Professional Documents
Culture Documents
2006 22
2006 22
PROSIDING, Simposium Nasional & Kongres IX Ikatan Ahli Teknik Perminyakan Indonesia (IATMI) 2006
Hotel The Ritz Carlton Jakarta, 15-17 November 2006
KEY ELEMENTS TO REVIVE THE MATURE HANDIL FIELD: LIGHT WORK OVER,
INFILL WELL AND EOR
Henricus Herwin, Hotma Yusuf, Iswahyuni Fifthana, Habib Alfian Tafsiri, Total E&P Indonsie
ABSTRACT
The future of Handil Field, a large mature oilfield,
relies on the successful application of Light Work
Over and Infill Well to recover by-passed oil and
un-drained areas, supported by EOR techniques to
maintain the reservoir pressure and sweep the tertiary
oil. This presentation discusses the most useful
concept and practices that are applicable to optimize
oil recovery in a multi-layer water-flooded field.
The Handil field, discovered in 1974, is a giant
mature oilfield located in the Mahakam Delta,
Indonesia. The field consists of 555 accumulations
and was developed using conventional oil recovery
methods: natural depletion and peripheral water
injection. After many reservoirs have been waterflooded, EOR lean gas injection project was started in
November 1995 on five reservoirs and following its
positive result, the project was extended to other six
reservoirs in 2000. However, the field production
continued to decline from 200,000 BOPD in the late
seventies to 12,500 BOPD in 2003.
An integrated study on the largest EOR reservoir was
performed to assess the projects performance,
including 3D geo-modeling, reservoir simulation and
chemical tracer injection. The study permitted to
track the main effects of the gas injection and define
reservoir management guidelines for the other lean
gas injection reservoirs. In the same year, dynamic
synthesis has been performed in all accumulation in
Handil Field with objective to identify potential oil
spots to be recovered by Light Work Over or/and
Infill Well.
Following the study, an intensive Light Work Over
campaign has been launched and three pilot wells,
each with different completion type, have been
successfully put on production; horizontal well
equipped by gas lift to recover viscous sandy
reservoir in very shallow zone, gravel pack +
swelling packer multi-target well equipped by ESP to
recover sandy reservoirs in shallow zone and
monobore multi-target well equipped by gas lift to
recover reservoirs in main zone.
INTRODUCTION
The Handil field, located in the Mahakam Delta,
comprises of 555 hydrocarbon accumulations in
structurally stacked and compartmentalized deltaic
sands. The accumulations are trapped along Handil
Anticline which is cut by a major impermeable fault
dividing the field into two compartments, North and
South.
Lying 10 km long and 4 km wide in the surface,
hydrocarbon accumulations are found at depths as
shallow as 200 mSS and continue down as deep as
3500 mSS.
2.
3.
PRODUCTION HISTORY
The Handil field was discovered in 1974 and the
production started up one year later under natural
depletion. The production peak was reached in 1977
with production of around 200,000 BOPD.
In order to maintain the production plateau as well as
the reservoir pressure, water injection was started in
1978 and it had helped to maintain the 160.000
BOPD of production up to 1985, except for one year
drop due to OPEC restriction. As addition to optimize
the lifting system, gas lift has been introduced in
1979 and has been implemented in field scale in 1991
by using a dedicated compressor.
o Likely-Productive:
If porosity 13.5%
2m
and netsand
o Possibly-Productive:
If-porosity- 13.5%-and-netsand<-2m--or
If 11% porosity < 13.5% and
netsand > 2m
o Likely-Non-Productive:
If_11%--porosity-<-13.5%-andnetsand-<-2m--or
If porosity < 11%
Proximity
to
producer
(drainage area excluded)
Figure. 6.
A. Static cutoffs
For each reservoir on the logs, from the netsand
thickness and the porosity response.
Note : The empirical cut off of porosity >13.5% is
based on dynamic results (productivity of perforated
intervals) where Porosity > 13.5% corresponds to Kh
> 5mD.
B. Apply Dynamic Cut off
Areas 10m above water contacts (GWC-init or GWCwr), with expected good permeability and away from
producing wells
C. Final sweet spot to transfer as 3D grid parameter
SWEET SPOT GRID PARAMETER &
PROPOSAL TARGET
As the purpose of this study is to enable to
position a certain number of wells that are
expected to be good producers, Sweet spot
maps have been produced per layer.
These sweet spots maps will be put as grid
parameter and visualised in 3D by assigning
filter on numeric code (0 for likely nonproductive, 1 for possibly productive or 2 for
likely productive).
Figure. 7.
INFILL WELL
Although Light Work Over is the most economical
way to recover the remaining oil, the well condition
is sometime difficult to technical intervention. In this
case, the only way to recover the potential is by using
new well or what a so-called, infill well.
In general there are three cases where infill wells are
preferred and it would effect the well design and
architecture.
1.
Gas Injection
OIL
GOR
After Water-flooded
Oil-rim
BSW
WHFP
Gravity drainage
Sorw
Sorw
Sorw
Sorw ~ 25%
Sorwg = 10 20
EOR OPTIMIZATION
Figure .12. Gravity Drainage Mechanism
All reservoirs are divided into several production
rows with row one being the closest production row
to the gas injector (Fig. 13)
North-South
Section
Cross
GAS INJ.
Production Row 3
Production Row 2
Production Row 1
GAS INJ.
GAS INJ.
So ~ Sorg
Poor connected
Disconnected
1995
Water Flooded Condition / GI Project Start Up
2003
End of History Matching
CONCLUSION
An integrated geosciences and reservoir study can
help to redefine the remaining potential in a mature
field. However, when the huge number of reservoirs,
wells and long production history are concerned,
simple dynamic synthesis and material balance can
be a good compromise to identify the potential, thus
optimize the production.
In the Handil field, the study was followed up by
three operations, Light Work Over, Infill Well and
EOR that become the key elements to increase the
production from 12,500 BOPD in 2003 to 21,000
BOPD today.
Close
GASINJECTOR
ROW 1 PROD.
ROW 2 PROD.
ROW 3. PROD.
Injection
2000
35
1800
Reduced
Cycling
actual
1600
Q
o
,b
o
p
d
30
25
1400
1200
20
1000
15
800
600
10
WI Decline
400
5
200
0
5
v-9
o
N
0
96
rp
A
6
-9
ep
S
7
b-9
Fe
97
lJu
7
c-9
e
D
8
-9
ay
M
8
-9
ct
O
9
-9
ar
M
99
gu
A
00
nJa
0
-0
n
Ju
0
v-0
o
N
01
rp
A
1
-0
ep
S
2
b-0
Fe
02
lJu
2
c-0
e
D
months
W I Decline
Actua l
Q-GI
3
-0
ay
M
3
-0
ct
O
Q
g
i, M
M
scfd
Gas