CURRENT TIMELINE/WORK SCHEDULE FOR DEVELOPMENT

NOTE
Depending on the priority Level of molds(Style), it can vary the current schedule.
Depending on Customer comment & to correct mold error, its need to modify & Re-Machine the mold

ID

Task Name

Description

Start

Finish

Jun 2015

Duration
15

M&S Spacer 34B Design

6/15/2015

6/15/2015

1d

AL Blocks order for M&S Spacer


34B

Lead Time for 34B Blocks, M&S Spacer

6/15/2015

6/19/2015

5d

Re-Machine

Modification for Re-Machine George

6/18/2015

6/26/2015

7d

6/16/2015

6/17/2015

2d

Sample of New Mold (MSDM)

MSDM 36DD 1st Sample

6/18/2015

6/19/2015

2d

Sample of Re-Machined Molds


(Rebbeca & George)

Sample Rebbeca 32GG V1


Sample George 34B V1

6/24/2015

6/26/2015

3d

New Mold Machining One Mold

M&S Spacer 34B -V0

6/19/2015

6/24/2015

4d

Re-Machine (George) Two Mold

George 34D V1
George 42C V1

6/26/2015

7/3/2015

6d

Sample of New Mold (M&S Spacer)

M&S 34B 1st Sample

6/24/2015

6/25/2015

2d

10

M&S Spacer 34D & 38DD Design

3D Scan Plastic Shot & Mold Design

6/18/2015

6/19/2015

2d

11

AL Order for M&S Spacer- 34D &


38DD Mold

Lead Time for 34D & 38DD Blocks, M&S


Spacer

6/19/2015

6/25/2015

5d

12

New Molds Machining One Mold

M&S Spacer 34D & 38DD V0

6/26/2015

7/3/2015

6d

13

Sample of New Mold (M&S Spacer)


34D , 38DD

M&S 34D & 38DD- 1st Sample

7/3/2015

7/6/2015

2d

14

Sample of Re-Machine George Molds 2nd Sample of George 34D,42C

7/3/2015

7/7/2015

3d

15

3D Scan Plastic Shot & Mold Design

Rebbeca 32GG V1
George 34B V1
George 34D V1
George 42C V1

16

17

18

19

20

21

22

23

Jul 2015
24

25

26

27

28

29

30

10

11

12

13

14

15