Professional Documents
Culture Documents
"Raising of Road Over Bridge On Western Railway": Synopsis
"Raising of Road Over Bridge On Western Railway": Synopsis
"Raising of Road Over Bridge On Western Railway": Synopsis
on
Western Railway
by
N D Chumber *
R Tolani **
SYNOPSIS
The paper describes the raising scheme adopted in raising of the ROBs at Sidhpur in Delhi
Ahmedabad Section, Ahmedabad Division of Western Railway. This work was carried out in
connection with operation of Double Stack Container (9.50 ft. high) between Palanpur Mehsana
Viramgam section of Western Railway. The ROB, 779 M long, is having 34 Nos. of spans of different
length. These all spans were raised within a period of 2 months using Hydraulic Synchronized lifting of
Girders without taking any traffic block. The scheme of raising of Girders have been illustrated in the
paper.
1.0 INTRODUCTION :
Indian Railways with network of Approx 63000 Route Kms
across the length and the breadth of the country is the
largest railway system under a single management in the
world. The transportation of goods for consumption, for
import and exports has grown exponentially in the recent
past. Transportation of goods globally takes place
predominantly by sea routes and ports are very important
links in the transportation. Gujarat has developed ports
along its coast line to meet the growing demand of the
galloping economy. Since the newly developed ports are
source of additional goods traffic, the railways face a
continuous challenge to augment the system to meet its
obligation towards country with the sectional capacities
getting over-saturated on all routes connecting ports to the
Northern hinterland. There are various ways by which the
capacity augmentation has been done by traffic facility
27
Foundation
Open trapezoidal sedimentary.
4.0 PLANNING:
The ROB was under construction when the planning for the
raising was being done. The railway span had already been
constructed by the construction organization of Western
Railway and the approach spans were already cast by the
state government. The detailed drawings of the existing
ROB collected from the respective organizations to study
the feasibility of raising the ROB.
The revised gradient of approach roads after lifting the
Railway span by 450mm was calculated. In the case of
Sidhpur ROB the length of approached road could not be
increased due to space constraints at the city end. The
existing gradient on Approach Road was approximately
1:24.5 and after raising the Railway span by 450mm, the
gradient on approach span became 1:23.5. This was within
the limits of gradient laid down in IRC and hence it was
decided that the length of the existing approaches be
maintained and the gradient be changed. This also avoided
earthwork and raising/ altering the approach retaining walls
and the entire raising was done in the girders only.
SIDHPUR ROB
682/11-12. The ROB is Connecting Sidhpur City to NH8.
The ROB crosses railway track near the Sidhpur yard and
the nearest points and crossing is within 50 m of the ROB.
The gradient in the yard is 1 in 400 i.e. already at the
minimum allowed gradient in the yards. The creation of
clearance for the double stack containers required the track
to be lowered by 45 cm. This would have necessitated an
increase in gradient. This would have required the approval
of CRS and condonation of Railway Board. Such
condonation also requires provision of extra safety
measures such as catch/ slip siding or operating
restrictions. Since this would have required more time for
execution, and was not a preferred long term arrangement
for the running of the trains, the raising of the ROB was
decided as the better alternative.
3.0 TECHNICAL DATA OF ROB SIDHPUR:
l
l
l
28
By the time the preparations for the raising were done, the
state government had completed the work and was ready
for opening the ROB for public. The decision of raising only
the girders increased the speed of work, and this helped in
securing the permission of the state government for closing
the ROB for the lifting work. For the duration of the work, the
level crossing in lieu of which the ROB had been
constructed was kept open to give the alternate way to the
ROB users.
As per planning, the GAD was prepared and submitted to
Western Railway H.Q. design office for approval along with
the original design document to check the stability of ROB
at raised position. The existing sub structure and
foundation were found fit even for the raised girders. After
accepting the approval from H.Q. design office, the GAD
and design was submitted to R&B Department, Gujarat
Government for approval.
5.0 SELECTION OF RAISING SCHEME
The main aim of the scheme made was to execute the work
as speedily as possible to meet the railway's requirements
of early completion of work as well as to mitigate the
problems being faced by the ROB users as early as
possible. The work was a difficult one as handling the PSC
girders requires skill. The spans consisted of multiple Isection PSC girders tied together by RCC deck slab and
diaphragms. All the I-girders have to be raised
simultaneously else the RCC components can very easily
get cracked. Any such failure in the girders would have led
to increase in the time for completing the work. Since the
girders belonged to the state government, the work was to
be done extra cautiously lest the railway's reputation be
sullied during the execution of the work.
It was deemed that the work was of specialized nature,
requiring precise handling of the girders, with adequate
care and safety margins. This required the agency chosen
l
l
6.2
6.3
6.4
6.5
6.6
6.7
6.8
6.9
6.10
6.11
6.12
6.13
6.14
6.15
6.16
6.17
6.18
6.19
29
30
9.2
9.3
9.4
9.5
9.7
9.8
9.9
9.10
9.11
9.12
9.13
CLEANING OF PEDESTALS
31
32