Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 18

Providing & laying of M-60 grade concrete for expension joi

Description
Providing & laying of M-60 grade concrete

Providing & laying of M-60 grade concrete for expension joint


Unit = Rmt
Taking output = 12 Rmt
a) Labour
Skilled
Unskilled
b)

Machinery
Concrete Pump
Vibrator (Needle 40 mm)
Water tanker6 KL capacity for curing

c)

Material
Concrete M60 Grade As per analysis
Hessian Cloth

d)

Shuttering @ 4% of (a+b+c)

e) Overhead charges @ 25% on (a+b+c+d)


f) Contractor's profit @ 10% on (a+b+c+d+e)
g) Labour Welfare Cess @ 1% of (a+b+c+d+e+f)
Cost for 12 M = a+b+c+d+e+f+g
Rate per M = (a+b+c+d+e+f+g)/12

12.8 C

Concrete production( M-60) with Batching Plant, Transit Mixer


Unit : cum
Taking Output = 120 cum
a) Material
Cement - 43 grade
Coarse Sand
20 mm Aggregate
10 mm Aggregate
Admixture (Sika)
Admixture (Silica)

Wastage@5%
b)

Labour

c)

Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity

Transit Mixer - L = lead in km


Add 10 per cent of cost of carriage to cover cost of loading and unloading
d) Quality Control Sampling/Testing Charges @ 1% on (a+b+c+d)
Cost for 120 cum = a+b+c+d
Rate per cum = ( a+b+c+d )/120

grade concrete for expension joint


Unit

Quantity

Rate Rs

Cost Rs

Remarks/ Input ref.

Qty.- 5.694 Cum

day

0.50

487.00

243.50 As per Site (Output of 1 Skilled


802.00 and 4 unskilled labour - 10
Cum/day )

day

2.00

401.00

Cum

5.69

150.00

854.10 DSR 0009

hour
hour

0.08
0.50

43.75
150.00

3.50 DSR 0012


75.00 DSR 0057

cum
Sqm

6.77
57.00

6617.00
45.00

44783.86
2565.00 DSR - 765
1973.08

say

12825.01
6412.50
705.38
71242.92
5936.91
5937.00

tonne

54.00

6000.08

324004.05 PO Rate

tonne

78.36

1008.00

78986.88 PO Rate-HC0554

tonne

85.80

1237.50

106177.50 PO Rate-HC0550

tonne

57.24

1237.50

70834.50 PO Rate-HC0550

liter

516.00

107.38

55406.79 PO Rate-HC0530

Kg

3480.00

25.21

87730.80 PO Rate-HC0530

hour

6.00

2500.00

15000.00 DSR 0066

hour

6.00

500.00

3000.00 DSR 0070/16

hour

6.00

900.00

5400.00 DSR 0052/16

km/Cum

120 x 10

30.00

36000.00
3600.00
7861.41
794001.93
6616.68

say

6617.00

Lead = 10 km, DSR 0029/16

CEMENT CONCRETE PAVEMENT


Sr No
6.1

Ref. to MoRTH
Spec.
601

Description
Dry Lean Cement Concrete Sub- base
Construction of un-reinforced, plain cement concrete pavement over a prepared sub
base with 43 grade cement @ 400 kg per cum, coarse and fine aggregate conforming
to IS 383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a
batching and mixing plant as per approved mix design, transported to site, laid with a
fixed form or slip form paver, spread, compacted and finished in a continuous
operation including provision of contraction, expansion, construction and longitudinal
joints, joint filler, separation membrane, sealant primer, joint sealant, debonding strip,
admixtures as approved, curing compound, finishing to lines and grades as per
drawing

Unit = cum
Taking output = 1050 cum (2415 tonne)
a) Labour
Mate

b)

Mazdoor skilled
Mazdoor
Machinery
Road Sweeper @ 1250 sqm per hour
Concrete Pump
Water tanker6 KL capacity
Plate compactor

Concrete joint cutting machine .


