FKAAS SDN. BHD.

CONSTRUCTION OF SURAU AT TAMAN MANIS 6,


PARIT RAJA, BATU PAHAT, JOHOR
FOR THE FKAAS SDN. BHD.

DOCUMENT CONTRACT

CODE OF CONTRACT

FKAAS/48/2015/0229

CONTRACT DURATION

4TH JULY 2016 4TH SEPTEMBER 2016

CONTRACT PRICE

RM 748, 411

PROJECT INSTRUCTION

1.

Submission of project should consist:


a. Introduction: Group members with picture, detail, etc.
b. Project details: Working hours, table on duration estimation, public holiday, etc.
c. Work Programme using Microsoft Project 2010/2013/2015.
d. Physical vs Financial S-curve using Microsoft Excel.
e. Save project name as Project.

2.

Save your work in a folder. Folder name should consist your section and your group members name.
Example:
Name : Siti Khalijah AND Aira Hazirah
Section : 4
Folder Name : S4 Siti and Aira

3.

Please put your group members name on the legend, left section in Page Setup (Microsoft Project).

4.

You can make any logic assumption to complete the task. All information/ assumption that you used
shall be written in your report.

5.

Please submit your report before 16th June 2016 and email your zip folder to
notes.uthm@gmail.com.

6.

Please read

the instruction. Thank you!

Prepared by;
Siti Khalijah Yaman,
6th June 2016.

Productivity rate.
Please use this productivity rate to determine your duration. The number of workers use for each
group should be difference. You can use any numbers as long it can fit the project duration.
Item

Type of work

Excavation/ filling work

2
3

Concrete work
Reinforcement work

Wood work

5
6
7
8

Metal work
Masonry work
Installation of door and window
Finishing work
Floor
Ceiling
Wall

Productivity rate
50m2/group/day
35m3/group/day
10m3/group/day
300 kg/group/day
70m2/group/day
80m/group/day
100m2/group/day
45m2/group/day
20no/group/day
50m2/group/day
15m2/group/day
45m2/group/day