Professional Documents
Culture Documents
Lean Construction5 PDF
Lean Construction5 PDF
Downloaded from ascelibrary.org by Universidad Politecnica De Valencia on 06/16/15. Copyright ASCE. For personal use only; all rights reserved.
Introduction
Lean production is a concept that aims to systematically eliminate wastes, simplify production procedures, and speed up production Ballard 1999. This lean concept has been applied in
many other industries as well as the manufacturing industry. Consequently, a wide range of benefits have been obtained, including
1 waste reduction; 2 production cost reduction; 3 decreased
production cycle times; 4 labor reduction; 5 inventory reduction; 6 capacity increase of existing facilities; 7 higher quality;
8 higher profits; 9 higher system flexibility; and 10 improved
cash flows Kotelnikov 2006.
Recently, the lean concept has been introduced into the construction industry with varying levels of success for different
projects. However, currently there are no practical guidelines for
the application of the lean concept in the construction industry. In
many construction projects, the implementation of the lean concept is still in the experimental stage and just applies to the lean
principles as developed in the manufacturing industry without any
changes or modifications. Some changes or modifications have to
be made in order to better apply these principles in the construction industry because some lean production principles as developed and successfully adopted in the manufacturing industry may
not be equally applicable and successful in the construction in1
Lean Production
Downloaded from ascelibrary.org by Universidad Politecnica De Valencia on 06/16/15. Copyright ASCE. For personal use only; all rights reserved.
Lean Construction
Lean Construction and Its Characteristics
The process of delivering a constructed facility in the construction
industry is similar to that of making a product in the manufacturing industry. The two industries have the same goal of generating
a product that meets the clients requirements within the shortest
time and at the lowest cost. The concept of lean production was
introduced to the construction industry following its success in
the manufacturing industry. Consequently, the terminology of
lean construction was formed.
Lean construction aims to maximize the customers satisfaction through concurrent the design of both the constructed facilities and the construction process that delivers these facilities, and
through the consequent control of each stage in the construction
process. Three features distinguish the lean construction practice
from a conventional construction management practice Howell
1999. First, lean construction focuses on reducing wastes that
may exist in any format in the construction process, such as
inspection, transportation, waiting, and motion. Second, lean construction aims to reduce variability and irregularity so that material and information can flow in the system without interruptions.
Third, construction material is expected to be on site only when it
is needed.
Lean Construction Practices
Lean production principles have been applied to the construction
industry and many positive results have been achieved worldwide
in many areas of the construction industry, with enhanced value,
reduced costs, and increased customer satisfaction. For example,
Ballard and Howell 1994 achieved a 30% productivity increase
by matching labors with the workflow of backlog and by shielding direct production from upstream variation and uncertainty.
Lean principles were also deployed to improve the productivity in
installing metal wall frames and in building ganged forms for
digester tanks Halpin and Kueckmann 2002.
Downloaded from ascelibrary.org by Universidad Politecnica De Valencia on 06/16/15. Copyright ASCE. For personal use only; all rights reserved.
process. It classifies construction activities into main and supportive activities and/or into normal and interactive activities from
two different perspectives.
Main Activity and Supportive Activity
A main activity is one that directly consumes construction materials and contributes physically to the final project. On the
other hand, a supportive activity is one that supports and facilitates the execution of main activities but may not contribute
physically to the final project. Main activities have to be kept in
the construction process whereas supportive activities may not be
necessary.
Please note that the classification of main and supportive activities are relative depending on the type of project and the methods and technologies deployed to construct the project. For
example, the activity of soil transportation in an earth-moving
project may be classified as a main activity since moving soil
from one location to the other is the purpose of the project. In
contrast, the activity of material transportation in a road surface
construction project may be classified as a supportive activity
because surface pavement is the projects objective. In addition,
the main activity could change in the same project while all supportive activates may remain unchanged if a different construction method is used. For example, the main activity would change
from rolling to spraying if a spray gun is used to substitute a
roller in a wall painting project while the supportive activities
such as wall cleaning and edge taping remain the same.
This classification of activities facilitates the endeavor to reengineer the construction process for minimized wastes by examining both main and supportive activities and making appropriate
changes/modifications to part or the whole of the construction
process. For example, the duration of both main and supportive
activities may be reduced for earlier project completion and potential productivity improvement. In addition, innovative construction technologies may be applied such that, without affecting
the main activities, some supportive activities may be eliminated,
and consequently, wastes associated with these supportive activities may be avoided.
