Strategic Reservoirs at Taif Time Schedule

ID

WBS

Task Name

Duration

SteelReservoirConstruction(1.530.000m)

M-1 M1 M2 M3 M4

M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23 M24 M25 M26 M27 M28 M29 M30 M31 M32 M33 M34 M35 M36 M37

1095days

1.1

1.1.1

ContractAward

0days

1.1.2

CommencementDate(14daysaftercontractAward)

0days

1.1.3

SitePossesionDate

0days

1.1.4

Completionof3TanksReadyforEarlyOperation(600days)

0days

1.1.5

CompletionofAllWorks(1095days)

0days

1.1.6

CompletionofReservoir#1

0days

1.1.7

CompletionofReservoir#2

0days

10

1.1.8

CompletionofReservoir#3

0days

11

1.1.9

CompletionofReservoir#4

0days

12

1.1.10

CompletionofReservoir#5

0days

13

1.1.11

CompletionofReservoir#6

0days

14

1.1.12

CompletionofReservoir#7

0days

15

1.1.13

CompletionofReservoir#8

0days

16

1.1.14

CompletionofReservoir#9

0days

17

1.2

Mobilization

90days

18

1.3

Design

350days

19

1.3.1

PreparationandApprovalofLayoutPlan

30days

20

1.3.2

PreparationandApprovalofPreliminaryDesign

60days

21

1.3.3

PreparationandApprovalofDetailDesign

330days

22

1.4

23

1.4.1

Reservoir#1SteelPlatesMaterialonSite

0days

24

1.4.2

Reservoir#2SteelPlatesMaterialonSite

0days

25

1.4.3

Reservoir#3SteelPlatesMaterialonSite

0days

26

1.4.4

Reservoir#4SteelPlatesMaterialonSite

0days

27

1.4.5

Reservoir#5SteelPlatesMaterialonSite

0days

28

1.4.6

Reservoir#6SteelPlatesMaterialonSite

0days

29

1.4.7

Reservoir#7SteelPlatesMaterialonSite

0days

30

1.4.8

Reservoir#8SteelPlatesMaterialonSite

0days

31

1.4.9

Reservoir#9SteelPlatesMaterialonSite

0days

32

1.5

33

1.5.1

Reservoir#1SteelPlatesFabricationandDeliverytoSite

120days

34

1.5.2

Reservoir#2SteelPlatesFabricationandDeliverytoSite

120days

35

1.5.3

Reservoir#3SteelPlatesFabricationandDeliverytoSite

120days

36

1.5.4

Reservoir#4SteelPlatesFabricationandDeliverytoSite

170days

KeyDatesandMilestones

1095days

MaterialonFabricationYard

243days

FabricationandDeliverytoSite

637days

Critical

Split

Finish-only

Baseline Milestone

Manual Summary

Inactive Task

Critical Split

Task Progress

Duration-only

Milestone

Project Summary

Inactive Milestone

Critical Progress

Manual Task

Baseline

Summary Progress

External Tasks

Inactive Summary

Task

Start-only

Baseline Split

Summary

External Milestone

Deadline

Page 1

Strategic Reservoirs at Taif Time Schedule


ID

WBS

Task Name

Duration

37

1.5.5

Reservoir#5SteelPlatesFabricationandDeliverytoSite

170days

38

1.5.6

Reservoir#6SteelPlatesFabricationandDeliverytoSite

170days

39

1.5.7

Reservoir#7SteelPlatesFabricationandDeliverytoSite

170days

40

1.5.8

Reservoir#8SteelPlatesFabricationandDeliverytoSite

174days

41

1.5.9

Reservoir#9SteelPlatesFabricationandDeliverytoSite

174days

42

1.6

43

1.6.1

SitePreparationandExcavation

206days

44

1.6.1.1

SettingOutandSiteSurvey

26days

45

1.6.1.2

GeneralExcavation(GradingWorks)

180days

46

1.6.1.3

ExcavationofReservoir1

15days

47

1.6.1.4

ExcavationofReservoir2

15days

48

1.6.1.5

ExcavationofReservoir3

15days

49

1.6.1.6

ExcavationofReservoir4

15days

50

1.6.1.7

ExcavationofReservoir5

15days

51

1.6.1.8

ExcavationofReservoir6

15days

52

1.6.1.9

ExcavationofReservoir7

15days

53

1.6.1.10

ExcavationofReservoir8

15days

54

1.6.1.11

ExcavationofReservoir9

15days

55

1.6.2

56

1.6.2.1

FoundationofReservoir1

40days

57

1.6.2.2

FoundationofReservoir2

40days

58

1.6.2.3

FoundationofReservoir3

40days

59

1.6.2.4

FoundationofReservoir4

40days

60

1.6.2.5

FoundationofReservoir5

40days

61

1.6.2.6

FoundationofReservoir6

40days

62

1.6.2.7

FoundationofReservoir7

40days

63

1.6.2.8

FoundationofReservoir8

40days

64

1.6.2.9

FoundationofReservoir9

40days

65

1.6.3

SteelReservoirsConstruction

849days

66

1.6.3.1

67

1.6.3.1.1

AnnularPlate

10days

68

1.6.3.1.2

BottomPlate

25days

69

1.6.3.1.3

ShellPlate

120days

70

1.6.3.1.4

WindGirders

18days

71

1.6.3.1.5

Stairway&Handrail

21days

72

1.6.3.1.6

RoofDome

70days

ConstructionWorks

M-1 M1 M2 M3 M4

M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23 M24 M25 M26 M27 M28 M29 M30 M31 M32 M33 M34 M35 M36 M37

974days

FoundationofReservoirs

360days

Reservoir#1

277days

Critical

Split

Finish-only

Baseline Milestone

Manual Summary

Inactive Task

Critical Split

Task Progress

Duration-only

Milestone

Project Summary

Inactive Milestone

Critical Progress

Manual Task

Baseline

Summary Progress

External Tasks

Inactive Summary

Task

Start-only

Baseline Split

Summary

External Milestone

Deadline

Page 2

Strategic Reservoirs at Taif Time Schedule


ID

WBS

Task Name

Duration

73

1.6.3.1.7

Painting

45days

74

1.6.3.1.8

MixingSystem

14days

75

1.6.3.1.9

DisinfectionandTest

35days

76

1.6.3.2

77

1.6.3.2.1

AnnularPlate

10days

78

1.6.3.2.2

BottomPlate

25days

79

1.6.3.2.3

ShellPlate

120days

80

1.6.3.2.4

WindGirders

18days

81

1.6.3.2.5

Stairway&Handrail

21days

82

1.6.3.2.6

RoofDome

70days

83

1.6.3.2.7

Painting

45days

84

1.6.3.2.8

MixingSystem

14days

85

1.6.3.2.9

DisinfectionandTest

35days

86

1.6.3.3

87

1.6.3.3.1

AnnularPlate

10days

88

1.6.3.3.2

BottomPlate

25days

89

1.6.3.3.3

ShellPlate

120days

90

1.6.3.3.4

WindGirders

18days

91

1.6.3.3.5

Stairway&Handrail

21days

92

1.6.3.3.6

RoofDome

70days

93

1.6.3.3.7

Painting

45days

94

1.6.3.3.8

MixingSystem

14days

95

1.6.3.3.9

DisinfectionandTest

35days

96

1.6.3.4

97

1.6.3.4.1

AnnularPlate

10days

98

1.6.3.4.2

BottomPlate

25days

99

1.6.3.4.3

ShellPlate

120days

100

1.6.3.4.4

WindGirders

18days

101

1.6.3.4.5

Stairway&Handrail

21days

102

1.6.3.4.6

RoofDome

70days

103

1.6.3.4.7

Painting

45days

104

1.6.3.4.8

MixingSystem

14days

105

1.6.3.4.9

DisinfectionandTest

35days

106

1.6.3.5

107

1.6.3.5.1

AnnularPlate

10days

108

1.6.3.5.2

BottomPlate

25days

Reservoir#2

M-1 M1 M2 M3 M4

M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23 M24 M25 M26 M27 M28 M29 M30 M31 M32 M33 M34 M35 M36 M37

307days

Reservoir#3

312days

Reservoir#4

277days

Reservoir#5

277days

Critical

Split

Finish-only

Baseline Milestone

Manual Summary

Inactive Task

Critical Split

Task Progress

Duration-only

Milestone

Project Summary

Inactive Milestone

Critical Progress

Manual Task

Baseline

Summary Progress

External Tasks

Inactive Summary

Task

Start-only

Baseline Split

Summary

External Milestone

Deadline

Page 3

Strategic Reservoirs at Taif Time Schedule


ID

WBS

Task Name

Duration

109

1.6.3.5.3

ShellPlate

120days

110

1.6.3.5.4

WindGirders

18days

111

1.6.3.5.5

Stairway&Handrail

21days

112

1.6.3.5.6

RoofDome

70days

113

1.6.3.5.7

Painting

45days

114

1.6.3.5.8

MixingSystem

14days

115

1.6.3.5.9

DisinfectionandTest

35days

116

1.6.3.6

117

1.6.3.6.1

AnnularPlate

10days

118

1.6.3.6.2

BottomPlate

25days

119

1.6.3.6.3

ShellPlate

120days

120

1.6.3.6.4

WindGirders

18days

121

1.6.3.6.5

Stairway&Handrail

21days

122

1.6.3.6.6

RoofDome

70days

123

1.6.3.6.7

Painting

45days

124

1.6.3.6.8

MixingSystem

14days

125

1.6.3.6.9

DisinfectionandTest

35days

126

1.6.3.7

127

1.6.3.7.1

AnnularPlate

10days

128

1.6.3.7.2

BottomPlate

25days

129

1.6.3.7.3

ShellPlate

120days

130

1.6.3.7.4

WindGirders

18days

131

1.6.3.7.5

Stairway&Handrail

21days

132

1.6.3.7.6

RoofDome

70days

133

1.6.3.7.7

Painting

45days

134

1.6.3.7.8

MixingSystem

14days

135

1.6.3.7.9

DisinfectionandTest

35days

136

1.6.3.8

137

1.6.3.8.1

AnnularPlate

10days

138

1.6.3.8.2

BottomPlate

25days

139

1.6.3.8.3

ShellPlate

120days

140

1.6.3.8.4

WindGirders

18days

141

1.6.3.8.5

Stairway&Handrail

21days

142

1.6.3.8.6

RoofDome

70days

143

1.6.3.8.7

Painting

45days

144

1.6.3.8.8

MixingSystem

14days

Reservoir#6

M-1 M1 M2 M3 M4

M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23 M24 M25 M26 M27 M28 M29 M30 M31 M32 M33 M34 M35 M36 M37

277days

Reservoir#7

277days

Reservoir#8

277days

Critical

Split

Finish-only

Baseline Milestone

Manual Summary

Inactive Task

Critical Split

Task Progress

Duration-only

Milestone

Project Summary

Inactive Milestone

Critical Progress

Manual Task

Baseline

Summary Progress

External Tasks

Inactive Summary

Task

Start-only

Baseline Split

Summary

External Milestone

Deadline

Page 4

Strategic Reservoirs at Taif Time Schedule


ID

WBS

Task Name

Duration

145

1.6.3.8.9

146

1.6.3.9

147

1.6.3.9.1

AnnularPlate

10days

148

1.6.3.9.2

BottomPlate

25days

149

1.6.3.9.3

ShellPlate

120days

150

1.6.3.9.4

WindGirders

18days

151

1.6.3.9.5

Stairway&Handrail

21days

152

1.6.3.9.6

RoofDome

70days

153

1.6.3.9.7

Painting

45days

154

1.6.3.9.8

MixingSystem

14days

155

1.6.3.9.9

DisinfectionandTest

36days

156

1.6.4

157

1.6.4.1

InletOutletPipeErection

360days

158

1.6.4.2

ValveInstallation

240days

159

1.6.5

160

1.6.5.1

161

1.6.5.1.1

Reservoir#1

14days

162

1.6.5.1.2

Reservoir#2

14days

163

1.6.5.1.3

Reservoir#3

14days

164

1.6.5.1.4

Reservoir#4

14days

165

1.6.5.1.5

Reservoir#5

14days

166

1.6.5.1.6

Reservoir#6

14days

167

1.6.5.1.7

Reservoir#7

14days

168

1.6.5.1.8

Reservoir#8

14days

169

1.6.5.1.9

Reservoir#9

14days

170

1.6.5.2

171

1.6.5.2.1

Reservoir#1

14days

172

1.6.5.2.2

Reservoir#2

14days

173

1.6.5.2.3

Reservoir#3

14days

174

1.6.5.2.4

Reservoir#4

14days

175

1.6.5.2.5

Reservoir#5

14days

176

1.6.5.2.6

Reservoir#6

14days

177

1.6.5.2.7

Reservoir#7

14days

178

1.6.5.2.8

Reservoir#8

14days

179

1.6.5.2.9

Reservoir#9

14days

180

1.6.5.3

DisinfectionandTest

M-1 M1 M2 M3 M4

M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23 M24 M25 M26 M27 M28 M29 M30 M31 M32 M33 M34 M35 M36 M37

35days

Reservoir#9

278days

ReservoirSiteMechanicalWorks

360days

ReservoirSiteElectricalWorks

863days

Grounding

334days

CathodicProtectionatBottomofReservoir

CathodicProtectionatInsideofReservoir

334days

578days

Critical

Split

Finish-only

Baseline Milestone

Manual Summary

Inactive Task

Critical Split

Task Progress

Duration-only

Milestone

Project Summary

Inactive Milestone

Critical Progress

Manual Task

Baseline

Summary Progress

External Tasks

Inactive Summary

Task

Start-only

Baseline Split

Summary

External Milestone

Deadline

Page 5

Strategic Reservoirs at Taif Time Schedule


ID

WBS

Task Name

Duration

181

1.6.5.3.1

Reservoir#1

7days

182

1.6.5.3.2

Reservoir#2

7days

183

1.6.5.3.3

Reservoir#3

7days

184

1.6.5.3.4

Reservoir#4

7days

185

1.6.5.3.5

Reservoir#5

7days

186

1.6.5.3.6

Reservoir#6

7days

187

1.6.5.3.7

Reservoir#7

7days

188

1.6.5.3.8

Reservoir#8

7days

189

1.6.5.3.9

Reservoir#9

7days

190

1.6.5.4

CablingWorksfor3Tanks

60days

191

1.6.5.5

CablingWorkfor6Tanks

100days

192

1.6.6

193

1.6.6.1

RoadConstruction

30days

194

1.6.6.2

FencesandGates

21days

195

1.6.6.3

SiteLighting

30days

196

1.6.6.4

OverflowWaterChannel

240days

197

1.7

CommissioningandTakingintoService

90days

198

1.8

CommencementofWarantyPeriod

0days

199

1.9

HandovertoSWCC

0days

SiteWork

M-1 M1 M2 M3 M4

M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23 M24 M25 M26 M27 M28 M29 M30 M31 M32 M33 M34 M35 M36 M37

711days

Critical

Split

Finish-only

Baseline Milestone

Manual Summary

Inactive Task

Critical Split

Task Progress

Duration-only

Milestone

Project Summary

Inactive Milestone

Critical Progress

Manual Task

Baseline

Summary Progress

External Tasks

Inactive Summary

Task

Start-only

Baseline Split

Summary

External Milestone

Deadline

Page 6