Professional Documents
Culture Documents
Soil Investigation Report
Soil Investigation Report
Mawande
214053520
Table of contents
1. Soil investigation report .
.
.
.
.
P2
2. Scope work
.
.
.
.
.
.
.
P2-5
3. Laboratory testing .
.
.
.
.
.
P5-6
4. Subsoil condition
.
.
.
.
.
.
.
P6-7
5. SI work summary for Kuilsriver residential place
.
P7
6. Table showing relation of SPT results and consistency
.
P8-9
7. Trial pits .
.
.
.
.
.
.
.
P9-10
8. Foundation used
.
.
.
.
.
.
.
P10
9. Additional level report
.
.
.
.
.
.
P11
10.
South African Building Regulations .
.
.
P11-18
11.
References
.
.
.
.
.
.
.
P19
12.
Drawings .
.
.
.
.
.
.
P20-21
13.
Appendices
.
.
.
.
.
.
.
P22
14.
CTM 200S
Page 1
Mbambisa`
Mawande
214053520
Location:
Kuilsriver
Client:
Introduction
General
This report presents the soil investigation based on six boreholes,
conducted at Kuilsriver. The main purpose of the soil investigation is to
obtain and understand the geotechnical information on the subsoil
conditions required for the design and construction works.
Name of the project:
Location:
Kuilsriver
Client:
Period of work:
Scope of work:
Number of Borehole
6 nos
Drilling in Soil
293.00m
73 nos
Undisturbed Sample
2 nos
Scope work
Site conditions
The project is located in Kuilsriver in Cape Town at Western Cape, in
South Africa.
CTM 200S
Page 2
Mbambisa`
Mawande
214053520
Location
Drilling
Drilling was carried out using hydraulic feed rotary boring machine. A
metal crown bit as a cutting tool was attached at the lower end of the
drilling rods and circulated mud water was pumped through the hollow
rods into the bottom of borehole to wash out the cuttings to ground
surface. Six nos of boreholes were performed at Kuilsriver area. The
diameter of the borehole is 100mm. In this project, total drilling is
293.00m.
CTM 200S
Page 3
Mbambisa`
Mawande
214053520
Undisturbed sampling
Undisturbed sampling was carried out by using a thin-wall tube sampler
with outer diameter of 75mm. prior to do sampling; the borehole was
flushed with water to remove the remnants left at the bottom of the
borehole. The bottom was measured to confirm the depth at which the
soil sample was taken. The sample tube was lowered down to the
bottom of the hole and jacked into soil. After the sample tube was jacked
to the required depth, the sample tube out to the surface. Wax was then
applied to form a seal on both sides of the UD tube and labelled properly
before transporting to the laboratory for testing. In this project, total 2
numbers of undisturbed samples were collected by taking UD samples
at various depths of every borehole whenever the conditions are
favourable.
Standard penetration test
Once the borehole has reached the required test depth, the borehole
was cleaned by flushing with water before starting the test. It was
performed using a split-barrel sampler with a 50.8mm external and
34.9mm internal diameter which was connected to the lower end of
boring rods. The sampler was driven into the soil by means of a 63.5kg
hammer falling freely through a height of 76cm onto an anvil attached to
the top of the rods. A trip-release mechanism and guiding assembly
were used to control the falling hammer and the driving energy was thus
transmitted through the rods to the SPT sampler. The sampler was
driven 45cm into soil with the number of blows required for each 15cm of
penetration recorded. The resistance, N-value, was taken as the number
of blows foe the last 30cm of penetration. At the end of the test, the
sampler was withdrawn and some extracted soil was placed into a
plastic container and labelled. These samples were used to describe the
type of soil existing in the boring points. In this project, total 73 numbers
of SPT were taken in order to get the information and technical data on
the insitu strength and type of soil.
