Professional Documents
Culture Documents
Principes and Practices of Management
Principes and Practices of Management
PGP-CM-MODULE-01
ASSIGNMENT NO: 01
COURSE TITLE:
PRINCIPLES AND
PRACTICES OF
MANAGEMENT
COURSE CODE PGCM11
DATE OF DISPATCH: 25/11/2015
LAST DATE OF RECEIPT: 30/11/2015
ASSIGNMENT TASK
Your company has bagged a lucrative contract to construct a housing colony for an
Industrial Group to be located in western Maharashtra in coastal belt. You as a project
manager have been asked by the company to evolve organization structure with the
following conditions;
I.
II.
All supervisor to down below will be temporary for project duration only to be
recruited locally from 100km radius
PROJECT
Documents:
The project execution plan is on of a number of documents that define the project
and describe how the project will be delivered. These documents are supported by
management plans, policies and procedures.
Approved budget
Approved schedule
Project execution plan
Design basis report
Technical specification and drawings for all works
Scope of work:
Completing civil work, MEP works and interior fit out works. Internal roads and
landscaping work is also forms the part of works.
Project Organization:
Clients
Contractor
Consultant and owners engineer
Architect, interior designer
The selection of personnel will be lean and is done by the contractor and the
project manager is a full-time worker. The contractors personnel can be full-time
or part-time workers. The project employees will be available at their particular
work places.
The project is divided into several number of phases in order to ease the work and
cause no further complications.
Phase I 10 Bungalows for senior executives
Phase II 20 Apartments in five buildings
Phase III 100 Dwellings for white collar workers
Phase IV 300 Dwellings for the blue collar workers
Phase V Roads and landscaping work
Phase VI Market and entertainment complex
SR.no
Job Title
No
Project Manager
Project Coordinator
Quantity Surveyors
10
Cost Control
11
Planning Engineer
12
13
14
15
16
17
Supervisors
20
18
Clients Team:
Project Manager:
Architects are involved from the earliest stages of a building project, which
starts with developing ideas with the client, establishing budgets, assessing the
needs of the building and its users, and its impact within the local environment.
They assist with site selection and work closely with contractors on site,
ensuring that works are carried out to specific standards and that, above all, the
building is sustainable, functional and aesthetically pleasing. They also need to
have an awareness of commercial and financial considerations.
Construction Team:
Champions the project.
Ensures relevant management plans are prepared and implemented.
Oversees and reviews progress of the work on daily basis.
Manage and reviews safety and environmental performance on a daily basis.
Manage contractual issues.
Manage industrial issues on the project site.
Negotiation and purchase of materials according to the requirement of the
clients.
Trains the personnel under his/her control in order to complete the task.
Ensures the work is being completed in time according to the schedule provided
by the planning department.
Project Coordinator:
Leading the project team and coordinating the project.
Implementing the agreed action plan to the agreed standards and deadlines.
Prepare project organization and communication charts.
Ensuring the effective preparation and delivery of all project events and
meetings and production of all necessary documentation.
Maintain contract execution tracking log.
Track & manage contemplated change notices and change orders in the
database.
Prepare substantial completion certificates and ensure all required project close
out documents are obtained.
Keep the Project Manager (PM) and others informed about project status and
issues that may impact client relations.
Effectively and accurately communicate relevant project information to the
client and project team.
Review field inspection reports from Consultants throughout the lifecycle of the
project.
Issue contracts, letters of intent, purchase orders, etc.
Quantity Surveyors:
Estimation of control cost.
Cost planning and cost controlling.
Preparation of bills of quantities for inviting tenders including schedules of
materials, labour, equipments and transport requirements.
Interpretation and use of standard contract forms.
Planning Engineer:
Prepare and update project schedule based on the contract.
Set work program and target milestones for each phase based on the project
plan.
Monitor critical activities based on the project schedule and advise project
management.
Prepares and submit updated work program and cash flow curve showing
actual progress and identify areas of weakness and establishes means and
methods for recovery, if any, as well as new critical activities.
Monitor day to day work progress and prepare the weekly and monthly
program and report.
Maintain and record update of site work progress obtained from Project
Manager.
Prepares monthly report reflecting work progress summary.
Report to the Project Manager about the current work progress and make
comparison between plan and actual progress and study impact of alternative
approaches to work.
Participate in project meetings and discussions with the Client as required.
Assists in preparing work program, cash flow and manpower histogram for
tenders.
Performs other duties and responsibilities as may be assigned from time to
time.
Site Engineers:
Setting out the works in accordance with the drawings and specifications.
Observance of safety requirements.
Resolving technical issues with employers representatives
Checking materials and work in progress for compliance with the specified
requirements.
Liaising with the company or project purchasing department to ensure that
purchase orders adequately define the specified requirements.
Measurement and valuation ( in collaboration with the quantity surveyor
where appropriate).
Providing data in respect of variation orders and site instructions.
Preparing record drawings, technical reports and site diary.
Job review of subordinate staff.
Supervisors:
Accomplishes construction human resource objectives by selecting, orienting,
training , assigning, scheduling, coaching, counselling and disciplining
employees; communicating job expectations; planning, monitoring,
Project Management: Generally the project site work will consist of the
following broad functions.
