Professional Documents
Culture Documents
MEIC Comments On NorthWestern Energy's 2015 Resource Procurement Plan
MEIC Comments On NorthWestern Energy's 2015 Resource Procurement Plan
resource planning process prior to its formal filing at the PSC. The current rules
acknowledge the importance of public involvement but there is limited opportunity
for diverse stakeholders to participate in the planning process prior to the final plan
being filed with the Commission. MEIC participates in the TAC assembled by
NorthWestern and acknowledges and appreciates the opportunity to provide input
to the utility through that committee. In past planning cycles, NorthWestern
regularly convened the TAC on a monthly basis prior to its submittal of the resource
plan. During the development of the 2015 Plan, there were only five TAC meetings.
Since the TAC serves as the primary forum for stakeholder involvement with
planning preparation there should be at the very least, more frequent meetings.
More importantly though, the planning process should be improved to increase
public and Commission involvement. Increasing the planning cycle from every two
years to every three years is an important first step to facilitating more stakeholder
and public involvement and engagement. The current planning process and limited
public involvement are incongruent with a plan that is intended to be a long-term
vision.
Energys planning process and rules provided in Graceful Systems, LLC final report
to the Commission in Docket# N2012.5.56. We recommend the Commission and
NorthWestern review those recommendations in the context of NorthWesterns
changing portfolio and move to becoming a more vertically integrated utility with
the purchase of the dams. It is also critical that the planning rules acknowledge the
multiple gas-fired resources of different sizes and technology types phased into the
portfolio at different times. The purpose of these gas plants is to provide capacity
and resource adequacy that NWE determined it will need due to certain changing
conditions in the Northwest over the next decade. Rather than analyzing the costs
and risks of relying on other resources in the region to continue to provide capacity,
NorthWestern assumes that it will need to supply all of its customers capacity
needs and used it as an assumption in the PowerSimm model. NorthWestern Energy
constrained the model based on an assumption of its need for capacity without
analyzing viable alternatives to meeting capacity needs by other means.
NorthWesterns limited economic analysis of gas resources is also constrained by
only a high level analysis of natural gas transmission infrastructure costs. Without
a more detailed analysis, it is difficult to determine whether the EOP truly minimizes
costs to meet customers future needs.
resources is shortsighted and is not realistic about the inherent volatility of gasfired resources. We understand that Northwestern is concerned about the risks
associated with continuing to rely on market purchases for capacity, resource
adequacy, and reliability. We also acknowledge that there are changes occurring
across the energy system in the Northwest that could have impacts on the cost and
risk of relying on market purchases. But, we believe that exchanging the risk of
market purchases for the risk of natural gas fuel prices is imprudent because it
ignores other alternatives that could be much lower cost and risk in the long run.
One of these alternatives, demand response, is identified in the Northwest Power
Planning and Conservation Councils 7th Power Plan as the least-cost strategy for
the regions utilities to meet winter peaking capacity needs. We will go into more
detail about demand response opportunities later in our comments. We are
concerned that the EOP with a focus on developing gas resources ignores demand
response strategies and other alternatives that are a less expensive, more
sustainable, and less risky investment for Northwestern and its customers.
Current low natural gas prices have not reduced the volatility associated with
its fuel costs. Northwestern must weigh this and other risks when forecasting longterm economic impacts to ratepayers, including future state and federal regulations
aimed at reducing climate change emissions and water and air pollution from
natural gas production. Natural gas has many end uses and is susceptible to extreme
weather events. These factors have contributed to natural gass historic price
volatility. These risk factors are only going to intensify in the future as more utilities
invest in new natural gas power plants during this period of low prices. The natural
gas prices at the Henry Hub Terminal between 2002-2014 from the Energy
Information Administration displayed below illustrate the extreme volatility of
natural gas prices over time.
$/MMBtu
10
8
6
4
2
0
2002
2004
2006
2008
2010
2012
2014
For more than a decade, U.S. natural gas prices have been subject to significant volatility, which can harm consumers and the economy.
*At the Henry Hub Terminal in Erath, Louisiana.
SOURCE: EIA 2014F.
13
Modernizing the Power Grid outlines some operational and grid management
techniques that can improve flexibility of the grid at lower costs. 1
Energy Efficiency and Demand Side Management
Although new avoided costs are likely to be lower than those applied in
throughput incentive to increase energy sales. The recent elimination of the Lost
Revenue Adjustment Mechanism as well as anticipated low avoided cost calculation
amplifies the need to eliminate barriers to energy efficiency acquisition. We
strongly encourage NorthWestern and the Commission to work with stakeholders
and the public to ensure robust energy efficiency acquisition is guaranteed in future
planning cycles.
Demand Response
Plan identifies cost-effective demand response as the least cost solution for
providing peaking capacity in the Northwest. NorthWesterns 2015 Plan includes
only a cursory analysis of demand response resources available to meet its capacity
needs. Because NorthWestern identified meeting capacity as a top priority in this
planning cycle, we encourage a much more in-depth cost-effectiveness analysis of
demand response resources available to meet these capacity needs. The
Economically Optimal Portfolio identified in the 2015 Plan includes building new
gas resources to meet capacity needs, a costly undertaking that can take years
longer than anticipated. Demand response can be deployed sooner and in quantities
better matched to peak capacity needs than building new gas resources. Demand
response can also avoid the need to expend significant capital on new supply side
resources in order to meet capacity needs that occur in only a handful of hours per
year.
into how much load from these customers could be reduced during peak load
periods. This information is not, however, demonstrative of the total amount of
demand response available from residential and small commercial customers. The
2015 Plan focuses on qualitative limits to demand response savings available to
NorthWestern from each sector. These limits include low penetration rates of
electric water heaters and electric space heat in NorthWesterns service area.
NorthWesterns end-use studies show a 3% penetration rate for electric space heat
and a 21% penetration rate for residential electric heat. This is compared with the
Councils analysis in the 7th Plan that shows a 33% penetration rate for residential
electric space heat and a 57% penetration rate for residential electric water heat.
Most of the lowest cost demand response savings the Council identified in the 7th
Plan come from these two residential consumption categories. We understand that
NorthWesterns lower penetration rates functionally limit some potential savings
from demand response programs focused on electric heat and electric water
heaters. But, these limitations do not mean that there are not any cost-effective
demand response savings available on NorthWesterns system. The low cost of
demand response resources combined with their ability to reduce peak capacity
needs makes them an extremely valuable resource worthy of a more in-depth
economic analysis. NorthWesterns 2015 Plan lacks this analysis, despite their
description of this plan as a capacity first plan. NorthWestern should model
demand response resources from the residential, commercial, and industrial sectors
to determine peak capacity quantities available and at what price. These results
should be compared against the cost of gas resources in the current EOP.
NorthWestern has not performed this quantitative analysis and therefore should
not rule out demand response as a cost-effective resource strategy in its 2015 Plan.
Renewable Energy
will take to comply with the Community Renewable Energy Project (CREP)
requirements. The RPS requires NorthWestern to have secured around 65.4 MW of
capacity from CREP eligible projects in 2015. Currently, NorthWestern admits to
only having about 25 MW of CREP capacity and being out of compliance with the
law. The 2013 RPP detailed specific steps NorthWestern had taken to comply with
CREPs. An account of these efforts from the past two years is missing, making it
difficult to assess what compliance efforts have taken place. Regardless of any
challenges NorthWestern may or may not have faced in securing CREP qualifying
projects, the lack of a roadmap or detailed discussion for how to come into
compliance is disturbing and without justification.
discussions about joining organized regional markets such as the Energy Imbalance
Market (EIM). We encourage continued analysis of the benefits and costs associated
with the regional EIM that continues to gain more participation. As more of the
regions utilities join and are active in the EIM, we believe there could be
tremendous benefits to NorthWestern and its customers in joining.
Colstrips Future and Modeling Scenarios
In November 2015, the University of Montana Bureau of Business and
Economic Research (BBER) released a study commissioned by NorthWestern aimed
at estimating potential impacts of the Clean Power Plan on Montana. The report is
titled The Economic Implications of Implementing the EPA Clean Power Plan in
Montana, and NorthWestern included it in its entirety as reference within the RPP
(Volume 2, Chapter 4, Number 2).2 One of the key findings is the claim that The size
of the required CO2 reductions imposed by the Clean Power Plan, and limited
options available raise the prospect that compliance will result in the complete
closure of the Colstrip generating station, (page 3). Regarding this closure the
report states, It will also require significant new investment in replacement
generation assets, as well as in the transmission system improvement necessary to
support them, (page 2).
2 http://www.northwesternenergy.com/docs/default-source/documents/defaultsupply/plan15/volume2/um-bber-report
10
11
significant consideration to this potential future. The inclusion of the BBER report as
supplemental material in the RPP would also indicate NorthWestern takes its
findings seriously, presumably including its claims about a Colstrip closure. Both the
BBER report and NorthWesterns filing against the Clean Power Plan came in
November 2015. The RPP was filed with the Commission on March 31, 2016. This
makes the exclusion of the Colstrip closure possibility from the Plans modeling
scenarios a significant deficiency of the Plan. It also raises questions as to why this
scenario was not modeled and presented to the Commission when the company in
other venues has explored it in detail.
Similarly there are other issues related to the Colstrip plant that were
omitted from the analysis in the RPP. For example, the closure of Units 1 and 2 has
been subject to much speculation and analysis. NorthWestern failed to consider its
April 2015 analysis that considered the impact to the transmission system if
Colstrip Units 1 and 2 were closed.4 This study was completed prior to the submittal
of the RPP to the Commission yet was not considered in the RPP. Furthermore, no
analysis was provided on how closure of a portion of the plant may impact the longterm economics of the remainder of the plant.
The RPP also failed to mention how the price of mined coal could affect the
economics of the Colstrip plant. The price of coal for the Colstrip plant averages
$25.64 per ton. That price is expected to be $23.60 in 2016. (Table 4-2 Colstrip Coal
Price Forecast). NorthWestern, as well as the other owners of the Colstrip plant
have failed to control the price of coal from the Rosebud Mine owned by Western
4 NorthWestern Energy, EPA 111-D Consideration Retirement of CS units 1 & 2. Prepared for Regional Electric Transmission
Planning. April 2015.
12
Energy. Consumers are stuck paying a bill for that coal that is dramatically greater
than market prices. Powder River Basin (PRB) coal for the week of August 12, 2016,
sold for $8.70 per ton. According to the Energy Information Administration, PRB
coal has not made it above $15 per ton since at least January 2011 and has been
steadily declining since then. NorthWestern overpays for the coal used at the
Colstrip plant and a better deal may be available with a different coal provider that
would directly benefit ratepayers.
Finally, NorthWestern assumes that it will not need to install selective
catalytic reduction (SCR) technology on Units 3 and 4 at any time during the 20-year
planning horizon for compliance with the reasonable progress requirements of EPA
Regional Haze rule. Other Colstrip owners have projected otherwise. Puget Sound
Energy, in its 2013 Integrated Resource Plan mid-cost scenario, analyzed the
installation of SCR on Units 3 and 4 by 2027. Pacificorp, in an Oregon utility
commission proceeding, recently estimated Units 3 and 4 would need to install SCR
technology by December 2023. The other owners of Colstrip are considering the
installation of SCR within the 20-year time horizon. NorthWestern should as well.
Conclusion
The Commission should review its rules and require an improved public
process in the next RPP. NorthWestern should better analyze demand management
and the potential changes that closure of Colstrip Units 1 and 2 could have on its
Montana customers. NorthWestern should also analyze the impacts of closing units
3 and 4 within the planning horizon, the increased cost of mining on Montana
13
consumers, the fact that other owners are being required to depreciate their interest
in the facility, and the impact of federal regulations on the plant.
14