CTM 200S
Page 4
Mbambisa`
Mawande
214053520
Laboratory testing
General
The laboratory tests were performed on undisturbed samples based on
the available of soil sample. The tests related to physical and
mechanical properties were performed in Lab Service Private Limited
laboratory. The quantities of laboratory tests are summarised in table.
Moisture content
To determine the moisture content of soils, a soil sample is dried at a
temperature of 105 0C to 110 0C for about 24 hours. The loss in weight of
the soil sample represents the weight of moisture in the soil. The
moisture content of the soil to dry weight of soil in percentage is the
moisture content of testing soil.
Bulk and dry determination test
CTM 200S
Page 5
Mbambisa`
Mawande
214053520
The bulk density of a soil is the mass per unit volume of the soil deposit
including any water it contains. The dry density is the mass of dry soil
contained in a unit volume. Both are expressed in mg/m 3, which is
numerically the same as g/cm3.
Subsoil condition
This section briefly describes the soil conditions encountered at site.
Detailed soil conditions are presented in each log of boring in the
Appendices Borehole Logs. Based on the data collected from 8 numbers
of boreholes, it can be classified the soil layers as follows:
Soil layers
Fill
Clayey sand
Silty clay
CTM 200S
Page 6
Mbambisa`
Mawande
214053520
Fill
From the surface to the depth of 1.2 to 8 meters was covered with back
fill soil such as light yellowish brown sandy silt mixed with hard core
material and organic remains. Standard penetration test were not taken
for the layer.
Clayey sand
This soil type can be found in every bore holes. The layer consists of
light grey, light yellow, yellowish brown to reddish brown clayey sand.
Thickness is ranging about 18.20 to 26.70 meters and SPT consistency
is loose to very dense.
Silty clay
This soil type can be found in every hole. The layer consists of light grey
to purplish brown silty clay. Thickness is ranging about 16.41 to 33.36
meters and SPT consistency is hard.
General geology
The project area lies within the geological formation of older alluvium
formation with layers of clayey sand and silty clay.
SI work summary for Kuilsriver residential place
No BH
NO
Standar
d date
Finish date
12Jan
2002
20 Jan
2002
01Feb
2002
15Feb
2002
20 Feb
2002
01Mar
2
3
4
5
6
BH1
BH2
BH3
BH4
BH5
BH-
CTM 200S
SPT
15 Jan 2002
Drilling UD
depth
(m)
53
-
13
Terminati
on depth
(m)
53.38
25 Jan 2002
48
12
48.4
03Feb 2002
53
13
53.36
18Feb 2002
48
12
48.42
23 Feb 2002
43
11
43.41
05Mar 2002
48
12
48.4
Page 7
Mbambisa`
Mawande
214053520
2002
Grac
e
Fresh
No visible sign of rock material weathering perhaps 1
slight discontinuity surface
Slightly
Discoloration indicates weathering of rock material 2
weathered and discontinuity surface. All the rock material may
be discoloured by weathering
Moderately Less than half of rock material is decomposed or 3
weathered disintegrated to a soil. Fresh or discoloured rock is
present either as a continuous framework or as
CTM 200S
Description
Page 8
Mbambisa`
Highly
weathered
Completel
y
weathered
Residual
soil
Mawande
214053520
core stones.
More than of rock material decomposed or 4
disintegrated to a soil. Fresh or discoloured rock is
present either as a continuous framework.
All rock material is decomposed and disintegrated 5
to soil. The original mass structure is still largely
intact
All rock material is converted to soil. The mass 6
structure and material fabric are destroyed. There is
large change in volume but the soil has not been
significantly transported.
Rod %
Very poor
Poor
Fair
Good
Excellent
0-25
25-50
50-75
75-90
90-100
Trial pits
A trial pit is an excavation of ground in order to study or sample the
composition and structure of the subsurface, usually dug during a site
investigation, a soil survey or a geological survey. Trial pits are dug
before the construction.
CTM 200S
Page 9
Mbambisa`
Mawande
214053520
Foundation used
After the soil tests were done, the foundation used is a strip foundation.
