Rekap Kebutuhan SDM Seksi 1: No. Struktur STA Target Mulai

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 12

REKAP KEBUTUHAN SD

No.

Struktur

STA

Target Mulai

RCP 1/2 Median 60

0+060

15-Jul-16

RCP 1/2 Median 60

0+550

15-Jul-16

Box Tunnel Overpass (2x18.0x6.25)

0+639

15-Jul-16

Box Culvert 2x10.0x4.0

0+675

15-Jul-16

Jembatan Pipa Gas

1+167

15-Jul-16

Jembatan Pipa Minyak 1

1+389

15-Jul-16

Jembatan Pipa Minyak 2

1+483

15-Jul-16

Box Culvert 1x3.0x2.0

1+750

12-Aug-16

Box Culvert 1x3.0x2.0

2+075

5-Aug-16

10

Box Culvert 1x3.0x2.0

2+350

29-Jul-16

11

Box Culvert 1x3.0x2.0

2+625

11-Aug-16

12

RCP 1/2 Median 60

2+700

15-Aug-16

13

Box Culvert (14.4 x 7.13)+(16.0 x 7.13)

3+075

2-Sep-16

14

Box Culvert 1x3.0x2.0

4+900

29-Jul-16

15

RCP 1/2 Median 60

5+225

15-Aug-16

16

Box Culvert 1x3.0x2.0

5+400

8-Aug-16

17

Jembatan Pemulutan

5+613

15-Jul-16

18

Jembatan Akses Pemulutan

1+498

15-Jul-16

JUMLAH
Pekerja Masuk Tanggal 11/8/16

Mengetahui,
PT. Tri Jayaguna Bersama

Habib Burdin Hasan

M. Romli

Project Manager

Site Engineering Manager

EBUTUHAN SDM SEKSI 1

Target Penyelesaian

Kebutuhan SDM
Tahap 1

25-Jul-16

15

25-Jul-16

15

11-Aug-16

30

18-Aug-16

50

11-Aug-16

15

18-Aug-16

15

30-Aug-16

30

Tahap 2

25-Aug-16

30 (menyesuaikan produksi)

18-Aug-16

30 (menyesuaikan produksi)

11-Aug-16

30 (menyesuaikan produksi)

25-Aug-16

30 (menyesuaikan produksi)

25-Aug-16

15

6-Oct-16

50

18-Aug-16

30 (menyesuaikan produksi)

25-Aug-16

15

18-Aug-16

30 (menyesuaikan produksi)
25

10-Nov-16

50

25-Aug-16

30
280

270

Palembang, 27 Juni 2016


Mengetahui,
PT. Hutama Karya Infrastruktur

Ardyan Ari Wardhana

Nur Rochmad

Site Engineering Manager

Site Operation Manager

Keterangan
ARIF
ARIF
KASBAN
KASBAN
RIYANTO
RIYANTO
NURSANTO
SAJIYO
SAJIYO
SAJIYO
SAJIYO
SAJIYO
SOLEH
SAJIYO
ARIF
SOLEH
NURSANTO

RIYANTO

REKAP KEBUTUHAN SD

No.

Struktur

STA

Target Mulai

Jembatan

20+868

15-Jul-16

Box Culvert

20+400

15-Jul-16

Barier Tengah Median

15-Jul-16

JUMLAH

Mengetahui,
PT. Tri Jayaguna Bersama

Habib Burdin Hasan

M. Romli

Project Manager

Site Engineering Manager

EBUTUHAN SDM SEKSI 3

Target Penyelesaian

Kebutuhan SDM
Tahap 1

30-Oct-16

20

30-Aug-16

20

kontinyu

15

Tahap 2

55

Palembang, 27 Juni 2016


Mengetahui,
PT. Hutama Karya Infrastruktur

Ardyan Ari Wardhana

Nur Rochmad

Site Engineering Manager

Site Operation Manager

Keterangan