FIFTH EDITION

MAY 2016

GCC:
The GCC 2015 (3rd Edition)
Welcomed with Open Arms
Commentary on the Changes
Introduced by the GCC 2015 (3rd
Edition)
Author: Odette Potgieter

During November 2015 the GCC drafting committee of


SAICE published the GCC 2015, 3rd Edition.
It wasnt clear what prompted the issuing of the 3rd
Edition even though the Industry knew that changes
were necessary. However, Mr Willie Claassen, a
member of the drafting committee clarified the purpose
and motivation for the publication of this edition namely:
- The employers ongoing failure to make timeous
payment to contractors after the issuing of
payment certificates;

- The need to clarify the Escalation Calculation and


which Indices should be used.
- The CIDB not willing to register sub-contractors.
Clause 4.4.2 is an additional requirement for
approval of sub contractors.
There are pertinent issues in the GCC 2010 (2nd
Edition) that needed to be addressed and which
required clarification. Prior to reviewing the 3rd Edition,
we were quietly holding thumbs and hoping that the
changes introduced by the drafting committee in the
3rd Edition would address these issues and other
shortcomings of the 2nd Edition.

Page 2
Fifth Edition May 2016
We will now, in this article look at some of the changes introduced in the latest edition of the GCC, and provide a summary
of commentary on such changes.
General changes throughout the contract document
The drafting committee made certain amendments to general terms throughout the contract. These changes are:
-

The definition of and reference to Engineer has been deleted and replaced with Employers Agent. This change
was implemented and it was necessary to change the description of the person administering the contract as the GCC
2015 is now also suitable for other than construction and building projects.

The word Legally has been added to precede deemed and where the word deemed was considered redundant
the word deemed has been deleted and replaced with other appropriate words. Only where the meaning / purpose
of the word deemed is the legal meaning, namely, the event must be considered as conclusive in the absence of
evidence or facts, it remained.

Amendments to defined terms


The following definitions have been amended:
Clause 1.1.21

General Items means items stipulated in the Pricing Data relating to general obligations, site services,
facilities, and/or items that cover elements of the cost of the work which are not considered as proportional
to the quantities cost of the Permanent Works.

Commentary:

The difficulty with the wording as per the GCC 2010 is that it is illogical to think it could be proportional
to the quantities of the Permanent Works. General Items, as defined in this clause, are usually paid on
a time related basis. This amendment clarifies any possible confusion.

Clause 1.1.22

Permanent Works means the permanent works to be designed (if required), constructed, and/or
provided in accordance with the Contract.

Commentary:

Previously the GCC 2010 could only be used for construct only projects. This change is introduced to
the GCC to now allow for different contracting strategies namely design and construct and therefore it is
more suited to Mechanical and Electrical projects.

Amendments to the core clauses of the contract


Clause 1.3.6 is a new clause and is titled Employers copyright and provides for:

Page 3
Fifth Edition May 2016
Clause 1.3.6:

Except where otherwise stated in the Contract, the Employer shall retain the copyright and other
intellectual property rights in documents supplied to the Contractor under the Contract.
The Employer shall legally be deemed to have given the Contractor a non-terminable, transferable, nonexclusive, royalty-free licence to copy, use and communicate the Employers documents for the purposes
of the Contract.

Commentary:

This change seems to be introduced in support of the amended definition of Permanent Works (see
clause 1.1.22) and the idea that the GCC, what was originally a civil construction contract where the
employer provided the design, can also now be used for projects other than engineering projects and
where the contractor would do the design which would be required to conform to the Employers
requirements. It addresses the copyright issue in regard to information provided by the Employer and
the use of such information and documentation for the specific project only.

