JOINTING WORK (Procedure & Check Point)

Jointing Procedure & Check Point for 150kV XLPE :


Preparation

1) Accy Check.
2) Bending Radius > 20 times than Ds

Arrange the Cable &


Outer Jacket, AL Sheath Removing

1) Checking the insertion direction of sliding


2) No damage on the insulation layer

No.

Annealing

1) Keeping 1005, 1.5Hours

Cable Cutting

1) Perpendicular cutting to the cable axis

Removing Semi-Conductive Layer

1) No damage on the insulation layer

Exposing the Cable Conductor &


Polishing the XLPE Insulation

1) No scrape/nick on the conductor


2) Round Sanding not particular one side

Grooving XLPE Insulation &


Compressing Conductor Sleeve (long side)

1) Checking the dimension of outer ins.


2) Checking the elongation of sleeve

No.
1

No.

No.
4
No.
5
No.
6

No.
7

JOINTING WORK (Procedure & Check Point)


Jointing Procedure & Check Point for 150kV XLPE (continued) :

No.

Expanding the Pre-molded unit &


Preparing the assembling parts

1) Checking the insertion direction of sliding


2) No damage on the insulation layer

Compressing Conductor Sleeve &


Grooving XLPE Insulation (short side)

1) Checking the elongation of sleeve


2) Checking the dimension of outer ins.

No.

Assembling the corona shield

1) Comparison with outer diameter of corona


shield and insulation

Setting the unit &


Wrapping the tape

1) Applications direction of silicon grease


2) Wrapping the tape without gap

Setting the case &


Making anti corrosion layer

1) Paying attention to make anti corrosion


layer

No.

10

No.
11

No.
12