Professional Documents
Culture Documents
ch09 PDF
ch09 PDF
Chapter 9
Project Management
Learning Outcomes
Elaborate upon the eight basic elements of
project planning;
Prepare schedules for specific projects,
utilizing bar charts, CPM and PERT;
Discuss the key dimensions of effective
project control;
9-2
11/8/2015
9-3
9-4
11/8/2015
9-5
Project Elements
Objective
Scope
Contract requirements
Schedules
Resources
Personnel
Control
Risk and problem analysis
9-6
11/8/2015
Matrix organization
a team structure with members from functional
areas, depending on skills required
Project manager
most important member of project team
9-7
Scope Statement
Scope statement
a document that provides an understanding,
justification, and expected result of a project
Statement of work
written description of objectives of a project
9-8
11/8/2015
9-9
9-10
11/8/2015
9-11
9-12
11/8/2015
9-13
Project Scheduling
Steps
Define activities
Sequence activities
Estimate time
Develop schedule
Techniques
Gantt chart
CPM/PERT
Software
Microsoft Project
9-14
11/8/2015
Gantt Chart
Slack
amount of time an activity can be delayed without
delaying the project
9-15
Month
4
10
Activity
Design house
and obtain
financing
Lay foundation
Order and
receive
materials
Build house
Select paint
Select carpet
Finish work
Month
Copyright 2011 John Wiley & Sons, Inc.
9-16
11/8/2015
Project Control
Time management
Cost management
Performance management
Earned Value Analysis standard procedure to
numerically measure a projects progress
forecast its completion date and cost
measure schedule and budget variation
9-17
Project Control
Quality management
Communication
Enterprise project management
9-18
11/8/2015
CPM/PERT
Critical Path Method (CPM)
DuPont & Remington-Rand
Deterministic task times
Activity-on-node network construction
9-19
Project Network
Activity-on-node (AON)
nodes represent activities
arrows show precedence
relationships
Branch
1
Node
2
Activity-on-arrow (AOA)
arrows represent activities
nodes are events for
points in time
Event
completion or beginning
of an activity in a project
Copyright 2011 John Wiley & Sons, Inc.
9-20
10
11/8/2015
Lay
foundation
2
3
Design house
and obtain
financing
Dummy
Build
house
0
1
Order and
receive
materials
4
Select
paint
Finish
work
3
1
Select
carpet
9-21
Concurrent Activities
Dummy
two or more activities cannot share same start and
end nodes
Lay foundation
Lay
foundation
3
Order material
3
Dummy
2
0
1
Order material
(b) Correct precedence
relationship
9-22
11
11/8/2015
Build
house
2
2
4
3
Activity Number
Activity Time
1
3
Start
7
1
Design house
and obtain
financing
Finish work
3
1
5
1
6
1
Order &receive
materials
Select
paint
Select
carpet
9-23
Critical Path
2
2
Start
1
3
7
1
3
1
A:
B:
C:
D:
4
3
1-2-4-7
3 + 2 + 3 + 1 = 9 months
1-2-5-6-7
3 + 2 + 1 + 1 + 1 = 8 months
1-3-4-7
3 + 1 + 3 + 1 = 8 months
1-3-5-6-7
3 + 1 + 1 + 1 + 1 = 7 months
5
1
6
1
Critical path
12
11/8/2015
2
2
Start
4
3
Finish at 9 months
1
3
7
1
3
1
5
1
Start at 3 months
Finish
6
1
Start at 6 months
9-25
Node Configuration
Activity
number
Activity
duration
Earliest
start
Earliest
finish
Latest
start
Latest
finish
9-26
13
11/8/2015
Activity Scheduling
Earliest start time (ES)
earliest time an activity can start
ES = maximum EF of immediate predecessors
Forward pass
starts at beginning of CPM/PERT network to determine
earliest activity times
9-27
Build house
Start
Finish work
Design house
and obtain
financing
1
3
1
Order and
receive materials
1
5
Select carpet
Select paint
9-28
14
11/8/2015
Activity Scheduling
Latest start time (LS)
Latest time an activity can start without delaying critical
path time
LS= LF - t
Backward pass
Determines latest activity times by starting at the end of
CPM/PERT network and working forward
9-29
Start
Build house
Finish work
Design house
and obtain
financing
Order and
receive materials
Select carpet
Select paint
9-30
15
11/8/2015
Activity Slack
Activity
LS
ES
LF
EF
Slack S
*1
*2
*4
*7
* Critical Path
9-31
t=
a + 4m + b
6
b-a
2 = 6
a = optimistic estimate
m = most likely time estimate
b = pessimistic time estimate
Copyright 2011 John Wiley & Sons, Inc.
9-32
16
11/8/2015
P(time)
P(time)
Time
P(time)
Time
m=t
Time
Copyright 2011 John Wiley & Sons, Inc.
9-33
6,8,10
2,4,12
System
development
Start
Equipment testing
and modification
2
3,6,9
Position
recruiting
Manual
testing
System
training
Job Training
1,3,5
3,4,5
10
3,7,11
1,4,7
1,10,13
5
2,3,4
Final
debugging
Finish
11
2,4,6
System
testing
System
changeover
Orientation
7
2,2,2
Copyright 2011 John Wiley & Sons, Inc.
