Download as pdf or txt
Download as pdf or txt
You are on page 1of 31

11/8/2015

Chapter 9
Project Management

Learning Outcomes
Elaborate upon the eight basic elements of
project planning;
Prepare schedules for specific projects,
utilizing bar charts, CPM and PERT;
Discuss the key dimensions of effective
project control;

Copyright 2011 John Wiley & Sons, Inc.

9-2

11/8/2015

Project Management Process


Project
unique, one-time operational activity or effort

Copyright 2011 John Wiley & Sons, Inc.

9-3

Project Management Process

Copyright 2011 John Wiley & Sons, Inc.

9-4

11/8/2015

Project Management Process

Copyright 2011 John Wiley & Sons, Inc.

9-5

Project Elements

Objective
Scope
Contract requirements
Schedules
Resources
Personnel
Control
Risk and problem analysis

Copyright 2011 John Wiley & Sons, Inc.

9-6

11/8/2015

Project Team and Project Manager


Project team
made up of individuals from various areas and
departments within a company

Matrix organization
a team structure with members from functional
areas, depending on skills required

Project manager
most important member of project team

Copyright 2011 John Wiley & Sons, Inc.

9-7

Scope Statement
Scope statement
a document that provides an understanding,
justification, and expected result of a project
Statement of work
written description of objectives of a project

Copyright 2011 John Wiley & Sons, Inc.

9-8

11/8/2015

Work Breakdown Structure


Work breakdown structure (WBS)
Breaks a project into components,
subcomponents, activities, and tasks

Copyright 2011 John Wiley & Sons, Inc.

9-9

Work Breakdown Structure for Computer Order


Processing System Project
Copyright 2011 John Wiley & Sons, Inc.

9-10

11/8/2015

Responsibility Assignment Matrix


Organizational Breakdown Structure (OBS)
a chart that shows which organizational units are
responsible for work items

Responsibility Assignment Matrix (RAM)


shows who is responsible for work in a project

Copyright 2011 John Wiley & Sons, Inc.

9-11

Responsibility Assignment Matrix

Copyright 2011 John Wiley & Sons, Inc.

9-12

11/8/2015

Global and Diversity Issues in Project


Management
Global project teams are formed from different
genders, cultures, ethnicities, etc.
Diversity among team members can add an
extra dimension to project planning
Cultural research and communication are
important elements in the planning process

Copyright 2011 John Wiley & Sons, Inc.

9-13

Project Scheduling
Steps

Define activities
Sequence activities
Estimate time
Develop schedule

Copyright 2011 John Wiley & Sons, Inc.

Techniques
Gantt chart
CPM/PERT

Software
Microsoft Project

9-14

11/8/2015

Gantt Chart

Graph or bar chart


Bars represent the time for each task
Bars also indicate status of tasks
Provides visual display of project schedule

Slack
amount of time an activity can be delayed without
delaying the project

Copyright 2011 John Wiley & Sons, Inc.

9-15

Example of Gantt Chart


0

Month
4

10

Activity
Design house
and obtain
financing
Lay foundation
Order and
receive
materials
Build house
Select paint
Select carpet
Finish work

Month
Copyright 2011 John Wiley & Sons, Inc.

9-16

11/8/2015

Project Control
Time management
Cost management
Performance management
Earned Value Analysis standard procedure to
numerically measure a projects progress
forecast its completion date and cost
measure schedule and budget variation

Copyright 2011 John Wiley & Sons, Inc.

9-17

Project Control
Quality management
Communication
Enterprise project management

Copyright 2011 John Wiley & Sons, Inc.

9-18

11/8/2015

CPM/PERT
Critical Path Method (CPM)
DuPont & Remington-Rand
Deterministic task times
Activity-on-node network construction

Project Evaluation and Review Technique (PERT)


US Navy and Booz, Allen & Hamilton
Probabilistic task time estimates
Activity-on-arrow network construction

Copyright 2011 John Wiley & Sons, Inc.

9-19

Project Network
Activity-on-node (AON)
nodes represent activities
arrows show precedence
relationships

Branch
1

Node
2

Activity-on-arrow (AOA)
arrows represent activities
nodes are events for
points in time

Event
completion or beginning
of an activity in a project
Copyright 2011 John Wiley & Sons, Inc.

