Professional Documents
Culture Documents
Pmstudy Processchart Formula PDF
Pmstudy Processchart Formula PDF
Pmstudy Processchart Formula PDF
Process
Chart
PMstudy
Process
Chart
Process Group
Knowledge Area
Integration
Initiating
Planning
Develop Project
Charter
Develop Project
Management Plan
Executing
Monitoring &
Controlling
Closing
Close Project
or Phase
- Deliverables
- Work Performance
- Data
Perform Integrated
Change Control
Plan Scope
Management
Validate Scope
Collect Requirements
Scope
Final product,
service, or result
transition
Accepted Deliverables
Control Scope
Define Scope
Scope Statement
Create WBS
Scope Baseline
Plan Schedule
Management
Define Activities
Activity List
Time
Activity Resource
Requirements
Activity Duration
Estimates
Sequence Activities
Control Schedule
Estimate Activity
Resources
Estimate Activity
Durations
Develop Schedule
Project Schedule
Plan Cost
Management
Cost
Activity Cost
Estimates
Determine Budget
Plan Quality
Management
Quality
Control Costs
Estimate Costs
Cost Baseline
Control Quality
Perform Quality
Assurance
Acquire Project
Team
Human Resource
Communications
Plan Human
Resource
Management
Develop Project
Team
Plan
Communications
Management
Manage
Communications
Verified
Deliverables
Staff Assignments
Team Performance
Assessments
Manage Project
Team
Control
Communications
Plan Risk
Management
Risk Register
Identify Risks
Perform Qualitative
Risk Analysis
Risk
Control Risks
Perform Quantitative
Risk Analysis
Plan Risk Responses
Procurement
Stakeholder
Identify
Stakeholders
Agreements
Closed
Procurements
Close
Procurements
Plan Procurement
Management
Conduct
Procurements
Control
Procurements
Plan Stakeholder
Management
Manage Stakeholder
Engagement
Control Stakeholder
Engagement
Stakeholder Register
Issue Log
PMP and PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.
V1
Term Definitions
(Do not reproduce in PMP Exam)
PV
Planned Value
EV
Earned Value
AC
Actual Cost
BAC
Formula
PERT = (P + 4M + O)/6
Std. Deviation = (P - O)/6
Variance = {(P - O)/6}2 or SD2
Normal Distribution
6 sigma = 99.99%
3 sigma = 99.73%
2 sigma = 95.46%
1 sigma = 68.26%
Budget at Completion
SV
Schedule Variance
EV - PV
CV
Cost Variance
EV - AC
SPI
EV / PV
CPI
EV / AC
Percent Complete
1. AC + ETC
2. AC + BAC - EV
3. BAC / CPI
Present Value =
ETC
Estimate to Complete
EAC - AC
VAC
Variance at Completion
BAC - EAC
(BAC - EV)
% Complete
EAC
Communication Channels
= N (N - 1) / 2
Future Value
(1 + r)t
(BAC - AC)
TCPI
To-Complete Performance Index
(Based on EAC)
(BAC - EV)
(EAC - AC)
Procurement Formula
Acronym
AF
Term Definitions
(Do not reproduce in PMP Exam)
AF = Actual Fee; TC = Target Cost;
AC = Actual Cost; TF = Target Fee;
SSR = Sellers Share Ratio
Formula
{ ( TC - AC) SSR } + TF
Hints for PMstudy Process Chart (no need to reproduce in final PMP exam)
1. The PMstudy Process Chart should be dumped from memory in 15-minute tutorial time before you start the actual PMP exam.
Practice and abbreviate as much as possible.
2. You do not need to write down the Term Definitions in the final PMP exam (i.e., black text on this page).
3. For Earned Value calculations,
Formulas for SV, CV, SPI, CPI have EV as first term.
Positive SV, CV values are good. CPI, SPI ratios > 1 are good.
TCPI ratio < 1 is good.
4.
: Shows primary output is .... Management Plan for all marked processes (total = 10).
5. For most Monitoring and Controlling processes, inputs include Work Performance Data, the Project Management Plan and relevant Project
Documents. Outputs typically include Change Requests, Work Performance Information, and updates to the Project Management Plan, Project
Documents and Organizational Process Assets.
PMP and PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.
V1