Procedure of Issuing Building Permit & Building Completion Certificate from DM

version(2) : 01/08/2011

Responsibility

Consultant

3rd - Multi story & Public Buildings

Necessary Actions

Obtain Building Permit from


Building Department / DM

How to
Submit

Building Permit &


Control System
(BPCS)
ON LINE

Consultant
&
Contractor

R
t & Receive
R
i IInspection
ti
Request
of Foundations before casting
Concrete

Consultant
&
Contractor

Request & Receive Inspection


of Floors' Slabs before casting
Concrete

Consultant
&
Contractor

Request & Receive Inspection


for Metal Frames

Consultant
&
Contractor

Request & Receive


Completion Certificate

Building
g Permit &
Control System
(BPCS)
ON LINE

Building Permit &


Control System
(BPCS)
ON LINE

Building Permit &


Control System
(BPCS)
ON LINE

Building Permit &


Control System
(BPCS)
ON LINE

Comments

Application and drawings must be


submitted online, DM issues the building
Permits & stamps all drawings thru BPCS,
then contractor or consultant can print them
online.

the request is achieved within 24 hours


even if it meets holidays or after the duty
time

the request is achieved within 24 hours


even if it meets holidays or after the duty
time

only for multi story buildings with Steel


structure,the request is achieved within 24
hours even if it meets holidays or after the
duty time

Contractor & consultant must notify DM that


the work is completed at site thru the
system, then DM does the final checking &
issues the Completion certificate online