Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 287

Gulf Contracting Co.

WLL
Barzan Onshore Project, Package#2 [EPC BUILDING WORKS]
Site Weekly QA/QC Metrics
Period :

From:

22-Nov-2011

29-Nov-2011

To:

Rep. No.:

"Leading" Indicators

"Lagging" Indicators

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)
Planned as of

Actual as of

NCR Status (Non-Conformance Report)


Items

Plan

Actual

GCC

Total NCR Issued

FQC Manager

Total NCR Closed

DFQC Manager

Total NCR Open

Sr.QA/QC Engineer

QA Engineer

QC Inspectors

CQCE

In Vacation

Document controller

In Vacation

Total NCR Issued (This Week)


1

3(&3 in vacation)

Quality Audits
Item
Scheduled

Audit Findings (*)

Date

Discipline

20th Dec 2011

Internal Audit

Completed

CAR

OBS

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR SR Status
(Surveillance Report)

CTR CAR Status


(Corrective Action Request)

Total SR Issued

Total CAR Issued

Open

Total SR Closed

Total CAR Closed

Total SR Open

Total CAR Open

Total CAR Issued


(This Week)

Findings

Closed

Civil works control assessment

Open

Total SR Issued
(This Week)

SDR status (Specification Deviation Request)


CPY SDR

GCC SDR

Other S/C SDR

MEP - 2

Total SDR Approved

Nil

Nil

Nil

Total SDR Rejected

Nil

Nil

Nil

Total SDR Closed

Nil

Nil

Nil

Items
Total SDR Issued

Conducted
this Week

Total DR Issued

Closed

Assessment Title

Total No. of
Assessment

Total CAR Issued

Balance :
CPY Q & IM Assessment

CPY CAR Status

CPY DR Status
(Deficiency Report)

Total :

Completed:

C/list No.

GCC

Status in
brief
Issued

Cumulative :

S/C

NCR Status (Non-Conformance Report)

In Vacation

DFO Co-ordinator
TOTAL

WQM-GCC-001

Cumulative to Date Deficient (Red)

Concern (Amber)

Satisfactory
(Green)

Status of Deliverables (PQP/QCP/ITP/MS)


GCC

No. of
Deliverables

Documents

Submitted

Approved

GCC
GCC
GCC

1
45
1

PQP
ITP
QCP

1
2

1
0

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk
Discipline

Score (%)

Score (%)

This Period

Last Period

85.00%

N/A

Civil

% Difference

Items
Action Required
Yes

0.0

No

Remarks

Accepted

Rejected

Cancelled

Resched.

Issued This Week

16

JGC Witnessed

16

CPY Witnessed
Document For Operation (DFO)
DFO Complete as of

Q&IM Training (*)


Item

Cumulative
Date

Scheduled

18 Oct. 2011

Completed

08 Oct. 2011

Barzan on shore project

0%

Total

Completed

Balance

Nil

QA/QC Highlights

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2 [EPC BUILDING WORKS]
Site Weekly QA/QC Metrics
Period :

From:

30-Nov-2011

06-Nov-2011

To:

Rep. No.:

"Leading" Indicators

"Lagging" Indicators

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)
Planned as of

Actual as of

NCR Status (Non-Conformance Report)


Items

Plan

Actual

GCC

Total NCR Issued

FQC Manager

Total NCR Closed

DFQC Manager

Total NCR Open

Sr.QA/QC Engineer

QA Engineer

QC Inspectors

CQCE

Document controller

Total NCR Issued (This Week)

6(&1 in vacation)

Quality Audits
Item
Scheduled

Audit Findings (*)

Date

Discipline

20th Dec 2011

Internal Audit

Completed

CAR

OBS

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR SR Status
(Surveillance Report)

CTR CAR Status


(Corrective Action Request)

Closed

Total SR Issued

Total CAR Issued

Balance :

Open

Total SR Closed

Total CAR Closed

Total SR Open

Total CAR Open

Total CAR Issued


(This Week)

CPY Q & IM Assessment

Assessment Title

Findings

Closed

Civil works control assessment

Open

Total SR Issued
(This Week)

SDR status (Specification Deviation Request)


CPY SDR

GCC SDR

Other S/C SDR

MEP - 2

Total SDR Approved

Nil

Nil

Nil

Total SDR Rejected

Nil

Nil

Nil

Total SDR Closed

Nil

Nil

Nil

Items
Total SDR Issued

Total No. of
Assessment

Conducted
this Week

Total DR Issued

Total :

Completed:

C/list No.

CPY CAR Status


Total CAR Issued

GCC

Status in
brief
Issued

Cumulative :

CPY DR Status
(Deficiency Report)

In Vacation

S/C

NCR Status (Non-Conformance Report)

DFO Co-ordinator
TOTAL

WQM-GCC-002

Cumulative to Date Deficient (Red)

Satisfactory
(Green)

Concern (Amber)

Status of Deliverables (PQP/QCP/ITP/MS)


GCC

No. of
Deliverables

Documents

Submitted

Approved

GCC
GCC
GCC

1
45
1

PQP
ITP
QCP

1
3
1

1
2
Review

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk
Discipline

Score (%)

Score (%)

This Period

Last Period

88.00%

85.00%

Civil

% Difference

Items
Action Required
Yes

3.0

Remarks

No

Improvement

Accepted

Rejected

Cancelled

Issued This Week

20

JGC Witnessed

20

CPY Witnessed
Document For Operation (DFO)
DFO Complete as of
QA/QC Highlights

0%

1. NCR-02 to be resolved.
Q&IM Training (*)
Item

Cumulative
Date

Scheduled

18 Oct. 2011

Completed

08 Oct. 2011

Barzan on shore project - Building works - Package#2

Total

Completed

Balance

Nil

Weekly Quality Metrics

Resched.

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2 [EPC BUILDING WORKS]
Site Weekly QA/QC Metrics
Period :

From:

07-Dec-2011

13-Dec-2011

To:

Rep. No.:

"Leading" Indicators

"Lagging" Indicators

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)
Planned as of

Actual as of

NCR Status (Non-Conformance Report)


Items

Plan

Actual

GCC

Total NCR Issued

FQC Manager

Total NCR Closed

DFQC Manager

Total NCR Open

Sr.QA/QC Engineer

QA Engineer

QC Inspectors

CQCE

Document controller

Total NCR Issued (This Week)

6(&1 in vacation)

Quality Audits
Item
Scheduled

Audit Findings (*)

Date

Discipline

15th Jan 2011

Internal Audit

Completed

0
CPY CAR Status

CPY DR Status
(Deficiency Report)

In Vacation

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

GCC

Status in
brief

CAR

OBS

CTR CAR Status


(Corrective Action Request)

Closed

Total CAR Issued

Balance :

Open

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

CPY Q & IM Assessment

Assessment Title

Findings

Closed

Civil works control assessment

Open

SDR status (Specification Deviation Request)


CPY SDR

GCC SDR

Other S/C SDR

MEP - 2

Total SDR Approved

Nil

Nil

Nil

Total SDR Rejected

Nil

Nil

Nil

Total SDR Closed

Nil

Nil

Nil

Items
Total SDR Issued

Total No. of
Assessment

Conducted
this Week

Total :

Completed:

C/list No.

Total CAR Issued

Total DR Issued

Issued

Cumulative :

S/C

NCR Status (Non-Conformance Report)

DFO Co-ordinator
TOTAL

WQM-GCC-003

Cumulative to Date Deficient (Red)

Satisfactory
(Green)

Concern (Amber)

Status of Deliverables (PQP/QCP/ITP/MS)


GCC

No. of
Deliverables

Documents

Submitted

Approved

GCC
GCC
GCC

1
45
1

PQP
ITP
QCP

1
6
1

1
0
1

ITP's

3 on MEP & 3 on Civil/Arch.

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk
Discipline

Score (%)

This Period

Last Period

88.00%

85.00%

3.0

Improvement

92.5 & 88%

88.0

2.0

Improvement

Civil(C300)
Civil(C300 &
C200)

Items

Score (%)

% Difference

Action Required
Yes

Remarks

No

Accepted

Rejected

Cancelled

Resched.

Issued This Week

29

27

JGC Witnessed

27

27

CPY Witnessed
Document For Operation (DFO)
DFO Complete as of
QA/QC Highlights

0%

1. NCR-02 to be resolved.
Q&IM Training (*)
Item

Cumulative
Date

Scheduled

18 Oct. 2011

Completed

08 Oct. 2011

Barzan on shore project - Building works - Package#2

2. Discipline training on concrete scheduled on 15/12/11

Total

Completed

Balance

Nil

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2 [EPC BUILDING WORKS]
Site Weekly QA/QC Metrics
Period :

From:

14-Dec-2011

20-Dec-2011

To:

Rep. No.:

"Leading" Indicators

"Lagging" Indicators

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)
Planned as of

Actual as of

NCR Status (Non-Conformance Report)


Items

Plan

Actual

GCC

Total NCR Issued

FQC Manager

Total NCR Closed

DFQC Manager

Total NCR Open

Sr.QA/QC Engineer

QA Engineer

QC Inspectors

CQCE

Document controller

Total NCR Issued (This Week)

Quality Audits

Scheduled

Date

Discipline

15th Jan 2011

Internal Audit

CPY CAR Status

Completed:

Total CAR Closed

Total DR Closed

Total CAR Open

6(&1 in vacation)

Total DR Open

Audit Findings (*)

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

GCC
CAR

OBS

CTR CAR Status


(Corrective Action Request)

Total :

Closed

Total CAR Issued

Balance :

Open

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

CPY Q & IM Assessment


C/list No.
1

Assessment Title

Findings

Closed

Civil works control assessment

Open

SDR status (Specification Deviation Request)


Items

CPY SDR

GCC SDR

Other S/C SDR

MEP - 2

Total SDR Approved

Nil

Nil

Nil

Total SDR Rejected

Nil

Nil

Nil

Total SDR Closed

Nil

Nil

Nil

Total SDR Issued

Total No. of
Assessment

Issued

Cumulative :

Total CAR Issued

Total DR Issued

Status in
brief

Completed

CPY DR Status
(Deficiency Report)

In Vacation

Item

S/C

NCR Status (Non-Conformance Report)

DFO Co-ordinator
TOTAL

WQM-GCC-004

Conducted this
Cumulative to Date Deficient (Red)
Week

Concern (Amber) Satisfactory (Green)

Discipline Trainings (In next 6 months)


Item

Status of Deliverables (PQP/QCP/ITP/MS)

Cumulative

Date

Scheduled

Total

Completed

Balance

22 Dec. 2011

Completed

GCC

No. of
Deliverables

Documents

Submitted

Approved

GCC
GCC
GCC

1
45
1

PQP
ITP
QCP

1
6
1

1
2
1

ITP's

3 on MEP & 3 on Civil/Arch.

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

Civil(C300)

89.00%

85.00%

4.0

Improvement

Civil(C300 & C200)

92.50%

89.0

3.5

Improvement

Civil(C300 & C200)

87.00%

92.5

4.5

Discipline

% Difference

Action Required
Yes

Remarks

No

Issued This Week


JGC Witnessed

25

Accepted

Rejected

Cancelled

Resched.

23

23

CPY Witnessed
Document For Operation (DFO)
DFO Complete as of
QA/QC Highlights

0%

1. NCR-02 is closed.

Civil(C300 & C200)

Quality awareness Training (*)


Item

Cumulative
Date

Scheduled

18 Oct. 2011

Completed

08 Oct. 2011

Barzan on shore project - Building works - Package#2

2. Discipline training on EARTHWORKS scheduled on 22/12/11

Total

Completed

Balance

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2 [EPC BUILDING WORKS]
Site Weekly QA/QC Metrics
Period :

From:

21-Dec-2011

27-Dec-2011

To:

Rep. No.:

"Leading" Indicators

"Lagging" Indicators

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)
Planned as of

Actual as of

NCR Status (Non-Conformance Report)


Items

Plan

Actual

GCC

Total NCR Issued

FQC Manager

Total NCR Closed

DFQC Manager

Total NCR Open

Sr.QA/QC Engineer

QA Engineer

QC Inspectors

CQCE

Document controller

Total NCR Issued (This Week)

Scheduled

Audit Findings (*)

Date

Discipline

15th Jan 2011

Internal Audit

CPY CAR Status

Completed:

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CAR

OBS

CTR CAR Status


(Corrective Action Request)

Total :

Closed

Total CAR Issued

Balance :

Open

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

CPY Q & IM Assessment


C/list No.
1

Assessment Title

Findings

Closed

Civil works control assessment

Open

SDR status (Specification Deviation Request)


Items

CPY SDR

GCC SDR

Other S/C SDR

MEP - 2

Total SDR Approved

Nil

Nil

Nil

Total SDR Rejected

Nil

Nil

Nil

Total SDR Closed

Nil

Nil

Nil

Total SDR Issued

Total No. of
Assessment

Total DR Issued

Issued

Cumulative :

Total CAR Issued

GCC

Status in
brief

Completed

CPY DR Status
(Deficiency Report)

Quality Audits
Item

S/C

NCR Status (Non-Conformance Report)

DFO Co-ordinator
TOTAL

WQM-GCC-005

Conducted this
Cumulative to Date Deficient (Red)
Week

Concern (Amber) Satisfactory (Green)

Discipline Trainings (In next 6 months)


Item

Status of Deliverables (PQP/QCP/ITP/MS)

Cumulative

Date

Scheduled

Total

Completed

Balance

22 Dec. 2011

Completed

GCC

No. of
Deliverables

Documents

Submitted

Approved

GCC
GCC
GCC

1
45
1

PQP
ITP
QCP

1
6
1

1
2
1

ITP's

3 on MEP & 3 on Civil/Arch.

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

Civil(C300)

89.00%

85.00%

4.0

Improvement

Civil(C300 & C200)

92.50%

89.0

3.5

Improvement

Civil(C300 & C200)

87.00%

92.5

4.5

Civil(C300 & C200)

92.00%

87.0

5.0

Discipline

% Difference

Action Required
Yes

Scheduled

18 Oct. 2011

Completed

08 Oct. 2011

Barzan on shore project - Building works - Package#2

Accepted

Rejected

Cancelled

Resched.

46

46

Document For Operation (DFO)


0%

1. NCR-02 is closed.

Improvement

47

CPY Witnessed

Cumulative
Date

JGC Witnessed

DFO Complete as of
QA/QC Highlights

Quality awareness Training (*)


Item

Remarks

No

Issued This Week

2. Discipline training on EARTHWORKS completed on 22/12/11

Total

Completed

Balance

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2 [EPC BUILDING WORKS]
Site Weekly QA/QC Metrics
Period :

From:

28-Dec-2011

03-Jan-2012

To:

Rep. No.:

"Leading" Indicators

"Lagging" Indicators

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)
Planned as of

Actual as of

NCR Status (Non-Conformance Report)


Items

Plan

Actual

GCC

Total NCR Issued

FQC Manager

Total NCR Closed

DFQC Manager

Total NCR Open

Sr.QA/QC Engineer

QA Engineer

QC Inspectors

CQCE

Document controller

Total NCR Issued (This Week)

Scheduled

Audit Findings (*)

Date

Discipline

15 & 16 th Jan 2011

Internal Audit

CPY CAR Status

Completed:

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CAR

OBS

CTR CAR Status


(Corrective Action Request)

Total :

Closed

Total CAR Issued

Balance :

Open

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

CPY Q & IM Assessment


C/list No.
1
Total No. of
Assessment

Assessment Title

Findings

Civil works control assessment

Closed

Open

Conducted this
Cumulative to Date Deficient (Red)
Week

Total DR Issued

Issued

Cumulative :

Total CAR Issued

GCC

Status in
brief

Completed

CPY DR Status
(Deficiency Report)

Quality Audits
Item

S/C

NCR Status (Non-Conformance Report)

DFO Co-ordinator
TOTAL

WQM-GCC-006

Concern (Amber) Satisfactory (Green)

Status of Deliverables (PQP/QCP/ITP/MS)


GCC

No. of
Deliverables

Documents

Submitted

Approved

GCC
GCC
GCC

1
45
1

PQP
ITP
QCP

1
8
1

1
3
1

5 on MEP & 3 on Civil/Arch.

ITP's

SDR status (Specification Deviation Request)


CPY SDR
0

GCC SDR
1

Other S/C SDR

Total SDR Approved

Nil

Nil

Nil

Total SDR Rejected

Nil

Nil

Nil

Total SDR Closed

Nil

Nil

Nil

Items
Total SDR Issued

MEP - 2

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk
Score (%)

Score (%)

This Period

Last Period

Civil(C300)

92.50%

89.00%

3.5

Civil(C300 & C200)

87.00%

92.5

5.5

Civil(C300 &
B200,C200)

92 & 92%

87.0

Civil(C300 &
B200,C200)

90 & 85.5%

92 & 92

Discipline

% Difference

Items
Action Required
Yes

Improvement

5.0

Improvement

5.0

Improvement

Scheduled

18 Oct. 2011

Completed

08 Oct. 2011

Rejected

Cancelled

Resched.

49

49

0%

1. NCR-02 is closed.
2. Discipline training on EARTHWORKS completed on 29/12/11

Completed

Balance

Total

Completed

Balance

Cumulative
Date

Scheduled

29-Dec-2011

Completed

29-Dec-2011

Barzan on shore project - Building works - Package#2

Accepted

Document For Operation (DFO)


DFO Complete as of
QA/QC Highlights

Total

Discipline Training (*)


Item

50

CPY Witnessed

Cumulative
Date

JGC Witnessed

Quality awareness Training (*)


Item

Remarks

No

Issued This Week

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

04-Jan-2012

10-Jan-2012

To:

Rep. No.:

"Leading" Indicators

"Lagging" Indicators

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)
Planned as of

Actual as of

NCR Status (Non-Conformance Report)


Items

Plan

Actual

GCC

Total NCR Issued

FQC Manager

Total NCR Closed

DFQC Manager

Total NCR Open

Sr.QA/QC Engineer

QA Engineer

QC Inspectors

CQCE

Document controller

Total NCR Issued (This Week)

Scheduled

Audit Findings (*)

Date

Discipline

22 & 23 rd Jan 2011

Internal Audit

CPY CAR Status

Completed:

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CAR

OBS

CTR CAR Status


(Corrective Action Request)

Total :

Closed

Total CAR Issued

Balance :

Open

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

CPY Q & IM Assessment


C/list No.
1

Assessment Title

Findings

Civil works control assessment

Total No. of
Assessment

Conducted this
Week

Total DR Issued

Issued

Cumulative :

Total CAR Issued

GCC

Status in
brief

Completed

CPY DR Status
(Deficiency Report)

Quality Audits
Item

S/C

NCR Status (Non-Conformance Report)

DFO Co-ordinator
TOTAL

WQM-GCC-007

Closed

Open

Cumulative to Date Deficient (Red)

Concern (Amber) Satisfactory (Green)

Status of Deliverables (PQP/QCP/ITP/MS)


GCC

No. of
Deliverables

Documents

Submitted

Approved

GCC
GCC
GCC

1
45
1

PQP
ITP
QCP

1
8
1

1
3
0

5 on MEP & 3 on Civil/Arch.

ITP's

SDR status (Specification Deviation Request)


CPY SDR
0

GCC SDR
1

Other S/C SDR

Total SDR Approved

Nil

Nil

Nil

Total SDR Rejected

Nil

Nil

Nil

Total SDR Closed

Nil

Nil

Nil

Items
Total SDR Issued

MEP - 2

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

Civil(C300 & C200)

87.00%

92.50%

5.5

Civil(C300 & C200)

92 & 92%

87.0

5.0

Civil(C300 &
B200,C200)

90 & 85.5%

92 & 92

4.0

Civil(C300 &
B200,C200)

90 & 91.4%

90 & 85.5%

2.5

Discipline

% Difference

Action Required
Yes

Quality awareness Training (*)


Item

11 Jan. 2012

Completed

Scheduled
Completed
Barzan on shore project - Building works - Package#2

JGC Witnessed

Accepted

Rejected

Cancelled

Resched.

42

42

CPY Witnessed
Document For Operation (DFO)
DFO Complete as of
QA/QC Highlights

Total

Completed

Balance

Total

Completed

Balance

Discipline Training (*)


Item

Remarks

42

0%

Cumulative
Date

Scheduled

No

Issued This Week

Cumulative
Date
22-Feb-2012

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

11-Jan-2012

17-Jan-2012

To:

Rep. No.:

"Leading" Indicators

"Lagging" Indicators

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)
Planned as of

Actual as of

NCR Status (Non-Conformance Report)


Items

Plan

Actual

GCC

Total NCR Issued

FQC Manager

Total NCR Closed

DFQC Manager

Total NCR Open

Sr.QA/QC Engineer

QA Engineer

QC Inspectors

CQCE

Document controller

Total NCR Issued (This Week)

Scheduled

Audit Findings (*)

Date

Discipline

22 & 23 rd Jan 2011

Internal Audit

CPY CAR Status

Completed:

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CAR

OBS

CTR CAR Status


(Corrective Action Request)

Total :

Closed

Total CAR Issued

Balance :

Open

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

CPY Q & IM Assessment

Total DR Issued

Issued

Cumulative :

C/list No.

Total CAR Issued

GCC

Status in
brief

Completed

CPY DR Status
(Deficiency Report)

Quality Audits
Item

S/C

NCR Status (Non-Conformance Report)

DFO Co-ordinator
TOTAL

Assessment Title

Findings

Civil works control assessment

Total No. of
Assessment

Conducted this
Week

WQM-GCC-008

Closed

Open

Cumulative to Date Deficient (Red)

Concern (Amber) Satisfactory (Green)

Status of Deliverables (PQP/QCP/ITP/MS)


GCC

No. of
Deliverables

Documents

Submitted

Approved

GCC
GCC
GCC

1
45
1

PQP
ITP
QCP

1
8
1

1
3
0

SDR status (Specification Deviation Request)


GCC SDR
1

Items
Total SDR Issued

MEP - 1

Total SDR Approved

Total SDR Rejected

Nil

Nil

Nil

Nil

Total SDR Cancelled


5 on MEP & 3 on Civil/Arch.

ITP's

Other S/C SDR

Total SDR Closed

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

Civil(C300 & C200)

92 & 92%

87.00%

5.0

Civil(C300 & C200)

90 & 85.5%

92 & 92%

4.0

Discipline

Civil(C300 &
B200,C200)

% Difference

90 & 91.4%

90 & 85.5%

2.0

89 & 90%

90 & 91.4%

1.0

Civil(C300 &
B200,C200)

Action Required
Yes

Scheduled

11-Mar-2012

Completed

Scheduled
Completed
Barzan on shore project - Building works - Package#2

Accepted

Rejected

Cancelled

Resched.

47

47

Document For Operation (DFO)


0%

6 set's of NITOCOTE ET402 curing compound applied cubes

were crushed and found results unsatisfactory & inconsistent.

Total

Completed

Balance

Total

Completed

Balance

Discipline Training (*)


Item

JGC Witnessed

52

DFO Complete as of
QA/QC Highlights

Cumulative
Date

Issued This Week


CPY Witnessed

Quality awareness Training (*)


Item

No

Remarks

(Note : Trail cubes)

Cumulative
Date
22-Feb-2012

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

18-Jan-2012

24-Jan-2012

To:

Rep. No.:

"Leading" Indicators

"Lagging" Indicators

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)
Planned as of

Actual as of

NCR Status (Non-Conformance Report)


Items

Plan

Actual

GCC

Total NCR Issued

FQC Manager

Total NCR Closed

DFQC Manager

Total NCR Open

Sr.QA/QC Engineer

QA Engineer

QC Inspectors

CQCE

Document controller

Total NCR Issued (This Week)

Audit Findings (*)

Date

Discipline

Scheduled

22 & 23 rd Jan 2011

Internal Audit

Completed

22 & 23 Jan 11

Completed:

CPY CAR Status

CAR

Total :

Closed

Balance :

Open

C/list No.
1

Findings

Civil works control assessment

Total No. of
Assessment

Conducted this
Week

Total DR Issued

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

OBS

CTR CAR Status


(Corrective Action Request)

Audit report
awaited.

CPY Q & IM Assessment


Assessment Title

Total CAR Issued

GCC

Status in
brief
Issued

Cumulative :

CPY DR Status
(Deficiency Report)

Quality Audits
Item

S/C

NCR Status (Non-Conformance Report)

DFO Co-ordinator
TOTAL

WQM-GCC-009

Closed

Open

Total CAR Issued

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

Cumulative to Date Deficient (Red)

Concern (Amber) Satisfactory (Green)

Status of Deliverables (PQP/QCP/ITP/MS)


GCC

No. of
Deliverables

Documents

Submitted

Approved

GCC
GCC
GCC

1
45
1

PQP
ITP
QCP

1
8
1

1
3
0

SDR status (Specification Deviation Request)


GCC SDR
2

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Nil

Nil

Items
Total SDR Issued

Total SDR Cancelled


5 on MEP & 3 on Civil/Arch.

