ENMAS O & M SERVICES PRIVATE

LIMITED
TULSYAN NEC POWER LIMITED GUMMIDIPOONDI
35 MW CAPTIVE POWER PLANT
TRIP /BREAK DOWN REPORT ON 04/10/2014
Name of the equipment Tripped/Break
down
Date of Trip /Break down

TG
04.10.2014

Time of Trip/ Break down

11:20 Hrs & 13.45 Hrs

Re- Star/ Synchronizing time

12:20 Hrs & 14.15 Hrs

Loss time

01:30 Hrs

Reason for Trip/Break down

TG tripped due to UAT over current trip, At 13.45 PM GT breaker manually


opened due to LAPT core-1 R Phase Metering PT supply failure

Analysis
1. Informed to EB about to maintain the voltage ,LAPT R phase PT racked out, cleaned
and inserted, tightness checked
Conclusion
1. At 12.20 PM plant synchronized with grid at the same time GRP-1 R phase metering
PT supply not came, so that LAPT R phase PT racked out, cleaned and inserted,
tightness checked ,then PT supply came
.