:
PROCEDURAL ISSUES
SETTING UP OF THE
PROCEDURES FOR
RECORDING
ESTABLISHMENT OF
TAKING-OVER
PROGRAMME
ESTABLISHMENT OF THE
RELEVANT DELIVERABLES
DEFECTS
HSKS
10.0
DEFECTS
RECENT DEVELOPMENTS
RELEVANT CASES
HII SOO CHIONG V BOARD OF MANAGEMENT YEE TING PRIMARY SCHOOL [1973] 2 MLJ 204
HSKS
DANCOM ENGINEERING PTE LTD. V TAKASAGO THERMAL ENGINEERING CO. LTD. [1989] BLD
[MAY] 606
PIRELLI GENERAL CABLE WORKS LTD. V OSCAR FABER & PARTNERS [1983] 2 AC 1
PEARCE & HIGH LTD. V JOHN BAXTER & MRS. A.S. BAXTER [1999] BLR 101
DUTTON V BOGNOR REGIS UNITED BUILDING CO. LTD. & ANOR [1972] 1 QB 373
STEVEN PHOA CHENG LOON & 72 ORS V HIGHLAND PROPERTIES SDN. BHD. & 9 ORS [2000]
3 AMR 3567
HSKS
STANDARD OF
WORKMANSHIP
PATENT DEFECT
LATENT DEFECT
TYPES
QUALITY OF
MATERIAL
STANDARD
OF DESIGN
NATURE
MANAGEMENT FEE
CONTRACTING
TRADITIONAL GENERAL
CONTRACTING
PACKAGE DEAL
DEAL TYPES
OF CONTRACTS
Quality of Materials
Standard of Workmanship
WHOLLY EMPLOYER
DESIGNED CONTRACT
PARTLY EMPLOYER
DESIGNED CONTRACT
Standard of Design
Quality of Materials
Quality of Materials
Standard of Workmanship
Standard of Workmanship
PARTLY EMPLOYER
DESIGNED CONTRACT
WHOLLY EMPLOYER
DESIGNED CONTRACT
Quality of Materials
Quality of Materials
Standard of Workmanship
Standard of Workmanship
ARISING FROM
FAIR WEAR AND TEAR
HAVING NUMBER OF
CAUSES, CONTRACTORS
PORTION BEING MINOR
WAIVED BY EMPLOYER
POST-COMPLETION STAGE
PRE-COMPLETION STAGE
POST-CMGD STAGE
Or During Currency of
Construction, Installation,
etc.
Or Post-Certification of
Completion of Making Good
Defects
DETERMINATION OF
CONTRACTORS EMPLOYMENT
UNDER THE CONTRACT
POSTPONEMENT/NONCERTIFICATION OF COMPLETION
OF WORKS
MISCELLANEOUS ACTS
E.G. RAILWAYS ACT
1991 (SECTION 97) CIVIL
LAW ACT 1965 (SECTION
7(5), ETC.
LIMITATION: RELEVANT
STATUTORY ENACTMENTS
PUBLIC AUTHORITIES
PROTECTION ACT 1948
(REV. 1978)
LIMITATION ORDINANCE
1952 (REPRINT 1966) SABAH
LIMITATION ACT (CAP 14)
REVISED EDN. 2000 BRUNEI
Serious and/or
Impracticable or inconvenient
for contractor to make good
Material
EMPLOYER TO UNDERTAKE
WORKS HIMSELF I.E.
DEPARTMENTALLY
RD PARTY ACTION
TAKE 3RD
c) as a liquidated demand
c) as a liquidated demand
DISCHARGES
CONTRACTORS RIGHTS
UNDER CONTRACT TO
PHYSICALLY ATTEND TO
DEFECTS
CONTRACTORS LIABILITY
FOR LATENT AND PATENT
DEFECTS CONTINUES FOR
THE STATUTORY PERIOD OF
LIMITATION
PARTIES OUTSTANDING
ISSUE OF CERTIFICATE
MAKING GOOD OF
DEFECTS: PRINCIPAL
EFFECTS ON PARTIES
DISCHARGES LIABILITY OF
GUARANTORS, INSURERS,
ETC. UNDER THE
CONTRACT
FIG. 10-8:
EMPLOYER HAS TO
RELEASE SECOND MOIETY
OF RETENTION SUM THAT
IS WITHHELD
MARKS THE
COMMENCEMENT OF THE
CONTRACTUAL PERIOD
FOR CONTRACT
ADMINISTRATOR TO ISSUE
FINAL CERTIFICATE
POST-COMPLETION
AND
FINAL ACCOUNT
HSKS
11.0
TRAINING
O & M MANUALS
AS-BUILT DRAWINGS
RELEVANT CASES
CHEW SIN LONG CONSTRUCTION CO. LTD. V COSY HOUSING DEVELOPMENT PTE LTD.