ITP's

Total SDR Closed

MEP - 4

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

Civil(C300 & C200)

90 & 85.5%

92 & 92%

4.0

Civil(C300 & C200)

90 & 91.4%

90 & 85.5%

2.0

Discipline

Civil(C300 &
B200,C200)
Civil(C300 &
B200,C200)

% Difference

89 & 90%

90 & 91.4%

1.0

90 & 92 %

89 & 90%

1.0

Action Required
Yes

Item

Date

Completed

Completed
Barzan on shore project - Building works - Package#2

Accepted

Rejected

Cancelled

Resched.

47

47

Document For Operation (DFO)


DFO Complete as of
QA/QC Highlights

0%

Total

Completed

Balance

Total

Completed

Balance

Discipline Training (*)


Scheduled

JGC Witnessed

48

Cumulative

11-Mar-2012

Item

Issued This Week


CPY Witnessed

Quality awareness Training (*)


Scheduled

No

Remarks

Cumulative
Date
22-Feb-2012

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

25-Jan-2012

31-Jan-2012

To:

Rep. No.:

"Leading" Indicators

"Lagging" Indicators

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)
Planned as of

Actual as of

NCR Status (Non-Conformance Report)


Items

Plan

Actual

GCC

Total NCR Issued

FQC Manager

Total NCR Closed

DFQC Manager

Total NCR Open

Sr.QA/QC Engineer

QA Engineer

QC Inspectors

CQCE

Document controller

Total NCR Issued (This Week)

Audit Findings (*)

Date

Discipline

Scheduled

22 & 23 rd Jan 2011

Internal Audit

Completed

22 & 23 Jan 11
Total :

Completed: 01

Balance :

CPY CAR Status

CAR

OBS

Open

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

CPY Q & IM Assessment


C/list No.
1

Assessment Title

Findings

Civil works control assessment

Total No. of
Assessment

Conducted this
Week

Total DR Issued

Closed
7

Total CAR Issued

GCC

Status in
brief
Issued

Cumulative :

CPY DR Status
(Deficiency Report)

Quality Audits
Item

S/C

NCR Status (Non-Conformance Report)

DFO Co-ordinator
TOTAL

WQM-GCC-010

Closed

Open

Total CAR Issued

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

Cumulative to Date Deficient (Red)

Concern (Amber) Satisfactory (Green)

Status of Deliverables (PQP/QCP/ITP/MS)


GCC

No. of
Deliverables

Documents

Submitted

Approved

GCC
GCC
GCC

1
45
1

PQP
ITP
QCP

1
8
1

1
3
1

SDR status (Specification Deviation Request)


GCC SDR
2

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Nil

Nil

Items
Total SDR Issued

Total SDR Cancelled


5 on MEP & 3 on Civil/Arch.

ITP's

Total SDR Closed

MEP - 4

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

Civil(C300 & C200)

90 & 91.4%

90 & 85.5%

2.0

Civil(C300 & C200)

89 & 90%

90 & 91.4%

1.0

Discipline

Civil(C300 &
B200,C200)
Civil(C300 &
B200,C200)

% Difference

90 & 92 %

89 & 90%

1.0

89 & 92.5%

90 & 92 %

1.0

Action Required
Yes

11-Mar-2012

Completed

Scheduled
Completed
Barzan on shore project - Building works - Package#2

Accepted

Rejected

Cancelled

Resched.

41

41

Document For Operation (DFO)


DFO Complete as of
QA/QC Highlights

0%

Total

Completed

Balance

Total Trained

30

Total

Completed

Balance

Total Trained

39

Discipline Training (*)


Item

JGC Witnessed

50

Cumulative
Date

Scheduled

Issued This Week


CPY Witnessed

Quality awareness Training (*)


Item

No

Remarks

Cumulative
Date
22-Feb-2012

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

01-Feb-2012

07-Feb-2012

To:

Rep. No.:

"Leading" Indicators

"Lagging" Indicators

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)
Planned as of

Actual as of

WQM-GCC-011

NCR Status (Non-Conformance Report)


Items

Plan

Actual

GCC

S/C

Total NCR Issued

FQC Manager

Total NCR Closed

DFQC Manager

Total NCR Open

Sr.QA/QC Engineer

Total NCR Issued (This Week)

QA Engineer

QC Inspectors

CQCE

Document controller

Total DR Issued

QA/QC Trainer & DFO Co-ordinator

TOTAL

11

10

Quality Audits
Item

Discipline

Scheduled

22 & 23 rd Jan 2011

Internal Audit

Completed

22 & 23 Jan 11

Completed: 01

Balance :

CAR

OBS

Closed
7

Total CAR Issued

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

GCC

Status in
brief
Issued

Total :

CPY CAR Status

CPY DR Status
(Deficiency Report)

Audit Findings (*)

Date

Cumulative :

NCR Status (Non-Conformance Report)

Open

CTR CAR Status


(Corrective Action Request)

Total CAR Issued

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

CPY Q & IM Assessment


C/list No.
1

Assessment Title

Findings

Civil works control assessment

Total No. of
Assessment

Conducted this
Week

Closed

Open

Cumulative to Date Deficient (Red)

Concern (Amber) Satisfactory (Green)

Status of Deliverables (PQP/QCP/ITP/MS)


GCC

No. of
Deliverables

Documents

Submitted

Approved

GCC
GCC
GCC

1
45
1

PQP
ITP
QCP

1
8
1

1
3
1

SDR status (Specification Deviation Request)


GCC SDR
2

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Nil

Nil

Items
Total SDR Issued

Total SDR Cancelled


5 on MEP & 3 on Civil/Arch.

ITP's

Total SDR Closed

MEP - 4

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

Civil(C300 & C200)

89 & 90%

90 & 91.4%

1.0

Civil(C300 & C200)

90 & 92 %

89 & 90%

1.0

Discipline

Civil(C300 &
B200,C200)
Civil(C300 &
B200,C200)

% Difference

89 & 92.5%

90 & 92 %

1.0

88 & 93.33%

89 & 92.5%

1.0

Action Required
Yes

11-Mar-2012

Completed

Scheduled
Completed
Barzan on shore project - Building works - Package#2

Accepted

Rejected

Cancelled

Resched.

35

35

Document For Operation (DFO)


DFO Complete as of
QA/QC Highlights

0%

Total

Completed

Balance

Total Trained

30

Total

Completed

Balance

Total Trained

39

Discipline Training (*)


Item

JGC Witnessed

47

Cumulative
Date

Scheduled

Issued This Week


CPY Witnessed

Quality awareness Training (*)


Item

No

Remarks

Cumulative
Date
22-Feb-2012

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

08-Feb-2012

14-Feb-2012

To:

Rep. No.:

"Leading" Indicators

"Lagging" Indicators

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)
Planned as of

11

Actual as of

10

WQM-GCC-012

NCR Status (Non-Conformance Report)


Items

Plan

Actual

GCC

S/C

Total NCR Issued

FQC Manager

Total NCR Closed

DFQC Manager

Total NCR Open

Sr.QA/QC Engineer

Total NCR Issued (This Week)

QA Engineer

QC Inspectors

CQCE

Document controller

Total DR Issued

QA/QC Trainer & DFO Co-ordinator

TOTAL

11

10

Quality Audits
Item
Scheduled

Discipline

13 & 14th Mar 2012

Next Internal Audit

Completed
Total :

Completed: 01

Balance :

CPY CAR Status

CPY DR Status
(Deficiency Report)

Audit Findings (*)

Date

Cumulative :

NCR Status (Non-Conformance Report)


Total CAR Issued

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

GCC

Status in
brief

CAR

OBS

Issued

Closed

Total CAR Issued

Open

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

CTR CAR Status


(Corrective Action Request)

CPY Q & IM Assessment


C/list No.
1

Assessment Title

Findings

Civil works control assessment

Total No. of
Assessment

Conducted this
Week

Closed

Open

Cumulative to Date Deficient (Red)

Concern (Amber) Satisfactory (Green)

Status of Deliverables (PQP/QCP/ITP/MS)


GCC

No. of
Deliverables

Documents

Submitted

Approved

GCC
GCC
GCC

1
45
1

PQP
ITP
QCP

1
12
1

1
5
1

SDR status (Specification Deviation Request)


GCC SDR
2

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Nil

Nil

Items
Total SDR Issued

Total SDR Cancelled


5 on MEP & 7 on Civil/Arch.

ITP's

Total SDR Closed

MEP - 4

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk
Score (%)

Score (%)

This Period

Last Period

Civil(C300 & C200)

90 & 92 %

89 & 90%

1.0

Civil(C300 & C200)

89 & 92.5%

90 & 92 %

1.0

Discipline

Civil(C300 &
B200,C200)
Civil(C300 &
B200,C200)

% Difference

88 & 93.33%

89 & 92.5%

1.0

87 & 92.5%

88 & 93.33%

1.0

Action Required
Yes

11-Mar-2012

Completed

Scheduled
Completed
Barzan on shore project - Building works - Package#2

Accepted

Rejected

Cancelled

Resched.

50

45

JGC Witnessed

45

CPY Witnessed

17

Document For Operation (DFO)


DFO Complete as of
QA/QC Highlights

0%

Total

Completed

Balance

Total Trained

30

Total

Completed

Balance

Total Trained

39

Discipline Training (*)


Item

Issued

Cumulative
Date

Scheduled

Remarks

Quality awareness Training (*)


Item

No

Items
Issued This Week

Cumulative
Date
22-Feb-2012

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

15-Feb-2012

21-Feb-2012

To:

Rep. No.:

"Leading" Indicators

"Lagging" Indicators

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)
Planned as of

11

Actual as of

10

WQM-GCC-013

NCR Status (Non-Conformance Report)


Items

Plan

Actual

GCC

S/C

Total NCR Issued

FQC Manager

Total NCR Closed

DFQC Manager

Total NCR Open

Sr.QA/QC Engineer

Total NCR Issued (This Week)

QA Engineer

QC Inspectors

CQCE

Document controller

Total DR Issued

QA/QC Trainer & DFO Co-ordinator

TOTAL

11

09

Quality Audits
Item
Scheduled

Discipline

1st IA : 22-01-12&1st EA :
19-02-12

All

Completed 1st IA : 22-01-12&1st EA : 19-02-12


Total :

Completed: 01

Balance :

GCC

Status in
brief

CPY CAR Status

CPY DR Status
(Deficiency Report)

Audit Findings (*)

Date

Cumulative :

NCR Status (Non-Conformance Report)


Total CAR Issued

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

JGC

CAR & OBS

CTR CAR Status


(Corrective Action Request)

Issued

10

Closed

11
0

Total CAR Issued

Open

11

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

CPY Q & IM Assessment


C/list No.
1

Assessment Title

Findings

Civil works control assessment

Total No. of
Assessment

Conducted this
Week

Closed

Open

Cumulative to Date Deficient (Red)

Concern (Amber) Satisfactory (Green)

Status of Deliverables (PQP/QCP/ITP/MS)


GCC

No. of
Deliverables

Documents

Submitted

Approved

GCC
GCC
GCC

1
45
1

PQP
ITP
QCP

1
12
1

1
5
1

SDR status (Specification Deviation Request)


GCC SDR
2

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Nil

Nil

Items
Total SDR Issued

Total SDR Cancelled


5 on MEP & 7 on Civil/Arch.

ITP's

Total SDR Closed

MEP - 4

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk
Score (%)

Score (%)

This Period

Last Period

Civil(C300 & C200)

89 & 92.5%

90 & 92 %

1.0

Civil(C300 & C200)

88 & 93.33%

89 & 92.5%

1.0

Discipline

Civil(C300 &
B200,C200)
Civil(C300 &
B200,C200)

% Difference

87 & 92.5%

88 & 93.33%

1.0

88.5&92.5%

87 & 92.5%

1.0

Action Required
Yes

11-Mar-2012

Completed

15-Mar-2012

Completed

Cancelled

14

JGC Witnessed

66

14

CPY Witnessed

37

10

Document For Operation (DFO)


DFO Complete as of
QA/QC Highlights

Total

Completed

Balance

Total Trained

30

Total

Completed

Balance

Total Trained

39

Total

Completed

Craft Training (*)


Item

Rejected

66

0%

Cumulative
Date

Scheduled

Accepted

81

Discipline Training (*)


Item

Issued

Cumulative
Date

Scheduled

Remarks

Quality awareness Training (*)


Item

No

Items
Issued This Week

Cumulative
Date

Balance

Total Trained

Scheduled
Completed
Barzan on shore project - Building works - Package#2

Weekly Quality Metrics

Resched.

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

22-Feb-2012

28-Feb-2012

To:

Rep. No.:

"Leading" Indicators

Planned as of

11

Actual as of

10

WQM-GCC-014

"Lagging" Indicators

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)

NCR Status (Non-Conformance Report)


Items

Plan

Actual

GCC

S/C

Total NCR Issued

FQC Manager

Total NCR Closed

DFQC Manager

Total NCR Open

Sr.QA/QC Engineer

Total NCR Issued (This Week)

QA Engineer

QC Inspectors

CQCE

Document controller

Total DR Issued

QA/QC Trainer & DFO Co-ordinator

TOTAL

11

10

Completed
Cumulative :
Completed: 01

GCC

Total CAR Issued

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

JGC
CAR

All

OBS

2nd IA : 13-03-12

Status in
brief

OBS

Scheduled

Discipline

CPY CAR Status

CPY DR Status
(Deficiency Report)

Audit Findings (*)

Date

CAR

Quality Audits
Item

NCR Status (Non-Conformance Report)

Issued

CTR CAR Status


(Corrective Action Request)

Total :

Closed

Total CAR Issued

Balance :

Open

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

CPY Q & IM Assessment


C/list No.
1
Total No. of
Assessment

Assessment Title

Findings

Civil works control assessment

Open

Conducted this
Cumulative to Date Deficient (Red)
Week

10

Closed

Concern (Amber)

Satisfactory (Green)

10

Status of Deliverables (PQP/QCP/ITP/MS)


GCC

No. of
Deliverables

Documents

Submitted

Approved

GCC
GCC
GCC

1
45
1

PQP
ITP
QCP

1
12
1

1
6
1

SDR status (Specification Deviation Request)


GCC SDR
2

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Nil

Nil

Items
Total SDR Issued

Total SDR Cancelled


5 on MEP & 7 on Civil/Arch.

ITP's

Total SDR Closed

MEP - 4

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk
Score (%)

This Period

Last Period

Civil(C300 & C200)

88 & 93.33%

89 & 92.5%

1.0

Civil(C300 & C200)

92 & 93.33%

88 & 93.33%

2.0

Discipline

Civil(C300 &
B200,C200)
Civil(C300 &
B200,C200)

% Difference

Action Required
Yes

No

92.5&87 %

92 & 93.33%

2.0

88.5% & 92.5

92.5&87 %

1.0

Quality awareness Training (*)


Item
Scheduled

11-Mar-2012

Completed

15-Mar-2012

Completed

Scheduled

Cancelled

JGC Witnessed

57

CPY Witnessed

28

Document For Operation (DFO)


DFO Complete as of
QA/QC Highlights

0%

Open NCRs - 5 No's (3 NCRs closed, formal transmittal awaited


from JGC)

Completed

Balance

Total Trained

30

Total

Completed

Balance

Total Trained

39

Total

Completed

JGC Craft Training (*)


Item

Rejected

57

Cumulative
Date

Scheduled

Remarks

Total

Discipline Training (*)


Item

Accepted

64

Issued This Week

Cumulative
Date

Issued

Items

Score (%)

Cumulative
Date

Balance

Total Trained

03-03-12 to 08-03-12

Completed
Barzan on shore project - Building works - Package#2

Weekly Quality Metrics

Resched.

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

29-Feb-2012

06-Mar-2012

To:

Rep. No.:

"Leading" Indicators

Overall Plan

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)

NCR Status (Non-Conformance Report)

18

WQM-GCC-015

"Lagging" Indicators

Items
Plan

As of Today :

Actual

GCC

S/C

Total NCR Issued

FQC Manager

Total NCR Closed

DFQC Manager

Total NCR Open

Sr.QA/QC Engineer

Total NCR Issued (This Week)

QA Engineer

QC Inspectors

CQCE

Document controller

Total DR Issued

QA/QC Trainer & DFO Co-ordinator

11

10

TOTAL

NCR Status (Non-Conformance Report)

Total

All

Completed
Cumulative :
Completed: 01

GCC

Total CAR Issued

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

JGC
CAR

2nd IA : 13-03-12

Status in
brief

OBS

Discipline

OBS

Scheduled

Audit Findings (*)

Date

CAR

Quality Audits
Item

CPY CAR Status

CPY DR Status
(Deficiency Report)

Issued

CTR CAR Status


(Corrective Action Request)

Total :

Closed

Total CAR Issued

Balance :

Open

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

CPY Q & IM Assessment


C/list No.
1
Total No. of
Assessment

Assessment Title

Findings

Civil Control - Concrete works

Conducted this
Cumulative to Date Deficient (Red)
Week

TBI

Closed

Open

Concern (Amber)

Satisfactory (Green)

13

Status of Deliverables (PQP/QCP/ITP)


S.No.

No. of
Deliverables

Documents

Submitted

Approved

1
2
3

1
51
1

PQP
ITP
QCP

1
12
1

1
6
1

SDR status (Specification Deviation Request)


GCC SDR
2

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Nil

Nil

Items
Total SDR Issued

Total SDR Cancelled


Total SDR Closed

MEP - 4

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

Civil(C300 & C200)

92 & 93.33%

88 & 93.33%

1.0

Civil(C300 & C200)

92.5&87 %

92 & 93.33%

3.0

Discipline

Civil(C300 &
B200,C200)
Civil(C300 &
B200,C200)

% Difference

Action Required
Yes

No

88.5% & 92.5

92.5&87 %

0.0

87 % & 92.5

88.5% & 92.5

1.0

Quality awareness Training (*)


Item

11-Mar-2012

Completed

15-Mar-2012

Completed

Scheduled

Rejected

Cancelled

62

18

62

18

31

14

45

Document For Operation (DFO)


DFO Complete as of
QA/QC Highlights

0%

Open NCRs - 2 No's (1 NCR closed, formal transmittal awaited


from JGC)

Completed

Balance

Total Trained

30

Total

Completed

Balance

Total Trained

39

Total

Completed

JGC Craft Training (*)


Item

Accepted

80

Cumulative
Date

Scheduled

Issued

JGC Witnessed
CPY Witnessed

Total

Discipline Training (*)


Item

Remarks

Cumulative
Date

Scheduled

Issued This Week

Cumulative
Date

Balance

Total Trained

03-03-12 to 08-03-12

Completed
Barzan on shore project - Building works - Package#2

Weekly Quality Metrics

Resched.

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

07-Mar-2012

13-Mar-2012

To:

Rep. No.:

"Leading" Indicators

Overall Plan

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)

NCR Status (Non-Conformance Report)

18

WQM-GCC-016

"Lagging" Indicators

Items
Plan

As of Today :

Actual

GCC

S/C

Total NCR Issued

FQC Manager

Total NCR Closed

DFQC Manager

Total NCR Open

Sr.QA/QC Engineer

Total NCR Issued (This Week)

QA Engineer

QC Inspectors

CQCC

Document controller

Total DR Issued

QA/QC Trainer & DFO Co-ordinator

13

11

TOTAL

NCR Status (Non-Conformance Report)

Total
Audit Findings (*)

2nd IA : 13-03-12

All

Completed

2nd IA : 13-03-12

Cumulative :
Completed: 02

GCC

Total CAR Issued

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

JGC
CAR

Scheduled

Status in
brief

OBS

Discipline

OBS

Date

CAR

Quality Audits
Item

CPY CAR Status

CPY DR Status
(Deficiency Report)

Issued

CTR CAR Status


(Corrective Action Request)

Total :

Closed

Total CAR Issued

Balance :

Open

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

CPY Q & IM Assessment


C/list No.
1
Total No. of
Assessment

Assessment Title

Findings

Civil Control - Concrete works

Conducted this
Cumulative to Date Deficient (Red)
Week

TBI

Closed

Open

Concern (Amber)

Satisfactory (Green)

13

Status of Deliverables (PQP/QCP/ITP)


S.No.

No. of
Deliverables

Documents

Submitted

Approved

1
2
3

1
51
1

PQP
ITP
QCP

1
12
1

1
6
1

SDR status (Specification Deviation Request)


GCC SDR
2

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Nil

Nil

Items
Total SDR Issued

Total SDR Cancelled


Total SDR Closed

MEP - 4

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

Civil(C300 & C200)

92.5&87 %

92 & 93.33%

3.0

Civil(C300 & C200)

88.5% & 92.5

92.5&87 %

0.0

Discipline

Civil(C300 &
B200,C200)
Civil(C300 &
B200,C200)

% Difference

Action Required
Yes

No

87 % & 92.5

88.5% & 92.5

1.0

85.7 & 90%

87 % & 92.5

1.0

Quality awareness Training (*)


Item
Scheduled

11-Mar-2012

Completed

07-Mar-2012

22-Mar-2012

Completed

Cancelled

14

110

14

47

10

57

Document For Operation (DFO)


DFO Complete as of
QA/QC Highlights

0%

Open NCRs - 2 No's

Completed

Balance

Total Trained

38

Total

Completed

Balance

Total Trained

39

Total

Completed

JGC Craft Training (*)

Scheduled

Rejected

110

Cumulative
Date

Item

Accepted

124

JGC Witnessed
CPY Witnessed

Total

Discipline Training (*)

Scheduled

Remarks

Issued

Cumulative
Date

Item

Issued This Week

Cumulative
Date

Balance

Total Trained

N/A

Completed
Barzan on shore project - Building works - Package#2

Weekly Quality Metrics

Resched.

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

14-Mar-2012

20-Mar-2012

To:

Rep. No.:

"Leading" Indicators

Overall Plan

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)

NCR Status (Non-Conformance Report)

18

WQM-GCC-017

"Lagging" Indicators

Items
Plan

As of Today :

Actual

GCC

S/C

Total NCR Issued

FQC Manager

Total NCR Closed

DFQC Manager

Total NCR Open

Sr.QA/QC Engineer

Total NCR Issued (This Week)

QA Engineer

QC Inspectors

CQCC

Document controller

Total DR Issued

QA/QC Trainer & DFO Co-ordinator

13

11

TOTAL

NCR Status (Non-Conformance Report)

Total

S/C-BEMCCO

Completed
Cumulative :
Completed: 02

GCC

Total CAR Issued

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

JGC
CAR

3rd IA : 16-04-12

Status in
brief

OBS

Discipline

OBS

Scheduled

Audit Findings (*)

Date

CAR

Quality Audits
Item

CPY CAR Status

CPY DR Status
(Deficiency Report)

Issued

CTR CAR Status


(Corrective Action Request)

Total :

Closed

Total CAR Issued

Balance :

Open

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

CPY Q & IM Assessment


C/list No.

Assessment Title

Findings

Closed

Open

Concern (Amber)

Satisfactory (Green)

1
Total No. of
Assessment

Conducted this
Cumulative to Date Deficient (Red)
Week

TBI

13

Status of Deliverables (PQP/QCP/ITP)


S.No.

No. of
Deliverables

Documents

Submitted

Approved

1
2
3
4
5

1
30
1
7
35

PQP
ITP
QCP
QMP
LTSC

1
10
1
7
22

1
6
1

SDR status (Specification Deviation Request)


GCC SDR
2

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Nil

Nil

Items
Total SDR Issued

17

Total SDR Cancelled


Total SDR Closed

MEP - 4

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

Civil(C300 & C200)

88.5% & 92.5

92.5&87 %

0.0

Civil(C300 & C200)

87 % & 92.5

88.5% & 92.5

1.0

Discipline

Civil(C300 &
B200,C200)
Civil(C300 &
B200,C200)

% Difference

Action Required
Yes

No

85.7 & 90%

87 % & 92.5

1.0

91.4 & 85.7%

85.7 & 90%

1.0

Quality awareness Training (*)


Item

10-May-2012

Completed

29-Mar-2012

Completed

Scheduled

CPY Witnessed

Resched.

28

N/A

90

28

N/A

34

15

N/A

49

Rejected

Document For Operation (DFO)


DFO Complete as of
QA/QC Highlights

0%

Open NCRs - 3 No's

Completed

Balance

Total Trained

45

Total

Completed

Balance

Total Trained

39

Total

Completed

JGC Craft Training (*)


Item

Cancelled

90

RFIs Submission : No Rescheduling, need to be raised with new RFI number.

Cumulative
Date

Scheduled

Accepted

118

JGC Witnessed

Total

Discipline Training (*)


Item

Remarks

Issued

Cumulative
Date

Scheduled

Issued This Week

Cumulative
Date

Balance

Total Trained

N/A

Completed
Barzan on shore project - Building works - Package#2

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

21-Mar-2012

To:

27-Mar-2012

Rep. No.:

"Leading" Indicators

Overall Plan

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)

NCR Status (Non-Conformance Report)

18

WQM-GCC-018

"Lagging" Indicators

Items
Plan

As of Today :

Actual

GCC

S/C

Total NCR Issued

10

FQC Manager

Total NCR Closed

DFQC Manager

Total NCR Open

Sr.QA/QC Engineer

Total NCR Issued (This Week)

QA Engineer

QC Inspectors

CQCC

Document controller

Total DR Issued

QA/QC Trainer & DFO Co-ordinator

13

11

TOTAL

NCR Status (Non-Conformance Report)

Total

LTSC-BEMCCO

Completed
Cumulative :
Completed: 02

GCC

Total CAR Issued

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

JGC
CAR

3rd IA : 16-04-12

Status in
brief

OBS

Discipline

OBS

Scheduled

Audit Findings (*)

Date

CAR

Quality Audits
Item

CPY CAR Status

CPY DR Status
(Deficiency Report)

Issued

11

CTR CAR Status


(Corrective Action Request)

Total :

Closed

11

Total CAR Issued

Balance :

Open

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

CPY Q & IM Assessment


C/list No.