Clause 2.1.2

The Contractor shall be deemed to have inspected and examined the Site and its surroundings and to
have studied all available information pertaining thereto before submitting his tender (as far as is
reasonable). The Contractor shall thus be deemed considered knowledgeable in respect of:

Commentary:

The site conditions and the circumstances under which the work is to be carried out places an onus on
the Contractor and presents challenges and potential risks to the Contractor. It is important that the
Contractor understands its obligations and responsibilities in this regard.
It could be argued that the wording of the GCC 2010 gave rise to a degree of unreasonableness and
that the obligations on the Contractor was extremely onerous.
The modifications to this clause are intended to clarify the Contractors obligations and responsibilities
and to introduce a measure of reasonableness. The inclusion of the wording (as far as is reasonable)
means the information gathered will be limited to the facts made available during the inspection of the
Site with the tenderers, in the tender documents and other documents referred to. This places a
responsibility on the Employer and the Employers Agent to make pertinent information available to the
tenderers at tender stage. If not, it may result in a claim if such unknown conditions are encountered
later. Please refer clause 2.1.1 and 2.3.1.

Clause 2.1.3:

The Contractor shall, in general, be deemed to have obtained all attainable available information on
risks, contingencies and all other circumstances which may influence or affect the Works (as far as is
reasonable).

Page 4
Fifth Edition May 2016
Commentary:

Similar to my commentary under clause 2.1.2, the GCC 2010 wording could be argued to be onerous
and to place an unreasonable onus on the Contractor to research the circumstances under which the
work is to be carried out. The lengths to which the Contractor is supposed to go to obtain information
have been moderated in this clause which is perceived to be less susceptible and more reasonable.

Clause 3.1.1 provides for the Qualification of the Employers Agent and states that:
Clause 3.1.1:

The natural person acting, or purporting to act, as the Employers Agent shall be a registered professional
in a built environment profession that is appropriate to the Scope of Work.

Commentary:

As the GCC 2015 is now also suitable for projects other than engineering projects, it was necessary to
change the name of the person administering the contract.
In addition to this, it is a common (and serious) problem in the construction industry that the person
appointed to act as engineer / principal agent often does not possess adequate experience or
understanding that is required for successful management of a contract / project.
This clause sets out the minimum requirements that need to be complied with in order to act as the
Employers Agent (i.e. the Engineer). However, we believe that the inclusion of this clause will only go
part way to addressing the issue and that a minimum amount of experience together with the stipulated
qualification would be a better approach.

Clause 4.4.2:

Except where otherwise provided in the Contract, the Contractor shall not subcontract any part of the
Contract without the prior written consent of the Employers Agent, which consent shall not be
unreasonably withheld.

Commentary:

The GCC 2004 (1st Edition) made provision for approval by the engineer of subcontractors, however
such provision was excluded in the GCC 2010 as it was taken that the CIDB would require subcontractors
to register.
However, this did not happen and as a result thereof this provision had to be re-introduced.

Clause 5.11.1 is a new clause which is titled Suspension of the Works by the Contractor and states the following:

Page 5
Fifth Edition May 2016
Clause 5.11.1:

The Contractor may, after giving fourteen (14) days written n notice to the Employer, with a copy to the
Employers Agent, (with specific reference to this Clause) suspend the progress of the Works where the
Employers Agent or the Employer has failed in terms of Clause 6.10.4 to:
5.11.1.1 Deliver a payment certificate, or
5.11.1.2 Make full payment of the amount certified in the payment certificate without prejudice to the
Contractors other rights under this Contract or by law.

Commentary:

This new clause entitles the Contractor to suspend its works if payment is not forthcoming and will
hopefully force the Employer to make payment timeously. This clause is included as a result of the supply
chain management taking over from the technical professionals. Hopefully the new Standard for
Infrastructure Procurement and Delivery Management issued by the National Treasury and the CIDB
prompt payment regulations (which are currently still in draft format) will solve the issue of non-payment,
which are currently one of the biggest issues Contractors and Sub-contractors are experiencing in the
construction industry.

