Description Quantity Pricelist Amount A. Earthworks
Description Quantity Pricelist Amount A. Earthworks
Description Quantity Pricelist Amount A. Earthworks
QUANTITY
A. EARTHWORKS
Land Clearing
350 sq. M
Excavation
6.68cu.m
Land fill
108.57cu.m*
Gravel Fill
350sq.m
SUBTOTAL
B. CONCRETE WORKS
FOUNDATION
cement
90 bags
sand
12 cu.m
CHB
400 pcs.
SUBTOTAL
COLUMN
cement
40 bags
sand
1.96 cu.m.
gravel
3.91 cu.m
PRICELIST
AMOUNT
16 mm
10mm
using 16 cm tie wire
SUBTOTAL
BEAMS
cement
sand
gravel
15pcs
53pcs
11.83 kg
310/pc
150/pc
60/kg
70 bags
4 cu.m.
6.9 cu.m.
250/bag
700/cu.m
950/cu.m
17500
2,800
6555
16 mm
100pcs
310/pc
31000
10 mm
using 16 cm tie wire
SUBTOTAL
FLOORING
cement
sand
gravel
80pcs.
30kg
150/pc
60/kg
12000
1800
71655
500bags
20.43 cu.m
40.85 cu.m
250/bag
700/cu.m
950/cu.m
100/sq.m
250/sq.m
200/sq.m
448/sq.m
250/bag
700/cu.m
20/pc
8000
250/bag
700/cu.m
950/cu.m
4650
7950
709.8
28396.3
125000
14301
38807.5
10 mm
43.63pcs
150/pc
using 16 cm tie wire
30kg
60/kg
SUBTOTAL
C. FORMWORKS/ CARPENTRY WOKS
SUBTOTAL
D. MASONRY WORKS
"6 CHB
6,588pcs
20/pc
cement
499 bags
250/bag
sand
68 cu.m
700/cu.m
6544.5
1800
186453
gravel
51 cu.m
10 mm
230pcs
tie wire
SUBTOTAL
E.ROOFING WORKS
Long span roofing
420m
Angular Bar
15pcs
Purlins
30pcs
welding rod
1box
tekscrew
2999pcs
gutter
60m
rigde roll
14pcs
SUBTOTAL
F.PAINTING WORKS
G.PLUMBING
H. ELECTRICAL WORKS
I.DOORS / WINDOW
J.PARKING
48450
34500
360
387420
10000
131760
124750
47600
950/cu.m
150/pc
100/m
630/pc
370/pc
2000/box
2/pc
400/m
248/pc
TOTAL =
2069761.753
LABOR COST (35%)
724416.614
TOTAL =
2788178.367
42000
9450
11100
2000
5998