Assessment Title

Findings

Closed

Open

Concern (Amber)

Satisfactory (Green)

1
Total No. of
Assessment

Conducted this
Cumulative to Date Deficient (Red)
Week

TBI

13

Status of Deliverables (PQP/QCP/ITP)


S.No.

No. of
Deliverables

Documents

Submitted

Approved

1
2
3
4
5

1
30
1
7
TBF

PQP
ITP
QCP
QMP
LTSC

1
10
1
7
25

1
6
1
5
22

SDR status (Specification Deviation Request)


GCC SDR
2

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Nil

Nil

Items
Total SDR Issued

Total SDR Cancelled


Total SDR Closed

MEP - 4

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

Civil(C300 & C200)

87 % & 92.5

88.5% & 92.5

1.0

Civil(C300 & C200)

85.7 & 90%

87 % & 92.5

1.0

Discipline

Civil(C300 &
B200,C200)
Civil(C300 &
B200,C200)

% Difference

Action Required
Yes

No

91.4 & 85.7%

85.7 & 90%

1.0

90&87.5%

91.4 & 85.7%

0.0

Quality awareness Training (*)


Item

10-May-2012

Completed

29-Mar-2012

Completed

Scheduled

CPY Witnessed

Resched.

21

N/A

101

21

N/A

41

12

N/A

53

Rejected

Document For Operation (DFO)


DFO Complete as of
QA/QC Highlights

0%

Open NCRs - 3 No's

Completed

Balance

Total Trained

45

Total

Completed

Balance

Total Trained

39

Total

Completed

JGC Craft Training (*)


Item

Cancelled

101

RFIs Submission : No Rescheduling, need to be raised with new RFI number.

Cumulative
Date

Scheduled

Accepted

122

JGC Witnessed

Total

Discipline Training (*)


Item

Remarks

Issued

Cumulative
Date

Scheduled

Issued This Week

Cumulative
Date

Balance

Total Trained

N/A

Completed
Barzan on shore project - Building works - Package#2

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

28-Mar-2012

To:

03-Apr-2012

Rep. No.:

"Leading" Indicators

Overall Plan

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)

NCR Status (Non-Conformance Report)

18

WQM-GCC-019

"Lagging" Indicators

Items
Plan

As of Today :

Actual

GCC

S/C

Total NCR Issued

10

FQC Manager

Total NCR Closed

DFQC Manager

Total NCR Open

Sr.QA/QC Engineer

Total NCR Issued (This Week)

QA Engineer

QC Inspectors

CQCC

Document controller

Total DR Issued

QA/QC Trainer & DFO Co-ordinator

13

11

TOTAL

NCR Status (Non-Conformance Report)

Total

LTSC-BEMCCO

Completed
Cumulative :
Completed: 02

GCC

Total CAR Issued

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

JGC
CAR

3rd IA : 16-04-12

Status in
brief

OBS

Discipline

OBS

Scheduled

Audit Findings (*)

Date

CAR

Quality Audits
Item

CPY CAR Status

CPY DR Status
(Deficiency Report)

Issued

11

CTR CAR Status


(Corrective Action Request)

Total :

11

Closed

11

Total CAR Issued

Balance :

Open

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

CPY Q & IM Assessment


C/list No.

Assessment Title

Findings

Closed

Open

Concern (Amber)

Satisfactory (Green)

1
Total No. of
Assessment

Conducted this
Cumulative to Date Deficient (Red)
Week

TBI

13

Status of Deliverables (PQP/QCP/ITP)


S.No.

No. of
Deliverables

Documents

Submitted

Approved

1
2
3
4
5

1
30
1
7
TBF

PQP
ITP
QCP
QMP
LTSC

1
10
1
7
27

1
6
1
5
20

SDR status (Specification Deviation Request)


GCC SDR
2

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Nil

Nil

Items
Total SDR Issued

Total SDR Cancelled


Total SDR Closed

MEP - 4

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

Civil(C300 & C200)

85.7 & 90%

87 % & 92.5

1.0

Civil(C300 & C200)

91.4 & 85.7%

85.7 & 90%

1.0

Discipline

Civil(C300 &
B200,C200)
Civil(C300 &
B200,C200)

% Difference

Action Required
Yes

No

90&87.5%

91.4 & 85.7%

1.0

90&92.5%

90&87.5%

0.0

Quality awareness Training (*)


Item

10-May-2012

Completed

Scheduled

29-Mar-2012

Completed

02-Apr-2012

CPY Witnessed

Cancelled

Resched.

20

N/A

73

20

N/A

16

N/A

47

31

Document For Operation (DFO)


DFO Complete as of
QA/QC Highlights

0%

Open NCRs - 3 No's

Completed

Balance

Total Trained

45

Total

Completed

Balance

Total Trained

49

Total

Completed

JGC Craft Training (*)

Scheduled

Rejected

73

Cancellation of RFIs due to works incompletion as scheduled.


RFI Rejection - Due to early Columns Deshuttering.

Cumulative
Date

Item

Accepted

94

JGC Witnessed

Total

Discipline Training (*)


Item

Remarks

Issued

Cumulative
Date

Scheduled

Issued This Week

Cumulative
Date

Balance

Total Trained

N/A

Completed
Barzan on shore project - Building works - Package#2

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

04-Apr-2012

To:

10-Apr-2012

Rep. No.:

"Leading" Indicators

Overall Plan

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)

NCR Status (Non-Conformance Report)

18

WQM-GCC-020

"Lagging" Indicators

Items
Plan

As of Today :

Actual

GCC

S/C

Total NCR Issued

10

FQC Manager

Total NCR Closed

DFQC Manager

Total NCR Open

Sr.QA/QC Engineer

Total NCR Issued (This Week)

QA Engineer

QC Inspectors

CQCC

Document controller

Total DR Issued

QC Engineer & DFO Co-ordinator

13

11

TOTAL

NCR Status (Non-Conformance Report)

Total

LTSC-BEMCCO

Completed
Cumulative :

GCC

Total CAR Issued

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

JGC
CAR

3rd IA : 16-04-12

Status in
brief

OBS

Discipline

OBS

Scheduled

Audit Findings (*)

Date

CAR

Quality Audits
Item

CPY CAR Status

CPY DR Status
(Deficiency Report)

Issued

11

CTR CAR Status


(Corrective Action Request)

Total :

11

Closed

11

Total CAR Issued

Balance :

Open

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

Completed: 02

CPY Q & IM Assessment


C/list No.
1
Total No. of
Assessment

Assessment Title

Findings

Civil/Supervisory Control

None

Conducted this
Cumulative to Date Deficient (Red)
Week

15

Closed

Open

N/A

None

Concern (Amber)

Satisfactory (Green)

15

Status of Deliverables (PQP/QCP/ITP)


S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
19
1
7
51

PQP
ITP
QCP
QMP
LTSC

1
12
1
7
30

1
6
1
5
24

SDR status (Specification Deviation Request)


GCC SDR
2

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Nil

Nil

Items
Total SDR Issued

Total SDR Cancelled


Total SDR Closed

MEP - 4

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

Civil(C300 & C200)

91.4 & 85.7%

85.7 & 90%

1.0

Civil(C300 & C200)

90&87.5%

91.4 & 85.7%

1.0

Discipline

Civil(C300 &
B200,C200)
Civil(C300 &
B200,C200)

% Difference

Action Required
Yes

No

90&92.5%

90&87.5%

0.0

91.6&86%

90&92.5%

0.0

Quality awareness Training (*)


Item

Date
10-May-2012

Completed(Previous)

07-Mar-2012

Item

Date

Scheduled(Upcoming)-Electrical

18-Apr-2012

Completed(Previous)

02-Apr-2012

Barzan on shore project - Building works - Package#2

CPY Witnessed

Cancelled

Resched.

73

17

N/A

73

17

N/A

27

N/A

36

Rejected

Document For Operation (DFO)


DFO Complete as of
QA/QC Highlights

0%

Open NCRs - 2 No's

Completed

Balance

Total Trained

45

Total

Completed

Balance

Total Trained

49

Date

Total

Completed

Cancellation of RFIs due to works incompletion as scheduled.

Cumulative

JGC Craft Training (*) - APR 2012

Completed(Previous)

Accepted

90

JGC Witnessed

Total

Discipline Training (*)(In Next 6 months)

Scheduled(Upcoming)-Piping

Remarks

Issued

Cumulative

Scheduled(Upcoming)

Item

Issued This Week

Cumulative
Balance

Total Trained

18th,23rd & 25th April


None

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

11-Apr-2012

To:

17-Apr-2012

Rep. No.:

"Leading" Indicators

Overall Plan

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)

NCR Status (Non-Conformance Report)

18

WQM-GCC-021

"Lagging" Indicators

Items
Plan

As of Today :

Actual

GCC

S/C

Total NCR Issued

10

FQCM & FQAM

Total NCR Closed

DFQC Manager

Total NCR Open

Sr.QA/QC Engineer

Total NCR Issued (This Week)

QC Engineer

QC Inspectors

CQCC

Document controller

Total DR Issued

DFO Co-ordinator

13

12

TOTAL

NCR Status (Non-Conformance Report)

Total
Audit Findings (*)

Scheduled(N
ext)

4th IA : 30-04-12

LTSC-QAIG

Completed(L
ast)

3rd IA : 16-04-12

LTSC-BEMCCO

Cumulative :

OBS

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

JGC

GCC/LTSC

Status in
brief

Total CAR Issued

CAR

Discipline

OBS

Date

CAR

Quality Audits
Item

CPY CAR Status

CPY DR Status
(Deficiency Report)

Issued

14

CTR CAR Status


(Corrective Action Request)

Total :

11

Closed

11

Total CAR Issued

Balance :

Open

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

Completed: 03

CPY Q & IM Assessment


C/list No.
1
Total No. of
Assessment

Assessment Title

Findings

Civil/Supervisory Control

None

Conducted this
Cumulative to Date Deficient (Red)
Week

15

15

Closed

Open

FCS status (Field Change Sheet)

N/A

None

Concern (Amber)

Satisfactory (Green)

15

Total Issued
Total Open
Total Closed

26
8
18

Status of Deliverables (PQP/QCP/ITP)


S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
19
1
7
51

PQP
ITP
QCP
QMP
LTSC

1
11
1
7
31

1
9
1
4
27

SDR status (Specification Deviation Request)


GCC SDR
2

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Nil

Nil

Items
Total SDR Issued

Total SDR Cancelled


Total SDR Closed

MEP - 4

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

Civil(C300 &
C200)

90&87.5%

91.4 & 85.7%

1.0

Civil(C300 &
C200)

90&92.5%

90&87.5%

0.0

Civil(C300 &
B200,C200)

91.6&86%

90&92.5%

0.0

Civil(C300 &
B200,C200)

92&91.25%

91.6&86%

0.0

Discipline

% Difference

Action Required
Yes

Quality awareness Training (*)


Item

Date
10-May-2012

Completed(Previous)

07-Mar-2012

Item

Date

Scheduled(Upcoming)-Electrical

19-Apr-2012

Completed(Previous)

02-Apr-2012

Barzan on shore project - Building works - Package#2

CPY Witnessed

Cancelled

Resched.

119

15

N/A

119

15

N/A

36

10

N/A

46

Rejected

Document For Operation (DFO)


DFO Complete as of
QA/QC Highlights

0%

Open NCRs - 1 No

Total

Balance

Total Trained

45

Total

Completed

Balance

Total Trained

49

Date

Total

Completed

18th,23rd & 25th April

Balance

Total Trained

18-Apr-2012

Cancellation of RFIs due to works incompletion as scheduled.

Cumulative

JGC Craft Training (*) - APR 2012

Completed(Previous)

Accepted

134

JGC Witnessed

Completed

Discipline Training (*)(In Next 6 months)

Scheduled(Upcoming)-Piping

Remarks

Issued

Cumulative

Scheduled(Upcoming)

Item

No

Issued This Week

Cumulative

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

18-Apr-2012

To:

24-Apr-2012

Rep. No.:

"Leading" Indicators

Overall Plan

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)

NCR Status (Non-Conformance Report)

18

WQM-GCC-022

"Lagging" Indicators

Items
Plan

As of Today :

Actual

GCC

S/C

Total NCR Issued

10

FQCM & FQAM

Total NCR Closed

DFQC Manager

Total NCR Open

Sr.QA/QC Engineer

Total NCR Issued (This Week)

QC Engineer

QC Inspectors

CQCC

Document controller

Total DR Issued

DFO Co-ordinator

13

12

TOTAL

NCR Status (Non-Conformance Report)

Total
Audit Findings (*)

Scheduled(N
ext)

4th IA : 30-04-12

LTSC-QAIG

Completed(L
ast)

3rd IA : 16-04-12

LTSC-BEMCCO

Cumulative :

OBS

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

JGC

GCC/LTSC

Status in
brief

Total CAR Issued

CAR

Discipline

OBS

Date

CAR

Quality Audits
Item

CPY CAR Status

CPY DR Status
(Deficiency Report)

Issued

13

CTR CAR Status


(Corrective Action Request)

Total :

11

Closed

11

Total CAR Issued

Balance :

Open

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

Completed: 03

CPY Q & IM Assessment


C/list No.
1
Total No. of
Assessment

Assessment Title

Findings

Civil/Supervisory Control

None

Conducted this
Cumulative to Date Deficient (Red)
Week

15

15

Closed

Open

FCS status (Field Change Sheet)

N/A

None

Concern (Amber)

Satisfactory (Green)

15

Status of Deliverables (PQP/QCP/ITP)


S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
19
1
7
51

PQP
ITP
QCP
QMP
LTSC

1
11
1
7
34

1
9
1
4
28

Total Issued
Total Open
Total Closed

36
7

Total Rejected

26

SDR status (Specification Deviation Request)


GCC SDR
2

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Nil

Nil

Items
Total SDR Issued

Total SDR Cancelled


Total SDR Closed

MEP - 4

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

Civil(C300 &
C200)

90&92.5%

87.5 & 90%

1.0

Civil(C300 &
C200)

91.6&86%

90&92.5%

0.0

Civil(C300 &
B200,C200)

92&91.25%

91.6&86%

0.0

Civil(C300 &
B200,C200)

91&92%

92&91.25%

0.0

Discipline

% Difference

Action Required
Yes

Quality awareness Training (*)


Item

Date
10-May-2012

Completed(Previous)

07-Mar-2012

Date

Scheduled(Upcoming)-HVAC

25-Apr-2012

Completed(Previous)-Elect

19-Apr-2012

Date

Scheduled(Upcoming)-Elect

Barzan on shore project - Building works - Package#2

CPY Witnessed

Cancelled

Resched.

87

N/A

87

N/A

37

N/A

44

Rejected

Document For Operation (DFO)


DFO Complete as of
QA/QC Highlights

0%

Open NCRs - 1 No

Total

Balance

Total Trained

45

Total

Completed

Balance

Total Trained

57

Total

Completed

Balance

Total Trained

18-Apr-2012

Cancellation of RFIs due to works incompletion as scheduled.

Cumulative

JGC Craft Training (*) - APR 2012

Completed(Previous)-piping

Accepted

96

JGC Witnessed

Completed

Discipline Training (*)(In Next 6 months)

Item

Remarks

Issued

Cumulative

Scheduled(Upcoming)

Item

No

Issued This Week

Cumulative

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

25-Apr-2012

To:

01-May-2012

Rep. No.:

"Leading" Indicators

Overall Plan

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)

NCR Status (Non-Conformance Report)

18

WQM-GCC-023

"Lagging" Indicators

Items
Plan

As of Today :

Actual

GCC

S/C

Total NCR Issued

10

FQCM & FQAM

Total NCR Closed

DFQC Manager

Total NCR Open

Sr.QA/QC Engineer

Total NCR Issued (This Week)

QC Engineer

QC Inspectors

CQCC

Document controller

Total DR Issued

DFO Co-ordinator

13

12

TOTAL

NCR Status (Non-Conformance Report)

Total
Audit Findings (*)

5th IA : 17-06-12

GCC-IA

Completed(L
ast)

4th IA : 30-04-12

LTSC-QAIG

Cumulative :

Total CAR Issued

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

JGC

GCC/LTSC

CAR

Scheduled(N
ext)

Status in
brief

OBS

Discipline

OBS

Date

CAR

Quality Audits
Item

CPY CAR Status

CPY DR Status
(Deficiency Report)

Issued

13

CTR CAR Status


(Corrective Action Request)

Total :

11

Closed

11

Total CAR Issued

Balance :

Open

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

Completed: 03

CPY Q & IM Assessment


C/list No.
1
Total No. of
Assessment

Assessment Title

Findings

Civil/Supervisory Control

None

Conducted this
Cumulative to Date Deficient (Red)
Week

15

15

Closed

Open

FCS status (Field Change Sheet)

N/A

None

Concern (Amber)

Satisfactory (Green)

15

Status of Deliverables (PQP/QCP/ITP)


S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
19
1
7
41

PQP
ITP
QCP
QMP
LTSC

1
13
1
7
35

1
6
1
4
33

Total Issued
Total Open
Total Closed

44
6

Total Rejected

Total cancelled

35

SDR status (Specification Deviation Request)


GCC SDR
2

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Nil

Nil

Items
Total SDR Issued

Total SDR Cancelled


Total SDR Closed

MEP - 4

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

Civil(C300 &
C200)

90&92.5%

87.5 & 90%

1.0

Civil(C300 &
C200)

91.6&86%

90&92.5%

0.0

Civil(C300 &
B200,C200)

91&92%

91.6&86%

0.0

Civil(C300 &
B200,C200)

90&90%

91&92%

0.0

Discipline

% Difference

Action Required
Yes

Quality awareness Training (*)

Issued This Week

Remarks

No
q

CPY Witnessed

20

N/A

42

15

N/A

57

0%

Cumulative

45

Date

Total

Completed

Balance

Total Trained

Scheduled(Upcoming)-Drainage and

19-May-2012

Completed(Previous)-HVAC

25-Apr-2012

65

Date

Scheduled(Upcoming)

10-May-2012

Completed(Previous)

07-Mar-2012

Discipline Training (*)(In Next 6 months)

Date

Scheduled(Upcoming)18-Apr-2012

Cancellation of RFIs due to works incompletion as scheduled.

Cumulative

JGC Craft Training (*) - APR 2012

Barzan on shore project - Building works - Package#2

N/A

104

Open NCRs - 1 No

Total Trained

Completed(Previous)-piping

Resched.

20

Rejected

Document For Operation (DFO)

Balance

Item

Cancelled

104

DFO Complete as of
QA/QC Highlights

Total

Item

Accepted

124

JGC Witnessed

Completed

Item

Issued

Cumulative
Total

Completed

Balance

Total Trained

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

09-May-2012

To:

15-May-2012

Rep. No.:

"Leading" Indicators

Overall Plan

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)

NCR Status (Non-Conformance Report)

18

WQM-GCC-025

"Lagging" Indicators

Items
Plan

As of Today :

Actual

S/C

11

Total NCR Closed

FQCM & FQAM

DFQC Manager

0(Vacation)

Total NCR Open

Sr.QA/QC Engineer

Total NCR Issued (This Week)

QC Engineer

QC Inspectors

CQCC

Document controller

Total DR Issued

DFO Co-ordinator

13

11

TOTAL

1( 1-vacation)

GCC

Total NCR Issued

NCR Status (Non-Conformance Report)

Total
Audit Findings (*)

5th IA : 17-06-12

GCC-IA

Completed(L
ast)

4th IA : 30-04-12

LTSC-QAIG

Cumulative :

Total CAR Issued

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

JGC

GCC/LTSC

CAR

Scheduled(N
ext)

Status in
brief

OBS

Discipline

OBS

Date

CAR

Quality Audits
Item

CPY CAR Status

CPY DR Status
(Deficiency Report)

Issued

15

CTR CAR Status


(Corrective Action Request)

Total :

11

Closed

11

Total CAR Issued

Balance :

Open

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

Completed: 03

CPY Q & IM Assessment


C/list No.
1
Total No. of
Assessment

Assessment Title

Findings

Civil/Supervisory Control

None

Conducted this
Cumulative to Date Deficient (Red)
Week

15

15

Closed

Open

FCS status (Field Change Sheet)

N/A

None

Concern (Amber)

Satisfactory (Green)

15

Status of Deliverables (PQP/QCP/ITP)


S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
19
1
7
41

PQP
ITP
QCP
QMP
LTSC

1
13
1
8
39

1
6
1
6
37

Total Issued
Total Open
Total Closed

56
19

Total Rejected

Total cancelled

33

SDR status (Specification Deviation Request)


GCC SDR
3

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Nil

Nil

Items
Total SDR Issued

Total SDR Cancelled


Total SDR Closed

MEP - 4

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

Civil(C300 &
C200)

92&91.0%

91.25& 92%

1.0

Civil(C300 &
C200)

90&90%

92&91.0%

0.0

Civil(C300 &
B200,C200)

88&92.5%

90&90%

0.0

Civil(C300 &
B200,C200)

90&92.5%

88&92.5%

0.0

Discipline

% Difference

Action Required
Yes

Quality awareness Training (*)

No

Issued This Week

Remarks

CPY Witnessed

Balance

Total Trained

55

Date

Total

Completed

Balance

Total Trained

Scheduled(Upcoming)-Drainage and

19-May-2012

Completed(Previous)-HVAC

25-Apr-2012

65

24-May-2012

Completed(Previous)

10-May-2012

Discipline Training (*)(In Next 6 months)


Item

Item

Date

Completed(Previous)-piping
Barzan on shore project - Building works - Package#2

18-Apr-2012

49

68

27

95

Cancelled

0%

Cancellation of RFIs due to works incompletion as scheduled & readymix unable to


supply etc

Cumulative

JGC Craft Training (*) - APR 2012

Scheduled(Upcoming)-

49

154

Rejected

Open NCRs - 2 No (Note:out of 2 one NCR disposition was approved)

Total

Scheduled(Upcoming)

154

Document For Operation (DFO)


DFO Complete as of
QA/QC Highlights

Cumulative
Date

Accepted

203

JGC Witnessed

Completed

Item

Issued

Cumulative
Total

Completed

Balance

Total Trained

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

16-May-2012

To:

22-May-2012

Rep. No.:

"Leading" Indicators

Overall Plan

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)

NCR Status (Non-Conformance Report)

18

WQM-GCC-026

"Lagging" Indicators

Items
Plan

As of Today :

Actual

S/C

11

Total NCR Closed

FQCM & FQAM

DFQC Manager

0(Vacation)

Total NCR Open

Sr.QA/QC Engineer

Total NCR Issued (This Week)

QC Engineer

QC Inspectors

QC Inspectors(MEP)

###

CQCC

Total CAR Issued

Document controller

Total DR Issued

Total CAR Closed

DFO Co-ordinator

Total DR Closed

Total CAR Open

16

14

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

TOTAL

1( 1-vacation)

GCC

Total NCR Issued

NCR Status (Non-Conformance Report)

Total
Audit Findings (*)

5th IA : 17-06-12

GCC-IA

Completed(L
ast)

4th IA : 30-04-12

LTSC-QAIG

Cumulative :

JGC

GCC/LTSC

Status in
brief

CAR

Scheduled(N
ext)

OBS

Discipline

OBS

Date

CAR

Quality Audits
Item

CPY CAR Status

CPY DR Status
(Deficiency Report)

Issued

15

CTR CAR Status


(Corrective Action Request)

Total :

11

Closed

11

Total CAR Issued

Balance :

Open

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

Completed: 03

CPY Q & IM Assessment


C/list No.
1
Total No. of
Assessment

Assessment Title

Findings

Civil/Supervisory Control

None

Conducted this
Cumulative to Date Deficient (Red)
Week

15

15

Closed

Open

FCS status (Field Change Sheet)

N/A

None

Concern (Amber)

Satisfactory (Green)

15

Status of Deliverables (PQP/QCP/ITP)


S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
19
1
7
41

PQP
ITP
QCP
QMP
LTSC

1
13
1
8
39

1
6
1
7
38

Total Issued
Total Open
Total Closed

61
9

Total Rejected

41

Total cancelled

SDR status (Specification Deviation Request)


GCC SDR
5

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Nil

Nil

Items
Total SDR Issued

Total SDR Cancelled


Total SDR Closed

MEP - 4

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

Civil(C300 &
C200)

90&90.0%

92& 91%

0.0

Civil(C300 &
C200)

88.5&92.5%

92&91.0%

0.0

Discipline

% Difference

Action Required
Yes

No

Civil(C300 &
B200,C200)

90&92.5%

90&90%

0.0

Civil(C300 &
B200,C200)

89&91.66%

88&92.5%

0.0

Quality awareness Training (*)

Issued This Week

Remarks

CPY Witnessed

28

0%

Cumulative

55

Date

Total

Completed

Balance

Total Trained

Scheduled(Upcoming)-HVAC -2nd

07-Jun-2012

Completed(Previous)-Drainage

25-Apr-2012

1
5

7
0

6
65

Total

Completed

Balance

Total Trained

Date

Scheduled(Upcoming)

24-May-2012

Completed(Previous)

10-May-2012

Discipline Training (*)(In Next 6 months)

Date

Scheduled(Upcoming)18-Apr-2012

Cancellation of RFIs due to works readymix unable to supply etc

Cumulative

JGC Craft Training (*) - APR 2012

Barzan on shore project - Building works - Package#2

56

50

78

Cancelled

Open NCRs - 2 No (Note:out of 2 one NCR disposition was approved)

Total Trained

Completed(Previous)-piping

56

113

Rejected

Document For Operation (DFO)

Balance

Item

113

DFO Complete as of
QA/QC Highlights

Completed

Item

Accepted

169

JGC Witnessed

Total

Item

Issued

Cumulative

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

13-Jun-2012

To:

19-Jun-2012

Rep. No.:

"Leading" Indicators

"Lagging" Indicators

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR Status (Non-Conformance Report)

19

Items

As of Today :

WQM-GCC-030

Plan

Actual

S/C

11

Total NCR Closed

10

FQCM & FQAM

DFQC Manager

Total NCR Open

Lead QC engineer

Total NCR Issued (This Week)

QC Engineer

QC Inspectors

MEP QC Mgr

QC Inspectors(MEP)

CQCC

Total CAR Issued

Document controller

Total DR Issued

Total CAR Closed

DFO Co-ordinator

Total DR Closed

Total CAR Open

19

17

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

TOTAL

GCC

Total NCR Issued

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)

Total
Quality Audits

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

6th IA : 16-09-12

GCC-IA

Status in
brief

Completed(L
ast)

5th IA : 14&16.06.12

GCC-IA

Issued

15

Total :

11

Closed

11

Total CAR Issued

Balance :

Open

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

Cumulative :
Completed: 05

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

CTR CAR Status


(Corrective Action Request)

CPY Q & IM Assessment


C/list No.
1
Total No. of
Assessment

Assessment Title

Findings

Civil/Supervisory Control

None

Conducted this
Cumulative to Date Deficient (Red)
Week

15

15

Closed

Open

FCS status (Field Change Sheet)

N/A

None

Concern (Amber)

Satisfactory (Green)

15

Status of Deliverables (PQP/QCP/ITP)


S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
20
1
8
41

PQP
ITP
QCP
QMP
LTSC

1
14
1
8
39

1
6
1
7
38

Total Issued
Total Open
Total Closed

100
16

Total Rejected

10

72

Total cancelled

SDR status (Specification Deviation Request)


Items
Total SDR Issued

GCC SDR
9

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Nil

Total SDR Cancelled

Nil

Total SDR Closed

Total SDR open

MEP - 4

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk
Score (%)

Score (%)

This Period

Last Period

Civil(C300 &
C200)

88&91.40%

89&91,66%

0.0

Civil(C300 &
C200)

88,3&90%

88&91.40%

0.0

Discipline

% Difference

Action Required
Yes

No

Civil(C300 &
B200,C200)

89&92.5%

88,3&90%

0.0

Civil(C300 &
B200,C200)

89%&92.5

89&92.5%

0.0

Quality awareness Training (Refresher)


Item

Date

Scheduled(Upcoming)

24-Jun-2012

Completed(Previous)

10-May-2012

Remarks

129

86

129

86

91

40

CPY Witnessed

131

Rejected

Cancelled

Document For Operation (DFO)


DFO Complete as of
QA/QC Highlights

0%

1) Open NCRs - 1 No (Note: Rev 0-approved with comments, Revision 1 submitted)

Total

Completed

Balance

Total Trained

55

2) percentage of cancellation :40%.

Cumulative

Date

Total

Completed

Balance

Scheduled(Upcoming)-HVAC -2nd

24-Jun-2012

Completed(Previous)-Drainage

25-Apr-2012

65

Date

Total

Completed

Balance

Total Trained

JGC Craft Training (*) -

Total Trained

Cumulative

Scheduled(Upcoming)-

Barzan on shore project - Building works - Package#2

Accepted

215

JGC Witnessed

Item

Completed(Previous)-piping

Issued

Issued This Week

Cumulative

Discipline Training (*)(In Next 6 months)

Item

Items

18-Apr-2012

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

20-Jun-2012

To:

26-Jun-2012

Rep. No.:

"Leading" Indicators

"Lagging" Indicators

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR Status (Non-Conformance Report)

21

Items

As of Today :

WQM-GCC-031

Plan

Actual

GCC

S/C

Total NCR Issued

11

FQCM & FQAM

Total NCR Closed

10

DFQC Manager

Total NCR Open

Lead QC engineer

Total NCR Issued (This Week)

QC Engineer

QC Inspectors

MEP QC Mgr/QC Engr

QC Inspectors(MEP)

CQCC

Total CAR Issued

Document controller

Total DR Issued

Total CAR Closed

DFO Co-ordinator

Total DR Closed

Total CAR Open

21

19

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

TOTAL

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)

Total
Quality Audits

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

6th IA : 16-09-12

GCC-IA

Status in
brief

Completed(L
ast)

5th IA : 14&16.06.12

GCC-IA

Issued

15

Total :

11

Closed

13

Total CAR Issued

Balance :

Open

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

Cumulative :
Completed: 05

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

CTR CAR Status


(Corrective Action Request)

CPY Q & IM Assessment


C/list No.
1
Total No. of
Assessment

Assessment Title

Findings

Civil/Supervisory Control

None

Conducted this
Cumulative to Date Deficient (Red)
Week

16

16

Closed

Open

FCS status (Field Change Sheet)

N/A

None

Concern (Amber)

Satisfactory (Green)

16

Status of Deliverables (PQP/QCP/ITP)


S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
19
1
8
40

PQP
ITP
QCP
QMP
LTSC

1
19
1
8
40

1
9
1
8
37

Total Issued
Total Open
Total Closed

94
14

Total Rejected

72

Total cancelled

SDR status (Specification Deviation Request)


Items
Total SDR Issued

GCC SDR
7

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Nil

Total SDR Cancelled

Nil

Total SDR Closed

Total SDR open

MEP - 8

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk
Score (%)

Score (%)

This Period

Last Period

Civil(C300 &
C200)

88,3&90%

88&91.40%

0.0

Civil(C300 &
C200)

89&92.5%

88,3&90%

0.0

Discipline

% Difference

Action Required
Yes

No

Civil(C300 &
B200,C200)

89%&92.5

89&92.5%

0.0

Civil(C300 &
B200,C200,B100)

91.4&89%

89&92.5%

0.0

Quality awareness Training (Refresher)


Item

Date

Scheduled(Upcoming)

08-Jul-2012

Completed(Previous)

10-May-2012

Date

Scheduled(Upcoming)-HVAC -2nd

02-Jul-2012

Completed(Previous)-Drainage

25-Apr-2012

Barzan on shore project - Building works - Package#2

234

64

234

64

78

34

CPY Witnessed

112

Rejected

Cancelled

Document For Operation (DFO)


DFO Complete as of
QA/QC Highlights

0%

1) Open NCRs - 1 No (Note: Rev 0-approved with comments,


Revision 1 submitted)

Completed

Balance

Total Trained

55

Total

Completed

Balance

Total Trained

Total

Completed

Balance

Total Trained

2) percentage of cancellation : 21.4 %

Cumulative

Cumulative
Date

Scheduled(Upcoming)-

Completed(Previous)-piping

Accepted

298

JGC Witnessed

Total

JGC Craft Training (*) Item

Issued

Cumulative

Discipline Training (*)(In Next 6 months)


Item

Remarks

Items
Issued This Week

18-Apr-2012

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

27-Jun-2012

To:

03-Jul-2012

Rep. No.:

"Leading" Indicators

"Lagging" Indicators

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR Status (Non-Conformance Report)

22

Items

As of Today :

WQM-GCC-032

Plan

Actual

GCC

S/C

Total NCR Issued

11

FQCM & FQAM

Total NCR Closed

10

DFQC Manager

Total NCR Open

Lead QC engineer

Total NCR Issued (This Week)

QC Engineer

QC Inspectors

MEP QC Mgr/QC Engr

QC Inspectors(MEP)

CQCC

Total CAR Issued

Document controller(GCC+BEMCCO)

Total DR Issued

Total CAR Closed

DFO Co-ordinator

Total DR Closed

Total CAR Open

22

20

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

TOTAL

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)

Total
Quality Audits

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

6th IA : 16-09-12

GCC-IA

Status in
brief

Completed(L
ast)

5th IA : 14&16.06.12

GCC-IA

Issued

15

Total :

11

Closed

15

Total CAR Issued

Balance :

Open

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

Cumulative :
Completed: 05

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

CTR CAR Status


(Corrective Action Request)

CPY Q & IM Assessment


C/list No.
1
Total No. of
Assessment

Assessment Title

Findings

Civil/Supervisory Control

None

Conducted this
Cumulative to Date Deficient (Red)
Week

17

17

Closed

Open

FCS status (Field Change Sheet)

N/A

None

Concern (Amber)

Satisfactory (Green)

16

Status of Deliverables (PQP/QCP/ITP)

Total Issued
Total Open
Total Closed

112
23
81

Total Rejected

S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
18
1
8
37

PQP
ITP
QCP
QMP
LTSC

1
17
1
8
37

1
10
1
8
37

Total cancelled

SDR status (Specification Deviation Request)


Items
Total SDR Issued

Quality Tool Box Talks


Total Condcuted : 4, This week : 0

GCC SDR
8

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Nil

Total SDR Cancelled

Nil

Total SDR Closed

Total SDR open

MEP - 8

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk
Score (%)

Score (%)

This Period

Last Period

Civil(C300 &
C200)

89&92.5%

88,3&90%

0.0

Civil(C300 &
C200)

89%&92.5

89&92.5%

0.0

Discipline

% Difference

Action Required
Yes

No

Civil(C300 &
B200,C200)

91.4&89%

89&92.5%

0.0

Civil(C300 & B200,C200)

92.5&93%

91.4&89%

0.0

Quality awareness Training (Refresher)


Item

Date

Scheduled(Upcoming)

15-Aug-2012

Completed(Previous)

03-Jul-2012

Scheduled(Upcoming)-HVAC -2nd
Completed(Previous)-Drainage

Date
09-Jul-2012
19-May-2012

Barzan on shore project - Building works - Package#2

227

62

227

62

87

32

CPY Witnessed

119

Rejected

Cancelled

Document For Operation (DFO)


DFO Complete as of
QA/QC Highlights

0%

1) Open NCRs - 1 No (Note: Rev 0-approved with comments,


Revision 1 submitted)

Completed

Balance

Total Trained

60

Total

Completed

Balance

Total Trained

Total

Completed

Balance

Total Trained

2) percentage of cancellation : 21.45 %

Cumulative

Cumulative
Date

Scheduled(Upcoming)-

Completed(Previous)-piping

Accepted

289

JGC Witnessed

Total

JGC Craft Training (*) Item

Issued

Cumulative

Discipline Training (*)(In Next 6 months)


Item

Remarks

Items
Issued This Week

18-Apr-2012

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

04-Jul-2012

To:

10-Jul-2012

Rep. No.:

"Leading" Indicators

"Lagging" Indicators

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR Status (Non-Conformance Report)

23

Items

As of Today :

WQM-GCC-033

Plan

Actual

GCC

S/C

Total NCR Issued

11

FQCM & FQAM

Total NCR Closed

11

DFQC Manager

Total NCR Open

Lead QC engineer+MEP QC Engg.

Total NCR Issued (This Week)

QC Engineer

QC Inspectors

MEP QC Mgr/QC Engr

QC Inspectors(MEP)

CQCC

Total CAR Issued

Document controller(GCC+BEMCCO)

Total DR Issued

Total CAR Closed

DFO Co-ordinator

Total DR Closed

Total CAR Open

23

21

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

TOTAL

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)

Total
Quality Audits

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

6th IA : 16-09-12

GCC-IA

Status in
brief

Completed(L
ast)

5th IA : 14&16.06.12

GCC-IA

Issued

15

Total :

11

Closed

15

Total CAR Issued

Balance :

Open

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

Cumulative :
Completed: 05

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

CTR CAR Status


(Corrective Action Request)

CPY Q & IM Assessment


C/list No.
1
Total No. of
Assessment

Assessment Title

Findings

Civil/Supervisory Control

None

Conducted this
Cumulative to Date Deficient (Red)
Week

17

17

Closed

Open

FCS status (Field Change Sheet)

N/A

None

Concern (Amber)

Satisfactory (Green)

16

Status of Deliverables (PQP/QCP/ITP)


No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
17
1
8
38

PQP
ITP
QCP
QMP
LTSC

1
17
1
8
38

1
11
1
8
37

Quality Tool Box Talks

SDR status (Specification Deviation Request)


GCC SDR
8

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Nil

Total SDR Cancelled

Nil

Total SDR Closed

Total SDR open

Weekly Site Quality Walk


This Period

Last Period

Civil(C300 &
C200)

89&92.5%

89&92.5%

0.0

Civil(C300 &
C200)

91.4&89%

89&92.5%

0.0

% Difference

Action Required
Yes

No

92.5&93%

91.4&89%

0.0

90.83 & 90%

92 & 93%

0.0

Quality awareness Training (Refresher)


Item

Date

Scheduled(Upcoming)

15-Aug-2012

Completed(Previous)

03-Jul-2012

Date

Scheduled(Upcoming)-Piping, Doors &


Windows

15-Jul-2012

Completed(Previous)-Drainage

Barzan on shore project - Building works - Package#2

Accepted

226

198

28

198

28

83

15

CPY Witnessed

98

Rejected

Cancelled

Document For Operation (DFO)


DFO Complete as of
QA/QC Highlights

Completed

Balance

Total Trained

60

Total

Completed

0%

Balance

Total Trained

Total

Completed

Balance

Total Trained

1) percentage of cancellation : 12.39 %

Cumulative

19-May-2012

Cumulative
Date

Scheduled(Upcoming)-

Completed(Previous)-piping

Issued

JGC Witnessed

Total

JGC Craft Training (*) Item

Remarks

Items
Issued This Week

Cumulative

Discipline Training (*)(In Next 6 months)


Item

MEP - 8

Weekly Field Inspection Status (RFI)

Score (%)

Civil(C300 & B200,C200)

Total cancelled

Field cured sample maintain & Curing of concrete

Score (%)

Civil(C300 &
B200,C200)

92

Items
Total SDR Issued

Total Condcuted : 5, This week : 1

Discipline

124
25

Total Rejected

S.No.

Description:

Total Issued
Total Open
Total Closed

18-Apr-2012

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

11-Jul-2012

To:

17-Jul-2012

Rep. No.:

"Leading" Indicators

"Lagging" Indicators

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR Status (Non-Conformance Report)

23

Items

As of Today :

WQM-GCC-034

Plan

Actual

GCC

S/C

Total NCR Issued

11

FQCM & FQAM

Total NCR Closed

11

DFQC Manager

Total NCR Open

Lead QC engineer+MEP QC Engg.

Total NCR Issued (This Week)

QC Engineer

QC Inspectors

MEP QC Mgr/QC Engr

QC Inspectors(MEP)

CQCC

Total CAR Issued

Document controller(GCC+BEMCCO)

Total DR Issued

Total CAR Closed

DFO Co-ordinator

Total DR Closed

Total CAR Open

23

21

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

TOTAL

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)

Total
Quality Audits

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

6th IA : 16-09-12

GCC-IA

Status in
brief

Completed(L
ast)

5th IA : 14&16.06.12

GCC-IA

Issued

15

Total :

11

Closed

15

Total CAR Issued

Balance :

Open

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

Cumulative :
Completed: 05

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

CTR CAR Status


(Corrective Action Request)

CPY Q & IM Assessment


C/list No.
1
Total No. of
Assessment

Assessment Title

Findings

Civil/Supervisory Control

None

Conducted this
Cumulative to Date Deficient (Red)
Week

17

17

Closed

Open

FCS status (Field Change Sheet)

N/A

None

Concern (Amber)

Satisfactory (Green)

17

Status of Deliverables (PQP/QCP/ITP)


No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
17
1
8
39

PQP
ITP
QCP
QMP
LTSC

1
17
1
8
39

1
10
1
8
37

Quality Tool Box Talks

SDR status (Specification Deviation Request)


GCC SDR
8

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Nil

Total SDR Cancelled

Nil

Total SDR Closed

Total SDR open

MEP - 8

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk
Score (%)

This Period

Last Period

Civil(C300 &
C200)

91.4&89%

89&92.5%

0.0

Civil(C300 &
C200)

92.5&93%

91.4&89%

0.0

Civil(C300 & B200,C200)

Total cancelled

N/A

Score (%)

Civil(C300 &
B200,C200)

106

Items
Total SDR Issued

Total Condcuted : 5, This week : 0

Discipline

134
21

Total Rejected

S.No.

Description:

Total Issued
Total Open
Total Closed

% Difference

Action Required
Yes

No

90.83 & 90%

92 & 93%

0.0

92 & 93%

90.83 & 90%

0.0

Quality awareness Training (Refresher)


Item

Date

Scheduled(Upcoming)

15-Aug-2012

Completed(Previous)

03-Jul-2012

Date

Scheduled(Upcoming)-Piping, Doors &


Windows

22-Jul-2012

Completed(Previous)-Drainage

Barzan on shore project - Building works - Package#2

226

23

226

23

67

14

CPY Witnessed

81

Rejected

Cancelled

Document For Operation (DFO)


DFO Complete as of
QA/QC Highlights

Completed

Balance

Total Trained

60

Total

Completed

0%

Balance

Total Trained

Total

Completed

Balance

Total Trained

1) percentage of cancellation : 9.24 %

Cumulative

19-May-2012

Cumulative
Date

Scheduled(Upcoming)-

Completed(Previous)-piping

Accepted

249

JGC Witnessed

Total

JGC Craft Training (*) Item

Issued

Cumulative

Discipline Training (*)(In Next 6 months)


Item

Remarks

Items
Issued This Week

18-Apr-2012

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

18-Jul-2012

To:

24-Jul-2012

Rep. No.:

"Leading" Indicators

"Lagging" Indicators

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR Status (Non-Conformance Report)

23

Items

As of Today :

WQM-GCC-035

Plan

Actual

GCC

S/C

Total NCR Issued

11

FQCM & FQAM

Total NCR Closed

11

DFQC Manager

Total NCR Open

Lead QC engineer+MEP QC Engg.

Total NCR Issued (This Week)

QC Engineer

QC Inspectors

MEP QC Mgr/QC Engr

QC Inspectors(MEP)

CQCC

Total CAR Issued

Document controller(GCC+BEMCCO)

Total DR Issued

Total CAR Closed

DFO Co-ordinator

Total DR Closed

Total CAR Open

23

21

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

TOTAL

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)

Total
Internal Quality Audits

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

6th IA : 16-09-12

GCC-IA

Status in
brief

Completed(L
ast)

5th IA : 14&16.06.12

GCC-IA

Issued

15

Total :

11

Closed

15

Total CAR Issued

Balance :

Open

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

Cumulative :
Completed: 05

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

CTR CAR Status


(Corrective Action Request)

CPY Q & IM Assessment


C/list No.
1
Total No. of
Assessment

Assessment Title

Findings

Civil/Supervisory Control

None

Conducted this
Cumulative to Date Deficient (Red)
Week

17

17

Closed

Open

FCS status (Field Change Sheet)

N/A

None

Concern (Amber)

Satisfactory (Green)

17

Status of Deliverables (PQP/QCP/ITP)


No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
17
1
8
40

PQP
ITP
QCP
QMP
LTSC

1
17
1
8
40

1
11
1
8
39

Quality Tool Box Talks

SDR status (Specification Deviation Request)


GCC SDR
8

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Nil

Total SDR Cancelled

Nil

Total SDR Closed

Total SDR open

MEP - 8

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk
Score (%)

This Period

Last Period

Civil(C300 &
C200)

92.5&93%

91.4&89%

0.0

Civil(C300 &
C200)

90.83 & 90%

92 & 93%

0.0

Civil(C300 & B200,C200)

Total cancelled

N/A

Score (%)

Civil(C300 &
B200,C200)

118

Items
Total SDR Issued

Total Condcuted : 5, This week : 0

Discipline

149
23

Total Rejected

S.No.

Description:

Total Issued
Total Open
Total Closed

% Difference

Action Required
Yes

No

92 & 93%

90.83 & 90%

0.0

90 & 90 %

92 & 93%

0.0

Quality awareness Training (Refresher)


Item

Date

Scheduled(Upcoming)

15-Aug-2012

Completed(Previous)

03-Jul-2012

Date

Scheduled(Upcoming)-Tiling

09-Aug-2012

Completed(Previous)-Drainage

19-May-2012

Barzan on shore project - Building works - Package#2

Rejected

Cancelled

127

85

127

85

CPY Witnessed

56

29

27

Document For Operation (DFO)


DFO Complete as of
QA/QC Highlights

0%

Completed

Balance

Total Trained

60

Total

Completed

Balance

Total Trained

Total

Completed

Balance

Total Trained

1) percentage of cancellation : 39.99 %

Cumulative

Cumulative
Date

Scheduled(Upcoming)-

Completed(Previous)-piping

Accepted

213

JGC Witnessed

Total

JGC Craft Training (*) Item

Issued

Cumulative

Discipline Training (*)(In Next 6 months)


Item

Remarks

Items
Issued This Week

18-Apr-2012

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

25-Jul-2012

To:

31-Jul-2012

Rep. No.:

"Leading" Indicators

"Lagging" Indicators

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR Status (Non-Conformance Report)

23

Items

As of Today :

WQM-GCC-036

Plan

Actual

GCC

S/C

Total NCR Issued

11

FQCM & FQAM

Total NCR Closed

11

DFQC Manager

Total NCR Open

Lead QC engineer+MEP QC Engg.

Total NCR Issued (This Week)

QC Engineer

QC Inspectors

MEP QC Mgr/QC Engr

QC Inspectors(MEP)

CQCC

Total CAR Issued

Document controller(GCC+BEMCCO)

Total DR Issued

Total CAR Closed

DFO Co-ordinator

Total DR Closed

Total CAR Open

23

21

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

TOTAL

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)

Total
Internal Quality Audits

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

6th IA : 16-09-12

GCC-IA

Status in
brief

Completed(L
ast)

5th IA : 14&16.06.12

GCC-IA

Issued

15

Total :

11

Closed

15

Total CAR Issued

Balance :

Open

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

Cumulative :
Completed: 05

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

CTR CAR Status


(Corrective Action Request)

CPY Q & IM Assessment


C/list No.
1
Total No. of
Assessment

Assessment Title

Findings

Civil/Supervisory Control

None

Conducted this
Cumulative to Date Deficient (Red)
Week

17

17

Closed

Open
None
Satisfactory (Green)

17

Status of Deliverables (PQP/QCP/ITP)


S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
17
1
8
40

PQP
ITP
QCP
QMP
LTSC

1
17
1
8
40

1
12
1
8
40

Quality Tool Box Talks

Weekly Site Quality Walk


This Period

Last Period

Civil(C300 &
C200)

90.83 & 90%

92 & 93%

0.0

Civil(C300 &
C200)

92 & 93%

90.83 & 90%

0.0

Civil(C300 & B200,C200)

130

% Difference

Action Required
Yes

No

90 & 90 %

92 & 93%

0.0

90 & 93.33%

90 & 90 %

0.0

Quality awareness Training (Refresher)


Item

Date

Scheduled(Upcoming)

15-Aug-2012

Completed(Previous)

03-Jul-2012

Date

Scheduled(Upcoming)-Doors & Windows

15-Aug-2012

Completed(Previous)-R.C.Piping

29-Jul-2012

Barzan on shore project - Building works - Package#2

Total Rejected

Total Rejected

Total cancelled

Total cancelled

SDR status (Specification Deviation Request)


GCC SDR
8

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Nil

Total SDR Cancelled

Nil

Total SDR Closed

Total SDR open

MEP - 8

Items

Issued

Accepted

Rejected

Cancelled

Issued This Week

224

138

85

138

85

JGC Witnessed
CPY Witnessed

65

36

29

Document For Operation (DFO)


DFO Complete as of
QA/QC Highlights

0%

Completed

Balance

Total Trained

60

Total

Completed

Balance

Total Trained

14

Total

Completed

Balance

Total Trained

1) percentage of cancellation : 37.99 %

Cumulative

Cumulative
Date

Scheduled(Upcoming)-

Completed(Previous)-piping

Remarks

Total

JGC Craft Training (*) Item

4
0

Cumulative

Discipline Training (*)(In Next 6 months)


Item

Total Issued
Total Open
Total Closed

Weekly Field Inspection Status (RFI)

Score (%)

Civil(C300 &
B200,C200)

159
22

Plaster Ingredients mixing using gauge boxes [BSS-107]

Score (%)

Discipline

Total Issued
Total Open
Total Closed

Items
Total SDR Issued

Total Condcuted : 6, This week : 1


Description:

FTR status (Field Trouble Request)

FCS status (Field Change Sheet)

N/A
Concern (Amber)

18-Apr-2012

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

01-Aug-2012

To:

07-Aug-2012

Rep. No.:

"Leading" Indicators

"Lagging" Indicators

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR Status (Non-Conformance Report)

25

Items

As of Today :

WQM-GCC-037

Plan

Actual

GCC

S/C

Total NCR Issued

11

FQCM & FQAM(Civil&Arch.)

Total NCR Closed

11

DFQC Manager(Civil&Arch.)

Total NCR Open

Lead QC engineer(Civil&Arch.)

Total NCR Issued (This Week)

QC Inspectors(Civil&Arch.)

MEP QC Mgr/QCI

CQCC

Document controller(GCC+BEMCCO)

DFO Co-ordinator

TOTAL

23

CPY CAR Status


CPY DR Status
(Deficiency Report)

19

Internal Quality Audits

Audit Findings (*)

Total CAR Issued

Total DR Issued

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

Date

Discipline

Scheduled(N
ext)

6th IA : 16-09-12

GCC-IA

Status in
brief

Completed(L
ast)

5th IA : 14&16.06.12

GCC-IA

Issued

15

Total :

11

Closed

15

Total CAR Issued

Balance :

Open

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

Cumulative :
Completed: 05

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

NCR Status (Non-Conformance Report)

CTR CAR Status


(Corrective Action Request)

CPY Q & IM Assessment


C/list No.
1
Total No. of
Assessment

Assessment Title

Findings

Civil/Supervisory Control

None

Conducted this
Cumulative to Date Deficient (Red)
Week

17

17

Closed

Open
None
Satisfactory (Green)

17

Status of Deliverables (PQP/QCP/ITP)


S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
17
1
8
40

PQP
ITP
QCP
QMP
LTSC

1
17
1
8
40

1
12
1
8
40

Quality Tool Box Talks

Weekly Site Quality Walk


This Period

Last Period

Civil(C300 &
C200)

92 & 93%

90.83 & 90%

0.0

Civil(C300 &
C200)

90 & 90 %

92 & 93%

0.0

Civil(C300 & B200,C200)

135

Total Issued
Total Open
Total Closed

4
0
4

Total Rejected

Total Rejected

Total cancelled

Total cancelled

SDR status (Specification Deviation Request)


GCC SDR
8

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Total SDR Cancelled

Nil

Total SDR Closed

Total SDR open

MEP - 8

Weekly Field Inspection Status (RFI)


Score (%)

Civil(C300 &
B200,C200)

163
21

N/A

Score (%)

Discipline

Total Issued
Total Open
Total Closed

Items
Total SDR Issued

Total Condcuted : 6, This week : 0


Description:

FTR status (Field Trouble Request)

FCS status (Field Change Sheet)

N/A
Concern (Amber)

% Difference

Action Required
Yes

No

90 & 93.33%

90 & 90 %

0.0

90 & 90%

90 & 93.33%

0.0

Quality awareness Training (Refresher)


Item

Date

Scheduled(Upcoming)

15-Aug-2012

Completed(Previous)

03-Jul-2012

Date

Scheduled(Upcoming)-Doors & Windows

15-Aug-2012

Completed(Previous)-R.C.Piping

29-Jul-2012

Barzan on shore project - Building works - Package#2

Rejected

Cancelled

128

95

128

95

39

63

CPY Witnessed

102

Document For Operation (DFO)


DFO Complete as of
QA/QC Highlights

0%

Completed

Balance

Total Trained

60

Total

Completed

Balance

Total Trained

14

Total

Completed

Balance

Total Trained

1) percentage of cancellation : 42.79 %

Cumulative

Cumulative
Date

Scheduled(Upcoming)-

Completed(Previous)-piping

Accepted

222

JGC Witnessed

Total

JGC Craft Training (*) Item

Issued

Cumulative

Discipline Training (*)(In Next 6 months)


Item

Remarks

Items
Issued This Week

18-Apr-2012

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

08-Aug-2012

To:

14-Aug-2012

Rep. No.:

"Leading" Indicators

"Lagging" Indicators

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR Status (Non-Conformance Report)

25

Items

As of Today :

WQM-GCC-038

Plan

Actual

GCC

S/C

Total NCR Issued

11

FQCM & FQAM(Civil&Arch.)

Total NCR Closed

11

DFQC Manager(Civil&Arch.)

Total NCR Open

Lead QC engineer(Civil&Arch.)

Total NCR Issued (This Week)

QC Inspectors(Civil&Arch.)

MEP QC Mgr/QCI

CQCC

Document controller(GCC+BEMCCO)

DFO Co-ordinator

TOTAL

23

CPY CAR Status


CPY DR Status
(Deficiency Report)

19

Internal Quality Audits

Audit Findings (*)

Total CAR Issued

Total DR Issued

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

Date

Discipline

Scheduled(N
ext)

6th IA : 16-09-12

GCC-IA

Status in
brief

Completed(L
ast)

5th IA : 14&16.06.12

GCC-IA

Issued

15

Total :

11

Closed

15

Total CAR Issued

Balance :

Open

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

Cumulative :
Completed: 05

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

NCR Status (Non-Conformance Report)

CTR CAR Status


(Corrective Action Request)

CPY Q & IM Assessment


C/list No.
1
Total No. of
Assessment

Assessment Title

Findings

Civil/Supervisory Control

None

Conducted this
Cumulative to Date Deficient (Red)
Week

17

17

Closed

Open
None
Satisfactory (Green)

17

Status of Deliverables (PQP/QCP/ITP)


S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
17
1
8
41

PQP
ITP
QCP
QMP
LTSC

1
17
1
8
41

1
12
1
8
40

Quality Tool Box Talks

Weekly Site Quality Walk


This Period

Last Period

Civil(C300 &
C200)

90 & 90 %

92 & 93%

0.0

Civil(C300 &
C200)

90 & 93.33%

90 & 90 %

0.0

Civil(C300 & B200,C200)

147

Total Issued
Total Open
Total Closed

5
0
5

Total Rejected

Total Rejected

Total cancelled

Total cancelled

SDR status (Specification Deviation Request)


GCC SDR
8

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Total SDR Cancelled

Nil

Total SDR Closed

Total SDR open

MEP - 8

Weekly Field Inspection Status (RFI)


Score (%)

Civil(C300 &
B200,C200)

179
25

N/A

Score (%)

Discipline

Total Issued
Total Open
Total Closed

Items
Total SDR Issued

Total Condcuted : 6, This week : 0


Description:

FTR status (Field Trouble Request)

FCS status (Field Change Sheet)

N/A
Concern (Amber)

% Difference

Action Required
Yes

No

90 & 90%

90 & 93.33%

0.0

89 & 94.2%

90 & 90%

0.0

Quality awareness Training (Refresher)


Item

Date

Scheduled(Upcoming)

15-Aug-2012

Completed(Previous)

03-Jul-2012

Item

Date
21-Aug-2012

Completed(Previous)-R.C.Piping

29-Jul-2012

Barzan on shore project - Building works - Package#2

Rejected

Cancelled

128

46

128

46

37

22

CPY Witnessed

59

Document For Operation (DFO)


DFO Complete as of
QA/QC Highlights

0%

Completed

Balance

Total Trained

60

Cumulative
Total

Completed

Balance

Total Trained

14

Total

Completed

Balance

Total Trained

1) percentage of cancellation : 27.27 %

Note : RFI Rejections are due to insufficient document for


incoming material inspections.

Cumulative
Date

Scheduled(Upcoming)-

Completed(Previous)-piping

Accepted

176

JGC Witnessed

Total

JGC Craft Training (*) Item

Issued

Cumulative

Discipline Training (*)(In Next 6 months)

Scheduled(Upcoming)-Doors & Windows

Remarks

Items
Issued This Week

18-Apr-2012

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

22-Aug-2012

To:

28-Aug-2012

Rep. No.:

"Leading" Indicators

"Lagging" Indicators

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR Status (Non-Conformance Report)

25

Items

As of Today :

WQM-GCC-040

Plan

Actual

GCC

S/C

Total NCR Issued

14

FQCM & FQAM(Civil&Arch.)

Total NCR Closed

11

DFQC Manager(Civil&Arch.)

Total NCR Open

Lead QC engineer(Civil&Arch.)

Total NCR Issued (This Week)

QC Inspectors(Civil&Arch.)

MEP QC Mgr/QCI

CQCC

Document controller(GCC+BEMCCO)

DFO Co-ordinator

TOTAL

23

CPY CAR Status


CPY DR Status
(Deficiency Report)

19

Internal Quality Audits

Audit Findings (*)

Total CAR Issued

Total DR Issued

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

Date

Discipline

Scheduled(N
ext)

6th IA : 16-09-12

GCC-IA

Status in
brief

Completed(L
ast)

5th IA : 14&16.06.12

GCC-IA

Issued

15

Total :

11

Closed

15

Total CAR Issued

Balance :

Open

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

Cumulative :
Completed: 05

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

NCR Status (Non-Conformance Report)

CTR CAR Status


(Corrective Action Request)

Note : Next JGC Activity audit scheduled on 16-09-12


CPY Q & IM Assessment
Assessment Title

Findings

Electrical Control(23-08-12):91.66%

None

C/list No.
1
Total No. of
Assessment

Conducted this
Cumulative to Date Deficient (Red)
Week

18

18

Closed

Open
None
Satisfactory (Green)

18

Status of Deliverables (PQP/QCP/ITP)


S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
21
1
8
41

PQP
ITP
QCP
QMP
LTSC

1
21
1
8
41

1
19
1
7
41

Quality Tool Box Talks

194
31
156

Total Issued
Total Open
Total Closed

5
0
5

Total Rejected

Total Rejected

Total cancelled

Total cancelled

SDR status (Specification Deviation Request)


GCC SDR
8

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Total SDR Cancelled

Nil

Total SDR Closed

Total SDR open

N/A

MEP - 8

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk

Score (%)

Score (%)

This Period

Last Period

Civil(C300 &
C200)

90 & 90%

90 & 93.33%

0.0

Civil(C300 &
C200)

89 & 94.2%

90 & 90 %

0.0

Discipline

Total Issued
Total Open
Total Closed

Items
Total SDR Issued

Total Condcuted : 6, This week : 0


Description:

FTR status (Field Trouble Request)

FCS status (Field Change Sheet)

N/A
Concern (Amber)

% Difference

Action Required
Yes

No

Remarks

90.00%

89& 94.2&%

0.0

Civil(C300 & B200,C200)

90.00%

90.00%

0.0

No QWT in B200/C200 due


to red flag

Date

Scheduled(Upcoming)

25-Sep-2012

Completed(Previous)

15-Aug-2012

Item

Date
30-Aug-2012

Completed(Previous)-R.C.Piping

29-Jul-2012

Total

Completed

Balance

Total Trained

67

Barzan on shore project - Building works - Package#2

66

JGC Witnessed

232

166

66

87

59

28

DFO Complete as of
QA/QC Highlights

0%

1) percentage of cancellation : 28.45 %

Note : (Reason for RFI Rejection) - N/A

Total

Completed

Balance

Total Trained

14

Total

Completed

Balance

Total Trained

Cumulative
Date

Scheduled(Upcoming)-

Completed(Previous)-piping

Cancelled

Cumulative

JGC Craft Training (*) Item

Rejected

166

Cumulative

Discipline Training (*)(In Next 6 months)

Scheduled(Upcoming)-LV,MV&HV Cables

Accepted

232

Document For Operation (DFO)


No QWT in B200/C200 due
to red flag

Item

Issued

CPY Witnessed

Civil(C300 &
B200,C200)

Quality awareness Training (Refresher)

Items
Issued This Week

18-Apr-2012

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

29-Aug-2012

To:

04-Sep-2012

Rep. No.:

"Leading" Indicators

"Lagging" Indicators

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR Status (Non-Conformance Report)

27

Items

As of Today : 24

WQM-GCC-041

Plan

Actual

JGC

GCC

LTSC

Total NCR Issued

14

FQCM & FQAM(Civil&Arch.)

Total NCR Closed

11

DFQC Manager(Civil&Arch.)

Total NCR Open

Lead QC engineer(Civil&Arch.)

Total NCR Issued (This Week)

QC Inspectors(Civil&Arch.)

MEP QC Mgr/QCI[GCC+BEMCCO]

CQCC/Assistant

Document controller(GCC+BEMCCO)

DFO

TOTAL

27

CPY CAR Status


CPY DR Status
(Deficiency Report)

24
Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

6th IA : 23-09-12

GCC-IA

Status in
brief

Completed(L
ast)

5th IA : 14&16.06.12

GCC-IA

Issued

15

Total :

11

Closed

15

Balance :

Open

Cumulative :
Completed: 05

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

JGC
OBS

CAR

GCC/LTSC

OBS

Total CAR Issued


Total DR Issued

CAR

Internal Quality Audits


Item

NCR Status (Non-Conformance Report)

CTR CAR Status


(Corrective Action Request)

18

Total CAR Issued

10

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

Note : Next JGC Activity audit scheduled on 16-09-12


CPY Q & IM Assessment
Assessment Title

C/list No.

Findings

Closed

None

Total No. of
Assessment

Conducted this
Week

18

Cumulative to Date Deficient (Red)

18

Open
None
Satisfactory (Green)

18

Status of Deliverables (PQP/QCP/ITP)


S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
22
1
8
41

PQP
ITP
QCP
QMP
LTSC

1
22
1
8
41

1
17
1
7
41

Quality Tool Box Talks

200
22
169

Total Issued
Total Open
Total Closed

5
0
5

Total Rejected

Total Rejected

Total cancelled

Total cancelled

SDR status (Specification Deviation Request)


GCC SDR
8

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Total SDR Cancelled

Nil

Total SDR Closed

Total SDR open

N/A

MEP - 8

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk

Score (%)

Score (%)

This Period

Last Period

Civil(C300 &
C200)

89 & 94.2%

90 & 90 %

0.0

Civil(C300 &
C200)

90.00%

89& 94.2&%

0.0

Discipline

Total Issued
Total Open
Total Closed

Items
Total SDR Issued

Total Condcuted : 6, This week : 0


Description:

FTR status (Field Trouble Request)

FCS status (Field Change Sheet)

N/A
Concern (Amber)

% Difference

Action Required
Yes

No

Remarks

90.00%

90.00%

0.0

Civil(C300 & B200,C200)

90.00%

90.00%

0.0

No QWT in B200/C200 due


to red flag

Date

Scheduled(Upcoming)

25-Sep-2012

Completed(Previous)

15-Aug-2012

Date

Scheduled(Upcoming)-Ceramic Tiling

09-Sep-2012

Completed(Previous)-LV,MV&HV Cables

30-Aug-2012

Completed

Balance

Total Trained

67

Barzan on shore project - Building works - Package#2

52

JGC Witnessed

270

218

52

131

100

31

DFO Complete as of
QA/QC Highlights

0%

1) percentage of cancellation : 19.25 %

Note : (Reason for RFI Rejection) - N/A

Total

Completed

Balance

Total Trained

23

Total

Completed

Balance

Total Trained

Cumulative
Date

Scheduled(Upcoming)-

Completed(Previous)-piping

Cancelled

Cumulative

JGC Craft Training (*) Item

Rejected

218

Cumulative
Total

Discipline Training (*)(In Next 6 months)


Item

Accepted

270

Document For Operation (DFO)


No QWT in B200/C200 due
to red flag

Item

Issued

CPY Witnessed

Civil(C300 &
B200,C200)

Quality awareness Training (Refresher)

Items
Issued This Week

18-Apr-2012

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

05-Sep-2012

To:

11-Sep-2012

Rep. No.:

"Leading" Indicators

"Lagging" Indicators

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR Status (Non-Conformance Report)

31

Items

As of Today : 24

WQM-GCC-042

Plan

Actual

JGC

GCC

LTSC

Total NCR Issued

14

FQCM & FQAM(Civil/Arch./MEP)

Total NCR Closed

11

DFQC Manager(Civil&Arch.)

Total NCR Open

Lead QC engineer(Civil/Arch./MEP)

Total NCR Issued (This Week)

QC Inspectors(Civil&Arch.)

QC Inspectors(MEP)

CQCC/Assistant

Document controller

DFO

TOTAL

31

CPY CAR Status


CPY DR Status
(Deficiency Report)

24
Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

6th IA : 23-09-12

GCC-IA

Status in
brief

Completed(L
ast)

5th IA : 14&16.06.12

GCC-IA

Issued

15

Total :

11

Closed

15

Balance :

Open

Cumulative :
Completed: 05

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

JGC
OBS

CAR

GCC/LTSC

OBS

Total CAR Issued


Total DR Issued

CAR

Internal Quality Audits


Item

NCR Status (Non-Conformance Report)

CTR CAR Status


(Corrective Action Request)

18

Total CAR Issued

10

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

Note : Next JGC Activity audit scheduled on 16-09-12


CPY Q & IM Assessment
Assessment Title

C/list No.

Findings

Closed

None

Total No. of
Assessment

Conducted this
Week

18

Cumulative to Date Deficient (Red)

18

Open
None
Satisfactory (Green)

18

Status of Deliverables (PQP/QCP/ITP)


S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
22
1
8
41

PQP
ITP
QCP
QMP
LTSC

1
22
1
8
41

1
18
1
7
41

Quality Tool Box Talks

Weekly Site Quality Walk


This Period

Last Period

Civil(C300 &
C200)

90.00%

89& 94.2&%

0.0

Civil(C300 &
C200)

90.00%

90.00%

0.0

Civil(C300 & B200/C200)

180

Total Issued
Total Open
Total Closed

5
0
5

Total Rejected

Total Rejected

Total cancelled

Total cancelled

SDR status (Specification Deviation Request)


GCC SDR
8

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Total SDR Cancelled

Nil

Total SDR Closed

Total SDR open

MEP - 8

Weekly Field Inspection Status (RFI)


Score (%)

Civil(C300 &
B200,C200)

217
28

N/A

Score (%)

Discipline

Total Issued
Total Open
Total Closed

Items
Total SDR Issued

Total Condcuted : 6, This week : 0


Description:

FTR status (Field Trouble Request)

FCS status (Field Change Sheet)

N/A
Concern (Amber)

% Difference

90.00%

90.00%

0.0

85/92/76.4

90.00%

0.0

Action Required
Yes

Date

Scheduled(Upcoming)

25-Sep-2012

Completed(Previous)

01-Sep-2012

Date

Scheduled(Upcoming)-HVAC Series 2

19-Sep-2012

Completed(Previous)-LV,MV&HV Cables

30-Aug-2012

Barzan on shore project - Building works - Package#2

Cancelled

79

JGC Witnessed

343

264

79

168

121

45

DFO Complete as of
QA/QC Highlights

0%

Cumulative
Balance

Total Trained

107

1) percentage of cancellation : 23.00 %

Note : (Reason for RFI Rejection) - Due to the missing saddle clamp.

Cumulative
Total

Completed

Balance

Total Trained

23

Total

Completed

Balance

Total Trained

Cumulative
Date

Scheduled(Upcoming)-

Completed(Previous)-piping

Rejected

264

Document For Operation (DFO)


No QWT in B200/C200 due
to red flag

Completed

JGC Craft Training (*) Item

Accepted

343

CPY Witnessed

Total

Discipline Training (*)(In Next 6 months)


Item

Remarks

Issued

[C300 Ele.] Reconducted on


9/9/12 and scored:94.16%

Quality awareness Training (Refresher)


Item

No

Items
Issued This Week

18-Apr-2012

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

12-Sep-2012

To:

18-Sep-2012

Rep. No.:

"Leading" Indicators

"Lagging" Indicators

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR Status (Non-Conformance Report)

31

Items

As of Today : 25

WQM-GCC-043

Plan

Actual

JGC

GCC

LTSC

Total NCR Issued

14

FQCM & FQAM(Civil/Arch./MEP)

Total NCR Closed

11

DFQC Manager(Civil&Arch.)

Total NCR Open

Lead QC engineer(Civil/Arch./MEP)

Total NCR Issued (This Week)

QC Inspectors(Civil&Arch.)

QC Inspectors(MEP)

CQCC/QC Assistant

Document controller

DFO

TOTAL

31

CPY CAR Status


CPY DR Status
(Deficiency Report)

25
Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

6th IA : 23-09-12

GCC-IA

Status in
brief

Completed(L
ast)

5th IA : 14&16.06.12

GCC-IA

Issued

15

Total :

11

Closed

15

Balance :

Open

Cumulative :
Completed: 05

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

JGC
OBS

CAR

GCC/LTSC

OBS

Total CAR Issued


Total DR Issued

CAR

Internal Quality Audits


Item

NCR Status (Non-Conformance Report)

CTR CAR Status


(Corrective Action Request)

18

Total CAR Issued

10

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

Note : Next JGC Activity audit scheduled on 16-09-12


CPY Q & IM Assessment
Assessment Title

Findings

C300-MEP Works(17/9/12) : 88.89%

None

C/list No.
1

Total No. of
Assessment

Conducted this
Week

19

Cumulative to Date Deficient (Red)

19

Closed

Open
None
Satisfactory (Green)

19

Status of Deliverables (PQP/QCP/ITP)


S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
22
1
8
41

PQP
ITP
QCP
QMP
LTSC

1
22
1
8
41

1
20
1
8
41

Quality Tool Box Talks

Score (%)

This Period

Last Period

90.00%

90.00%

Civil(C300 &
C200)

197

90.00%

Total Issued
Total Open
Total Closed

5
0
5

Total Rejected

Total Rejected

Total cancelled

Total cancelled

SDR status (Specification Deviation Request)


GCC SDR
8

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Total SDR Cancelled

Nil

Total SDR Closed

Total SDR open

MEP - 8

Weekly Field Inspection Status (RFI)

Score (%)

Civil(C300 &
C200)

241
35

N/A
Weekly Site Quality Walk

Discipline

Total Issued
Total Open
Total Closed

Items
Total SDR Issued

Total Condcuted : 6, This week : 0


Description:

FTR status (Field Trouble Request)

FCS status (Field Change Sheet)

N/A
Concern (Amber)

% Difference

Action Required
Yes

0.0

90.00%

85/92/76.4

90.00%

0.0

C300 &
B200/C200

88.18/93/69

85/92/76.4

0.0

Date

Scheduled(Upcoming)

25-Sep-2012

Completed(Previous)

01-Sep-2012

Date

Scheduled(Upcoming)-HVAC Series 2

19-Sep-2012

Completed(Previous)-LV,MV&HV Cables

30-Aug-2012

Barzan on shore project - Building works - Package#2

Accepted

Rejected

Cancelled

341

270

71

JGC Witnessed

341

270

71

197

137

60

Document For Operation (DFO)


DFO Complete as of
QA/QC Highlights

0%

C300 Civil/Elec,Mech.

Cumulative
Balance

Total Trained

107

1) percentage of cancellation : 20.8 %

Note : (Reason for RFI Rejection) - N/A

Cumulative
Total

Completed

Balance

Total Trained

23

Total

Completed

Balance

Total Trained

Cumulative
Date

Scheduled(Upcoming)-

Completed(Previous)-piping

[C300 Ele.] Reconducted on


9/9/12 and scored:94.16%

Completed

JGC Craft Training (*) Item

Total

Discipline Training (*)(In Next 6 months)


Item

Issued

CPY Witnessed
No QWT in B200/C200 due
to red flag

Quality awareness Training (Refresher)


Item

Remarks

0.0

Civil(C300 &
B200,C200)

No

Items
Issued This Week

18-Apr-2012

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

19-Sep-2012

To:

25-Sep-2012

Rep. No.:

"Leading" Indicators

"Lagging" Indicators

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR Status (Non-Conformance Report)

31

Items

As of Today : 25

WQM-GCC-044

Plan

Actual

JGC

GCC

LTSC

Total NCR Issued

14

FQCM & FQAM(Civil/Arch./MEP)

Total NCR Closed

11

DFQC Manager(Civil&Arch.)

Total NCR Open

Lead QC engineer(Civil/Arch./MEP)

Total NCR Issued (This Week)

QC Inspectors(Civil&Arch.)