Clause 5.14.1 has been amended and now reads as follows:


Clause 5.14.1:

Save as otherwise provided in the Contract, the The Contractor shall be entitled to receive a Certificate of
Practical Completion when the Works have reached been completed to the requirements for achieving
Practical Completion as set out in the Contract Data. When the Works are about to reach the said stage,
the Contractor shall, in writing, request a Certificate of Practical Completion and the Engineer Employers
Agent shall, within 14 days after receiving such request, issue to the Contractor a written list setting out
the work to be completed to justify Practical Completion. Should the Engineer Employers Agent not issue
such a list within 14 days, Practical Completion shall be deemed to have been taken as achieved on the
Due Completion Date; or, if a penalty is imposed in terms of Clause 5.13, on expiry of the 14 days.
If the Contractor does not request a Certificate of Practical Completion if the Works reach
Practical Completion before the Due Completion Date, Practical Completion shall be considered
achieved on the Due Completion Date.

Commentary:

As we all know Practical Completion is a contentious issue and under most contracts a dispute usually
arises as to when Practical Completion was actually achieved. The Practical Completion Date is also
usually linked to the date from when delay damages / penalties are applied.

Page 6
Fifth Edition May 2016
The drafting committee of the GCC, by making the changes highlighted above, tried to overcome any
confusion surrounding the process of Practical Completion by introducing requirements for achieving
Practical Completion and similar to the latest revision of the JBCC, trying to eliminate the never ending
snag lists by setting out the requirements for Practical Completion in the Contract Data. It further places
an obligation on the Contractor to ensure that the Contractor requests the issuing of a Practical
Completion certificate if it believes Practical Completion was achieved.

Clause 8.3.1 titled Excepted risks has been changed as per the following:
Clause 8.3.1:

The excepted risks are risks of damage or physical loss or any other loss caused by or arising directly
or indirectly as a result or consequence of:
8.3.1.1
War, invasion, act of foreign enemies, hostilities or warlike operations (whether war be
declared or not) or civil war, or imposition of economic sanctions between governments
8.3.1.2

Insurrection, rebellion or revolution, acts of terrorism or civil war

8.3.1.3
Mutiny, military uprising, military or usurped power, martial law or state of siege, or any other
event or cause which determines the proclamation or maintenance of martial law or state of siege,
8.3.1.4
Any event which, at the closing date of the tenders, is defined as a risk in terms of insurance
offered by the South African Special Risks Insurance Association, Strike, riot, commotion, disorder,
violent demonstrations, sabotage or any form of civil disturbance (whether lawful or not) which
is not attributable to any action or inaction of the employees of the Contractor or his
Subcontractors,
8.3.1.5
Any occurrence for which a fund has been established in terms of the War Damage
Insurance and Compensation Act, as amended, The confiscation, commandeering, nationalization,
requisition or destruction of or damage to property by an order of government, or any public or
local authority,
8.3.1.6
The impact of meteorites, Disconnection of electricity supply not covered by the
agreement with the supply authority,
8.3.1.7 Pressure waves caused by aircraft or other aerial devices travelling at sonic or supersonic speeds,
Epidemic famine or plague

Page 7
Fifth Edition May 2016
8.3.1.8

Ionising radiation or contamination by radioactivity from any nuclear fuel or from any nuclear waste from
the combustion of nuclear fuels, The impact of meteorites,
8.3.1.9
The use of or occupation by the Employer or his employees or agents or other contractors
(not employed by the Contractor) of any part of the Works, Pressure waves caused by aircraft, or other
aerial devices, travelling at sonic or supersonic speeds,
8.3.1.11
The confiscation, commandeering, nationalisation, requisition or destruction of or damage
to property by an order of government, or any public or local authority, The use of or occupation by the
Employer or his employees or agents or other contractors (not employed by the Contractor) of
any part of the Works,
8.3.1.12
The fact that the value of materials, as supplied by the Employer for incorporation in the
Works, exceeds the value thereof as specified by or on behalf of the Employer at the time of delivery
thereof by the Employer. The design, specification or instruction of the Employers Agent, Employer
or any of their employees or agents, or defects in the materials supplied by the Employer for
incorporation in the Works, and/or
8.3.1.13
The fact that the value of materials, as supplied by the Employer for incorporation
in the Works, exceeds the value thereof as specified by, or on behalf of the Employer, at the time
of delivery thereof by the Employer.

