PRAMOD KUMAR

E-Mail: pramodkr.mech@gmail.com
Mobile: +91-9998818920

PROJECT ENGINEER (POWER PLANT)


Seeking challenging assignments commensurate with my managerial and analytical skill in a dynamic
organization

PROFILE & STRENGTH

Highly motivated, dependable and qualified B.E (Mechanical Engineering) with experience of 6 years across
the Industry. Presently spearheading functions as Sr. Engineer (Project) with UB Engineering Ltd,
Anchoring erection & commissioning of machines & equipments and ensuring completion of project in
minimum turnaround time effective resource utilisation to maximise the output.
In-depth knowledge in the erection of Boilers & Structure, Boiler Steam Drum, Pressure Parts & Non
Pressure Parts, blower ,blower piping Ldo&Hfo piping, FOPH, Fuel Storage Systems, Auxiliaries, Equipment
& Piping.
Preparing layouts for project as per the process, material flow needs and foreseeing performance bottlenecks
and taking corrective measures to avoid the same and ensuring safety at the site.
Responsible for site mobilization & site coordination with management, contractor & different vendors.
Correspondence with consultants & contractors.
Energetic, industrious & organized with an analytical & innovative approach towards work assigned.
Potential in handling multiple tasks & meeting deadlines in high pressure environments
An effective communicator with good skills in building relationships. Possess strong analytical, problem
solving and organizational abilities.
CORE COMPETENCIES

PROJECT EXECUTION & MANAGEMENT


Spearheading project activities involving working out various requirements & monitoring overall project
operations for ensuring timely completion of Commissioning activities.
Overseeing all technical & managerial aspects, developing various reports on performance analysis and
handling planning for better productivity.
Anchoring on-site construction activities to ensure completion of project within the time & cost parameters
and effective resource utilization to maximize the output.
Identifying scope for planning, implementing & monitoring of technological changes to enhance
productivity.
Deploying review systems to ensure execution of projects on time and as per budgeted parameters.
Having good knowledge of understanding people and process safety including protections requirements on
various equipments and systems like the basic working knowledge with various management systems
Well versed in conceptualization, design and execution of small in-house projects, modifications, identify,
develop and negotiate with various suppliers and contractors related to job requirements.
COORDINATION AND CLIENT SERVICING
Managing issues pertaining to customer complaints by regular follow-ups and ensuring quality as per
quality assurance plan laid by the organisation.
Coordinating with the vendors and conducting regular follow up for payments along with the preparation
and certification of contractor bills.

CAREER CONTOUR

UB Engineering Limited,
Since Sep2013 (Sr. Engineer)
Power Plant Capacity: 2x660 MW (Super Critical Boiler)
ROLES & RESPONSIBILITIES

Handling all erection & commissioning activities of 2*250 MW Boiler pressure part, piping, pressure
part & structure, Ducting system and cyclone in boiler area
Handling all erection activities of 5*660 MW Boiler pressure part, piping, non-pressure part & structure,.
Erection of boiler (High pressure piping) handling supervisor and fitters for pipeline fitting, their support
fitting, checking the elevation, position and alignment of piping.
Responsible for timely completion of Erection and Execution of Boiler Structure & Boiler auxiliaries.
Organizing material and resource planning at site for erection work in Boiler and auxiliary.
Erection & Execution of Boiler structure& pressure part, Ducting. Alignment checking of Boiler structure&
pressure part, Ducting.
Preparation of Pressure Parts Arrangement drawing of Boiler as per Contract Data Sheet received from
proposal dept, after confirming the requirements as per customer/consultant technical specification with
purchase orders.