QC Inspectors(MEP)

CQCC/QC Assistant

Document controller

DFO

TOTAL

31

CPY CAR Status


CPY DR Status
(Deficiency Report)

25
Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

6th IA : 14-10-12

GCC-IA

Status in
brief

Completed(L
ast)

5th IA : 14&16.06.12

GCC-IA

Issued

15

Total :

11

Closed

15

Balance :

Open

Cumulative :
Completed: 05

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

JGC
OBS

CAR

GCC/LTSC

OBS

Total CAR Issued


Total DR Issued

CAR

Internal Quality Audits


Item

NCR Status (Non-Conformance Report)

CTR CAR Status


(Corrective Action Request)

29

Total CAR Issued

21

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

Note :
CPY Q & IM Assessment
C/list No.
1

Assessment Title

Findings

HVAC[C300] & SITE LAB

None

Total No. of
Assessment

Conducted this
Week

22

Cumulative to Date Deficient (Red)

22

Closed

Open
None
Satisfactory (Green)

22

Status of Deliverables (PQP/QCP/ITP)


S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
22
1
8
41

PQP
ITP
QCP
QMP
LTSC

1
22
1
8
41

1
20
1
8
41

Quality Tool Box Talks

Civil(C300 &
C200)

Score (%)

This Period

Last Period

90.00%

90.00%

85/92/76.4

217

Total Issued
Total Open
Total Closed

5
0
5

Total Rejected

Total Rejected

Total cancelled

Total cancelled

SDR status (Specification Deviation Request)


GCC SDR
8

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Total SDR Cancelled

Nil

Total SDR Closed

Total SDR open

MEP - 8

Weekly Field Inspection Status (RFI)

Score (%)

Civil(C300 &
C200)

258
26

N/A
Weekly Site Quality Walk

Discipline

Total Issued
Total Open
Total Closed

Items
Total SDR Issued

Total Condcuted : 6, This week : 0


Description:

FTR status (Field Trouble Request)

FCS status (Field Change Sheet)

N/A
Concern (Amber)

% Difference

Action Required
Yes

0.0

90.00%

0.0

Civil(C300 &
B200,C200)

88.18/93/69

85/92/76.4

0.0

C300 &
B200/C200

90/93/89%

88.18/93/69

0.0

Date

Scheduled(Upcoming)

10-Oct-2012

Completed(Previous)

01-Sep-2012

Date

Scheduled(Upcoming)-Tiles/Doors

26-Sep-2012

Completed(Previous)-HVAC Series 2

19-Sep-2012

Barzan on shore project - Building works - Package#2

Issued

Accepted

Rejected

Cancelled

330

270

57

JGC Witnessed

330

270

57

166

116

23

CPY Witnessed

Document For Operation (DFO)


DFO Complete as of
QA/QC Highlights

C300 Civil/Elec,Mech.

0%

[C300 Ele.] Reconducted on


16/9/12 and scored:89%

Cumulative
Completed

Balance

Total Trained

107

Cumulative
Total

Completed

Balance

Total Trained

35

Total

Completed

Balance

Total Trained

1) percentage of cancellation : 17.3 %

Note : (Reason for RFI Rejection) - Offsite fabrication works(Handrails) surface


preparation prior to paint application

Cumulative
Date

Scheduled(Upcoming)-

Completed(Previous)-piping

[C300 Ele.] Reconducted on


9/9/12 and scored:94.16%

Total

JGC Craft Training (*) Item

No QWT in B200/C200 due to

Discipline Training (*)(In Next 6 months)


Item

Remarks

Quality awareness Training (Refresher)


Item

No

Items
Issued This Week

18-Apr-2012

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

26-Sep-2012

To:

02-Oct-2012

Rep. No.:

"Leading" Indicators

"Lagging" Indicators

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR Status (Non-Conformance Report)

31

Items

As of Today : 26

WQM-GCC-045

Plan

Actual

JGC

GCC

LTSC

Total NCR Issued

14

FQCM & FQAM(Civil/Arch./MEP)

Total NCR Closed

11

DFQC Manager(Civil&Arch.)

Total NCR Open

Lead QC engineer(Civil/Arch./MEP)

Total NCR Issued (This Week)

QC Inspectors(Civil&Arch.)

QC Inspectors(MEP)

10

CQCC/QC Assistant

Document controller

DFO

TOTAL

31

CPY CAR Status


CPY DR Status
(Deficiency Report)

26

Internal Quality Audits

Audit Findings (*)

Total CAR Issued

Total DR Issued

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

Date

Discipline

Scheduled(N
ext)

6th IA : 14-10-12

GCC-IA

Status in
brief

Completed(L
ast)

5th IA : 14&16.06.12

GCC-IA

Issued

15

29

Total :

11

Closed

15

12

Total CAR Issued

Balance :

Open

17

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

Cumulative :
Completed: 05

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

NCR Status (Non-Conformance Report)

CTR CAR Status


(Corrective Action Request)

Note :
CPY Q & IM Assessment
Assessment Title

C/list No.

Findings

Closed

None

Total No. of
Assessment

Conducted this
Week

22

Cumulative to Date Deficient (Red)

22

Open
None
Satisfactory (Green)

22

Status of Deliverables (PQP/QCP/ITP)


S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
22
1
8
41

PQP
ITP
QCP
QMP
LTSC

1
22
1
8
41

1
17
1
8
41

Quality Tool Box Talks

275
28
226

Total Issued
Total Open
Total Closed

5
0
5

Total Rejected

Total Rejected

Total cancelled

12

Total cancelled

SDR status (Specification Deviation Request)


GCC SDR
8

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Total SDR Cancelled

Nil

Total SDR Closed

Total SDR open

N/A

MEP - 8

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk

Discipline

Total Issued
Total Open
Total Closed

Items
Total SDR Issued

Total Condcuted : 6, This week : 0


Description:

FTR status (Field Trouble Request)

FCS status (Field Change Sheet)

N/A
Concern (Amber)

Score (%)

Score (%)

This Period

Last Period

% Difference

Action Required
Yes

No

Remarks

Civil(C300 &
C200)

85/92/76.4

90.00%

0.0

Civil(C300 &
C200)

88.18/93/69

85/92/76.4

0.0

C300 Civil/Elec,Mech.

[C300 Ele.] Reconducted on


9/9/12 and scored:94.16%

90/93/89%

88.18/93/69

0.0

[C300 Ele.] Reconducted on


16/9/12 and scored:89%

C300 &
B200/C200

90/90/86%

90/93/89%

0.0

C300 Civil/Elec/Mech.

Item

Date

Scheduled(Upcoming)

10-Oct-2012

Completed(Previous)

01-Sep-2012

Date

Scheduled(Upcoming)-Tiles/Doors

11-Oct-2012

Completed(Previous)-HVAC Series 2

26-Sep-2012

Completed

Balance

Total Trained

107

Cumulative
Total

Completed

Balance

Total Trained

40

Total

Completed

Balance

Total Trained

JGC Craft Training (*) Item

Barzan on shore project - Building works - Package#2

Rejected

Cancelled

243

67

JGC Witnessed

316

243

67

147

107

38

CPY Witnessed

DFO Complete as of
QA/QC Highlights

0%

1) percentage of cancellation : 21.2 %

Note : (Reason for RFI Rejection) - Pressure test & Cable insulation test
related.

Cumulative
Date

Scheduled(Upcoming)-

Completed(Previous)-piping

Accepted

316

Cumulative
Total

Discipline Training (*)(In Next 6 months)


Item

Issued

Document For Operation (DFO)

Civil(C300 &
B200,C200)

Quality awareness Training (Refresher)

Items
Issued This Week

18-Apr-2012

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

03-Oct-2012

To:

09-Oct-2012

Rep. No.:

"Leading" Indicators

"Lagging" Indicators

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR Status (Non-Conformance Report)

31

Items

As of Today : 26

WQM-GCC-046

Plan

Actual

JGC

GCC

LTSC

Total NCR Issued

14

FQCM & FQAM(Civil/Arch./MEP)

Total NCR Closed

11

DFQC Manager(Civil&Arch.)

Total NCR Open

Lead QC engineer(Civil/Arch./MEP)

Total NCR Issued (This Week)

QC Inspectors(Civil&Arch.)

QC Inspectors(MEP)

10

CQCC/QC Assistant

Document controller

DFO

TOTAL

31

CPY CAR Status


CPY DR Status
(Deficiency Report)

26

Internal Quality Audits

Audit Findings (*)

Total CAR Issued

Total DR Issued

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

Date

Discipline

Scheduled(N
ext)

6th IA : 14-10-12

GCC-IA

Status in
brief

Completed(L
ast)

5th IA : 14&16.06.12

GCC-IA

Issued

15

29

Total :

11

Closed

15

12

Total CAR Issued

Balance :

Open

17

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

Cumulative :
Completed: 05

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

NCR Status (Non-Conformance Report)

CTR CAR Status


(Corrective Action Request)

Note :
CPY Q & IM Assessment
Assessment Title

C/list No.

Findings

Closed

None

Total No. of
Assessment

Conducted this
Week

22

Cumulative to Date Deficient (Red)

22

Open
None
Satisfactory (Green)

22

Status of Deliverables (PQP/QCP/ITP)


S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
22
1
8
41

PQP
ITP
QCP
QMP
LTSC

1
22
1
8
42

1
16
1
7
41

Quality Tool Box Talks

286
27
237

Total Issued
Total Open
Total Closed

5
0
5

Total Rejected

Total Rejected

Total cancelled

15

Total cancelled

SDR status (Specification Deviation Request)


GCC SDR
8

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Total SDR Cancelled

Nil

Total SDR Closed

Total SDR open

N/A

MEP - 8

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk

Score (%)

Score (%)

This Period

Last Period

Civil(C300 &
C200)

88.18/93/69

85/92/76.4

0.0

Civil(C300 &
C200)

90/93/89%

88.18/93/69

0.0

Discipline

Total Issued
Total Open
Total Closed

Items
Total SDR Issued

Total Condcuted : 6, This week : 0


Description:

FTR status (Field Trouble Request)

FCS status (Field Change Sheet)

N/A
Concern (Amber)

% Difference

Action Required
Yes

No

90/90/86%

90/93/89%

0.0

C300 &
B200/C200

91/88/90%

90/90/86%

0.0

Quality awareness Training (Refresher)


Date

Scheduled(Upcoming)

10-Oct-2012

Completed(Previous)

01-Sep-2012

Date

Scheduled(Upcoming)-Tiles/Doors

11-Oct-2012

Completed(Previous)-HVAC Series 2

26-Sep-2012

Barzan on shore project - Building works - Package#2

Cancelled

35

JGC Witnessed

285

250

35

139

116

23

0%

Cumulative
Balance

Total Trained

112

1) percentage of cancellation : 12.2 %

Note : (Reason for RFI Rejection) - None

Cumulative
Total

Completed

Balance

Total Trained

40

Total

Completed

Balance

Total Trained

Cumulative
Date

Scheduled(Upcoming)-

Completed(Previous)-piping

Rejected

250

Document For Operation (DFO)

Completed

JGC Craft Training (*) Item

Accepted

285

DFO Complete as of
QA/QC Highlights

Total

Discipline Training (*)(In Next 6 months)


Item

Issued

CPY Witnessed

Civil(C300 &
B200,C200)

Item

Remarks

Items
Issued This Week

18-Apr-2012

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

09-Oct-2012

To:

15-Oct-2012

Rep. No.:

"Leading" Indicators

"Lagging" Indicators

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR Status (Non-Conformance Report)

31

Items

As of Today : 27

WQM-GCC-047

Plan

Actual

JGC

GCC

LTSC

Total NCR Issued

14

FQCM & FQAM(Civil/Arch./MEP)

Total NCR Closed

13

DFQC Manager(Civil&Arch.)

Total NCR Open

Lead QC engineer(Civil/Arch./MEP)

Total NCR Issued (This Week)

QC Inspectors(Civil&Arch.)

QC Inspectors(MEP)

10

CQCC/QC Assistant

Document controller

DFO

TOTAL

31

CPY CAR Status


CPY DR Status
(Deficiency Report)

27

Internal Quality Audits

Audit Findings (*)

Total CAR Issued

Total DR Issued

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

Date

Discipline

Scheduled(N
ext)

7th IA : 17-12-12

GCC-IA

Status in
brief

Completed(L
ast)

6th IA : 14&15.10.12

GCC-IA

Issued

15

29

Total :

11

Closed

15

12

Total CAR Issued

Balance :

Open

17

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

Cumulative :
Completed: 06

JGC
CAR

CAR

OBS

GCC/LTSC

OBS

Item

NCR Status (Non-Conformance Report)

CTR CAR Status


(Corrective Action Request)

Note : 6th Internal Audit Findings yet to receive.


CPY Q & IM Assessment
C/list No.
1
Total No. of
Assessment

Assessment Title

Findings

Closed

Open

Civil & Material Control

None

N/A

None

Concern (Amber)

Satisfactory (Green)

24

Conducted this
Cumulative to Date Deficient (Red)
Week

24

24

Status of Deliverables (PQP/QCP/ITP)


S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
22
1
8
45

PQP
ITP
QCP
QMP
LTSC

1
22
1
8
43

1
19
1
7
43

Quality Tool Box Talks

312
40
248

Total Issued
Total Open
Total Closed

5
0
5

Total Rejected

Total Rejected

Total cancelled

17

Total cancelled

SDR status (Specification Deviation Request)


GCC SDR
8

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Total SDR Cancelled

Nil

Total SDR Closed

Total SDR open

N/A

MEP - 8

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk

Discipline

Total Issued
Total Open
Total Closed

Items
Total SDR Issued

Total Condcuted : 6, This week : 0


Description:

FTR status (Field Trouble Request)

FCS status (Field Change Sheet)

Score (%)

Score (%)

This Period

Last Period

% Difference

Action Required
Yes

No

Civil(C300 &
C200)

90/93/89%

88.18/93/69

1.0

Civil(C300 &
C200)

90/90/86%

90/93/89%

2.0

Civil(C300 &
B200,C200)

91/88/90%

90/90/86%

2.0

C300 &
B200/C200

NO QWT

91/88/90%

0.0

Quality awareness Training (Refresher)


Item

Date

Scheduled(Upcoming)

25-Oct-2012

Completed(Previous)

10-Oct-2012

Item

Date

Barzan on shore project - Building works - Package#2

Accepted

Rejected

Cancelled

318

272

43

JGC Witnessed

318

272

43

157

124

30

CPY Witnessed

Document For Operation (DFO)


0%

Note : QWT Cancelled due


to Fog.

Balance

Total Trained

134

1) percentage of cancellation : 13.52 %

Note : (Reason for RFI Rejection) - Final visual Inspection for Refrigerent pipe/HVAC supports
rejected due to dimensional mis-matching & Masonry blocks surface finish is not good.

Cumulative
Total

Completed

Balance

Total Trained

53

Total

Completed

Balance

Total Trained

11-Oct-2012

Cumulative
Date

Scheduled(Upcoming)-

Completed(Previous)-piping

Issued

Cumulative

JGC Craft Training (*) Item

Items
Issued This Week

DFO Complete as of
QA/QC Highlights

Completed

Schedule yet to confirm

Completed(Previous)-HVAC Series 2

[C300 Ele.] Reconducted on


16/9/12 and scored:89%

Total

Discipline Training (*)(In Next 6 months)

Scheduled(Upcoming)-

Remarks

18-Apr-2012

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

16-Oct-2012

To:

22-Oct-2012

Rep. No.:

"Leading" Indicators

"Lagging" Indicators

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR Status (Non-Conformance Report)

31

Items

As of Today : 27

WQM-GCC-048

Plan

Actual

JGC

GCC

LTSC

Total NCR Issued

14

FQCM & FQAM(Civil/Arch./MEP)

Total NCR Closed

13

DFQC Manager(Civil&Arch.)

Total NCR Open

Lead QC engineer(Civil/Arch./MEP)

Total NCR Issued (This Week)

QC Inspectors(Civil&Arch.)

QC Inspectors(MEP)

10

CQCC/QC Assistant

Document controller

DFO

TOTAL

31

CPY CAR Status


CPY DR Status
(Deficiency Report)

27

Internal Quality Audits

Audit Findings (*)

Total CAR Issued

Total DR Issued

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

Date

Discipline

Scheduled(N
ext)

7th IA : 17-12-12

GCC-IA

Status in
brief

Completed(L
ast)

6th IA : 14&15.10.12

GCC-IA

Issued

21

29

Total :

11

Closed

15

12

Total CAR Issued

Balance :

Open

17

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

Cumulative :
Completed: 06

JGC
CAR

CAR

OBS

GCC/LTSC

OBS

Item

NCR Status (Non-Conformance Report)

CTR CAR Status


(Corrective Action Request)

CPY Q & IM Assessment


C/list No.
1
Total No. of
Assessment

Assessment Title

Findings

Closed

Open

Supervisory & HVAC control

None

N/A

None

Concern (Amber)

Satisfactory (Green)

26

Conducted this
Cumulative to Date Deficient (Red)
Week

26

26

Status of Deliverables (PQP/QCP/ITP)


S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
22
1
8
45

PQP
ITP
QCP
QMP
LTSC

1
22
1
8
44

1
20
1
8
43

Quality Tool Box Talks

344
42
275

Total Issued
Total Open
Total Closed

5
0
5

Total Rejected

Total Rejected

Total cancelled

18

Total cancelled

SDR status (Specification Deviation Request)


GCC SDR
8

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Total SDR Cancelled

Nil

Total SDR Closed

Total SDR open

N/A

MEP - 8

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk

Score (%)

Score (%)

This Period

Last Period

Civil(C300 &
C200)

90/90/86%

90/93/89%

1.0

Civil(C300 &
C200)

91/88/90%

90/90/86%

2.0

Civil(C300 &
B200,C200)

NO QWT

91/88/90%

2.0

C300 &
B200/C200

92/90/88.1%

NO QWT

0.0

Discipline

Total Issued
Total Open
Total Closed

Items
Total SDR Issued

Total Condcuted : 6, This week : 0


Description:

FTR status (Field Trouble Request)

FCS status (Field Change Sheet)

% Difference

Action Required
Yes

Date

Scheduled(Upcoming)

30-Oct-2012

Completed(Previous)

10-Oct-2012

Item

Date
07-Nov-2012

Completed(Previous)-HVAC Series 2

11-Oct-2012

Barzan on shore project - Building works - Package#2

Rejected

Cancelled

221

57

JGC Witnessed

280

221

57

148

114

32

DFO Complete as of
QA/QC Highlights

0%

Balance

Total Trained

134

1) percentage of cancellation : 20.35 %

Note : (Reason for RFI Rejection) - Material Not segregated properly & Painting inspection rejected
due to miscommunication between CTR & CPY.

Cumulative
Total

Completed

Balance

Total Trained

53+

Total

Completed

Balance

Total Trained

Cumulative
Date

Scheduled(Upcoming)-

Completed(Previous)-piping

Accepted

280

Cumulative
Completed

JGC Craft Training (*) Item

Issued

Document For Operation (DFO)


Note : QWT Cancelled due to
Fog.

Total

Refresher Discipline Training (*)(In Next 6 months)

Scheduled(Upcoming)-

Items
Issued This Week

CPY Witnessed

Quality awareness Training (Refresher)


Item

No

Remarks

18-Apr-2012

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

23-Oct-2012

To:

29-Oct-2012

Rep. No.:

"Leading" Indicators

"Lagging" Indicators

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR Status (Non-Conformance Report)

31

Items

As of Today : 27

WQM-GCC-049

Plan

Actual

JGC

GCC

LTSC

Total NCR Issued

14

FQCM & FQAM(Civil/Arch./MEP)

Total NCR Closed

13

DFQC Manager(Civil&Arch.)

Total NCR Open

Lead QCI (Civil/Arch./MEP)

Total NCR Issued (This Week)

QC Inspectors(Civil&Arch.)

QC Inspectors(MEP)

10

CQCC/QC Assistant

Document controller

DFO

TOTAL

31

CPY CAR Status


CPY DR Status
(Deficiency Report)

27

Internal Quality Audits

Audit Findings (*)

Total CAR Issued

Total DR Issued

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

Date

Discipline

Scheduled(N
ext)

7th IA : 17-12-12

GCC-IA

Status in
brief

Completed(L
ast)

6th IA : 14&15.10.12

GCC-IA

Issued

21

31

Total :

11

Closed

15

12

Total CAR Issued

Balance :

Open

19

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

Cumulative :
Completed: 06

JGC
CAR

CAR

OBS

GCC/LTSC

OBS

Item

NCR Status (Non-Conformance Report)

CTR CAR Status


(Corrective Action Request)

CPY Q & IM Assessment


Assessment Title

C/list No.

Findings

Closed

Open

None

N/A

None

Concern (Amber)

Satisfactory (Green)

26

1
Total No. of
Assessment

Conducted this
Cumulative to Date Deficient (Red)
Week

26

26

Status of Deliverables (PQP/QCP/ITP)


S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
23
1
8
44

PQP
ITP
QCP
QMP
LTSC

1
23
1
8
44

1
20
1
8
44

Quality Tool Box Talks

350
30
295

Total Issued
Total Open
Total Closed

5
0
5

Total Rejected

Total Rejected

Total cancelled

17

Total cancelled

SDR status (Specification Deviation Request)


GCC SDR
8

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Total SDR Cancelled

Nil

Total SDR Closed

Total SDR open

N/A

MEP - 8

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk

Score (%)

Score (%)

This Period

Last Period

Civil(C300 &
C200)

91/88/90%

90/90/86%

2.0

Civil(C300 &
C200)

NO QWT

91/88/90%

2.0

Civil(C300 &
B200,C200)

92/90/88.1%

NO QWT

0.0

C300 &
B200/C200

91.25&93.6%

92/90/88.1%

2.0

Discipline

Total Issued
Total Open
Total Closed

Items
Total SDR Issued

Total Condcuted : 6, This week : 0


Description:

FTR status (Field Trouble Request)

FCS status (Field Change Sheet)

% Difference

Action Required
Yes

Date

Scheduled(Upcoming)

Yet to submit

Completed(Previous)

30-Oct-2012

Item

Date
07-Nov-2012

Completed(Previous)-HVAC Series 2

11-Oct-2012

Barzan on shore project - Building works - Package#2

Rejected

Cancelled

150

47

JGC Witnessed

197

150

47

111

73

38

Document For Operation (DFO)


0%

Cumulative
Balance

Total Trained

147

1) percentage of cancellation : 23.85 %

Note : (Reason for RFI Rejection) - N/A

Cumulative
Total

Completed

Balance

Total Trained

53+

Total

Completed

Balance

Total Trained

Cumulative
Date

Scheduled(Upcoming)-

Completed(Previous)-piping

Accepted

197

DFO Complete as of
QA/QC Highlights

Completed

JGC Craft Training (*) Item

Issued

Note : QWT Cancelled due


to Fog.

Total

Refresher Discipline Training (*)(In Next 6 months)

Scheduled(Upcoming)-

Items
Issued This Week

CPY Witnessed

Quality awareness Training (Refresher)


Item

No

Remarks

18-Apr-2012

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

30-Oct-2012

To:

05-Nov-2012

Rep. No.:

"Leading" Indicators

"Lagging" Indicators

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR Status (Non-Conformance Report)

31

Items

As of Today : 27

WQM-GCC-050

Plan

Actual

JGC

GCC

LTSC

Total NCR Issued

14

FQCM & FQAM(Civil/Arch./MEP)

Total NCR Closed

13

DFQC Manager(Civil&Arch.)

Total NCR Open

Lead QCI (Civil/Arch./MEP)

Total NCR Issued (This Week)

QC Inspectors(Civil&Arch.)

QC Inspectors(MEP)

10

CQCC/QC Assistant

Document controller

DFO

TOTAL

31

CPY CAR Status


CPY DR Status
(Deficiency Report)

27

Internal Quality Audits

Audit Findings (*)

Total CAR Issued

Total DR Issued

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

Date

Discipline

Scheduled(N
ext)

7th IA : 17-12-12

GCC-IA

Status in
brief

Completed(L
ast)

6th IA : 14&15.10.12

GCC-IA

Issued

21

31

Total :

11

Closed

15

12

Total CAR Issued

Balance :

Open

19

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

Cumulative :
Completed: 06

JGC
CAR

CAR

OBS

GCC/LTSC

OBS

Item

NCR Status (Non-Conformance Report)

CTR CAR Status


(Corrective Action Request)

CPY Q & IM Assessment


C/list No.
1
Total No. of
Assessment

Assessment Title

Findings

Closed

Open

Civil Control[Bldg.]

None

N/A

None

Concern (Amber)

Satisfactory (Green)

27

Conducted this
Cumulative to Date Deficient (Red)
Week

27

27

Status of Deliverables (PQP/QCP/ITP)


S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
23
1
8
44

PQP
ITP
QCP
QMP
LTSC

1
23
1
8
44

1
22
1
8
44

Quality Tool Box Talks

378
31
322

Total Issued
Total Open
Total Closed

5
0
5

Total Rejected

Total Rejected

Total cancelled

16

Total cancelled

SDR status (Specification Deviation Request)


GCC SDR
8

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Total SDR Cancelled

Nil

Total SDR Closed

Total SDR open

N/A

MEP - 8

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk

Discipline

Total Issued
Total Open
Total Closed

Items
Total SDR Issued

Total Condcuted : 6, This week : 0


Description:

FTR status (Field Trouble Request)

FCS status (Field Change Sheet)

Score (%)

Score (%)

This Period

Last Period

% Difference

Action Required
Yes

No

Civil(C300 &
C200)

NO QWT

91/88/90%

2.0

Civil(C300 &
C200)

92/90/88.1%

NO QWT

0.0

Civil(C300 &
B200,C200)

91.25&93.6%

92/90/88.1%

2.0

C300 &
B200/C200

90/91.25/92.8%

91.25&93.6%

1.0

Quality awareness Training (Refresher)


Item

Date

Scheduled(Upcoming)

Yet to submit

Completed(Previous)

30-Oct-2012

Item

Date
07-Nov-2012

Completed(Previous)-HVAC Series 2

11-Oct-2012

Barzan on shore project - Building works - Package#2

Issued

Accepted

Rejected

Cancelled

295

253

42

JGC Witnessed

295

253

42

154

127

27

CPY Witnessed

Document For Operation (DFO)


0%

Cumulative
Balance

Total Trained

147

1) percentage of cancellation : 14.23 %

Note : (Reason for RFI Rejection) - N/A

Cumulative
Total

Completed

Balance

Total Trained

53+

Total

Completed

Balance

Total Trained

Cumulative
Date

Scheduled(Upcoming)-

Completed(Previous)-piping

Items
Issued This Week

DFO Complete as of
QA/QC Highlights

Completed

JGC Craft Training (*) Item

Note : QWT Cancelled due to


Fog.

