This document outlines the method statement for building a cable tray river crossing for a solar power plant in Gorontalo. It involves installing pile foundations using a diesel pile hammer and crane truck. The pad footings will be constructed by excavating, laying concrete, placing reinforcement cages, and pouring and compacting more concrete to form the foundation base. Next, the superstructure will be placed using a roller launch method where the bridge is constructed in situ and then jacked across the span using rollers and cantilever technique. Finally, the cable tray will be placed on the bridge and safety risk assessments will be conducted for the initial site setup and various construction activities.
This document outlines the method statement for building a cable tray river crossing for a solar power plant in Gorontalo. It involves installing pile foundations using a diesel pile hammer and crane truck. The pad footings will be constructed by excavating, laying concrete, placing reinforcement cages, and pouring and compacting more concrete to form the foundation base. Next, the superstructure will be placed using a roller launch method where the bridge is constructed in situ and then jacked across the span using rollers and cantilever technique. Finally, the cable tray will be placed on the bridge and safety risk assessments will be conducted for the initial site setup and various construction activities.
This document outlines the method statement for building a cable tray river crossing for a solar power plant in Gorontalo. It involves installing pile foundations using a diesel pile hammer and crane truck. The pad footings will be constructed by excavating, laying concrete, placing reinforcement cages, and pouring and compacting more concrete to form the foundation base. Next, the superstructure will be placed using a roller launch method where the bridge is constructed in situ and then jacked across the span using rollers and cantilever technique. Finally, the cable tray will be placed on the bridge and safety risk assessments will be conducted for the initial site setup and various construction activities.
River crossing work procedure of building for Gorontalo Solar Power
Plant is to demonstrate the process of making bridge for cable tray. 2. Equipment - Diesel Pile Hammer - Crane Truck - Theodolite - Survey Equipment - Automatic Level 3. Bridge Construction Sequence Foundation are required for abutments. Foundations can be either concrete pad pile. 1. Instal Pile Foundation 2. Pad footings are generally constructed as follows:
excavation to a depth of approximately 2.5 metres below
formation level
laying a concrete layer
fabricating cages of steel reinforcement, which is done on site,
with bars protruding vertically to required level
Placing formwork for the foundation slab.
Transporting concrete to the site and pouring and compacting
the concrete, by vibration to required level
Leaving the concrete for a period of time to enable it to cure
before stripping the formwork to from foundation base
3. Supper Structure Placement
Roller launch method. The bridge is constructed in situ and then jacked across the span using rollers and cantilever technique.
4. Placement Cable Tray
4. Safety The following Safety Risk Assessments are relevant to the works and will be produced by competent persons and attached to the detailed Method Statement in accordance with the Construction Phase Plan: