MPM Pinangah 2D Land Seismic Data Acquisition Survey

Activity

Duration

Start

End

Foundation establishment

6/Aug

16/Aug

Awardig letter

6/Aug

6/Aug

Signing contract

7/Aug

7/Aug

Subcontracting

10

7/Aug

16/Aug

BGP international personel applying

10

7/Aug

16/Aug

Equipment applying

17/Aug

19/Aug

Crew senior staff recruitment

13/Aug

17/Aug

Camp building staff recruiment

13/Aug

17/Aug

Advance party

59

17/Aug

14/Oct

BGP Base Camp building

45

25/Aug

8/Oct

Mobilization equipments

60

17/Aug

15/Oct

12

HSE advisor available

17/Aug

17/Aug

13

HSE plan

44

18/Aug

30/Sep

14

Subcontractor Base camp/staging camp building

30

7/Oct

5/Nov

107

30/Oct

13/Feb

Rintis &survey
15

Rintis&Survey crew mobilization

30/Oct

5/Nov

16

Survey instrument testing

6/Nov

6/Nov

17

Control network setup

7/Nov

8/Nov

18

Group training

9/Nov

10/Nov

19

Rintis&Survey production(Pinangah)

96

10/Nov

13/Feb

Drilling

106

15/Nov

28/Feb

22

Mobilization drilling crews+Loading crews

15

15/Nov

29/Nov

23

First group training (6 rigs)

23/Nov

24/Nov

24

Secend group training (7 rigs)

26/Nov

27/Nov

25

Third group training (7 rigs )

30/Nov

1/Dec

26

Drilling Production(Pinangah)

96

25/Nov

28/Feb

Recording

143

17/Nov

7/Apr

29

17/Nov

23/Nov

30

Advance recording crews mobilization (for equipment test)


+Training
Recording equipment test

10

24/Nov

3/Dec

31

Other personnel mobilization (Several Groups)

29/Nov

3/Dec

32

Recording crews training

4/Dec

5/Dec

33

Cable layout

6/Dec

9/Dec

34

recording production(Pinangah)

120

10/Dec

7/Apr

Damage compensation

129

10/Dec

16/Apr

37

Damage inventory

120

10/Dec

7/Apr

38

Line clearence and Damage compensation

120

10/Dec

7/Apr

39

Demobilization

15

8/Apr

22/Apr

Project closing

23/Apr

23/Apr

Agu

Sep

Oct

Nov

Dec

Remark:
1/4

Jan

Feb

Mar

Apr

MPM Pinangah 2D Land Seismic Data Acquisition Survey


Activity

Duration

Start

End

Agu

Sep

Oct

Nov

Dec

Jan

Feb

1.This plan is implemented according to the estimated date of the Sub-contractor camp start construction.also temporary Explosive magazine start construction date.
The actual schedule will be adjusted in due course.