EPCI FOR KEERA METERING STATION

PROJECT MASTER SCHEDULE


CONTRACT NO. : CON/EEES/16/009

ID

WBS

Task Name

Duration

Start

Finish

Task Calendar
M

0
1
20
21
22
23
24
40
58
104
105
107
119
140
160
161
162
163
169
171
182
200
211
212
217
232
270
320
323
325
326
334
338
344
362
386
392
410
411
413
417
430
436
441
450
474
476
477
481
483

0
1
2
2.1
2.2
3
3.1
3.2
3.3
3.4
3.4.1
3.4.2
3.4.3
3.4.4
3.5
3.5.1
3.6
3.6.1
3.6.2
3.6.3
3.6.4
3.6.5
3.7
3.7.1
3.7.2
3.7.3
3.7.4
3.7.5
3.7.6
3.8
3.8.1
3.8.2
3.8.3
3.8.4
3.8.5
3.8.6
3.8.7
3.9
3.9.1
3.9.2
3.9.3
3.9.4
3.9.5
3.9.6
3.9.7
3.9.8
3.10
3.10.1
3.10.2
3.10.3

WSB-KMS-GL-PRD-006 PMS RE_ADDS_PLANT_RELOC_B_(all-new)


252 days
MILESTONES
352 days
PROJECT MANAGEMENT
239 days
PROJECT MANAGEMENT TEAM
239 days
OVERHEAD
239 days
GENERAL PROCEDURE & DETAIL ENGINEERING
94 days
General
25 days
QA/QC
25 days
HSE
35 days
PROCESS
28 days
Design Basis
20 days
Study
25 days
Calculation
25 days
Drawing
25 days
HAZOP & HAZID STUDY
5 days
HAZOP & HAZID Study Report
5 days
MECHANICAL
43 days
Specification
20 days
List
20 days
Calculation
23 days
Data Sheet
25 days
Drawing
25 days
CIVIL & STRUCTURE
94 days
Plant Re-Location
90 days
Specification
20 days
Calculation
30 days
Drawing
40 days
TBA
15 days
MTO
15 days
INSTRUMENTATION & CONTROL
86 days
Specification
25 days
List
15 days
Calculation
20 days
Data Sheet
25 days
Drawing
66 days
MTO
15 days
TBA
25 days
ELECTRICAL
40 days
Design Basis
20 days
Study
20 days
Specification
25 days
List
23 days
Calculation
20 days
Data Sheet
25 days
Drawing
35 days
MTO
15 days
PIPING
40 days
Specitication
20 days
List
20 days
Calculation
20 days

Project: WSB-KMS-GL-PRD-006

3/15/16
3/15/16
4/1/16
4/1/16
4/1/16
4/1/16
4/1/16
4/8/16
4/1/16
4/1/16
4/1/16
4/1/16
4/6/16
4/1/16
5/9/16
5/9/16
4/1/16
4/1/16
4/1/16
4/27/16
4/27/16
4/6/16
4/1/16
5/13/16
4/1/16
5/30/16
5/30/16
4/29/16
7/11/16
4/1/16
4/1/16
4/8/16
4/1/16
4/8/16
4/8/16
7/11/16
4/8/16
4/1/16
4/1/16
4/1/16
4/1/16
4/1/16
4/1/16
4/8/16
4/8/16
4/29/16
4/1/16
4/1/16
4/15/16
4/22/16

3/1/17
3/1/17
3/1/17
3/1/17
3/1/17
8/10/16
5/5/16
5/12/16
5/19/16
5/10/16
4/28/16
5/5/16
5/10/16
5/5/16
5/13/16
5/13/16
5/31/16
4/28/16
4/28/16
5/27/16
5/31/16
5/10/16
8/10/16
8/10/16
4/28/16
7/8/16
7/22/16
5/19/16
7/29/16
7/29/16
5/5/16
4/28/16
4/28/16
5/12/16
7/8/16
7/29/16
5/12/16
5/26/16
4/28/16
4/28/16
5/5/16
5/3/16
4/28/16
5/12/16
5/26/16
5/19/16
5/26/16
4/28/16
5/12/16
5/19/16

Jan 25, '16


T

Mar 14, '16


T
F

May 2, '16
S
S

Jun 20, '16


M
T

Aug 8, '16
T

Sep 26, '16


S

None
7 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
7 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja

Task

Inactive Task

Manual Summary Rollup

External Milestone

Split

Inactive Milestone

Manual Summary

Deadline

Milestone

Inactive Summary

Start-only

Critical

Summary

Manual Task

Finish-only

Critical Split

Project Summary

Duration-only

External Tasks

Progress

Page 1 of 3

Manual Progress

Nov 14, '16


M
T

Jan 2, '17
W
T

Feb 20, '17


S

EPCI FOR KEERA METERING STATION


PROJECT MASTER SCHEDULE
CONTRACT NO. : CON/EEES/16/009

ID

WBS

Task Name

Duration

Start

Finish

Task Calendar
M

486
494
503
519
520
521
526
530
531
616
659
660
732
753
754
790
847
848
855
861
867
873
879
885
891
898
904
910
917
923
929
935
941
947
953
959
960
967
974
975
976
980
983
986
992
1006
1024
1029
1045
1050

3.10.4
3.10.5
3.10.6
4
4.1
4.1.1
4.1.2
4.2
4.2.1
4.2.2
4.3
4.3.1
4.3.2
4.4
4.4.1
4.4.2
4.5
4.5.1
4.5.2
4.5.3
4.5.4
4.5.5
4.5.6
4.5.7
4.5.8
4.5.9
4.5.10
4.5.11
4.5.12
4.5.13
4.5.14
4.5.15
4.5.16
4.5.17
4.5.18
4.6
4.6.1
4.6.2
5
5.1
5.1.1
5.1.2
5.1.3
5.1.4
5.1.5
5.1.6
5.1.7
5.1.8
5.1.9
5.1.10

Data Sheet
25 days
Drawing
25 days
Isometric
25 days
PROCUREMENT
170 days
CIVIL
22 days
PILE
22 days
BULK MATERIAL
15 days
MECHANICAL EQUIPMENT
150 days
BATCH - 1
144 days
BATCH - 2
150 days
PIPING MATERIALS
158 days
BATCH - 1
140 days
BATCH - 2
148 days
ELECTRICAL MATERIALS AND EQUIPMENT
156 days
BATCH - 1
140 days
BATCH - 2
156 days
INSTRUMENT MATERIALS
156 days
CUSTODY METER SKID
169 days
FLOW COMP
162 days
GAS CHROMATOGRAPH
208 days
H20 ANALYZER
153 days
H2S ANALYZER
109 days
MANUAL SAMPLING PROBE
153 days
SDV (Size 16", 12", 10")
183 days
CONTROL VALVES
158 days
METERING PANEL
162 days
SUPERVISORY COMP & HMI
153 days
ON/OFF VALVES
123 days
TRANSMITTER (DIFF PRESS & PRESS, TEMP & LEVEL) 183 days
GAUGES ( DIFF PRESS & PRESS, TEMP, LEVEL)
180 days
SWITCHES (DIFF PRESS, PRESS, TEMP, LEVEL)
183 days
INSTRUMENT CABLES
151 days
INSTRUMENT CABLE TRAYS
131 days
FLOW INDICATOR & FLOW TRANSMITTER
183 days
PCS/ESD/FGS MODULE
109 days
SAFETY SYSTEM
130 days
FIRE FIGHTING SYSTEM
150 days
FIRE & GAS DETECTOR SYSTEM
124 days
CONSTRUCTION
167 days
BATCH - 1
153 days
MOBILIZATION
14 days
SITE PREPARATION
1 day
GENERAL CIVIL WORKS
67 days
PREPARATION FOR FOUNDATION WORKS
33 days
EQUIPMENT FOUNDATION (ALL PROCESS EQUIPMENT)
25 days
MECHANICAL EQUIPMENT ERECTION
38 days
STEEL STRUCTURE PREP WORKS
43 days
SITE PIPE FABRICATION
13 days
STEEL STRUCTURE INSTALL WORK
33 days
PIPING CONSTRUCTION (C/W ACCESSORIES INSTALLATION)
38 days

Project: WSB-KMS-GL-PRD-006

4/22/16
4/15/16
4/20/16
5/25/16
8/1/16
8/1/16
8/1/16
5/25/16
6/1/16
5/25/16
6/8/16
6/8/16
6/22/16
6/3/16
6/3/16
6/3/16
6/10/16
6/10/16
6/24/16
6/10/16
6/10/16
6/10/16
6/10/16
6/10/16
6/10/16
8/5/16
8/5/16
6/10/16
6/10/16
6/27/16
6/10/16
8/1/16
8/1/16
6/10/16
8/5/16
7/20/16
7/20/16
9/16/16
8/17/16
8/17/16
8/17/16
8/30/16
9/1/16
9/22/16
10/6/16
11/25/16
10/23/16
11/25/16
11/16/16
12/10/16