Normal Activity and Interactive Activity
An assembly line in the manufacturing industry is usually built as
a one-way pass, where a large number of parts are installed in a
sequential manner. On the contrary, a construction project is a
unique product that is often delivered through repetitive work
activities either in a chain or circular format. For example, pipe
installation is a typical chain process as pipes are laid down one
after another along a trench while a cast-in-place piling project is
conducted in a circular manner with the repetition of three major
piling activities: drilling a hole, dropping a steel cage, and pouring concrete. Sometimes, a number of circular processes need to
be done concurrently to reduce total project duration. For example, following piling activities, carpenters and labors can rough
pile heads, and form and pour pile caps so that all works related
to pile foundation are finished not too long after piling is done.
It is known that the productivity variation of a production unit
in the production system can significantly increase the productivity variation of other production units in the system that are linked
to this unit, and consequently, the variation of the whole production system. Appropriate measures need to be taken to minimize
the variation of each production unit, particularly those units that
link to other units. Therefore, it is useful to decompose the con-
Downloaded from ascelibrary.org by Universidad Politecnica De Valencia on 06/16/15. Copyright ASCE. For personal use only; all rights reserved.
template was able to quantify the impact of reducing some nonvalue-adding activities and using just-in-time delivery for the
whole road construction process.
Downloaded from ascelibrary.org by Universidad Politecnica De Valencia on 06/16/15. Copyright ASCE. For personal use only; all rights reserved.
Downloaded from ascelibrary.org by Universidad Politecnica De Valencia on 06/16/15. Copyright ASCE. For personal use only; all rights reserved.
Tunnels are built in a wide range of infrastructure systems, including sewers, highways, subways, railways, and hydroelectric
structures. Modern tunnel construction methods have been developing for almost two centuries and are still evolving. The basic
tunneling process of the tunnel boring machine TBM is illustrated in Fig. 4. The process starts from shaft excavation. At least
two shafts are needed: one access shaft located at the tunnels
starting point and one TBM retrieving shaft located at the other
end. The diameter of a working shaft varies according to the
tunnels size. An undercut area, a space for locating and assembling TBM, is required at the bottom of the access shaft. A tail
tunnel is optional and primarily used to schedule the train for
sharing a single track. Once the undercut and tail tunnel have
been constructed, the TBM is assembled in the undercut area and
aligned to start excavation. A hoisting system is required on the
top of the access shaft to transport labor, equipment, and materials
into the tunnel. A train is used to remove the spoil from the tunnel
face to the undercut area, where it will be lifted up to the ground
surface.
The tunneling operation is a circular process carrying out dozens of tasks per stroke, including excavation, spoil removal, material transportation, and liner installation. The cycle of the
tunneling process may be repeated for hundreds or even thousands of times depending on the length of the tunnel. Because of
Downloaded from ascelibrary.org by Universidad Politecnica De Valencia on 06/16/15. Copyright ASCE. For personal use only; all rights reserved.
3.
4.
Downloaded from ascelibrary.org by Universidad Politecnica De Valencia on 06/16/15. Copyright ASCE. For personal use only; all rights reserved.
Parameter
Value
Number of trains
Empty speed km/h
Loaded speed km/h
Number of dirt cars
Number of material cars
Muck car capacity m3
2
5
5
3
1
4.59
Morning duration h
Afternoon duration h
Mobilization time min
Coffee break min
Lunch break min
Demobilization time min
4
4
Uniform 10,15
Uniform 25,35
Uniform 40,50
Uniform 10,15
TBM
1
3.2
Uniform 2,4
Uniform 30,45
10
15
Beta 1.6,1.3,1.2,5.6
1.35
50
Uniform 120,180
Exponential 3,000
Uniform 60,300
Hoist
Hook up min
Lift up min
Release min
Drop down min
Dump min
Shaft depth mOption A
1
depth/40
Uniform 1,2
depth/ 40+ 0.5
Triangular 1,3,5
80
Travel
Length of tunnel m
1,225
Train
Downloaded from ascelibrary.org by Universidad Politecnica De Valencia on 06/16/15. Copyright ASCE. For personal use only; all rights reserved.
