Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 4

As Planned vs As Built Comparison

As Planned Schedule:
o Detailed Critical Path Method schedule; or
o Bar chart schedule; or
o Narrative schedule
As Built Schedule:
o Final as-built CPM schedule with periodic updates; and
o Project daily reports;
o Meeting minutes;
o Inspection reports by the designer, owner, building
inspector
o Correspondence
o Memos to file
Benefits:
Simple to Prepare: 168 actual days 112 planned days = 56
delay days
Shortcomings:
No information on particular delay events;
Similar to Total Cost approach
Impacted as Planned Method
Begin with As Planned Schedule
Add Owner or Contractor Delays
Compute Owner caused delay and Contractor caused delay
Benefits:
Relatively simple to implement
Allows for mitigation of delays
Shortcomings:
Highly subjective
Assumes as-planned (baseline) logic holds.
Collapsed (But For) As Built Method
Begin with As Built Schedule, including;
Owner and Contractor Delays.
Remove Owner (Contractor) caused delays.
Resulting schedule shows when Contractor (Owner) would
have finished but for Owner (Contractor) delays.
Benefits:
Very good accuracy
Shortcomings:

No allowance for mitigation of delays

Comparison of Results
Method

Non
Excusable

As Planned vs As Built Comparison


Impacted as Planned (Owner Delays)
Impacted as Planned (Contractor
Delays)
Collapsed (But for) As-Built

Delay
Excusable
Non
compensable

Excusable
Compensabl
e

Comparison of Results
Comparison
Method

Accuracy/

Effort/Co
st

Data

Effectivene
Require
Required
ss
d
As Planned vs As
Built Comparison
Impacted as Planned
(Owner Delays)
Impacted as Planned
(Contractor Delays)
Collapsed (But for)
As-Built

You might also like