Time management and coordination with team members and release of fabrication drawings as per
scheduled date.
Regular monitoring of project schedule and implementation of remedial measures for likely delays.
Monitoring the contractual obligation of contractor and owner and releasing scope change orders through
proposal team.
Maintaining daily log book of critical events to serve as a documentary evidence for future reference.
Attending meeting with the contractor on regular intervals to extracts commitments from them to
complete the activity as per schedule and report their achievement and shortfalls to the manger.
Assessing drawing and planning pre-assembly, erection sequences and quality procedures accordingly
Supervising erection sequences to meet daily and monthly targets & generating working front for both the
erection and welding joints for a healthy daily progress
Comprehending material description and making proper arrangements so as to carryout proper QC
measures
Evaluating and assimilating all key elements related to contractual scope of the Customers/ Consultants
specification n so that these gets covered in the mechanical contracts developed for execution
Spearheaded site activities with the construction manager for completing erection & commissioning on time
Provide coordination of the project to ensure that the work is executed in accordance with the technical
scope requirements, and also with client requirement.
Report on overall progress and any significant issues, to ensure timely resolution of problems.
Preparing all bar charts, work programs and all site activities should be in accordance with the Project
Execution and Quality Plan.
ACHIEVED

Boiler hydrostatic test


Lightup of boiler
Acid cleaning of boiler
Steam blowing of boiler
Synchronisation of boiler

WORK EXPERIENCE (6 years)


Organization: Sunil Hi-Tech Engineers Limited (Sub Contractor to M/S Bharat Heavy Electricals Limited)
Period: 24/06/2010 To 25/07/2012
Designation: Engineer (pressure part)
Project: Looking on 2*500MW NTPC vindhyachal super thermal power project singrauli(MP)
Organization: Rukmani Infra Projects Private Limited(Sub Contractor to M/S Bharat Heavy Electricals Ltd
Period: 28/07/2012 To 31/08/2013
Designation: Sr. Engineer (pressure part)
Project: Looking on 2*525MW Thermal Power Plant For Monet Power Company Limited. Angul (Orissa)
Organization: UB Egineering Limited(Sub Contractor to Shanghai Electric Corporation)
Period: 05/09/2013 till Date
Designation: Sr .Engineer(Boiler Incharge)
Project: Looking on 5*660MW Tiroda Thermal Power Project ADANI Power Maharashtra Limited.
Project: Looking on 2*250MW CFBC Lignite Based TTP Bhavnagar Energy Company Ltd Gujarat.
Handled Erection Department independently & my responsibility is to satisfy deputed inspection agency
without any delay.
PREVIOUS ORGANIZATION

july 2012 aug 2013 with Rukmani Infra Projects Private Limited (Sub Contractor-M/S Bharat Heavy
Electricals LTD). Angul (Orissa) as Senior Engineer (Project) 2*525 MW
June 2010 July 2012 with Sunil Hi-Tech Engineers Limited (Sub Contractor-M/S Bharat Heavy Electricals
LTD). Singrauli (Madhya Pradesh) as Engineer -2*500 MW
ACADEMIC & PROFESSIONAL CREDENTIALS

B.E (Mechanical Engineering) 2010 with 58.50%


From Priyadarshni College of Engineering Nagpur University, India
Higher Secondary School (12th) Science 2003 with 61.50%
From Bihar intermediate Examination council Affiliated Y.A.S College Munger
High School (10th) 2000 with 50.02%
From D.H.C High School Barahat Affiliated Bihar State Board
IT Forte
CAD/
CAM- Pro Engineering, Ms-office, MS-DOS, WINDOW-98/XP/VISTA and Internet Application
PROJECT DONE

Final year project on PERFORMANCE ECALUATION OF HELICAL COIL HEAT EXCHANGER


INDUSTRIAL TRAINING:

2weeks training in Maharashtra State Power Generation Co. LTD. Koradih, Nagpur

Three day training of Power Plant Familiarization P.C.E Nagpur


Three days training in Casting & Pipeline Nico Co. Ltd. (M.I.D.C) Nagpur.

PERSONAL DOSSIER
Fathers Name
Date of Birth
Languages linguistics
Permanent Address

:
:
:
:

Shri Satyanaryan Prasad


05th July 1985
English & Hindi
Vill Radhanagar, Post-Dharmdhia, Dist-Banka, (Bihar)

Date: 15/08/2016 Bhavnagar(Gujarat)