9-20

10

11/8/2015

AOA Project Network for a House


3

Lay
foundation
2

3
Design house
and obtain
financing

Dummy
Build
house

0
1

Order and
receive
materials

4
Select
paint

Finish
work

3
1

Select
carpet

Copyright 2011 John Wiley & Sons, Inc.

9-21

Concurrent Activities
Dummy
two or more activities cannot share same start and
end nodes
Lay foundation

Lay
foundation

3
Order material

(a) Incorrect precedence


relationship

Copyright 2011 John Wiley & Sons, Inc.

3
Dummy
2

0
1

Order material
(b) Correct precedence
relationship

9-22

11

11/8/2015

AON Network for House Building


Project
Lay
foundation

Build
house

2
2

4
3

Activity Number
Activity Time

1
3

Start

7
1

Design house
and obtain
financing

Finish work

3
1

5
1

6
1

Order &receive
materials

Select
paint

Select
carpet

Copyright 2011 John Wiley & Sons, Inc.

9-23

Critical Path
2
2
Start

1
3

7
1
3
1

A:
B:
C:
D:

4
3

1-2-4-7
3 + 2 + 3 + 1 = 9 months
1-2-5-6-7
3 + 2 + 1 + 1 + 1 = 8 months
1-3-4-7
3 + 1 + 3 + 1 = 8 months
1-3-5-6-7
3 + 1 + 1 + 1 + 1 = 7 months

Copyright 2011 John Wiley & Sons, Inc.

5
1

6
1

Critical path

Longest path through a


network
Minimum project
completion time
9-24

12

11/8/2015

Activity Start Times


Start at 5 months

2
2
Start

4
3

Finish at 9 months

1
3

7
1
3
1

5
1

Start at 3 months

Finish

6
1
Start at 6 months

Copyright 2011 John Wiley & Sons, Inc.

9-25

Node Configuration
Activity
number

Activity
duration

Copyright 2011 John Wiley & Sons, Inc.

Earliest
start

Earliest
finish

Latest
start

Latest
finish

9-26

13

11/8/2015

Activity Scheduling
Earliest start time (ES)
earliest time an activity can start
ES = maximum EF of immediate predecessors

Forward pass
starts at beginning of CPM/PERT network to determine
earliest activity times

Earliest finish time (EF)


earliest time an activity can finish
earliest start time plus activity time
EF= ES + t

Copyright 2011 John Wiley & Sons, Inc.

9-27

Earliest Activity Start and Finish Times


Lay foundation

Build house

Start

Finish work

Design house
and obtain
financing

1
3

1
Order and
receive materials

Copyright 2011 John Wiley & Sons, Inc.

1
5

Select carpet

Select paint

9-28

14

11/8/2015

Activity Scheduling
Latest start time (LS)
Latest time an activity can start without delaying critical
path time
LS= LF - t

Latest finish time (LF)


latest time an activity can be completed without delaying
critical path time
LF = minimum LS of immediate predecessors

Backward pass
Determines latest activity times by starting at the end of
CPM/PERT network and working forward

Copyright 2011 John Wiley & Sons, Inc.

9-29

Latest Activity Start and Finish Times


Lay foundation

Start

Build house

Finish work

Design house
and obtain
financing

Order and
receive materials

Copyright 2011 John Wiley & Sons, Inc.

Select carpet

Select paint

9-30

15

11/8/2015

Activity Slack
Activity

LS

ES

LF

EF

Slack S

*1

*2

*4

*7

* Critical Path

Copyright 2011 John Wiley & Sons, Inc.

9-31

Probabilistic Time Estimates


Beta distribution
probability distribution traditionally used in CPM/PERT

Mean (expected time):


Variance:
where

t=

a + 4m + b
6

b-a
2 = 6

a = optimistic estimate
m = most likely time estimate
b = pessimistic time estimate
Copyright 2011 John Wiley & Sons, Inc.

9-32

16

11/8/2015

P(time)

P(time)

Examples of Beta Distributions

Time

P(time)

Time

m=t

Time
Copyright 2011 John Wiley & Sons, Inc.

9-33

Project with Probabilistic Time


Estimates
Equipment
installation

6,8,10

2,4,12

System
development

Start

Equipment testing
and modification

2
3,6,9
Position
recruiting

Manual
testing

System
training

Job Training

1,3,5

3,4,5

10

3,7,11

1,4,7

1,10,13

5
2,3,4

Final
debugging

Finish

11
2,4,6
System
testing

System
changeover

Orientation

7
2,2,2
Copyright 2011 John Wiley & Sons, Inc.

