The document contains comments on an EOT crane design package, listing several requirements for the crane drawings and specifications. The comments specify that the rail, wheel, and hook profiles must be shown in general arrangement drawings. Calculations must also be submitted for the main hoist, long travel, brakes, and motors. Dimensional details like rail height, floor levels, and maintenance platform size must be indicated. Safety components and temperature rise limits are addressed. Component data sheets and voltage variation parameters are also required.
The document contains comments on an EOT crane design package, listing several requirements for the crane drawings and specifications. The comments specify that the rail, wheel, and hook profiles must be shown in general arrangement drawings. Calculations must also be submitted for the main hoist, long travel, brakes, and motors. Dimensional details like rail height, floor levels, and maintenance platform size must be indicated. Safety components and temperature rise limits are addressed. Component data sheets and voltage variation parameters are also required.
The document contains comments on an EOT crane design package, listing several requirements for the crane drawings and specifications. The comments specify that the rail, wheel, and hook profiles must be shown in general arrangement drawings. Calculations must also be submitted for the main hoist, long travel, brakes, and motors. Dimensional details like rail height, floor levels, and maintenance platform size must be indicated. Safety components and temperature rise limits are addressed. Component data sheets and voltage variation parameters are also required.
(Make Century cranes) Rail, wheel & Hook profile shall be incorporated in the GA drawing. Minimum diameter of LT wheel shall be 320mm as per GTS. Drawings for Hoist arrangement & LT assembly shall be submitted. Calculations for Main hoist, Long travel, brakes and motors shall be submitted. Drawing shall be made to scale & shall be submitted in A1 size. DSL drawing shall be submitted. Creep speed shall be 10% of the main speed. End approach and side approach shall be marked in key plan of GA. These shall be verified by technology section. Fixed LT buffers location from respective column shall be indicated in the key plan of GA. Distance between Rail center line and column center line shall be shown in GA. Crane rail height shall be marked in the GA. Side view of crane in GA shall be shown with dimensions. Operating floor levels shall be indicated in the GA.
Control panels shall be mounted on access/Maintenance
platform. GA & Terminal block details of Crane panel shall be furnished. Size of maintenance platform for the crane shall be marked in GA. Pendant movement shall be independent of the movement of trolley. Length of the pendant shall be such that it does not fall short while operating from any point on the shop floor. Safety guards and covers shall be provided for all coupling. Makes of the components of the crane shall be as per RSP/MECON preferred vendors list enclosed in GTS. Design ambient temperature shall be considered as 50 0C. Temperature rise shall be limited Class B. Detail data sheet of Limit Switch shall be separately furnished. Detail data sheet of Motor shall be separately furnished. Voltage variation shall be considered as +10%,-15%.