Commentary:

The current climate of the construction industry, i.e. the increase in strikes and power outages,
necessitated the changes set out above. Clause 9.1 that deals with termination by the Contractor was
also amended and brought in line with the excepted risks which could lead to termination.

Clause 8.3.2 titled Claim for expected risks is a new clause and provides for:
Clause 8.3.2:

If, in carrying out the Works, any of the excepted risks, other than pertaining to the damage or physical
loss referred to in Clause 8.2.2.2, causes the Contractor to suffer delay to Practical Completion and/or
brings about proven additional costs, the Contractor shall be entitled to make a claim in accordance with
Clause 10.1.

Commentary:

Previously, under the GCC 2010, claims as a result of excepted risks were unusual. This was due to
Clause 8.3 not providing for the Contractors entitlement to submit a claim as a result of the occurrence
of an excepted risk nor did Clause 8.3 refer to Clause 10.1. However, then came along all the strikes
and the Employers and Contractors were unsure how to treat a claim for costs and delay due to excepted

Page 8
Fifth Edition May 2016
risks. In the GCC 2010 it had to go through as a dissatisfaction claim which was not the way the GCC
intended to handle such entitlement claims. Now, by introducing Clause 8.3.2 a claim due to an excepted
risk became an entitlement claim (see Clause 10.1) for the Contractor.

One of the most common problems in the South African construction industry is community unrest /
interference, which are typically associated with the aims and obligations of the employer. The occurrence
of these events usually result in loss of money and disruption and / or delay to the works without proper
compensation. Under and in terms of the GCC 2010 no specific provision was made for the Contractors
entitlement to an extension of time for the practical completion date and / or additional payment or
compensation.

As a result of this it was often argued that the occurrence of such event was beyond the Contractors
control (see clause 5.12.2.4). If argued successfully, the Contractor was only entitled to an extension of
time and payment of time related P&G costs. This clause placed an onus on the Contractor to prove that
such event was beyond its control and in any event did not provide for or entitle the Contractor to
payment of its direct costs / proven additional costs.

By amending clause 8.3.1.4 the Contractor is relieved of the onus to prove that the strike, community
unrest / interference was beyond its control and of creative thinking of proving that it is entitled to
payment of additional costs (excluding P&G). The loss of money and / or time due to strikes and
community unrest / interference is no longer the Contractors risk as this amendment and the inclusion
of Clause 8.3.2 provides for a claim, due to an excepted risk, to be an entitlement claim under Clause
10.1.
This will now entitle the Contractor to not only claim an extension to the practical completion date but
will also allow the Contractor to claim additional payment / compensation (including direct costs).

Clause 10.5.4 titled Implementation of decision is a new clause and states that:
Cause 10.5.4:

The parties shall implement the Adjudication Boards decision without delay whether or not the dispute is
to be referred to arbitration or court proceedings. Payment shall be made in accordance with Clause 6.10

Page 9
Fifth Edition May 2016
in the payment certificate which becomes due after the date of issue of the decision, unless otherwise
directed by the Adjudication Board.
Commentary:

By introducing this new Clause the drafting committee enforced standard practice and again imposed
the principle of an adjudication decision being binding notwithstanding a notice of dissatisfaction. This is
inescapable as this principle has been enforced in our courts.

By reviewing and considering the changes introduced by the GCC 2015, I experienced a warm fuzzy feeling that this revision
might just be the answer. This GCC revised edition provides clarity, and simplifies and clarifies a whole lot of issues.

This edition is welcomed with open arms!