Professional Documents
Culture Documents
Risk Assessment - Final
Risk Assessment - Final
Major
Hazard
Serious
Hazard
Slight
Hazard
Risk
High Risk
Medium Risk
Low Risk
How to control
Construct a barrier for trucks to near excavation
Construct a fence between outside and inside site to avoid
people intervention in to site.
Using a proper ladder for labours work in the site or inside
excavation
2- Diaphragm wall
Risk are:
hazard
Risk
High Risk
Medium Risk
Major
Hazard
Serious
Hazard
Slight
Hazard
Low Risk
Potential
hazard
Major
Hazard
Serious
Hazard
Slight
Hazard
Risk
High Risk
Medium Risk
Low Risk
How to control:
Sections of propped pipe must be design to resist compression force
applied by pressures behind diaphragm wall
The coordinates of ends should be done by sophisticated and
accurate equipment such as Total station to avoid inclination of
propped pipes.
Size of excavator machine should be selected to be fitted with
distance between two propped pipes
Dismantling should be done after installing beams in two basement
levels with paying attention of method of dismantling.
Failure in engine
Dropping materials
Crane failure due to overturning
Potential
hazard
Major
Hazard
Serious
Hazard
Slight
Hazard
Risk
High Risk
Medium Risk
Low Risk
How to control risk:
Kept in efficient during working time and providing good
maintenance up to date
High skilled labour should monitor the lifting material
and double checking before commanding to crane
driver.
Structurally designing crane tower basement and its
lever.
Potential
hazard
Major
Hazard
Serious
Hazard
Slight
Hazard
Risk
High Risk
Medium Risk
Low Risk
How to control risk:
Provision of high degree of connection. This can be
satisfied by verification good design for bolts and clits
with external column and edge beams
Good quality of substance used in expansion joint
which can resist the variation of temperature
Precast units should be monitored in the factory to
check whether these precast units are suitable to be
transmitted to the site.
Work must be done by crane tower with rigorous
supervision.
Potential
hazard
Major
Hazard
Serious
Hazard
Slight
Hazard
Risk
High Risk
Medium Risk
Low Risk
How to control:
Good supervision on electrical equipment, supplying all
electrical accessories to prevent misusing electric by different
equipment.
7- Weakness in connection
Caused by
- Careless of tightening bolts and splices
- Using different bolts strength grade
Risks are
hazard
Major
Hazard
Serious
Hazard
Slight
Hazard
Risk
High Risk
Medium Risk
Low Risk
Control by:
High supervision on connection
Testing bolts for its strength in laboratory.
Labour falls
Material falls
Potential
hazard
Risk
High Risk
Medium Risk
Major
Hazard
Serious
Hazard
Slight
Hazard
Low Risk
How to control:
Plan and organise work to keep people away from opening
area by providing guard wall or steel work.
Temporary flooring for opening area by scaffolds in order to
be accessible for labours.
by :
Cement plastering
Painting steel elements to avoid corrosion
Dust
Grouting substance
Asphalts for roof surfacing
Risks are:
hazard
Major
Hazard
Serious
Hazard
Slight
Hazard
Risk
High Risk
Medium Risk
Low Risk
Controlled by:
Worker must follow the instruction of site manager by wearing
safety cloths which protect them from dangerous material
During excavation the site should bewattered to prevent blowing
dust.
Worker should be trained to treat with these substances.
10 Fire explosion
Risks are:
Potential
hazard
Major
Hazard
Serious
Hazard
Slight
Hazard
Risk
High Risk
Medium Risk
Low Risk
Providing fire extinguisher in every level
workers must be trained how to use fire extinguisher
Extremely prohibiting fire holding in the site .this should be
satisfied by rigorous monitoring.
The water reservoir or water tanks should be installed on site and
contains a sufficient amount of water to coverage any fire
circumstance.