Texturing machine .
Water tanker6 KL capacity for curing
c) Material
As per analysis
d) Overhead charges @ 8% on (a+b+c)
e) Contractor's profit @ 10% on (a+b+c+d)
f) Labour cess @ 1 % on (a+b+c+d+e)
Cost for 1050 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/1050

12.8 C

Concrete production with Batching Plant, Transit Mixer and Concrete Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement - 43 grade
Coarse Sand
20 mm Aggregate
10 mm Aggregate
Water for mix
Admixture

Separation Membrane of impermeable plastic sheeting 125 micron thick

b)

Pre moulded Joint filler, 25 mm thick for expansion joint.


Joint sealant
Sealant primer
Curing compound
Hessian Cloth
Water for curing
Labour

c)

Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer - L = lead in km

Add 10 per cent of cost of carriage to cover cost of loading and unloading
d) Formwork @ 4 per cent on cost of concrete i.e. cost of material, labour and
machinery
e) Testing Charges @ 1%
Cost for 120 cum = a+b+c+d+e
Rate per cum = ( a+b+c+d+e )/120

CEMENT CONCRETE PAVEMENTS


Unit

Quantity

Rate Rs

Cost Rs

Remarks/ Input ref.

day

2.000

461.00

922.00

Min. wages

day
day

15.000
35.000

424.00
385.00

6360.00
13475.00

Min. wages
Min. wages

hour
Cum

4.200
1050.00

360.00
150.00

1512.00
157500.00

DSR 0075
DSR 0009

hour
hour

36.000
12.000

150.00
100.00

5400.00
1200.00

DSR 0057/16
Cl. 601.5.5.4

hour
hour
hour

12.000
12.000
110.250

112.50
115.63
150.00

1350.00
1387.50
16537.50

DSR 0047 / 16
DSR 0048 / 16
DSR 0057

cum

1050.000

7512.00

say

7887600.00
647459.52
874070.35
96147.74
9710921.61
9248.50
9248.00

tonne

48.00

4637.00

222576.00

tonne

74.66

938.00

70033.71

tonne

80.87

1055.25

85334.69

tonne

53.91

1055.25

56889.79

KL

19.32

100.00

1932.00

liter

120.00

121.00

14520.00

sqm

600.000

12.00

7200.00

DSR 323 / 16

sqm
kg
kg
liter
Sqm
KL

16.330
875.000
116.670
240.00
600.00
405.72

500.00
200.00
125.00
50.00
45.00
100.00

8165.00
175000.00
14583.75
12000.00
27000.00
40572.00

DSR 374 / 16

hour

6.00

2500.00

15000.00

DSR 0066

hour

6.00

500.00

3000.00

DSR 0070/16

hour

6.00

900.00

5400.00

DSR 0052/16

`300 x 10

30.00

90000.00

Lead = 10 km

tonne.km

9000.00
34328.28
8925.35
901460.57
7512.17
say

7512.00

DSR 371 / 16
DSR 349 / 16
DSR - 765

CEMENT CONCRETE PAVEMENTS


Sr No
6.2

Ref. to MoRTH
Spec.
602

CEMENT CONCRETE PAVEMENTS


Description

Unit

Quantity

Cement Concrete Pavement


Construction of un-reinforced, plain cement concrete pavement over a prepared sub
base with 43 grade cement @ 400 kg per cum, coarse and fine aggregate conforming
to IS 383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a
batching and mixing plant as per approved mix design, transported to site, laid with a
fixed form or slip form paver, spread, compacted and finished in a continuous
operation including provision of contraction, expansion, construction and longitudinal
joints, joint filler, separation membrane, sealant primer, joint sealant, debonding strip,
admixtures as approved, curing compound, finishing to lines and grades as per
drawing

Unit = cum
Taking output = 1050 cum (2415 tonne)
a) Labour
Mate

b)

Mazdoor skilled
Mazdoor
Machinery
Road Sweeper @ 1250 sqm per hour
Front end loader 1 cum bucket capacity
Cement concrete batch mix plant @ 75 cum per hour (effective output)

Electric generator 250 KVA


Slip form paver with electronic sensor
Water tanker6 KL capacity
Transit Mixer
Add 10 per cent of cost of carriage to cover cost of loading and unloading

c)

Concrete joint cutting machine .