Total

Refresher Discipline Training (*)(In Next 6 months)

Scheduled(Upcoming)-

Remarks

18-Apr-2012

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

06-Nov-2012

To:

12-Nov-2012

Rep. No.:

"Leading" Indicators

"Lagging" Indicators

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR Status (Non-Conformance Report)

31

Items

As of Today : 28

WQM-GCC-051

Plan

Actual

JGC

GCC

LTSC

Total NCR Issued

14

FQCM & FQAM(Civil/Arch./MEP)

Total NCR Closed

13

DFQC Manager(Civil&Arch.)

Total NCR Open

Lead QCI (Civil/Arch./MEP)

Total NCR Issued (This Week)

QC Inspectors(Civil&Arch.)

QC Inspectors(MEP)

10

CQCC/QC Assistant

Document controller

DFO

TOTAL

31

CPY CAR Status


CPY DR Status
(Deficiency Report)

28

Internal Quality Audits

Audit Findings (*)

Total CAR Issued

Total DR Issued

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

Date

Discipline

Scheduled(N
ext)

7th IA : 17-12-12

GCC-IA

Status in
brief

Completed(L
ast)

6th IA : 14&15.10.12

GCC-IA

Issued

21

31

Total :

11

Closed

15

15

Total CAR Issued

Balance :

Open

16

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

Cumulative :
Completed: 06

JGC
CAR

CAR

OBS

GCC/LTSC

OBS

Item

NCR Status (Non-Conformance Report)

CTR CAR Status


(Corrective Action Request)

CPY Q & IM Assessment


Assessment Title

C/list No.

Findings

Closed

Open

None

N/A

None

Concern (Amber)

Satisfactory (Green)

27

1
Total No. of
Assessment

Conducted this
Cumulative to Date Deficient (Red)
Week

27

27

Status of Deliverables (PQP/QCP/ITP)


S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
23
1
8
44

PQP
ITP
QCP
QMP
LTSC

1
23
1
8
44

1
19
1
8
44

Quality Tool Box Talks

400
36
338

Total Issued
Total Open
Total Closed

5
0
5

Total Rejected

Total Rejected

Total cancelled

17

Total cancelled

SDR status (Specification Deviation Request)


GCC SDR
8

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Total SDR Cancelled

Nil

Total SDR Closed

Total SDR open

N/A

MEP - 8

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk

Score (%)

Score (%)

This Period

Last Period

Civil(C300 &
C200)

92/90/88.1%

NO QWT

0.0

Civil(C300 &
C200)

91.25&93.6%

92/90/88.1%

2.0

Civil(C300 &
B200,C200)

90/91.25/92.8%

91.25&93.6%

1.0

C300 &
B200/C200

90.8&93.85%

90/91.25/92.8%

0.5

Discipline

Total Issued
Total Open
Total Closed

Items
Total SDR Issued

Total Condcuted : 6, This week : 0


Description:

FTR status (Field Trouble Request)

FCS status (Field Change Sheet)

% Difference

Action Required
Yes

Date

Scheduled(Upcoming)

28-Nov-2012

Completed(Previous)

30-Oct-2012

Item

Date
26-Nov-2012

Completed(Previous)-HVAC Series 2

11-Oct-2012

Barzan on shore project - Building works - Package#2

Rejected

Cancelled

265

48

JGC Witnessed

313

265

48

204

175

29

0%

Cumulative
Balance

Total Trained

147+

1) percentage of cancellation : 15.33 %

Note : (Reason for RFI Rejection) - N/A

Cumulative
Total

Completed

Balance

Total Trained

15

15

53+

Total

Completed

Balance

Total Trained

Cumulative
Date

Scheduled(Upcoming)-

Completed(Previous)-piping

Accepted

313

Document For Operation (DFO)

Completed

JGC Craft Training (*) Item

Issued

DFO Complete as of
QA/QC Highlights

Total

Refresher Discipline Training (*)(In Next 6 months)

Scheduled(Upcoming)-

Items
Issued This Week

CPY Witnessed

Quality awareness Training (Refresher)


Item

No

Remarks

18-Apr-2012

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

13-Nov-2012

To:

19-Nov-2012

Rep. No.:

"Leading" Indicators

"Lagging" Indicators

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR Status (Non-Conformance Report)

31

Items

As of Today : 29

WQM-GCC-052

Plan

Actual

JGC

GCC

LTSC

Total NCR Issued

14

FQCM & FQAM(Civil/Arch./MEP)

Total NCR Closed

14

DFQC Manager(Civil&Arch.)

Total NCR Open

Lead QCI (Civil/Arch./MEP)

Total NCR Issued (This Week)

QC Inspectors(Civil&Arch.)

QC Inspectors(MEP)

10

CQCC/QC Assistant

Document controller

DFO

TOTAL

31

CPY CAR Status


CPY DR Status
(Deficiency Report)

29

Internal Quality Audits

Audit Findings (*)

Total CAR Issued

Total DR Issued

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

Date

Discipline

Scheduled(N
ext)

7th IA : 17-12-12

GCC-IA

Status in
brief

Completed(L
ast)

6th IA : 14&15.10.12

GCC-IA

Issued

21

31

Total :

11

Closed

15

15

Total CAR Issued

Balance :

Open

16

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

Cumulative :
Completed: 06

JGC
CAR

CAR

OBS

GCC/LTSC

OBS

Item

NCR Status (Non-Conformance Report)

CTR CAR Status


(Corrective Action Request)

CPY Q & IM Assessment


C/list No.
1

Assessment Title

Findings

Closed

Open

Civil Control/TOMAS

None

N/A

None

Concern (Amber)

Satisfactory (Green)

28

Total No. of
Assessment

Conducted this
Week

29

Cumulative to Date Deficient (Red)

29

Status of Deliverables (PQP/QCP/ITP)


S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
23
1
8
44

PQP
ITP
QCP
QMP
LTSC

1
23
1
8
44

1
17
1
8
44

Quality Tool Box Talks

348

Total Issued
Total Open
Total Closed

5
0
5

Total Rejected

Total Rejected

Total cancelled

17

Total cancelled

SDR status (Specification Deviation Request)


GCC SDR
8

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Total SDR Cancelled

Nil

Total SDR Closed

Total SDR open

MEP - 8

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk
Score (%)

This Period

Last Period

Civil(C300 &
C200)

91.25&93.6%

92/90/88.1%

2.0

Civil(C300 &
C200)

90/91.25/92.8%

91.25&93.6%

1.0

Civil(C300 &
B200,C200)

90.8&93.85%

90/91.25/92.8%

0.5

92.5/95.7/87.5/90%

90.8&93.85%

1.0

C300 &
B200/C200

421
47

N/A

Score (%)

Discipline

Total Issued
Total Open
Total Closed

Items
Total SDR Issued

Total Condcuted : 6, This week : 0


Description:

FTR status (Field Trouble Request)

FCS status (Field Change Sheet)

% Difference

Action Required
Yes

Date

Scheduled(Upcoming)

28-Nov-2012

Completed(Previous)

30-Oct-2012

Item

Date
26-Dec-2012

Completed(Previous)-HVAC Series 2

15-Nov-2012

Barzan on shore project - Building works - Package#2

Rejected

Cancelled

261

40

JGC Witnessed

302

261

40

131

111

20

0%

Total No.of ITR's uploaded on TOMAS : 0


QA/QC Highlights

Cumulative
Balance

Total Trained

147+

1) percentage of cancellation : 13.24 %

Note : (Reason for RFI Rejection) - BSS:105 Bldg. Conduit installation, FCS was not approved.

Cumulative
Total

Completed

Balance

Total Trained

15

14

53+6

Total

Completed

Balance

Total Trained

Cumulative
Date

Scheduled(Upcoming)-

Completed(Previous)-piping

Accepted

302

Document For Operation (DFO)

Completed

JGC Craft Training (*) Item

Issued

DFO Complete as of

Total

Refresher Discipline Training (*)(In Next 6 months)

Scheduled(Upcoming)-

Items
Issued This Week

CPY Witnessed

Quality awareness Training (Refresher)


Item

No

Remarks

18-Apr-2012

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

20-Nov-2012

To:

26-Nov-2012

Rep. No.:

"Leading" Indicators

"Lagging" Indicators

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR Status (Non-Conformance Report)

31

Items

As of Today : 30

WQM-GCC-053

Plan

Actual

JGC

GCC

LTSC

Total NCR Issued

16

FQCM & FQAM(Civil/Arch./MEP)

Total NCR Closed

14

DFQC Manager(Civil&Arch.)

Total NCR Open

Lead QCI (Civil/Arch./MEP)

Total NCR Issued (This Week)

QC Inspectors(Civil&Arch.)

QC Inspectors(MEP)

NCR Status (Non-Conformance Report)

10

10

CQCC/QC Assistant

Document controller

DFO

TOTAL

31

30

Internal Quality Audits

Audit Findings (*)

Total CAR Issued

Total DR Issued

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

Date

Discipline

Scheduled(N
ext)

7th IA : 17-12-12

GCC-IA

Status in
brief

Completed(L
ast)

6th IA : 14&15.10.12

GCC-IA

Issued

21

34

Total :

11

Closed

15

21

Total CAR Issued

Balance :

Open

13

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

Cumulative :
Completed: 06

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

CPY CAR Status


CPY DR Status
(Deficiency Report)

CTR CAR Status


(Corrective Action Request)

CPY Q & IM Assessment


Assessment Title

C/list No.

Findings

Lab control/PMC

1
Total No. of
Assessment

Conducted this
Week

31

Closed

None

Open

N/A

None

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

31

29

Status of Deliverables (PQP/QCP/ITP)


S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
23
1
8
44

PQP
ITP
QCP
QMP
LTSC

1
23
1
8
44

1
16
1
8
44

Quality Tool Box Talks

299

Total Issued
Total Open
Total Closed

5
0
5

Total Rejected

Total Rejected

Total cancelled

16

Total cancelled

SDR status (Specification Deviation Request)


GCC SDR
8

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Total SDR Cancelled

Nil

Total SDR Closed

Total SDR open

MEP - 8

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk
Score (%)

This Period

Last Period

Civil(C300 &
C200)

90/91.25/92.8%

91.25&93.6%

1.0

Civil(C300 &
C200)

90.8&93.85%

90/91.25/92.8%

0.5

Civil(C300 &
B200,C200)

92.5/95.7/87.5/90%

90.8&93.85%

1.0

90.7/91.8/93%

92.5/95.7/87.5/90%

1.0

C300 &
B200/C200

372
48

N/A

Score (%)

Discipline

Total Issued
Total Open
Total Closed

Items
Total SDR Issued

Total Condcuted : 6, This week : 0


Description:

FTR status (Field Trouble Request)

FCS status (Field Change Sheet)

% Difference

Action Required
Yes

Date

Scheduled(Upcoming)

02-Dec-2012

Completed(Previous)

30-Oct-2012

Item

Date
05-Dec-2012

Completed(Previous)-HVAC Series 2

15-Nov-2012

18-Apr-2012

363

307

56

173

151

22

In Progress

Total No.of ITR's uploaded on TOMAS : 500 [BSS-001]


QA/QC Highlights

Balance

Total Trained

147+

1) percentage of cancellation : 15.4 %

Note : (Reason for RFI Rejection) - N/A

Cumulative
Total

Completed

Balance

Total Trained

15

14

53+6

Total

Completed

Balance

Total Trained

Total

Completed

Balance

Total Trained

38

Cumulative
Date

Scheduled(Upcoming)-Plumbing

28-Nov-2012

Completed(Previous)-HVAC & Electrical

25/26-11-12

Barzan on shore project - Building works - Package#2

56

JGC Witnessed

Document For Operation (DFO)

Completed

GCC Craft Training (*) Item

Cancelled

Cumulative
Date

Scheduled(Upcoming)-

Completed(Previous)-piping

Rejected

307

DFO Complete as of

Total

JGC Craft Training (*) Item

Accepted

363

Cumulative

Refresher Discipline Training (*)(In Next 6 months)

Scheduled(Upcoming)-R.C.PIPE

Remarks

Issued

CPY Witnessed

Quality awareness Training (Refresher)


Item

No

Items
Issued This Week

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

27-Nov-2012

To:

03-Dec-2012

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

32

Items

As of Today : 30

Plan

Actual

Total NCR Issued

FQCM & FQAM(Civil/Arch./MEP)

Total NCR Closed

DFQC Manager(Civil&Arch.)

Total NCR Open

Lead QCI (Civil/Arch./MEP)

Total NCR Issued (This Week)

QC Inspectors(Civil&Arch.)

QC Inspectors(MEP)

10

10

CQCC/QC Assistant

Document controller

DFO

NC

CPY DR Status
(Deficiency Report
Total DR Issued
Total DR Closed

TOTAL

32

30

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

7th IA : 17-12-12

GCC-IA

Status in
brief

Completed(L
ast)

6th IA : 14&15.10.12

GCC-IA

Issued

21

34

Total :

11

Closed

15

22

Balance :

Open

12

Cumulative :
Completed: 06

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

CPY Q & IM Assessment


Assessment Title

C/list No.
1
Total No. of
Assessment

Conducted this
Week

31

Findings

Closed

Open

None

N/A

None

FCS status (Field Change Sheet

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

31

29

Status of Deliverables (PQP/QCP/ITP)

Total Rejected

S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
24
1
8
44

PQP
ITP
QCP
QMP
LTSC

1
24
1
8
44

1
20
1
8
44

Quality Tool Box Talks

Discipline

SDR statu
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR open

N/A

Week
Weekly Site Quality Walk

Score (%)

Total cancelled

Total SDR Closed

Total Condcuted : 6, This week : 0


Description:

Total Issued
Total Open
Total Closed

Score (%)

% Difference

Items
Action Required

Remarks

Issued This Week

Discipline

% Difference

This Period

Last Period

Civil(C300 &
C200)

90.8&93.85%

90/91.25/92.8%

0.5

Civil(C300 &
C200)

92.5/95.7/87.5/90%

90.8&93.85%

1.0

Civil(C300 &
B200,C200)
C300 &
B200/C200

Yes

No

92.5/95.7/87.5/90%

1.0

92.5/93.6/91.5/91%

90.7/91.8/93%

0.5

Quality awareness Training (Refresher)


Date

Scheduled(Upcoming)

10-Dec-2012

Completed(Previous)

30-Oct-2012

Date

Scheduled(Upcoming)-R.C.PIPE

05-Dec-2012

Completed(Previous)-HVAC Series 2

15-Nov-2012

Scheduled(Upcoming)-

Completed(Prev.)-Paint/Wire Pull

Completed

Balance

Total Trained

147+

Cumulative

Scheduled(Upcoming)-Conduit Insta.
Completed(Previous)-Refri./Duct/Wire

Barzan on shore project - Building works - Package#2

BSS-001
BSS-107

Est.IT

1
Yet to

Note : Est. ITR No's may vary.

Total

Completed

Balance

Total Trained

15

14

53+6

1) percentage of cancellation :

Cumulative
Date
TBA
02/03-12-12

Total

Completed

Balance

Total Trained

38

GCC Craft Training (*) Item

Building Ref:

Total

JGC Craft Training (*) Item

Docum
DFO Complete as of

Cumulative

Refresher Discipline Training (*)(In Next 6 months)


Item

JGC Witnessed
CPY Witnessed

90.7/91.8/93%

Item

Remarks

Cumulative
Date
06-Dec-2012
29 Nov/01-12-12

Total

Completed

Balance

Total Trained

11

73

Note : (Reason for RFI Rejection)

tracting Co.WLL

nshore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-054

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

16

Total NCR Closed

14

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

FCS status (Field Change Sheet)

Total CAR Issued

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

FTR status (Field Trouble Request)


Total Issued
Total Open
Total Closed

9
0

11

Total Rejected

18

Total cancelled

391
38
324

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
8

Other S/C SDR

MEP - 8

Nil

Weekly Field Inspection Status (RFI)


Issued

Accepted

Rejected

Cancelled

350

303

46

350

303

46

192

164

28

Document For Operation (DFO/TOMAS)


DFO Complete as of

In Progress
TOMAS [Upload]
Est.ITR[No's]

Actual ITR[No's]

% Upload

1200

586

48.8

Yet to calculate

421

TBA

Note : Est. ITR No's may vary.


QA/QC Highlights
1) percentage of cancellation : 13.14 %

Note : (Reason for RFI Rejection) - Joint & Duct support properly not done.

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

04-Dec-2012

To:

10-Dec-2012

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

32

Items

As of Today : 31

Plan

Actual

Total NCR Issued

FQCM & FQAM(Bldg./MEP)

Total NCR Closed

DFQC Manager(Bldg.)

Total NCR Open

Lead QCI (Bldg./MEP) & QCE(MEP)

Total NCR Issued (This Week)

QC Inspectors(Bldg.)

QC Inspectors(MEP)

10

10

CQCC/QC Assistant

Document controller

DFO

NC

CPY DR Status
(Deficiency Report
Total DR Issued
Total DR Closed

TOTAL

32

31

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

7th IA : 17-12-12

GCC-IA

Status in
brief

Completed(L
ast)

6th IA : 14&15.10.12

GCC-IA

Issued

21

34

Total :

11

Closed

15

22

Balance :

Open

12

Cumulative :
Completed: 06

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

CPY Q & IM Assessment


C/list No.
1

Assessment Title

Findings

Closed

Open

Civil control/PMC BSS-109

None

Total No. of
Assessment

Conducted this
Week

33

FCS status (Field Change Sheet

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

33

30

Status of Deliverables (PQP/QCP/ITP)

Total Rejected

S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
24
1
8
44

PQP
ITP
QCP
QMP
LTSC

1
24
1
8
44

1
20
1
8
44

Quality Tool Box Talks

Discipline

SDR statu
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR open

N/A

Week
Weekly Site Quality Walk

Score (%)

Total cancelled

Total SDR Closed

Total Condcuted : 6, This week : 0


Description:

Total Issued
Total Open
Total Closed

Score (%)

% Difference

Items
Action Required

Remarks

Issued This Week

Discipline

% Difference

This Period

Last Period

Civil(C300 &
C200)

92.5/95.7/87.5/90%

90.8&93.85%

0.5

Civil(C300 &
C200)

90.7/91.8/93%

92.5/95.7/87.5/90%

1.0

Civil(C300 &
B200,C200)
C300 &
B200/C200

Yes

No

92.5/93.6/91.5/91%

90.7/91.8/93%

1.0

93.3/91.1/95.2%

92.5/93.6/91.5/91%

0.5

Quality awareness Training (Refresher)


Item

Date

Scheduled(Upcoming)

17-Dec-2012

Completed(Previous)

30-Oct-2012

Date

Scheduled(Upcoming)-R.C.PIPE

16-Dec-2012

Completed(Previous)-HVAC Series 2

15-Nov-2012

Scheduled(Upcoming)-

Completed(Prev.)-Paint/Wire Pull

Building Ref:

Balance

Total Trained

147+

BSS-001
BSS-107

Cumulative
Total

Completed

Balance

Total Trained

15

14

53+6

1) percentage of cancellation :

Cumulative
Date
TBA
02/03-12-12

Total

Completed

Balance

Total Trained

38

Cumulative
Date

Scheduled(Upcoming)-Refrigerant

13-Dec-2012

Completed(Previous)-Cable Tray

11-Dec-2012

Barzan on shore project - Building works - Package#2

Docum
DFO Complete as of

Completed

GCC Craft Training (*) Item

CPY Witnessed

Total

JGC Craft Training (*) Item

JGC Witnessed

Cumulative

Refresher Discipline Training (*)(In Next 6 months)


Item

Remarks

Total

Completed

Balance

Total Trained

16

121

Note : (Reason for RFI Rejection)

tracting Co.WLL

nshore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-055

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

17

Total NCR Closed

14

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

FCS status (Field Change Sheet)

Total CAR Issued

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

FTR status (Field Trouble Request)


9
0

343

Total Issued
Total Open
Total Closed

14

Total Rejected

18

Total cancelled

416
41

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
8

Other S/C SDR

MEP - 8

Nil

Weekly Field Inspection Status (RFI)


Issued

Accepted

Rejected

Cancelled

430

368

61

430

368

61

202

156

46

Document For Operation (DFO/TOMAS)


DFO Complete as of

In Progress
TOMAS [Upload]
ITR's Uploaded [No's]
717
582

QA/QC Highlights
1) percentage of cancellation : 14.18%

Note : (Reason for RFI Rejection) - Grout cubes failes[BSS-001 Electrical panel pedestal]

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

11-Dec-2012

To:

17-Dec-2012

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

34

Items

As of Today : 33

Plan

Actual

Total NCR Issued

FQCM & FQAM(Bldg./MEP)

Total NCR Closed

DFQC Manager(Bldg.)

Total NCR Open

Lead QCI (Bldg./MEP) & QCE(MEP)

Total NCR Issued (This Week)

QC Inspectors(Bldg.)

QC Inspectors(MEP)

10

10

CQCC/QC Assistant

Document controller

DFO Team

NC

CPY DR Status
(Deficiency Report
Total DR Issued
Total DR Closed

TOTAL

34

33

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

8th IA : 24-12-12[QAIG]

GCC-IA

Status in
brief

Completed(L
ast)

7th IA : 17-12-12[GCC]

GCC-IA

Issued

23

34

10

Total :

11

Closed

15

26

Balance :

Open

Cumulative : 11
Completed: 07

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

Note : 7th Internal Audit Findings - 1 CAR & 2 OBS.


CPY Q & IM Assessment
C/list No.
1

Assessment Title

Findings

Closed

Open

Concrete/Bldg/TOMAS

None

Total No. of
Assessment

Conducted this
Week

36

FCS status (Field Change Sheet

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

36

34

Status of Deliverables (PQP/QCP/ITP)

Total Rejected

S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
24
1
8
44

PQP
ITP
QCP
QMP
LTSC

1
24
1
8
44

1
20
1
8
44

Quality Tool Box Talks

Discipline

SDR statu
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR open

N/A

Week
Weekly Site Quality Walk

Score (%)

Total cancelled

Total SDR Closed

Total Condcuted : 6, This week : 0


Description:

Total Issued
Total Open
Total Closed

Score (%)

% Difference

Items
Action Required

Remarks

Issued This Week

Discipline

% Difference

This Period

Last Period

Civil(C300 &
C200)

90.7/91.8/93%

92.5/95.7/87.5/90%

1.0

Civil(C300 &
C200)

92.5/93.6/91.5/91%

90.7/91.8/93%

1.0

Civil(C300 &
B200,C200)
C300 &
B200/C200

Yes

No

93.3/91.1/95.2%

92.5/93.6/91.5/91%

0.5

92.31/93/94/94.5%

93.3/91.1/95.2%

0.5

Quality awareness Training (Refresher)


Item

Date

Scheduled(Upcoming)

20-Dec-2012

Completed(Previous)

30-Oct-2012

Date

Scheduled(Upcoming)-Electrical

20-Dec-2012

Completed(Previous)-R.C.PIPE

15-Dec-2012

Scheduled(Upcoming)-

Completed(Prev.)-Paint/Wire Pull

Docum
DFO Complete as of

Building Ref:

Completed

Balance

Total Trained

147+

BSS-001
BSS-107

Cumulative
Total

Completed

Balance

Total Trained

14

12

53+13

1) percentage of cancellation :

Cumulative
Date
TBA
02/03-12-12

Total

Completed

Balance

Total Trained

38

GCC Craft Training (*) -

Cumulative

Item

Date

Scheduled(Upcoming)-Conduit Insta.