[1988] 1 MLJ 331
THAMESA DESIGNS SDN. BHD. & ORS V KUCHING HOTELS SDN. BHD. [1993] 3 MLJ 28
SHEN YUAN PAI V DATO WEE HOOD TECK & ORS [1976] 1 MLJ 16
HSKS
GENERAL
POSITION
PURPOSE
EXTENT
FREQUENCY
To ensure Contractor
meets contractual
obligations
Implied from:
a) Statutory
requirements
Daily
Weekly
Monthly
Quarterly
Yearly
EXPRESS
EXPRESS
REQUIREMENTS
As stipulated:
a) In Contract
b) In Manufacturers
Warranties/
recommendations
c) In O & M Manuals
Warranties may be
compromised.
b) Trade usage
c) Local practice
PREVALENT
PREVALENT
PRACTICE
PRACTICE
EFFECT OF
FAILURE
a) Contract and/or
b) O & M Manuals
PROCEDURE
FOR
MONITORING
IMPLIED
REQUIREMENTS
REQUIREMENTS
In absence of express
stipulations implied
from:
a) Trade usage
b) Local practice
c) Statute
General implication is
that Employer will
undertake daily and
weekly servicing and
maintenance.
CONTRACT
ADMINISTRATOR
ADMINISTRATORS
RESPONSIBILITY
CONTRACTOR
CONTRACTORS
S
DUTY
DUTY
Monitoring of
Contractors work
Signing-off the
records
Reporting to
Employer of unusual
observations
EMPLOYERS
EMPLOYERS
OBLIGATIONS
Undertaking of routine
servicing and
maintenance e.g. daily,
weekly, etc.
Affording Contractor
proper access to work
being serviced.
Attending to unusual
observations reported.
AS-BUILT DRAWINGS
AS-INSTALLED DRAWINGS
AS-CONSTRUCTED DRAWINGS
GENERAL
POSITION
Type/Nature
Contents
Quantity
Timing for
Submission
TIMING FOR
SUBMISSION
TYPES/ NATURE
a) Before CPC
b) After CPC
c) Before CMGD
Contractors
responsibility at least
during Limitation Period
for:
a) Revisions due to
product
improvement.
Professionals to update
on safety issues and
errors detected.
OPERATION &
MAINTENANCE SCHEMATICS
/DIAGRAMMES
In Contract and
Tort
In Tort, on joint
and several basis
Primary
responsibility for
errors,
omissions, etc.
Especially so for
signing-off/
endorsing
Qualified
Person.
RECORDS OF FINAL
MEASUREMENT
PROFESSIONALS
RESPONSBILITY
CONTRACTORS
RESPONSBILITY
b) Errors/ inaccuracies
AS-BUILT/
AS-CONSTRUCTED/
AS-INSTALLED DRAWINGS
ACCURACY
UPDATING
FINAL CERTIFICATE
MISCELLANEOUS
LABELS
FINAL ACCOUNT
CERTIFICATE
PERFORMANCE
CERTIFICATE
ULTIMATE CERTIFICATE
FINAL PAYMENT
CERTIFICATE
FINALCERTIFICATE:
PRINCIPAL
CHARACTERISTICS
ISSUE OF PERFORMANCE
CERTIFICATE (P.C.)
SATISFACTION OF ALL
OTHER OBLIGATIONS/DUTIES
UNDER CONTRACT
EXPIRY OF DEFECT
NOTIFICATION PERIOD (DNP)
TYPICAL PRE-CONDITIONS TO
THE ISSUE OF THE
FINAL CERTIFICATE
CERTIFICATION OF
COMPLETION OF SERVICING
AND MAINTENANCE
PREPARATION AND
FINALIZATION OF THE FINAL
ACCOUNT
FIG. 11-6 : TYPICAL PRE-CONDITIONS TO THE ISSUE OF THE FINAL PAYMENT CERTIFICATE
HSKS
FIG. 11-7 :
FINAL CERTIFICATE:
TYPICAL CHALLENGES TO
CONCLUSIVENESS/FINALITY
THANK YOU
HSKS