Texturing machine .
Material
Crushed stone coarse aggregates of 25mm and 12.5mm nominal size @
0.90 cum/cum of concrete conforming to clause 602.2.4. .
Sand as per IS: 383 and conforming to clause 602.2.4 @ 0.45 cum/cum of
concrete
Cement 43 grade @ 400 kg/cum of concrete
32 mm mild steel dowel bars of grade S 240
16 mm deformed steel tie bars of grade S 415
Separation Membrane of impermeable plastic sheeting 125 micron thick
Pre moulded Joint filler, 25 mm thick for expansion joint.
Joint sealant
Sealant primer
Plastic sheath,1.25 mm thick for dowel bars

day

2.000

day
day

15.000
35.000

hour
hour
hour

2.800
18.000
6.000

hour
hour
hour
Cum.km

6.000
6.000
36.000
`2415x10 km

hour
hour

12.000
12.000

cum

945.000

cum

473.000

tonne
tonne
tonne
sqm

414.000
9.450
1.170
7000.000

sqm
kg
kg
sqm

16.330
875.000
116.670
46.670

Curing compound
Super plastisizer admixture IS marked as per 9103-1999 @ 0.5 per cent by
weight of cement
Cost of water
Add 1 per cent of material for cost of miscellaneous materials like tarpauline, Hessian
cloth, metal cap, cotton / compressible sponge and cradle for dowel bars, work
bridges for men to approach concrete surface without walking over it, cutting blades
and bites, minor equipments like scabbling machine, threads, ropes, guide wires and
any other unforeseen items.
d) Overhead charges @ 8% on (a+b+c)
e) Contractor's profit @ 10% on (a+b+c+d)
f) Labour cess @ 1 % on (a+b+c+d+e)
Cost for 1050 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/1050

liter
kg

1850.000
2070.000

KL

216.000

Rate Rs

Cost Rs

Remarks/ Input ref.

487.00

974.00

As per Site (Output of 1


Skilled and 4 unskilled labour
- 10 Cum/day )

401.00

6015.00

0.00
Err:509

360.00

1008.00
Err:509
Err:509

DSR 0075 / 16
Err:509
Err:509

700.00
2900.00
Err:509
Err:509

4200.00
17400.00
Err:509
Err:509
Err:509

DSR 0069/16
DSR 0068 /16
Err:509
Err:509

112.50
115.63

1350.00
1387.50

DSR 0047 / 16
DSR 0048 / 16

6617.00

6253065.00

Err:509

Err:509
Err:509

Err:509

Err:509

Err:509

0.00

Err:509

0.00
0.00
12.00

Err:509
0.00
0.00
84000.00

Err:509
NA
NA
DSR 323 / 16

500.00
200.00
125.00
0.00

8165.00
175000.00
14583.75
0.00

DSR 374 / 16
DSR 371 / 16
NA

50.00
187.31

92500.00
387736.88

200.00

43200.00
Err:509

say

Err:509
Err:509
Err:509
Err:509
Err:509
Err:509

DSR 349 / 16
PO # 424

UNIT COST OF LABOUR ENGAGED FOR THE WORK AS OF APR 2016


A

UNSKILLED

Statutory Requirement

Basic Pay

As per minimum Wages

P.F

As per statute

3
B

SEMI SKILLED

Basic Pay

As per minimum Wages

P.F

As per statute

3
C

SKILLED

Basic Pay

As per minimum Wages

P.F

As per statute

Rate
Rs 353 per day
13.61% of Basic
GROSS PAY / Day

Rs 390 per day


13.61% of Basic
GROSS PAY / Day

Rs 429 per day


13.61% of Basic
GROSS PAY / Day

353
48.04
401.00

390
53.08
443.00

429
58.39
487.00

Details of lead for carriage of mix materials


Sr. no.
1

Description
Camp to End point of Project, i.e. upto Ch. 7.800 (Mukarba Chowk)
From End point to Camp (Via Mukarba Chowk trumpet)
Average lead upto first point of project (A)

Length of project
Effective length (B)

Total average lead of carriage from camp to site (A + B)

erials
Length
6.80 km
5.40 km
6.10 km
7.80 km
3.90 km
10.00 km

You might also like