Shift controller
cut area where the muck car is unloaded. The travel element has
one input parameter, that is, the length of the tunnel. It has three
output parameters: the length of the finished tunnel, the total number of shifts in finishing the tunnel, and the average tunneling
production rate. The TBM element commences when a train arrives at the tunnel face, and a tunneling cycle is finished after the
liner installation of a full ring. To properly describe the tunneling
cycle, the following parameters are used as the input of the TBM
element: length of a tunnel unit; boring diameter; TBM resetting
time; liner installation duration; target number of sections before
extending tracks; track installation duration; TBM advance rate;
soil swell factor; duration of survey, and finished tunneling cycles
between surveys. The train element gives the SPS template flexibility to control the trains attributes. The user can decide the
number of trains to be used in tunnel construction, and the trains
empty and load speeds. In addition, the user has options to change
the number of dirt cars, the number of material cars, and the muck
cars capacity. The shift control element calculates the effective
working time. This element has six input parameters: working
duration in the morning, working duration in afternoon, duration
of mobilization, duration of demobilization, coffee break, and
lunch break. The input parameters of the five elements are summerized in Table 1.
The interactions between various resources and activities involved in VMC, TTC, and TEC are modeled in the sublayers of
Downloaded from ascelibrary.org by Universidad Politecnica De Valencia on 06/16/15. Copyright ASCE. For personal use only; all rights reserved.
tem is combined with the automated surveying system. By changing from the ribs-and-lagging liner to the bolted segmental liner,
the liner installation duration of one tunnel unit is reduced from
uniform distribution 30 and 45 min to uniform distribution 13
and 18 min. As a result, the productivity will be increased by
79% from 6.31 to 9.8 m / shift. The productivity improvement
achieved by reducing the duration of one of the two main activities of the tunneling process demonstrates the significant impact
of the time share of the main activities on the productivity of the
whole construction process. In terms of the total number of shifts
required to complete this tunnel, Option 3 only takes 125 shifts,
less than half of the total number of shifts required by the conventional process. The substantial reduction of the total construction duration represents a great cost savings and earlier utilization
of this tunnel to better serve the public.
Conclusions
Construction process reengineering may dramatically improve the
performance of the construction industry. Lean principles can be
applied in construction process reengineering. However, changes
or modifications may have to be made to some lean principles as
developed in the manufacturing industry in order to better apply
these principles in the construction industry in view of the
uniqueness of the construction industry. This paper develops a
construction process reengineering framework and corresponding
methodologies that integrate lean principles and computer simulation techniques.
Instead of classifying activities into value-adding and nonvalue-adding activities, or into conversion and flow activities, as
is common in lean production practices, this framework classifies
Option
Lining
duration
min
Conventional
Uniform
1
Uniform
2
Uniform
3
Uniform
Note: N / A = not available.
30,45
30,45
30,45
13,18
Survey
Survey
frequency
Productivity
m/shift
Productivity
increase
%
Total
shifts
Shift
decrease
%
Yes
Yes
Combined
Combined
15
15
N/A
N/A
4.42
5.72
6.31
9.80
29
43
122
277
214
194
125
0
23
30
55
Downloaded from ascelibrary.org by Universidad Politecnica De Valencia on 06/16/15. Copyright ASCE. For personal use only; all rights reserved.
References
AbouRizk, S. M., and Hajjar, D. 1998. A framework for applying
simulation in the construction industry. Can. J. Civ. Eng., 253,
604617.
Agbulos, A., and AbouRizk, S. M. 2003. An application of lean concepts and simulation for drainage operations maintenance crews.
Proc., Winter Simulation Conf., New Orleans, 15341540.
Al-Sudairi, A. A., Diekman, J. E., Songer, A. D., and Brown, H. M.
1999. Simulation of construction processes: Traditional practices
versus lean construction. Proc., 7th Int. Group for Lean Construction
Conf., Univ. of California at Berkeley, Berkeley, Calif., 3950.
Ballard, G. 1999. Improving work flow reliability. Proc. 7th Int.
Group for Lean Construction Conf., Univ. of California at Berkeley,
Berkeley, Calif., 275286.
Ballard, G., and Howell, G. 1994. Implementing lean construction:
Stabilizing work flow. Proc. 2nd Annual Meeting of the Int. Group
for Lean Construction, Santiago, Chile.
Centeno, M. A. 1996. An introduction to simulation modeling. Proc.,
Winter Simulation Conf., Coronado, Calif., 1522.
Christian, J., and Hachey, D. 1995. Effects of delay times on production rates in construction. J. Constr. Eng. Manage., 1211, 2026.