CTM 200S
Page 10
Mbambisa`
Mawande
214053520
CTM 200S
Page 11
Mbambisa`
Mawande
214053520
CTM 200S
Page 12
Mbambisa`
Mawande
214053520
Page 13
Mbambisa`
Mawande
214053520
Page 14
Mbambisa`
Mawande
214053520
Page 15
Mbambisa`
Mawande
214053520
report to such local authority on the nature and extent of the steps to be
taken, in the opinion of such architect or registered person, in order to
render such building, land or earthwork safe.
[Para. (a) substituted by s. 3 (a) of Act 49 of 1995.]
(b)
The local authority in question may by notice in writing, served by post
or delivered, order that any activities be stopped or prohibit the
performance of any activities which may increase the danger or hinder
or obstruct the architect or registered person referred to in paragraph (a)
from properly carrying out the investigation referred to in that paragraph.
[Para. (b) substituted by s. 3 (a) of Act 49 of 1995.]
(c)
If it is brought to the attention of a local authority or appears that an
architect or registered person instructed in terms of paragraph (a) to
perform certain duties is for any reason not competent to carry out the
duties in question, the local authority may require such architect or
registered person to submit evidence of his or her competence to carry
out such duties.
[Para. (c) Added by s. 3 (b) of Act 49 of 1995.]
(d)
If the architect or registered person contemplated in paragraph (c) is
unable to satisfy the local authority of his or her competence to carry out
the duties in question, the local authority may order the owner of the
building, land or earthwork in question to instruct another architect or
registered person to carry out the duties.
[Para. (d) Added by s. 3 (b) of Act 49 of 1995.]
(4)
If the local authority in question deems it necessary for the safety of any
person, it may by notice in writing, served by post or delivered(a)order the owner of any building to remove, within the period
specified in such notice, all persons occupying or working or being
for any other purpose in such building therefrom,
NATIONAL BUILDING REGULATIONS AND BUILDING STANDARDS
ACT NO. 103 OF 1977 (as amended) and to take care that any person
not authorized by such local authority does not enter such building;
(b)order any person occupying or working or being for any other
purpose in any building, to vacate such building immediately or
within a period specified in such notice.
(5)
No person shall occupy or use or permit the occupation or use of any
building in respect of which a notice was served or delivered in terms of
CTM 200S
Page 16
Mbambisa`
Mawande
214053520
CTM 200S
Page 17
Mbambisa`
Mawande
214053520
Page 18
Mbambisa`
Mawande
214053520
(c) the fire installation system, of any building the person appointed to
design such system and to inspect the erection or installation, shall
submit a certificate to the local authority indicating that such system has
been designed and erected or installed in accordance with the
application in respect of which approval was granted in terms of section
7
.
[Sub-s. (2A) inserted by s. 7 (c) of Act 62 of 1989 and substituted by s. 4
(b) of Act 49 of 1995.]
(3)
Any person who for the purposes of subsection (1)
(a)submits a certificate contemplated in subsection (2) or
(2A) which is substantially false or incorrect, knowing the same to be
false or incorrect; or
(c) in a fraudulent manner issues or obtains a certificate contemplated
in subsection (2) or (2A),shall be guilty of an offence.[Sub-s.
(3)substituted by s. 4 (c) of Act 49 of 1995.]
(4)(a)
The owner of any building or, any person having an interest therein,
erected or being erected with the approval of a local authority, who
occupies or uses such building or
References
1. https://www.google.co.za/maps/place/Kuilsriver,+Cape+Town/@33.9934321,18.6737028,16z/data=!4m2!3m1!
1s0x1dcc4fd2a9eef50b:0x4e25fb5431eb7616?hl=en
2. https://www.google.co.za/?gfe_rd=cr&ei=fC_VfukDueo8weVla64Bg&gws_rd=ssl#q=soil+investigation+report
3. City of Cape Town, Milnerton Municipality
4. South African Construction Regulations
CTM 200S
Page 19