Professional Documents
Culture Documents
GE Jan 1981 A Simple in Situ Load Test For Shallow Fill
GE Jan 1981 A Simple in Situ Load Test For Shallow Fill
'ors~a ow 'i
by
MICE,
Introduction
RE-DEVELOPMENT
OF inner city
areas frequently necessitates construction
on sites covered by old, relatively shallow fills (often less than 3m deep). A
simple solution to foundation
problems
may be to take the foundation
down
through the fill (using either deep strip
footings or piles) into a firm stratum below the fill. However, this solution may
for small, lightweight
prove expensive
structures. Also, in some situations the
fill may overlie soft natural
soils which
are themselves not adequate to carry the
foundation load and even deeper foundations must then be considered. For a
large, heavy structure there may be no
alternative.
For small,
lightly-loaded
buildings
economic factors may compel
a developer
to consider founding his
structures in the made-ground. In this situation it is necessary to have some method of assessing the quality of the fill as
Ilt
oac:es:
R. DRISCOLL, BSc
THE
a foundation
material.
Requirements
The
principal
of the in-situ
widths);
(c)
how long
tained; and
(d) how many
ticular site
variability,
be main-
Site investigation
It is important that the site investigation of an area covered by shallow fill
on which it is proposed to build small
structures should be appropriate for these
conditions '. The conventional
approach
in a geotechnical
site investigation is to
drill a number of boreholes, logging the
strata and taking 'undisturbed'amples
(usually 100mm diameter) for testing in
the laboratory. On a shallow fill site this
approach may give valuable information
about the depth of different strata and
the properties of the natural soil beneath
the fill. However, it will not usually be
possible to obtain 'undisturbed'amples
of the fill itself in this way, and, even
were it possible, such small samples
would be unrepresentative.
If a solution involving
founding structures in the fill is under consideration
should be
clearly the site investigation
concerned to some extent, though not, of
course, entirely, with the fill itself. Trial
pits at a number of locations enable a
significant amount of the fill to be visually
examined and handled, and an assessrelative
ment made of its composition,
of
density
and, hence, the feasibility
on the fill. In this
founding structures
situation the major uncertainty is usually
load
settle-
Vertical stress
50
tyt
(kN/ma)
100
=0 5m
vt
Cl
1
IE
1-
at
Y=bulk density
of
nt
'D
C
fill
0
Q
Ia
1981
31
strip
footings
TABLE I.
ply uniform
y(z
+ x).
(metres)
0.5
1.0
1.5
(metres)
1.0 x 1.0
1.5 x 1.5
2.0 x 2.0
and three
quirement
likely
variability
Wl~
~I
'as
32
Ground
Engineering
Fig,
MAIR
". Skip
behaviour
s'III
settlement
Case history
in
mainly of
clay with
brick fragments. Beneath the fill was a
layer of cohesive soil varying in thickness and composition across the site; over
part of the site the layer consisted of a
firm-to-stiff brown, silty clay
35
80kN/m'), whereas elsewhere there was
soft, clayey peat
18kN/m'). Underlying this layer was dense, sandy gravel
at a depth not exceeding 4m. The water
table was located near the base of the
(c=
(c=
fill.
I,
~"
'"
l II
jq ~ jj;j jj
The smaller movements that were measured in locations C and D suggest that
the fill was acting as a comparatively stiff
layer overlying softer material, so spreading the load and reducing the stress increment applied to the clayey peat.
A possible way of developing the site
might, therefore, be to use some form of
spread, reinforced concrete foundation at
a shallow depth in the fill. The practicality
of this approach must depend on both
the type of development
and the variability of the fill. Clearly, adequate reinforcement of the foundation can only be
achieved
economically
for small units
(say, semi-detached houses) and not for
long terraces. The measurement of similar
values of settlement for the four skips
suggests that the fill may not be very
variable. This would need to be confirmed
by visual inspection of numerous trial pits.
Concluding
remarks
ei(IIINLf
II
4
t
I'
++jrM~
34
Ground
Eng sacring
Fig. 5. Routine
invar staff
settlement
measurement
of a skip, using an
6
Key
~ Skip
Skip
0 Skip
Skip
8
C
SHORTAGE
and private
E 10 I)
E
12
E
1618
20
200
100
300
400
500
600
800
700
Time (hours)
Fig.
Key
~ Skip A
~l
j Concrete
e Srup 8
capping complete
o Skip C
e Skip 0
14-
9
16
ui
s
16
20
10
1
day
20
t
30
I
1month
Log,c (time)-lhoursl
year
I40
36
Ground Engineering
10 years
I60
t
46 years
scale
Acknowledgements
The work described in this Paper formed
part of the research programme
of the
Research Establishment
Building
and is
published by permission
of the Director
of the Building Research Establishment.
The authors are grateful to Dr. J, B.
Burland for his valuable advice and en-
couragement.
References
1. BRE Digest 222 (1979): Fill and hardcore (Feb.).
2, BRE Digest 67 (1970): Soils and Foundations,
Part 3.
3. Tomiinson, M. J., Driscoll, R. & Bur(and, J. B.
(1978): "Foundations for low-rise buildings".
The Structural Engineer, Part A, 56A (6), pp.
161-173 (Also BRE Current Paper CP 61/78).
4. Borland, J. BBroms, B. B. & de Mei/o,
V, F, B. (1977): "Behaviour of foundations
and structures". State of the Art report, 9th
Int, Conf. Soil Mech. & Fndn. Engg., Tokyo,
Vol. 2, pp. 495-546. (Also BRE Current Paper
CP 51/78).
5. Cox, D. W. (1978): Contribution to discussion: Conf. on Clay Fills. Instn, Civ. Engrs.,
London, p. 271.
6. Charles, J, A, (1979): "Geotechnical problems of building on deep fill". Soc. of ChemiConf, on Reclamation of Concal Industry's
taminated Land, Eastbourne.