Professional Documents
Culture Documents
Validation Opinion Paulinia Highlight
Validation Opinion Paulinia Highlight
Final
ESTRES Paulnia Landfill Gas Project (EPLGP)
in
Brazil
Country:
0165
Client:
Client contact:
Report No.:
Revision:
2015-BQ-41-MD
1.2 Aa
29/02/2016
Date of approval:
01/03/2016
Laura Severino
Methodology
Number:
Version:
Title:
Scale
SS(s):
ACM0001
13.0.0 of 11/05/2012
Large
13
RINA Services S.p.A. (RINA), commissioned by ESTRE Ambiental S/A, has performed the validation of post
registration changes for the project activity ESTRES Paulnia Landfill Gas Project (EPLGP) in Brazil.
It is RINAs opinion, the changes, as outlined in the revised PDD version 04.5 of 29/02/2016, from the
project activity as described in the registered PDD ensure that the level of accuracy and completeness in the
monitoring and verification process is not reduces as a result of the revision; the revisions are in accordance
with the applied monitoring methodology and the changes to the project activity comply with the
requirements established in the CDM Project Standard.
Hence RINA requests that the validation opinion on changes from the project activity as described in the
revised PDD for the project activity ESTRES Paulnia Landfill Gas Project (EPLGP) in Brazil may be
considered by the Board.
Keywords:
Protocol,
Clean
Rita Valoroso
Baseline Emissions
Corrective Action Request
Clean Development Mechanism
Modalities and Procedures CDM
Certified Emission Reduction(s)
Methane
Clarification Request
Carbon dioxide
Carbon dioxide equivalent
Coordination and Technical Control Staff
Certification Division of RINA Services Spa
Designated National Authority
Designated Operational Entity
Executive Board
Environmental Impact assessment
Emission Reductions
Forward Action Request
Greenhouse gas(es)
Global Warming Potential
Intergovernmental Panel on Climate Change
Letter of Approval
Means of Verification
Monitoring Plan
Monitoring Report
Non-governmental Organization
Official Development Assistance
Project Cycle Procedure
Project Design Document
Project Emission
Project Participant(s)
Project Standard
Document Reference
RINA Services Spa
Sectoral Scope(s)
Technical Area(s)
United Nations Framework Convention on Climate Change
Validation and Verification Standard
Page
1
1.1
1.2
INTRODUCTION ...................................................................................................................... 4
Objective
4
Scope
4
2
2.1
2.2
2.3
2.4
2.5
METHODOLOGY ..................................................................................................................... 4
Document Review
4
Follow-up actions
6
Resolution of outstanding issues
7
Internal quality control
8
Validation team and the technical reviewer(s)
8
3
3.1
3.2
3.3
3.4
1.1 Objective
The objective of the Validation is to have an independent evaluation of the changes of the project activity
from the registered PDD compliance with relevant UNFCCC requirements Project Standard to confirm that
it is sound and reasonable and meets the identified criteria and to ensure the level of accuracy and
completeness. The objective of this validation was to assess the revised project design document in order
to confirm its accuracy and completeness of the information reported for the ESTRES Paulnia Landfill
Gas Project (EPLGP) project in Brazil.
1.2 Scope
The validation scope is to review the revised project design document (PDD) against the UNFCCC criteria
for CDM and it is defined as required in the context of proposed revision of a registered CDM activity and
will result in a conclusion by the executing RINA as to whether a revised PDD is valid and should be
submitted to replace the previous version.
UNFCCC criteria refers to paragraph 62(g) of the modalities and procedures for the CDM
The Validation Opinion is not meant to provide any consultancy towards the project participants. However,
stated requests for clarifications and/or corrective actions may have provided input for improvement of the
project design.
2 METHODOLOGY
Validation was conducted using RINA procedures in line with the requirements specified in the CDM M&P,
the latest version of the CDM Validation and Verification Manual, and relevant decisions of the COP/MOP
and the CDM EB and applying standard auditing techniques.
The following sections outline each step in more detail.
UniCarbo Energia e Biogs Ltda. CDM-PDD for project activity ESTRES Paulnia Landfill Gas
Project (EPLGP) in Brazil, version 04.5 of 29/02/2016, version 04.4 of 24/11/2016, version 4.3
of 20/10/2015
/02/
CDM Executive Board: Clean Development Mechanism Project Cycle Procedure, version 09 of
20/02/2015
/04/
CDM Executive Board: Clean Development Mechanism Validation and Verification Standard,
version 09 of 20/02/2015
/05/
CDM Executive Board: Baseline and monitoring methodology ACM0001 Flaring or use of
landfill gas version 13.0.0 of 11/05/2012.
/06/
Econergy: CDM-PDD for project activity ESTRES Paulnia Landfill Gas Project (EPLGP) in
Brazil, version 4.2 of 26/04/2013 (renewal crediting period),
Econergy: CDM-PDD for project activity ESTRES Paulnia Landfill Gas Project (EPLGP) in
Brazil, version 3.1 of 18/01/2012
Econergy: CDM-PDD for project activity ESTRES Paulnia Landfill Gas Project (EPLGP) in
Brazil, version 2b of 04/12/2005
/07/
CDM Executive Board Tool to determine the mass flow of a greenhouse gas in a gaseous
stream, version 02.0.0 of 03/06/2011
/08/
CDM Executive Board Tool to calculate the emission factor for an electricity system, version
03.0.0 of 23/11/2012
/09/
/10/
CDM Executive Board: Baseline and monitoring methodology AM0003 Simplified financial
analysis for landfill gas capture projects version 3 of 30/09/2005.
/11/
CDM Executive Board: Project emissions from flaring, version 2.0.0 dated 20/07/2012
/12/
Biotecnogas technical memory of Central aspiration and biogas combustion, dated 09/2006
/13/
* Cetesb partial operational license number 37002080 for the landfill, dated 25/02/2014 valid
until 25/02/2019
* Cetesb operational license number 37001297 for biogas plant (flare 1 and 2) , dated
30/09/2011 valid until 30/09/2016
* Cetesb operational license number 37002348 for the flare 3 , dated 23/12/2014 valid until
23/12/2019
* Cetesb operational license number 37001298 for the flare 4 and 5 , dated 30/09/2011 valid
until 30/09/2016
* Cetesb operational license number 37002536 for the flare 6 , dated 31/07/205 valid until
31/07/2020
/14/
UniCarbo Energia e Biogs Ltda. CERs spreadsheet version 04.5 of 29/02/2016 CER
sheet_165 - v4.5.xlsx (revised to be in line with PDD version)
Version 04.4 of 24/11/2015 CER sheet_165 - v4.4.xlsx
version 4.3 of 20/10/2015 CER sheet_165 - V4.3.xlsx
/15/
Biotecnogas s.r.l., technical note regarding the flare maximum temperature and flow of the
flares installed at CGR Paulinia landfill (160229 - Paulinia Declaration.pdf)
Organization
Topic
/a/
28/09/2015
Nuno
Barbosaconsultant
Unicarbo
/b/
28/09/2015
Tiago Nascimento
Silva- Operational
manager
Estre
/c/
28/09/2015
Estre
/d/
28/09/2015
Henrique
Novais
Bicalho
Estre
/e/
28/09/2015
Adriano
AlmeidaBiogas Specislist
Estre
Emission
Reductions
calculation
Monitoring report
Monitoring plan
Monitoring methodology
Monitoring data
Implementation status of the
project
Monitoring equipment and
operation
Calibration of equipments
Emission Reductions
calculation
The project participants have made mistakes that will influence the ability of the project activity to
achieve real, measurable additional emission reductions.
Last Name
First Name
Country
Team
Leader/
Technical expert 13.1
De
Lima
Carvalho
Thas
Yes
Brazil
Validator/Verifier
Principe Branco
Saettoni
Geisa Maria
Yes
Brazil
Technical
TA 13.1
Valoroso
Rita
No
Italy
Reviewer
3 VALIDATION FINDINGS
The findings of the validation related to the project, as described in the version 04.5 of 29/02/2016 and
previous PDD version 04.4 of 24/11/2015 and version 4.3 of 20/10/2015 /01/, are stated in the following
sections.
The validation requirements, the means of validation and the results from validating the identified criteria
are documented in more detail in the validation report.
0165
Date of registration
03/03/2006
Methodology(ies)
Party(ies) involved
Brazil
Norway
Project Participants
Nordic Environment
Finance Corporation
10
- Ru: Universal ideal gases constant in accordance with Default value of 8,314 Pa.m /kmol.K as per the
Tool to determine the mass flow of a greenhouse gas in a gaseous stream (Version 02.0.0) /07/.
- wBM: Weighting of build margin emissions factor, 0.75 (75%) during the 2nd 7-year crediting period in
accordance with the default value as per the Tool to calculate the emission factor for an electricity system
(version 03.0.0) /08/
- wOM: Weighting of operating margin emissions factor, 0.25 (25%) during the 2nd 7-year crediting period in
accordance with the default value as per the Tool to calculate the emission factor for an electricity system
(version 03.0.0) /07/
RINA verified that level of accuracy and completeness of the monitoring is not reduced in the revised PDD
and complies with the applied monitoring methodology /05/ and applicable tool /07/
11
th
PP is requesting a temporary deviation for the 16 monitoring period 14/09/2013 to 30/09/2014 and 17
monitoring period 01/10/2014 - 31/07/2015 to apply the default value for the flare efficiency. Project activity
was registered under AM0003 Simplified financial analysis for landfill gas capture projects version 3 of
30/09/2005 /10/and renewal crediting period under ACM0001 Flaring or use of landfill gas version 13.0.0
of 11/05/2012 /05/ and has operated with a unique LFG flow meter installed for measuring the amount of
the LFG sent to all the installed high temperature enclosed flares (set of the installed flares). In order to be
in line with the applied methodology /05/ and Tool to determine the mass flow of a greenhouse gas in a
gaseous stream /07/a post registration change is requested as described in the section above.
For the current monitoring period as individual flow meters for each flare were not installed, PPs have
applied a conservative approach for calculating project emissions from flaring (PEflare,y) in accordance with
Option A of the methodological tool Project emissions from flaring /11/ applying the default value of 90%
for flare efficiency.
PP have provided the Biotecnogas technical memory /12/ which describes that all installed flares are
equipped with individual flame detectors (of which in case of no detection of flame in a particular flare
automatically trigger instantaneous closure of the main LFG supply valve for such particular flare, thus
preventing any possibility of LFG venting through that particular flare. PP clarified the operation procedures
to monitor the flare operational specifications (please, see detailed information in the CL 1). Moreover, a
conservative approach will be adopted for the emission reduction calculation, considering that no Emission
Reduction will be claimed with the flares operating in non-conformity with the specified operational
parameters.
During the completeness check the following issues were raised:
Regarding the temporary deviation, the DOE is required to provide more information on how the proposed
deviation to use option A of the tool complies with the tool Project emissions from flaring p. 3 and 4, in
particular:
1) The validation opinion (p 19-20) states that Although the flare manufacturer does not specify a
maximum value for flame temperature, the assumed maximum recommended set point of the flare (in
order to maintain the physical integrity of the flare isolation) is 1,200C. However, the tool requires that the
temperature of the flare (TEG.m) is within the manufacturers specification for the flare (SPECflare) in minute
m. Therefore, the DOE is requested to further substantiate how it has validated that the reported
temperature specifications comply with the manufacturers specifications of the type of installed flare.
2) The validation opinion (p 20-21) states that during the previous monitoring periods where the LFG plant
also operated with only one LFG flow meter installed, the control system of the flaring facility controlled the
LFG supply valve of each individual flare in order adjust the amount of LFG sent in each flare, thus
ensuring overall operation of the LFG flaring facility within the flares operational parameters inter alia in
terms of LFG flow. During such period LFG flaring capacity was programmed to a maximum flaring
3
capacity of 14,000 Nm /h of LFG. However, the tool requires that the flow rate of the residual gas to the
flare (FRG,m) has to be is within the manufacturers specification for the flare (SPECflare) in minute m.
Therefore, the DOE is required to further substantiate i) whether the maximum flaring capacity of 14,000
Nm3/h is within the manufacturer specifications, and ii) how flow rate of residual gas to the flare (FRG,m) has
been monitored as per the tool.
In order to address the issues RINA has amended the CL 1 to provide more detail how the manufacturer
specifications of the flares operation will be considered in the temporary deviation. Manufacturer has
provided technical note, dated 29/02/2016 /15/ to support the manufacturers specification.
PDD was revised to version 04.5 of 29/02/2016 to include the maximum operation temperature, in
accordance with the manufacturer technical note, dated 29/02/2016 /15/
Rina verified that the proposed deviation is not reducing the accuracy of the calculation of emission
reductions, as project participants will apply conservative assumptions to ensure that emission reductions
will not be overestimated as a result of the deviation.
Validation Opinion Post Registration Changes N 2015-BQ-41-MD, REV. 1.2 AA
CDM_VAL_OP_PDD-05-15
12
4 VALIDATION OPINION
RINA Services Spa (RINA) has performed a validation of post registration changes for the project activity
ESTRES Paulnia Landfill Gas Project (EPLGP) in Brazil, CDM Registration Reference N 0165. The
validation has s based on the information made available to us.
RINA has performed this validation on the basis of the following documents:
CDM Executive Board: Clean Development Mechanism Project Cycle Procedure, version 09 of
20/02/2015;
CDM Executive Board: Clean Development Mechanism Validation and Verification Standard,
version 09 of 20/02/2015
Approved baseline and monitoring methodology ACM0001 Flaring or use of landfill gas version
13.0.0 of 11/05/2012
It is RINAs opinion, the changes, as outlined in the revised PDD version 04.5 of 29/02/2016, from the
project activity as described in the registered PDD ensure that the level of accuracy and completeness in
the monitoring and verification process is not reduces as a result of the revision; the revisions are in
accordance with the applied monitoring methodology and the changes to the project activity comply with
the requirements established in the CDM Project Standard.
Hence RINA requests that the post registration changes from the project activity as described in the
registered PDD for the project activity ESTRES Paulnia Landfill Gas Project (EPLGP) in Brazil may be
considered by the Board.
Genova, 01/03/2016
Laura Severino
Authorized officer signing for the DOE
RINA Services S.p.A
13
APPENDIX A
1-A
Reference to Section
of the report
3.3
Validation Conclusion
Reference to Section
of the report
Validation Conclusion
methodology in
project activity.
the
registered
CDM
3-A
Reference to Section
of the report
Validation Conclusion
CPA;
The scale of the project activity is not
impacted by the change. Project remains
large scale.
(f) The eligibility criteria of PoA.
Not applicable.
This CAR is closed
CAR 2
Revised PDD updated the CERs estimative
considering the expansion of the landfill operation
until 2023, however, the estimative of waste
disposal was not updated in the table 8 of the
revised PDD
CAR 3
Revised PDD did not update section B.7.3 figure
4- Monitoring equipments location, to include the
meters for each flare. Moreover, the subsection
2.1 LFG flow, describes only 4 flares in the project
activity.
CAR 4
Revised PDD did not update the information
provided in Annex 4- table Key parameters
(projected year of landifil closure). Moreover, the
table do not consider the 10% discount in the flare
efficiency due to the low height flares installed.
3.3
3.4
3.4
4-A
Reference to Section
of the report
CL 1
PP is requested to clarify the quality control
quality assurance procedure to guarantee that the
biogas is burnt within the flares specifications
(temperature and flow) in all flares that are
operational at the same time.
