VIIPEKERJAAN WATER PROOFING

1Screeding tebal 3 cm

M2semen
pasir beton
tukang batu
kepala tukang batu
pekerja
mandor

0.288zak
0.039m3
0.1org/hr
0.01org/hr
0.2org/hr
0.01org/hr

2Screeding tebal 2 cm

M2semen
pasir beton
tukang batu
kepala tukang batu
pekerja
mandor

0.2zak
0.026m3
0.1org/hr
0.01org/hr
0.2org/hr
0.01org/hr

3Pekerjaan water proofing (coating)

M2pre treatment/ cleaning


curbing sudut
bahan waterproofting coating
sewa mixer
kuas
tukang batu
kepala tukang batu
pekerja
mandor

1m2
0.4m'
2.5kg
0.02bh
0.2unit
0.2org/hr
0.02org/hr
0.1org/hr
0.01org/hr

4Pekerjaan water proofing (membrance) M2material primer


water proofing membrnce
tukang batu
kepala tukang batu
pekerja
mandor

0.3kg
1.05m2
0.5org/hr
0.05org/hr
0.25org/hr
0.0125org/hr

5Pekerjaan Floor Hardener

6kg
0.125ltr
0.15org/hr
0.015org/hr
0.075org/hr
0.0075org/hr

M2Material natural non metalic


Curing compound
tukang batu
kepala tukang batu
pekerja
mandor