9-34
17
11/8/2015
1
2
3
4
5
6
7
8
9
10
11
MEAN TIME
VARIANCE
6
3
1
2
2
3
2
3
2
1
1
8
6
3
4
3
4
2
7
4
4
10
10
9
5
12
4
5
2
11
6
7
13
8
6
3
5
3
4
2
7
4
4
9
0.44
1.00
0.44
2.78
0.11
0.11
0.00
1.78
0.44
1.00
4.00
9-35
1
2
3
4
5
6
7
8
9
10
11
ES
EF
LS
LF
8
6
3
5
3
4
2
7
4
4
9
0.44
1.00
0.44
2.78
0.11
0.11
0.00
1.78
0.44
1.00
4.00
0
0
0
8
6
3
3
9
9
13
16
8
6
3
13
9
7
5
16
13
17
25
1
0
2
16
6
5
14
9
12
21
16
9
6
5
21
9
9
16
16
16
25
25
1
0
2
8
0
2
11
0
3
8
0
9-36
18
11/8/2015
Start
2 0
6 0
3 0
3 2
4 8 13
5 16 21
10 13 17
8 9
7 9
16
6 3
4 5
3
Finish
16
5 6
3 6
1 0
9 9 13
4 12 16
11 16 25
9 16 25
7 3 5
2 14 16
9-37
9-38
19
11/8/2015
9-39
Z=
x-
9-40
20
11/8/2015
= tp
Time
9-41
Southern Textile
What is probability that project is completed within 30 weeks?
P(x 30 weeks)
2 = 6.89 weeks
=
6.89
= 2.62 weeks
= 25 x = 30
Z=
=
x-
30 - 25
2.62
= 1.91
Time (weeks)
9-42
21
11/8/2015
Southern Textile
What is probability that project is completed within 22 weeks?
P(x 22 weeks)
= 0.1271
0.3729
2 = 6.89 weeks
=
6.89
= 2.62 weeks
x = 22 = 25
Z=
x-
= 22 - 25
2.62
= -1.14
Time (weeks)
9-43
Microsoft Project
Popular software package for project
management and CPM/PERT analysis
Relatively easy to use
9-44
22
11/8/2015
Microsoft Project
Click on Tasks
First step;
Start Date
9-45
Microsoft Project
Click on Format then Timescale
to scale Gantt chart.
Create precedence
relationships;
click on predecessor
activity, then
holding Ctrl Key,
click on successor
activity.
Precedence
relationships
Gantt chart;
click on View
to activate
9-46
23
11/8/2015
Microsoft Project
Click on View then
Network Diagram
Critical path
in red
9-47
9-48
24
11/8/2015
Enter % completion
9-49
Activities 1, 2 and 3
100% complete
9-50
25
11/8/2015
Click on PERT
calculator to compute
activity duration
9-51
9-52
26
11/8/2015
9-53
Project Crashing
Crashing
reducing project time by expending additional
resources
Crash time
an amount of time an activity is reduced
Crash cost
cost of reducing activity time
Goal
reduce project duration at minimum cost
9-54
27
11/8/2015
2
8
12
7
4
1
12
6
4
5
4
3
4
9-55
$5,000
Crashed activity
Slope = crash cost per week
$4,000
$3,000
$2,000
Normal activity
Normal cost
$1,000
Normal time
Crash time
|
2
|
4
|
6
|
8
|
10
|
12
|
14
Weeks
9-56
28
11/8/2015
Project Crashing
ACTIVITY
1
2
3
4
5
6
7
NORMAL
TIME
(WEEKS)
CRASH
TIME
(WEEKS)
NORMAL
COST
12
8
4
12
4
4
4
7
5
3
9
1
1
3
$3,000
2,000
4,000
50,000
500
500
15,000
$5,000
3,500
7,000
71,000
1,100
1,100
22,000
$75,000
$110,700
TOTAL
ALLOWABLE
CRASH TIME
(WEEKS)
CRASH
COST
5
3
1
3
3
3
1
CRASH
COST PER
WEEK
$400
500
3,000
7,000
200
200
7,000
9-57
$500
$7000
4
2
8
FROM
$7000
12
7
4
1
12
$400
3
4
$3000
6
4
5
4
$200
$200
TO
Project Duration:
31 weeks
Additional Cost:
$2000
$500
$7000
2
8
12
4
$7000
7
4
1
7
$400
3
4
$3000
Project Duration:
36 weeks
5
4
6
4
$200
$200
9-58
29
11/8/2015
Time-Cost Relationship
Crashing costs increase as project duration
decreases
Indirect costs increase as project duration
increases
Reduce project length as long as crashing costs
are less than indirect costs
9-59
Time-Cost Tradeoff
Minimum cost = optimal project time
Cost ($)
Indirect cost
Direct cost
Crashing
Time
Project duration
Copyright 2011 John Wiley & Sons, Inc.
9-60
30
11/8/2015
6-61
31