Second Penang Bridge Project
Second Penang Bridge Project
INTRODUCTION
PROJECT PARTICULARS
PKG
PROJECT
DESCRIPTION
CONTRACTOR
PROJECT
COST
(RM MIL.)
CHEC
Construction
(M) Sdn Bhd
2,200
Superstructure Works
of Approach Spans
UEM Builders
Bhd
1,550
3A
Cergas Murni
Sdn Bhd
152.7
3B
Batu Kawan
Expressways
IJM
Construction
Sdn Bhd
349.9
3C
HRA Teguh
Sdn Bhd
67.3
3D
Toll Plaza,
Administration Building
And Related Works
79.8
3E
TERAS
Teknologi Sdn
Bhd
14.97
3F
Itramas
Technology
Sdn Bhd
19.8
3G
Electrical Installations
TN Synergy
Sdn Bhd
13.38
INFORMATIONS
Length of
Bridge
16.4km
Length of
Expressway
7.1km
Lane
Configuration
method:
Approach Spans
Construction
Main Span
Navigational
Other
Channel
Spans
Total
OVERALL LAYOUT
Integrated Toll System
Package 3A:
Conventional
Works
4.5 billion
Contract Period
2008
Mth
Start
Finish
60
8-Nov-08
8 Nov-13
57
8-Nov-08
24-Jul-13
52
8-Jun-09
8-Sep-13
31
19-May-10
31-Mar-12
39
28-Jun-10
28-Sep-13
35
19-May-10
30-Apr-13
20
15-Nov-11
15-Jul-13
18
1- Jun-12
31-Aug-13
17
26-Jun-12
25-Jul-13
44 wks
26-Sep-12
30-Jul-13
2009
2010
2011
2012
2013
PROJECT ALIGNMENT
The Toll Plaza building is designed to achieve Platinum rating criteria of 87% Green Building
Index (GBI) which will be the first in Penang.
The building also incorporate 80% IBS components that minimize environmental disturbance
while maintaining high quality and aesthetical aspect as well as adopting fast construction
concept.
The land expressway is designed based on 100% earthwork compaction with removal of
surcharge requirements to achieve 100% primary consolidation and 50mm settlement in 20
years, providing minimal maintenance of the highway.