Activity:

Duration:
Concerned parties:

Tapping of new exhaust to SPC


1 hour 30 minutes (11:30AM-1:00PM)
Facility, TOENEC,Taikisha,SPC

Verified first the condition of the exhaust line located at the above ceiling. Upon verification, it was found
that the damper will not open once the fan was operated. As a measure, the counterweight was adjusted so
the damper would be operational. Simultaneously, the dummy dampers for GEX-1 and GEX-2 located outside
were also adjusted. Then current and air velocity readings were taken to determine that the parameters
Details of the activity : required were met. Once the readings were taken and adjustments were made, the section involved were
informed that the activity was done.

General exhaust current readings


GEX-1
GEX-2
L1
9.7A
L1
L2
9.9A
L2
L3
9.4A
L3

10A
10A
9.4A

Dummy Damper
GEX-1
GEX-2
70% closed 50% closed

Air velocity readings


Left
Right
12.4 m/s
13.5m/s