5/26/16
5/19/16
5/24/16
1/17/17
8/30/16
8/30/16
8/19/16
12/20/16
12/19/16
12/20/16
1/13/17
12/20/16
1/13/17
1/6/17
12/15/16
1/6/17
1/13/17
11/25/16
12/2/16
1/3/17
11/9/16
11/9/16
11/9/16
12/9/16
11/14/16
1/13/17
1/4/17
11/29/16
12/9/16
12/23/16
12/9/16
12/29/16
12/9/16
12/9/16
1/4/17
1/17/17
12/16/16
1/17/17
1/30/17
1/16/17
8/30/16
8/31/16
11/6/16
10/24/16
10/30/16
1/1/17
12/4/16
12/7/16
12/18/16
1/16/17

Jan 25, '16


T

Mar 14, '16


T
F

May 2, '16
S
S

Jun 20, '16


M
T

Aug 8, '16
T

Sep 26, '16


S

5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
5 Hari Kerja
7 Hari Kerja
7 Hari Kerja
7 Hari Kerja
7 Hari Kerja
5 Hari Kerja
7 Hari Kerja
7 Hari Kerja
7 Hari Kerja
7 Hari Kerja
7 Hari Kerja
5 Hari Kerja
7 Hari Kerja
7 Hari Kerja
7 Hari Kerja
7 Hari Kerja
7 Hari Kerja
7 Hari Kerja
5 Hari Kerja
5 Hari Kerja
7 Hari Kerja
7 Hari Kerja
7 Hari Kerja
7 Hari Kerja
7 Hari Kerja
7 Hari Kerja
7 Hari Kerja
7 Hari Kerja
7 Hari Kerja
7 Hari Kerja
7 Hari Kerja
7 Hari Kerja
7 Hari Kerja
7 Hari Kerja

Task

Inactive Task

Manual Summary Rollup

External Milestone

Split

Inactive Milestone

Manual Summary

Deadline

Milestone

Inactive Summary

Start-only

Critical

Summary

Manual Task

Finish-only

Critical Split

Project Summary

Duration-only

External Tasks

Progress

Page 2 of 3

Manual Progress

Nov 14, '16


M
T

Jan 2, '17
W
T

Feb 20, '17


S

EPCI FOR KEERA METERING STATION


PROJECT MASTER SCHEDULE
CONTRACT NO. : CON/EEES/16/009

ID

WBS

Task Name

Duration

Start

Finish

Task Calendar
M

1071
1077
1081
1084
1087
1088
1091
1105
1109
1129
1135
1136
1137
1138
1139
1140

5.1.11
5.1.12
5.1.13
5.1.14
5.2
5.2.1
5.2.2
5.2.3
5.2.4
5.2.5
6
6.1
6.2
7
7.1
7.2

INSTRUMENT EQUIPMENT
ELECTRICAL WORKS
CIVIL & BUILDING WORKS
SAFETY SYSTEM
BATCH - 2
MECHANICAL WORKS OUTSIDE PROCESS LINE
ELECTRICAL WORKS
CONTROL CABLE INSTALLATION
INSTRUMENTATION WORKS
OTHER CIVIL WORKS
PRE-COMMISSIONING & COMMISSIONING
PRE-COMMISSIONING & FUNCTION TEST
COMMISSIONING
PROJECT CLOSE OUT
DOCUMENT DOSIER
AS BUILT DRAWING

Project: WSB-KMS-GL-PRD-006

10 days
11 days
35 days
10 days
50 days
10 days
24 days
10 days
14 days
50 days
24 days
14 days
10 days
6 days
6 days
6 days

12/15/16
11/7/16
11/7/16
12/12/16
12/12/16
1/1/17
12/25/16
1/12/17
1/17/17
12/12/16
1/31/17
1/31/17
2/14/17
2/24/17
2/24/17
2/24/17

12/24/16
11/17/16
12/11/16
12/21/16
1/30/17
1/10/17
1/17/17
1/21/17
1/30/17
1/30/17
2/23/17
2/13/17
2/23/17
3/1/17
3/1/17
3/1/17

Jan 25, '16


T

Mar 14, '16


T
F

May 2, '16
S
S

Jun 20, '16


M
T

Aug 8, '16
T

Sep 26, '16


S

7 Hari Kerja
7 Hari Kerja
7 Hari Kerja
7 Hari Kerja
7 Hari Kerja
7 Hari Kerja
7 Hari Kerja
7 Hari Kerja
7 Hari Kerja
7 Hari Kerja
7 Hari Kerja
7 Hari Kerja
7 Hari Kerja
7 Hari Kerja
7 Hari Kerja
7 Hari Kerja

Task

Inactive Task

Manual Summary Rollup

External Milestone

Split

Inactive Milestone

Manual Summary

Deadline

Milestone

Inactive Summary

Start-only

Critical

Summary

Manual Task

Finish-only

Critical Split

Project Summary

Duration-only

External Tasks

Progress

Page 3 of 3

Manual Progress