Revisions are used to group greater maintenance tasks together under one number which are generally
planned on a long-term basis.
The revision offers the following possibilities:
2
2.1
The revision can be entered in the order. It is thus possible to group several orders together by
using a revision number.
A default date further for the start and the end of the revision is linked to the revision number.
The revision number can be used as a selection / search criterion in reports.
Third digit
used as
separator
Fourth digit
represent plant
SD = Shutdown
TA = Turnaround
RG = Regeneration
1 = ORC1
2 = ORC2
0001, 0002
SD-20001
SD-20002
TA-20001 etc.
2.2
2.3
Reports
All maintenance order reports can be filtered out using revision field for specific maintenance
shutdown activity. Also any related material issuance report against these shutdown orders can be
executed with shutdown orders selection.
Transaction Code: IW38, IW39
Select all Orders and select Goods Movements Report from Environment menu
Select all Orders and select Scheduling Overview Report from Goto menu