9-34

17

11/8/2015

Activity Time Estimates


TIME ESTIMATES (WKS)
ACTIVITY

1
2
3
4
5
6
7
8
9
10
11

MEAN TIME

VARIANCE

6
3
1
2
2
3
2
3
2
1
1

8
6
3
4
3
4
2
7
4
4
10

10
9
5
12
4
5
2
11
6
7
13

8
6
3
5
3
4
2
7
4
4
9

0.44
1.00
0.44
2.78
0.11
0.11
0.00
1.78
0.44
1.00
4.00

Copyright 2011 John Wiley & Sons, Inc.

9-35

Activity Early, Late Times & Slack


ACTIVITY

1
2
3
4
5
6
7
8
9
10
11

ES

EF

LS

LF

8
6
3
5
3
4
2
7
4
4
9

0.44
1.00
0.44
2.78
0.11
0.11
0.00
1.78
0.44
1.00
4.00

0
0
0
8
6
3
3
9
9
13
16

8
6
3
13
9
7
5
16
13
17
25

1
0
2
16
6
5
14
9
12
21
16

9
6
5
21
9
9
16
16
16
25
25

1
0
2
8
0
2
11
0
3
8
0

Copyright 2011 John Wiley & Sons, Inc.

9-36

18

11/8/2015

Earliest, Latest, and Slack


1 0
8 1

Start

2 0
6 0

3 0
3 2

Critical Path 2-5-8-11

4 8 13
5 16 21

10 13 17

8 9
7 9

16

6 3
4 5

3
Finish

16

5 6
3 6

1 0

9 9 13
4 12 16

11 16 25

9 16 25

7 3 5
2 14 16

Copyright 2011 John Wiley & Sons, Inc.

9-37

Total Project Variance


2 = 22 + 52 + 82 + 112
= 1.00 + 0.11 + 1.78 + 4.00
= 6.89 weeks

Copyright 2011 John Wiley & Sons, Inc.

9-38

19

11/8/2015

CPM/PERT With OM Tools

Copyright 2011 John Wiley & Sons, Inc.

9-39

Probabilistic Network Analysis


Determine probability that project is
completed within specified time
where
=
=
x=
Z=

Z=

x-

tp = project mean time


project standard deviation
proposed project time
number of standard deviations that
x is from the mean

Copyright 2011 John Wiley & Sons, Inc.

9-40

20

11/8/2015

Normal Distribution of Project Time


Probability

= tp

Time

Copyright 2011 John Wiley & Sons, Inc.

9-41

Southern Textile
What is probability that project is completed within 30 weeks?
P(x 30 weeks)

2 = 6.89 weeks
=

6.89

= 2.62 weeks
= 25 x = 30

Z=
=

x-

30 - 25
2.62

= 1.91

Time (weeks)

From Table A.1, (appendix A) a Z score of 1.91 corresponds to a


probability of 0.4719. Thus P(30) = 0.4719 + 0.5000 = 0.9719

Copyright 2011 John Wiley & Sons, Inc.

9-42

21

11/8/2015

Southern Textile
What is probability that project is completed within 22 weeks?
P(x 22 weeks)
= 0.1271

0.3729

2 = 6.89 weeks
=

6.89

= 2.62 weeks
x = 22 = 25

Z=

x-

= 22 - 25
2.62
= -1.14

Time (weeks)

From Table A.1, (appendix A) a Z score of 1.14 corresponds to a


probability of 0.3729. Thus P(22) = 0.5000 - 0.3729 = 0.1271

Copyright 2011 John Wiley & Sons, Inc.

9-43

Microsoft Project
Popular software package for project
management and CPM/PERT analysis
Relatively easy to use

Copyright 2011 John Wiley & Sons, Inc.

9-44

22

11/8/2015

Microsoft Project

Click on Tasks
First step;
Start Date

Copyright 2011 John Wiley & Sons, Inc.

9-45

Microsoft Project
Click on Format then Timescale
to scale Gantt chart.

Create precedence
relationships;
click on predecessor
activity, then
holding Ctrl Key,
click on successor
activity.

