Terms of Payments for Jet Airways: -

For Civil & Interior work excluding chairs and Furniture


15% Advance against BG (BG to be released after adjustment of Mobilization
advance start from 2nd RA to till pre final bill)
10% advance against approval of shop drawings
25% against completion /erection frame work of ceiling and paneling, civil works,
flooring work, partition framing works.
25% against finishing of counter, ceiling, completed flooring and paneling.
15% against final finishing, paint, polish, disengaging as completed
5% on 15 days after Virtual completion of the project.
5% to be retained for defects lability period of One year from the date of handing
over.

For Chairs and furniture: 15% Advance against BG


10% advance against approval of shop drawings
55% against Delivery at site
10% against installation
5% on 15 days after Virtual completion of the project.
5% to be retained for defects lability period of One year from the date of handing
over.

For Services Works: 25% Advance against BG. (BG to be released after adjustment of Mobilization
advance start from 2nd RA to till pre final bill)
55% against Delivery of materials at site
20% against installation
15% against completion, testing & Commissioning of systems
5% on Virtual completion of the project.
5% to be retained for defects lability period of One year from the date of handing
over.