3.5
Regarding
the
flare
operational
requirements of the flares in terms of
temperature, it is crucial to note that each
flare
is
equipped
with
individual
temperature meter (that measures the
temperature of the flame). Depending on
measurements of the temperature of the
flare, the air-LFG mixture is adjusted
through automatically opening and/or
closure of the air damper window located
in the bottom of the flare in order to have
Validation Conclusion
Reference to Section
of the report
Validation Conclusion
Reference to Section
of the report
Validation Conclusion
7-A
Reference to Section
of the report
Validation Conclusion
8-A
Reference to Section
of the report
Validation Conclusion
9-A
Reference to Section
of the report
Validation Conclusion
10-A
Reference to Table 2
FAR 1
11-A
CERTIFICATO DI QUALIFICA
QUALIFICATION CERTIFICATE
qualificato come :
is qualified as:
SCOPO SETTORIALE
SECTORAL SCOPE
1
1
2
13
DATA
DATE
19-08-2009
15-01-2015
Legend:
VAL:
Validator
CDM: Clean Development Mechanism
VER:
Verifier
VCS : Verified Carbon Standard:
TEC:
Technical Expert
GS: Gold Standard
TL:
Team Leader
SCS: SocialCarbon Standard
FIN-EXP:
Financial Expert
JI: Joint Implementation
DET:
Determiner
RINA Services S.p.A. accreditato da UNFCCC, quale Entit Operativa Designata (DOE), per condurre la Validazione e la Verifica di Progetti CDM, da
VCSA per condurre la Validazione e la Verifica di Progetti VCS, da GS Foundation, per condurre la Validazione e la Verifica di Progetti GS, da Ecologica
Institute per condurre la Validazione e la Verifica di rapporti SCS
RINA Services S.p.A. is accredited by the UNFCCC, as Designated Operational Entity (DOE), to carry out Validation and Verification of CDM Projects, by
the VCSA, to carry out Validation and Verification of VCS Projects, by the GS Foundation, to carry out Validation and Verification of GS Projects and by
the Ecologica Institute, to carry out Validation and Verification of SCS Reports
GHG_QUAL_CERT_EN_04_12
Page 1 of 1
CERTIFICATO DI QUALIFICA
QUALIFICATION CERTIFICATE
Si attesta che il sig./sig.ra:
SCOPO SETTORIALE
SECTORAL SCOPE
1
1
13
DATA
DATE
27-08-2009
17-07-2015
Legend:
VAL:
Validator
CDM: Clean Development Mechanism
VER:
Verifier
VCS : Verified Carbon Standard:
TEC:
Technical Expert
GS: Gold Standard
TL:
Team Leader
SCS: SocialCarbon Standard
FIN-EXP:
Financial Expert
JI: Joint Implementation
DET:
Determiner
RINA Services S.p.A. accreditato da UNFCCC, quale Entit Operativa Designata (DOE), per condurre la Validazione e la Verifica di Progetti CDM, da
VCSA per condurre la Validazione e la Verifica di Progetti VCS, da GS Foundation, per condurre la Validazione e la Verifica di Progetti GS, da Ecologica
Institute per condurre la Validazione e la Verifica di rapporti SCS
RINA Services S.p.A. is accredited by the UNFCCC, as Designated Operational Entity (DOE), to carry out Validation and Verification of CDM Projects, by
the VCSA, to carry out Validation and Verification of VCS Projects, by the GS Foundation, to carry out Validation and Verification of GS Projects and by
the Ecologica Institute, to carry out Validation and Verification of SCS Reports
GHG_QUAL_CERT_EN_04_12
Page 1 of 1
CERTIFICATO DI QUALIFICA
QUALIFICATION CERTIFICATE
Rita Valoroso
qualificato come1:
is qualified as:
1.2, 13.1
SCOPO SETTORIALE
SECTORAL SCOPE
1
13
DATA
DATE
18-01-10
22-12-2014
Il Resp. QPT
Head of QPT
Legend:
VAL:
Validator
CDM: Clean Development Mechanism
VER:
Verifier
VCS : Verified Carbon Standard:
TEC:
Technical Expert
GS: Gold Standard
TL:
Team Leader
SCS: SocialCarbon Standard
FIN-EXP:
Financial Expert
JI: Joint Implementation
DET:
Determiner
RINA Services S.p.A. accreditato da UNFCCC, quale Entit Operativa Designata (DOE), per condurre la Validazione e la Verifica di Progetti CDM, da
VCSA per condurre la Validazione e la Verifica di Progetti VCS, da GS Foundation, per condurre la Validazione e la Verifica di Progetti GS, da Ecologica
Institute per condurre la Validazione e la Verifica di rapporti SCS
RINA Services S.p.A. is accredited by the UNFCCC, as Designated Operational Entity (DOE), to carry out Validation and Verification of CDM Projects, by
the VCSA, to carry out Validation and Verification of VCS Projects, by the GS Foundation, to carry out Validation and Verification of GS Projects and by
the Ecologica Institute, to carry out Validation and Verification of SCS Reports
GHG_QUAL_CERT_EN_04_12
Page 1 of 1