Copyright 2011 John Wiley & Sons, Inc.

Precedence
relationships

Gantt chart;
click on View
to activate

9-46

23

11/8/2015

Microsoft Project
Click on View then
Network Diagram

Critical path
in red

Copyright 2011 John Wiley & Sons, Inc.

9-47

Microsoft Project Zoom View

Copyright 2011 John Wiley & Sons, Inc.

9-48

24

11/8/2015

Microsoft Project Task Information

Enter % completion

Copyright 2011 John Wiley & Sons, Inc.

9-49

Microsoft Project Degree of Completion

Activities 1, 2 and 3
100% complete

Copyright 2011 John Wiley & Sons, Inc.

Black bars show


degree of completion

9-50

25

11/8/2015

PERT Analysis with Microsoft Project


Click on PERT Entry
Sheet to enter 3
time estimates

Click on PERT
calculator to compute
activity duration

Copyright 2011 John Wiley & Sons, Inc.

9-51

PERT Analysis with Microsoft Project

Copyright 2011 John Wiley & Sons, Inc.

9-52

26

11/8/2015

PERT Analysis with Microsoft Project

Copyright 2011 John Wiley & Sons, Inc.

9-53

Project Crashing
Crashing
reducing project time by expending additional
resources

Crash time
an amount of time an activity is reduced

Crash cost
cost of reducing activity time

Goal
reduce project duration at minimum cost

Copyright 2011 John Wiley & Sons, Inc.

9-54

27

11/8/2015

Project Network Building a House


4

2
8

12

7
4

1
12

6
4

5
4

3
4

Copyright 2011 John Wiley & Sons, Inc.

9-55

Normal Time and Cost


vs. Crash Time and Cost
$7,000
$6,000
Crash cost

$5,000

Crashed activity
Slope = crash cost per week

$4,000
$3,000
$2,000

Normal activity
Normal cost

$1,000

Normal time

Crash time

|
2

Copyright 2011 John Wiley & Sons, Inc.

|
4

|
6

|
8

|
10

|
12

|
14

Weeks
9-56

28

11/8/2015

Project Crashing
ACTIVITY

1
2
3
4
5
6
7

NORMAL
TIME
(WEEKS)

CRASH
TIME
(WEEKS)

NORMAL
COST

12
8
4
12
4
4
4

7
5
3
9
1
1
3

$3,000
2,000
4,000
50,000
500
500
15,000

$5,000
3,500
7,000
71,000
1,100
1,100
22,000

$75,000

$110,700

TOTAL
ALLOWABLE
CRASH TIME
(WEEKS)

CRASH
COST

5
3
1
3
3
3
1

CRASH
COST PER
WEEK

$400
500
3,000
7,000
200
200
7,000

Copyright 2011 John Wiley & Sons, Inc.

9-57

$500

$7000
4

2
8

FROM

$7000

12

7
4

1
12

$400

3
4
$3000

6
4

5
4

$200

$200

TO
Project Duration:
31 weeks
Additional Cost:
$2000

$500

$7000

2
8

12

4
$7000
7
4

1
7

$400

3
4
$3000

Copyright 2011 John Wiley & Sons, Inc.

Project Duration:
36 weeks

5
4

6
4
$200

$200
9-58

29

11/8/2015

Time-Cost Relationship
Crashing costs increase as project duration
decreases
Indirect costs increase as project duration
increases
Reduce project length as long as crashing costs
are less than indirect costs

Copyright 2011 John Wiley & Sons, Inc.

9-59

Time-Cost Tradeoff
Minimum cost = optimal project time

Total project cost

Cost ($)

Indirect cost

Direct cost
Crashing

Time

Project duration
Copyright 2011 John Wiley & Sons, Inc.

9-60

30

11/8/2015

Copyright 2011 John Wiley & Sons, Inc.


All rights reserved. Reproduction or translation of this
work beyond that permitted in section 117 of the 1976
United States Copyright Act without express permission
of the copyright owner is unlawful. Request for further
information should be addressed to the Permission
Department, John Wiley & Sons, Inc. The purchaser
may make back-up copies for his/her own use only and
not for distribution or resale. The Publisher assumes no
responsibility for errors, omissions, or damages caused
by the use of these programs or from the use of the
information herein.

Copyright 2011 John Wiley & Sons, Inc.

6-61

31

You might also like