Project Administration
Project systems developer
Inspection and auditing of work
Resource management
Safety management
Environmental management
Project Administration:
General correspondence
Site communications
Security
Filing
Site meetings
Receipt of drawing and documentation
Site purchase orders
Minor contract
Material control
Request for information register
Planning:
Level I Project Milestone Schedule: The level I schedule shall include the most
significant events in the project and planned dates for the accomplishment of
each. This will be developed at the beginning of the project by the project
scheduler and maintained by the project controls engineer.
Summary Schedule: The summary schedule is a time sequence network of
summary activities and their associated planned dates. It is done by the project
scheduler by summarizing the level III schedule and provides and overview of
all phases of the project for the periodic corporate management.
Level III Control Schedule: The level III schedule will be prepared by the
project scheduler utilizing the precedence critical path method covering all
phases of the project and incorporating milestones and other key events defined
in the level I schedule. Activities included in the CS cover the permitting,
conceptual and detailed design, procurement, construction, and start-up.
Interfaces between all activities are included which assures integration of all
phases of the project. The construction and start-up portions of the CS will be
developed in sufficient detail to logically complete the project and to focus
engineering and procurement with early need dates. The CS will be utilized by
the project team to monitor and analyze construction and start-up activities and
progress of the engineering and sub contractors.
Estimating:
The estimate will be based upon preliminary engineering. Architecture and
interior designer fit out work. It will be based on a well defined site plot plan,
general arrangement drawings, and preliminary drawings.The project cost
estimate will be updated with actual award procurements and construction
proposal pricing that are received as the project progress. The number of
unknowns will be reduced and the accuracy of the estimate will therefore be
improved.
Budgeting:
The budget estimate has been developed in conjunction with the tender drawings
and is based on the approved scope of work and known constraints and site
conditions and site conditions at the time of preparation. The level of
contingency applied to the estimate aligns with the assumed level of project risk.
Reporting:
Monthly reports will be produced with a written summary prepared by the
project control group that indicates float analysis problem areas, trends and risks
for Project Manager and project ream to review. For critical activities that are
trending 20 days or more behind, will be required to develop recovery plans to
ensure the project completion date is not impacted.
Contract Management:
Contractor Interface:
Since the project involves a scope split of the permitting, preliminary and
owners engineering, and construction, a detailed division of
responsibility document shall be prepared, communicated, maintained,
finalized and implemented.
Risk Management:
Risk management for the project will be responsibility of all the clients project
management staff. It is expected that lessons learned from previous projects and
excellent planning will avoid many of risks present on this type of project.
Selection of appropriate expertise, based on knowledge and experience, will be
fundamental in addition to the requirement of good communications between the
owner and each contractor.
Quality:
A planned and systematic approach to the quality management will be adopted
for the project that will focus on delivering project outcomes that are fit for
purpose and meet or exceed project requirements.
Quality Assurance:
The quality system used on the project will comply with the requirements of
AS/NZ ISO 9001:2000. A quality management plan will be developed for the
project by the project manager in collaboration with the construction manager.
Continuous improvement
Procedures
Standard and codes
Audit and review
Correlative actions
Communications
Quality Control:
All construction work will be controlled through a site based quality control
plan. The key elements of the plan will be.
Conformance to the scope of work
Compliance with the specifications
Inspection and testing
The quality control plan will be developed by the construction manager in
collaboration with the project manager. The plan is a controlled document and
will be reviewed as required.
Environment:
A project specific environmental plan will be developed for the project by the
contractor in collaboration with the project manager and coordinator. The
management plan will define the issues and process for environment protection
on the site and may utilize existing procedures where appropriate. The
management plan will include the following.
Responsibilities
Targets and license conditions
Training and inductions
Communications
Procedures and mitigation strategies
Emergency response
Incident investigation and reporting
Waste management
Surface water
Air quality
Project Execution:
The site offices shall be prefabricated modular units manufactured by the
contractor and erected on the site and shall be in compliance with local
regulations.
The site offices will be fully furnished and well equipped with all
requirements of power, communications, sanitary and janitorial services to make
them fully operational with adequate provisions of safety and security.
The offices will be maintained in the appropriate condition in line with the
contractual requirements and the international industry standards.
Engineering:
Understanding the nature, complexity and technicality of the work to be
carried out is of the utmost importance.
All data sheets will be prepared and submitted to local authority for approval
prior to release of purchase orders.
All drawings and technical data will be performed electronically;
distribution in the field will be hard copy. The technical team will also be
responsible for maintaining as built documentation.
followed for the projects for the proposed facilities. The same shall be
periodically forwarded to our engineering office to enable them to proceed with
detailed engineering.
Corrective Maintenance:
Urgent reported faults.
Non urgent reported faults.
Non urgent faults reclassified as urgent due to the failure of another element of
the system.
A reclassified fault shall be a non-urgent fault, which due to further faults or
circumstances results in non-operation.
Faults shall be reported and logged as outlined in the specification.
Project completion:
Practical completion will be reached when the project works are completed in
accordance with the scope and performance criteria and are functionally ready.
Following practical completion and warranty period, the works will be handed
over to the owner for the operational purposes. A handover certificate will be
prepared and signed by the project manager for acceptance and sign-off by the
owner.
Project closeout occurs when all work has been completed and handed over to
the owner. A project review will be carried out by the project director and senior
members of the project team, following the handover. All relevant project
documentation and records will be archived and handed over to the owner.
BIBLIOGRAPHY:
MANAGEMENT BY KOONTZ AND ODONEAL MCGRAW HILL
PUBLICATIONS.