SIME DARBY PLANTATION

KERNEL CRUSHING PLANT (KCP)


PULAU CAREY, KUALA LANGAT, SELANGOR

REPORT
2
9 December- 23 DECEMBER

PROJECT NAME: WAREHOUSE RENOVATION


CONTRACTOR NAME: AKK ENGINEERING SDN BHD
PROJECT ESTIMATED TIME: 11 NOVEMBER 2013 11 MARCH 2014
CLIENT: SIME DARBY PLANTATION SDN BHD, KERNEL CRUSHING PLANT

Prepared by: Mohammad Haziq Bin Mahamad Alib


Date:23 December 2013

TABLE OF CONTENT

1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0

DESCRIPTION
SDP LAYOUT
SITE ORGARNISATION CHART
LIST OF MANPOWER AND MACHINERY
SAFETY AND HEALTH STATISTIC RECORD
INDUCTION AND TOOLBOX MEETING
MONTHLY AND WEEKLY INSPECTION
PERMIT TO WORK
EMERGENCY RESPONSE
APPENDIX

1.0

SIME DARBY PLANTATION LAYOUT

2.0

SITE ORGANISATION

SITE ORGANISATION CHART


AKK ENGINEERING SDN BHD

ANG TIONG TUCK


PROJECT MANAGER
012-7777129

ANG KEA JIN


PROJECT ENGINEER
019-7255090

FAIZ
CIVIL SUPERVISOR
012-6566065

NASRULLAH
STRUCTURE SUPERVISOR
019-7995501

LOH
ELECTRICAL SUPERVISOR
019-7128988

AUNG MYO KYAW


PROJECT EXECUTIVE
019-7103455

HAZIQ
SAFETY SUPERVISOR
017-2793169

3.0
LIST OF MANPOWER AND MACHINERY RECORD

AKK ENGINERING SDN BHD


SIME DARBY PLANTATION KCP, WAREHOUSE
MANPOWER RECORD
9 DECEMBER- 23 DECEMBER 2013

9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Manpower manager
Project manager
1
Project engineer
Project executive
Structure supervisor
Civil supervisor
1
Electrical supervisor
Safety supervisor
1
Site supervisor
1
Manpower labour
Roofer
2
Cutter & Wielder
2
Painter
2
Forklift driver
1
Scrap handler
1
Carpenter
2
Hacker
1
Crane driver
1
Boomlift operator
2
Cement worker
4
Cement lorry driver
Total
22

1 1

1 1 1 1 1 1 1

1 1
1

1 1 1
1

1 1 1

1
1

1
1

1
1

2
2
2
1
1
2
1
1
2
4

2
2
2
1
1
2
1
1
2
4

2
2
2
1
1
2
1

3
2
3
1
1
2
1

2
2
2
1
1
2
1
1
2
4

2
2
2
1
1
2
1
1
2
4

2
2
2
1
1
2
1
1
2
4

2
2
2
1
1
2
1

3
2
3
1
1
2
1

3
2
3
1
1
2
1

3 3
2 2
3 3
1 1
1 1
2 2
1 1
1
2 2 2 2 2 2 2
4 4 4 4 4 4 4
1
21 20 20 21 20 18 19 21 21 22 25 22

3
2
3
1
1
2
1

3
2
3
1
1
2
1

2 2
4 4
19 20

AKK ENGINEERING SDN BHD


SIMBE DARBY PLANTATION, KCP, WAREHOUSE
Machinery Record
9 December- 23 December 2013

Day 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

10 tonne lorry
Generator set
Skylift
Crane
Forklift
Lorry
Hand drill
Grinder
Hacking
Concrete mixer
Bar cutter
Bar bending
Circular saw
Oxy cutter
Total

2
2
1
1

2
2
1
1

2
2
1
1

2
2
1
1

2
2
1
1

2 2 2 2 2 2 2 2 2 2
2 2 3 3 3 3 3 3 3 3
1
1
1 1 1 1 1 1 1 1 1 1

1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1
1 1
2 2
5 5
18 18

1
1
2
5
18

1 1
1 1
2 2
5 5
18 18

1
1
2
5
18

1
1
2
5
17

1
1
2
5
18

1
1
2
5
18

1
1
2
5
18

1
1
2
5
18

1
1
2
5
19

1
1
2
5
18

1
1
2
5
18

1
1
2
5
18

4.0

Safety And Health Statistic Record

AKK ENGINEERING SDN BHD


SIME DARBY JOMALINA SDN BHD,KCP, WAREHOUSE

SAFETY AND HEALTH STATISTIC RECORD


9 December 23 December 2013

Description
Fatality
Lost time-injury
Total day lost
Total man hours
worked
Average workers
per day at site

Prepared by : Haziq
Date : 23/12/13

Current
3465

Previous
2904

Year-To-Date
6369

21

11

Remarks

5.0

Induction and Toolbox Meeting

5.1. Induction

5.2
Toolbox meeting

12/12/13

21/12/13

21/12/13

6.0

Monthly and Weekly Inspection

6.1 Crane and skylift

6.2 Full Body Safety Harness

6.3 Workplace

7.0
Permit to Work

7.0
Emergency Response
Evacuation Map
Emergency Response Team
Evacuation Procedure

EMERGENCY RESPONSE TEAM ORGANIZATION CHART

S&H CHAIRMAN
Ang Tiong Tuck

Team Leader
Ah Meng

Chieft of Fire Fighter

Chieft of Evacuation

Effendi

Mohd Haziq B. M. Alib

Fire fighter

Member of Evacuation

Adib

Saiful

Evacuation Procedure

SHO /Site Supervisor


Blew wiesel. Call police,
bomba and ambulance if
necessary

Ert Members
Ensure all stop work and
walk to assembly point

Foreman/Work Leader
Ensure workers assemble
and start head count

Foreman/Work Leader
Inform ERT leader total
headcount

ERT Leader
Recive reports from foreman/work leader.
Assist rescue team/report situation to police, bomba etc.
Order dismissal if situation permit

Apendixes

Report on missing item

Unsafe act & unsafe condition

10/12/13- Pekerja kontraktor dari Sime Darby menceroboh masuk ke tapak.

12/12/13- Terdapat papan lapis di atas power generator yang sedang berfungsi.

13/12/13- Pekerja memasuki tapak tanpa safety helmet.

14/12/13- Pekerja tidak menggunakan skylift untuk turun.

16/12/13- Skylift yang baru memasuki tapak diperhatikan sebelum diperiksa

17/12/13- Oxygen silinder yang kosong tidak di selenggara dengan betul.

17/12/13- Pembinaan tapak untuk kerja-kerja simen tidak bersesuaian.

18/12/13- Pekerja memakai helmet dengan cara yang salah

20/12/13- Kerja-kerja simen diteruskan walaupun hujan.

21/12/13- Hoarding yang dipasang jatuh.

23/12/13- Keadaan dalam cabin skylift tidak kemas.