COST ESTIMATES

I.)

DIRECT COST
A.) Materials
a.) Building
b.) Interior standard, Medium-end (50%-75% of building cost), highend (80%-100+%)
c.) Equipment (mechanical e.g. genset, etc.)- Lumpsum
B.) Labor (30% of building total cost)
C.) Land Development Cost (2,000-5,000/ sq.m)

II.)

INDIRECT COST
A.) Jobsite Overhead
a.) Warehouse - 10,000- 20,000
b.) Power Consumption/ Supply
b.1) monthly consumption (3,000- 5,000) x number of construction
months
b.2) temporary power supply 8,000-10,000
c.) Fuel (2,000-5,000) x number of construction months
d.) Temporary Water Connection (15,000 x 2 = 30,000)
e.) Small tools - 10,000
f.) Representation 5,000
g.) Supervision
g.1) Project Engineer 15,000/ month
g.2) Foreman 10,000- 12,000/ month
g.3) Warehouse man 6,000- 10,000/ month
B.) Contingency (5% of total DC)
C.) Profit (10% of total DC)
D.) Vat (12%)
Summation of Labor cost, JOH, Contingency, Profit x .12

III.)

Total Project Cost


A.) DC + IC