19-Dec-2012

Completed(Previous)-Proper Tools

17-Dec-2012

Barzan on shore project - Building works - Package#2

CPY Witnessed

Total

JGC Craft Training (*) Item

JGC Witnessed

Cumulative

Refresher Discipline Training (*)(In Next 6 months)


Item

Remarks

Total

Completed

Balance

Total Trained

16

11

151

Note : (Reason for RFI Rejection)

tracting Co.WLL

nshore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-056

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

17

Total NCR Closed

15

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

FCS status (Field Change Sheet)

Total CAR Issued

10

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

FTR status (Field Trouble Request)


9
0

363

Total Issued
Total Open
Total Closed

16

Total Rejected

18

Total cancelled

427
30

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
8

Other S/C SDR

MEP - 8

Nil

Weekly Field Inspection Status (RFI)


Issued

Accepted

Rejected

Cancelled

384

322

62

384

322

62

173

140

33

Document For Operation (DFO/TOMAS)


DFO Complete as of

In Progress
TOMAS [Upload]
ITR's Uploaded [No's]
718
584

QA/QC Highlights
1) percentage of cancellation : 16.14%

Note : (Reason for RFI Rejection) - Not Applicable

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

18-Dec-2012

To:

24-Dec-2012

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

34

Items

As of Today : 33

Plan

Actual

Total NCR Issued

FQCM & FQAM(Bldg./MEP)

Total NCR Closed

DFQC Manager(Bldg.)

Total NCR Open

Lead QCI (Bldg./MEP) & QCE(MEP)

Total NCR Issued (This Week)

QC Inspectors(Bldg.)

QC Inspectors(MEP)

10

10

CQCC/QC Assistant

Document controller

DFO Team

NC

CPY DR Status
(Deficiency Report
Total DR Issued
Total DR Closed

TOTAL

34

33

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

9th IA : 13-03-13[GCC]

GCC-IA

Status in
brief

Completed(L
ast)

8th IA : 24-12-12[QAIG]

GCC-IA

Issued

25

34

10

Total :

11

Closed

15

26

Balance :

Open

10

Cumulative : 11
Completed: 08

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

Note : Audit No.08 [QAIG] Findings - 2 OBS.


CPY Q & IM Assessment
C/list No.
1

Assessment Title

Findings

Closed

Open

None [Current week]

N/A

N/A

None

Total No. of
Assessment

Conducted this
Week

36

FCS status (Field Change Sheet

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

36

34

Status of Deliverables (PQP/QCP/ITP)

Total Rejected

S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
24
1
8
44

PQP
ITP
QCP
QMP
LTSC

1
22
1
8
44

1
21
1
5
44

Quality Tool Box Talks

Discipline

SDR statu
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR open

N/A

Week
Weekly Site Quality Walk

Score (%)

Total cancelled

Total SDR Closed

Total Condcuted : 6, This week : 0


Description:

Total Issued
Total Open
Total Closed

Score (%)

% Difference

Items
Action Required

Remarks

Issued This Week

Discipline

% Difference

This Period

Last Period

Civil(C300 &
C200)

92.5/93.6/91.5/91%

90.7/91.8/93%

1.0

Civil(C300 &
C200)

93.3/91.1/95.2%

92.5/93.6/91.5/91%

0.5

Yes

No

Civil(C300 &
B200,C200)

92.31/93/94/94.5%

93.3/91.1/95.2%

0.5

C300 &
B200/C200

91.8/92.85/92.31%

92.31/93/94/94.5%

0.5

Quality awareness Training [Nov'12 to Apr'13]


Item

Date

Scheduled(Upcoming)

30-Dec-2012

Completed(Previous)

20-Dec-2012

Date

Scheduled(Upcoming)-Blockwork/Plaster

02-Jan-2013

Completed(Previous)-Electrical

20-Dec-2012

Docum
DFO Complete as of

Building Ref:

Completed

Balance

Total Trained

147+13

BSS-001
BSS-107
BCCB

Cumulative
Total

Completed

Balance

Total Trained

14

11

53+29

1) percentage of cancellation :

Note : (Reason for RFI Rejection)


60.2,58.8,57.8, Avg : 58.93 Mpa.

Cumulative

Item

Date

Scheduled(Upcoming)-

TBA
02/03-12-12

Total

Completed

Balance

Total Trained

38

GCC Craft Training (*) - Dec'2012

Cumulative

Item

Date

Scheduled(Upcoming)-Conduit Insta.

26-Dec-2012

Completed(Previous)-Proper Tools

24-Dec-2012

Barzan on shore project - Building works - Package#2

CPY Witnessed

Total

JGC Craft Training (*) -

Completed(Prev.)-Paint/Wire Pull

JGC Witnessed

Cumulative

Refresher Discipline Training (*) [Nov'12 to Apr'13]


Item

Remarks

Total

Completed

Balance

Total Trained

16

14

196

tracting Co.WLL

nshore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-057

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

17

Total NCR Closed

15

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

FCS status (Field Change Sheet)

Total CAR Issued

10

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

FTR status (Field Trouble Request)


11
0

359

Total Issued
Total Open
Total Closed

16

Total Rejected

19

Total cancelled

461
67

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
8

Other S/C SDR

MEP - 9

Nil

Weekly Field Inspection Status (RFI)


Issued

Accepted

Rejected

Cancelled

299

266

32

299

266

32

125

101

24

Document For Operation (DFO/TOMAS)


DFO Complete as of

In Progress
TOMAS [Upload]
ITR's Uploaded [No's]
717
582
237

QA/QC Highlights
1) percentage of cancellation : 11%

Note : (Reason for RFI Rejection) - BSS-106,Ground Beam - 28D cube failure, Test Results :
60.2,58.8,57.8, Avg : 58.93 Mpa.

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

25-Dec-2012

To:

31-Dec-2012

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

34

Items

As of Today : 33

Plan

Actual

Total NCR Issued

FQCM & FQAM(Bldg./MEP)

Total NCR Closed

DFQC Manager(Bldg.)

Total NCR Open

Lead QCI (Bldg./MEP) & QCE(MEP)

Total NCR Issued (This Week)

QC Inspectors(Bldg.)

QC Inspectors(MEP)

10

10

CQCC/QC Assistant

Document controller

DFO Team

NC

CPY DR Status
(Deficiency Report
Total DR Issued
Total DR Closed

TOTAL

34

33

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

9th IA : 13-03-13[GCC]

GCC-IA

Status in
brief

Completed(L
ast)

8th IA : 24-12-12[QAIG]

GCC-IA

Issued

25

34

10

Total :

11

Closed

15

30

Balance :

Open

10

Cumulative : 11
Completed: 08

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

Note : Audit No.08 [QAIG] Findings - 2 OBS.


CPY Q & IM Assessment
C/list No.
1

Assessment Title

Findings

Closed

Open

None [Current week]

N/A

N/A

None

Total No. of
Assessment

Conducted this
Week

36

FCS status (Field Change Sheet

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

36

34

Status of Deliverables (PQP/QCP/ITP)

Total Rejected

S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
23
1
8
45

PQP
ITP
QCP
QMP
LTSC

1
23
1
8
45

1
23
1
5
45

Quality Tool Box Talks

Discipline

SDR statu
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR open

N/A

Week
Weekly Site Quality Walk

Score (%)

Total cancelled

Total SDR Closed

Total Condcuted : 6, This week : 0


Description:

Total Issued
Total Open
Total Closed

Score (%)

% Difference

Items
Action Required

Remarks

Issued This Week

Discipline

% Difference

This Period

Last Period

Civil(C300 &
C200)

93.3/91.1/95.2%

92.5/93.6/91.5/91%

0.5

Civil(C300 &
C200)

92.31/93/94/94.5%

93.3/91.1/95.2%

0.5

Civil(C300 &
B200,C200)
C300 &
B200/C200

Yes

No

91.8/92.85/92.31%

92.31/93/94/94.5%

0.5

92.2/92.86/94.5/93.33
%

91.8/92.85/92.31%

0.5

Quality awareness Training [Nov'12 to Apr'13]


Item

Date

Scheduled(Upcoming)

23-Jan-2013

Completed(Previous)

31-Dec-2012

Date

Scheduled(Upcoming)-Blockwork/Plaster

02-Jan-2013

Completed(Previous)-Electrical

20-Dec-2012

Date

Scheduled(Upcoming)-

Completed(Previous)-Wire Termination

Barzan on shore project - Building works - Package#2

Building Ref:

Completed

Balance

Total Trained

147+21

BSS-001
BSS-107
BCCB

Cumulative
Total

Completed

Balance

Total Trained

14

11

53+29

TBA
02/03-12-12

Total

Completed

Balance

Total Trained

38

GCC Craft Training (*) - Dec'2012

Scheduled(Upcoming)

Docum

DFO Complete as of [BSS

1) percentage of cancellation :

Cumulative

Item

Item

CPY Witnessed

Total

JGC Craft Training (*) -

Completed(Prev.)-Paint/Wire Pull

JGC Witnessed

Cumulative

Refresher Discipline Training (*) [Nov'12 to Apr'13]


Item

Remarks

Cumulative
Date
TBA

24-Dec-2012

Total

Completed

Balance

Total Trained

16

16

228

Note : (Reason for RFI Rejection)

tracting Co.WLL

nshore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-058

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

18

Total NCR Closed

15

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

FCS status (Field Change Sheet)

Total CAR Issued

10

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

FTR status (Field Trouble Request)


11
0

400

Total Issued
Total Open
Total Closed

20

Total Rejected

19

Total cancelled

480
41

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
8

Other S/C SDR

MEP - 9

Nil

Weekly Field Inspection Status (RFI)


Issued

Accepted

Rejected

Cancelled

381

361

20

381

361

20

146

135

11

Document For Operation (DFO/TOMAS)


DFO Complete as of [BSS-001]

9 Books

TOMAS [Upload]
ITR's Uploaded [No's]
717
582
1184

QA/QC Highlights
1) percentage of cancellation : 5.24%

Note : (Reason for RFI Rejection) - N/A

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

01-Jan-2013

To:

07-Jan-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

34

Items

As of Today : 33

Plan

Actual

Total NCR Issued

FQCM & FQAM(Bldg./MEP)

Total NCR Closed

DFQC Manager(Bldg.)

Total NCR Open

Lead QCI (Bldg./MEP) & QCE(MEP)

Total NCR Issued (This Week)

QC Inspectors(Bldg.)

QC Inspectors(MEP)

10

10

CQCC/QC Assistant

Document controller

DFO Team

NC

CPY DR Status
(Deficiency Report
Total DR Issued
Total DR Closed

TOTAL

34

33

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

9th IA : 13-03-13[GCC]

GCC-IA

Status in
brief

Completed(L
ast)

8th IA : 24-12-12[QAIG]

GCC-IA

Issued

24

34

10

Total :

11

Closed

15

31

Balance :

Open

Cumulative : 11
Completed: 08

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

Note : Audit No.08 [QAIG] Findings - 1 OBS.


CPY Q & IM Assessment
Assessment Title

Findings

Closed

Open

Civil Control,Site Document & Data Control

N/A

N/A

None

C/list No.
1

Total No. of
Assessment

Conducted this
Week

38

FCS status (Field Change Sheet

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

38

36

Status of Deliverables

Total Rejected

S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
23
1
8
45

PQP
ITP
QCP
QMP
LTSC

1
23
1
8
45

1
23
1
5
45

Quality Tool Box Talks

Discipline

SDR statu
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR open

N/A

Week
Weekly Site Quality Walk

Score (%)

Total cancelled

Total SDR Closed

Total Condcuted : 6, This week : 0


Description:

Total Issued
Total Open
Total Closed

Score (%)

% Difference

Items
Action Required

Remarks

Issued This Week

Discipline

% Difference

This Period

Last Period

Civil(C300 &
C200)

92.31/93/94/94.5%

93.3/91.1/95.2%

0.5

Civil(C300 &
C200)

91.8/92.85/92.31%

92.31/93/94/94.5%

0.5

Civil(C300 &
B200,C200)

92.2/92.86/94.5/93.33
%

91.8/92.85/92.31%

0.5

C300 &
B200/C200

94.28/97.5/91.81%

Yes

0.5

92.2/92.86/94.5/93.33%

Date

Scheduled(Upcoming)

23-Jan-2013

Completed(Previous)

31-Dec-2012

Scheduled(Upcoming)-Earthworks
Completed(Previous)-Blockwork/Plaster

Date

Completed

Balance

Total Trained

147+21

Total

Completed

Balance

Total Trained

14

10

53+39

02-Jan-2013

Cumulative
Date

Scheduled(Upcoming)-

TBA
02/03-12-12

Total

Completed

Balance

Total Trained

38

GCC Craft Training (*) - Dec'2012

Scheduled(Upcoming)
Completed(Previous)-Wire Termination

Barzan on shore project - Building works - Package#2

Bldg.Ref:

Planned

BSS-001

13

BSS-107

12

BCCB

19

BSS-900

14

BSS-108

14

Cumulative

09-Jan-2013

Item

Item

CPY Witnessed

Total

JGC Craft Training (*) -

Completed(Prev.)-Paint/Wire Pull

JGC Witnessed

Cumulative

Refresher Discipline Training (*) [Nov'12 to Apr'13]


Item

Remarks

Quality awareness Training [Nov'12 to Apr'13]


Item

No

TOM
Bldg.Ref:

Planned

BSS-001

865

BSS-107

734

BCCB

1352

BSS-900

393

BSS-108

308

Cumulative
Date
TBA

29-Dec-2012

Total

Completed

Balance

Total Trained

1) Percentage of cancellation :

16

16

228

Note : (Reason for RFI Rejectio

tracting Co.WLL

nshore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-059

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

19

Total NCR Closed

15

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

10

Total CAR Closed

Total DR Closed

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

FCS status (Field Change Sheet)

Total CAR Issued

10

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

FTR status (Field Trouble Request)


11
2

419

Total Issued
Total Open
Total Closed

20

Total Rejected

18

Total cancelled

497
40

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
8

Other S/C SDR

MEP - 9

Nil

Weekly Field Inspection Status (RFI)


Issued

Accepted

Rejected

Cancelled

382

358

23

382

358

23

143

130

13

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

13

69

12

19

14

14

Remarks
JGC Comments recd.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

865

719

83

734

584

80

1352

1196

88.46

393

242

61.58

308

56

18.18

Remarks

QA/QC Highlights
1) Percentage of cancellation : 6.28 %
Note : (Reason for RFI Rejection) - Installation as per standard switches to door issue.

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

08-Jan-2013

To:

14-Jan-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

34

Items

As of Today : 34

Plan

Actual

Total NCR Issued

FQCM & FQAM(Bldg./MEP)

Total NCR Closed

DFQC Manager(Bldg.)

Total NCR Open

Lead QCI (Bldg./MEP) & QCE(MEP)

Total NCR Issued (This Week)

QC Inspectors(Bldg.)

QC Inspectors(MEP/Welding)

10

10

CQCC/QC Assistant

Document controller

DFO Team

NC

CPY DR Status
(Deficiency Report
Total DR Issued
Total DR Closed

TOTAL

34

34

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

9th IA : 13-03-13[GCC]

GCC-IA

Status in
brief

Completed(L
ast)

8th IA : 24-12-12[QAIG]

GCC-IA

Issued

24

34

10

Total :

11

Closed

15

31

Balance :

Open

Cumulative : 11
Completed: 08

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

CPY Q & IM Assessment


C/list No.
1

Assessment Title

Findings

Closed

Open

Civil Conttrol[HVAC]

N/A

N/A

None

Total No. of
Assessment

Conducted this
Week

39

FCS status (Field Change Sheet

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

39

37

Status of Deliverables

Total Rejected

S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
23
1
8
45

PQP
ITP
QCP
QMP
LTSC

1
23
1
8
45

1
21
1
5
45

Quality Tool Box Talks

Discipline

SDR statu
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR open

N/A

Week
Weekly Site Quality Walk

Score (%)

Total cancelled

Total SDR Closed

Total Condcuted : 6, This week : 0


Description:

Total Issued
Total Open
Total Closed

Score (%)

% Difference

Items
Action Required

Remarks

Issued This Week

Discipline

% Difference

This Period

Last Period

Civil(C300 &
C200)

91.8/92.85/92.31%

92.31/93/94/94.5%

0.5

Civil(C300 &
C200)

92.2/92.86/94.5/93.33
%

91.8/92.85/92.31%

0.5

Civil(C300 &
B200,C200)

94.28/97.5/91.81%

92.2/92.86/94.5/93.33%

0.5

C300 &
B200/C200

90.9/90%

Yes

0.5

94.28/97.5/91.81%

Date

Scheduled(Upcoming)

23-Jan-2013

Completed(Previous)

31-Dec-2012

Date

Scheduled(Upcoming)-Electrical

16-Jan-2013

Completed(Previous)-Blockwork/Plaster

02-Jan-2013

Completed

Balance

Total Trained

147+21

Cumulative
Total

Completed

Balance

Total Trained

14

10

53+39

Cumulative

Item

Date

Scheduled(Upcoming)-

TBA
02/03-12-12

Total

Completed

Balance

Total Trained

38

GCC Craft Training (*) - Dec'2012


Item
Scheduled(Upcoming)
Completed(Previous)-Wire Termination

Barzan on shore project - Building works - Package#2

CPY Witnessed

Total

JGC Craft Training (*) -

Completed(Prev.)-Paint/Wire Pull

JGC Witnessed

Cumulative

Refresher Discipline Training (*) [Nov'12 to Apr'13]


Item

Remarks

Quality awareness Training [Nov'12 to Apr'13]


Item

No

Bldg.Ref:

Planned

BSS-001

13

BSS-107

12

BCCB

19

BSS-900

14

BSS-108

14

TOM
Bldg.Ref:

Planned

BSS-001

865

BSS-107

734

BCCB

1352

BSS-900

393

BSS-108

308

Cumulative
Date
TBA

29-Dec-2012

Total

Completed

Balance

Total Trained

1) Percentage of cancellation :

16

16

228

Note : (Reason for RFI Rejectio


detail.

tracting Co.WLL

nshore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-060

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

19

Total NCR Closed

16

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

13

Total CAR Closed

Total DR Closed

10

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

FCS status (Field Change Sheet)

Total CAR Issued

10

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

FTR status (Field Trouble Request)


11
2

436

Total Issued
Total Open
Total Closed

20

Total Rejected

18

Total cancelled

521
47

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
8

Other S/C SDR

MEP - 9

Nil

Weekly Field Inspection Status (RFI)


Issued

Accepted

Rejected

Cancelled

444

408

34

444

408

34

195

174

21

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

13

69

12

19

14

14

Remarks
JGC Comments recd.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

865

719

83

734

584

80

1352

1196

88.46

393

243

61.58

308

248

80

Remarks

QA/QC Highlights
1) Percentage of cancellation : 7.65 %
Note : (Reason for RFI Rejection) - Due to FCS & Installation not as per standard
detail.

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

15-Jan-2013

To:

21-Jan-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

34

Items

As of Today : 34

Plan

Actual

Total NCR Issued

FQCM & FQAM(Bldg./MEP)

Total NCR Closed

DFQC Manager(Bldg.)

Total NCR Open

Lead QCI (Bldg./MEP) & QCE(MEP)

Total NCR Issued (This Week)

QC Inspectors(Bldg.)

QC Inspectors(MEP/Welding)

10

10

CQCC/QC Assistant

Document controller

DFO Team

NC

CPY DR Status
(Deficiency Report
Total DR Issued
Total DR Closed

TOTAL

34

34

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

9th IA : 13-03-13[GCC]

GCC-IA

Status in
brief

Completed(L
ast)

8th IA : 24-12-12[QAIG]

GCC-IA

Issued

24

34

10

Total :

11

Closed

15

32

Balance :

Open

Cumulative : 11
Completed: 08

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

CPY Q & IM Assessment


Assessment Title

Findings

Closed

Open

Civil Conttrol[lab]&Site supervisory control

N/A

N/A

None

C/list No.
1

Total No. of
Assessment

Conducted this
Week

41

FCS status (Field Change Sheet

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

41

39

Status of Deliverables

Total Rejected

S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
23
1
8
46

PQP
ITP
QCP
QMP
LTSC

1
23
1
8
46

1
22
1
5
45

Quality Tool Box Talks

Discipline

SDR statu
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR open

N/A

Week
Weekly Site Quality Walk

Score (%)

Total cancelled

Total SDR Closed

Total Condcuted : 6, This week : 0


Description:

Total Issued
Total Open
Total Closed

Score (%)

% Difference

Items
Action Required

Remarks

Issued This Week

Discipline

% Difference

This Period

Last Period

Civil(C300 &
C200)

92.2/92.86/94.5/93.33
%

91.8/92.85/92.31%

0.5

Civil(C300 &
C200)

94.28/97.5/91.81%

92.2/92.86/94.5/93.33%

0.5

Civil(C300 &
B200,C200)

90.9/90%

94.28/97.5/91.81%

0.5

C300 &
B200/C200

92&93.75%

Yes

0.5

90.9/90%

Date

Scheduled(Upcoming)

03-Feb-2013

Completed(Previous)

31-Dec-2012

Scheduled(Upcoming)-Concrete
Completed(Previous)-Electrical

Date

Completed

Balance

Total Trained

147+21

Cumulative
Total

Completed

Balance

Total Trained

14

53+49

27-Jan-2013
17-Jan-2013

Cumulative

Item

Date

Scheduled(Upcoming)-

TBA
02/03-12-12

Total

Completed

Balance

Total Trained

38

GCC Craft Training (*) - Dec'2012


Item
Scheduled(Upcoming)
Completed(Previous)-Wire Termination

Barzan on shore project - Building works - Package#2

CPY Witnessed

Total

JGC Craft Training (*) -

Completed(Prev.)-Paint/Wire Pull

JGC Witnessed

Cumulative

Refresher Discipline Training (*) [Nov'12 to Apr'13]


Item

Remarks

Quality awareness Training [Nov'12 to Apr'13]


Item

No

Bldg.Ref:

Planned

BSS-001

13

BSS-107

12

BCCB

19

BSS-900

14

BSS-108

14

Note : Re

TOM
Bldg.Ref:

Planned

BSIH-108

219

BSS-105

331

BSS-001

1059

BSS-107

811

BCCB

1395

BSS-900

337

BSS-108

358

Cumulative
Date
TBA

29-Dec-2012

Total

Completed

Balance

Total Trained

1) Percentage of cancellation :

16

16

228

Note : (Reason for RFI Rejectio


surveyor not available.

tracting Co.WLL

nshore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-061

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

19

Total NCR Closed

16

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

14

Total CAR Closed

Total DR Closed

13

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

FCS status (Field Change Sheet)

Total CAR Issued

10

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

FTR status (Field Trouble Request)


11
2

465

Total Issued
Total Open
Total Closed

22

Total Rejected

20

Total cancelled

551
44

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
8

Other S/C SDR

MEP - 9

Nil

Weekly Field Inspection Status (RFI)


Issued

Accepted

Rejected

Cancelled

405

373

30

405

373

30

173

152

21

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

13

69

12

53

19

14

14

Remarks

Note : Refer attachment #9 for more details.


TOMAS - NO.OF ITR's [UPLOAD]
Planned

Actual

% Prog.

219

136

62.1

331

312

93.66

1059

720

68

811

774

96

1395

1197

86

337

243

72

358

248

70

Remarks

Note : Refer
attachment #9 for
more details.

QA/QC Highlights
1) Percentage of cancellation : 7.4 %
Note : (Reason for RFI Rejection) - bolt thread was large and can't be tightened,
surveyor not available.

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

22-Jan-2013

To:

28-Jan-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

34

Items

As of Today : 34

Plan

Actual

Total NCR Issued

FQCM & FQAM(Bldg./MEP)

Total NCR Closed

DFQC Manager(Bldg.)

Total NCR Open

Lead QCI (Bldg./MEP) & QCE(MEP)

Total NCR Issued (This Week)

QC Inspectors(Bldg.)

QC Inspectors(MEP/Welding)

10

10

CQCC/QC Assistant

Document controller

DFO Team

NC

CPY DR Status
(Deficiency Report
Total DR Issued
Total DR Closed

TOTAL

34

34

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

9th IA : 13-03-13[GCC]

GCC-IA

Status in
brief

Completed(L
ast)

8th IA : 24-12-12[QAIG]

GCC-IA

Issued

24

34

10

Total :

11

Closed

15

32

Balance :

Open

Cumulative : 11
Completed: 08

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

CPY Q & IM Assessment


C/list No.

Assessment Title

Findings

Closed

Open

TOMAS

N/A

N/A

None

1
Total No. of
Assessment

Conducted this
Week

42

FCS status (Field Change Sheet

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

42

39

Status of Deliverables

Total Rejected

S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
24
1
8
46

PQP
ITP
QCP
QMP
LTSC

1
24
1
8
46

1
23
1
5
46

Quality Tool Box Talks

Discipline

SDR statu
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR open

N/A

Week
Weekly Site Quality Walk

Score (%)

Total cancelled

Total SDR Closed

Total Condcuted : 6, This week : 0


Description:

Total Issued
Total Open
Total Closed

Score (%)

% Difference

Items
Action Required

Remarks

Issued This Week

Discipline

% Difference

This Period

Last Period

Civil(C300 &
C200)

94.28/97.5/91.81%

92.2/92.86/94.5/93.33%

0.5

Civil(C300 &
C200)

90.9/90%

94.28/97.5/91.81%

0.5

Civil(C300 &
B200,C200)

92&93.75%

90.9/90%

0.5

C300 &
B200/C200

94/89/93%

92&93.75%

0.5

Yes

Quality awareness Training [Nov'12 to Apr'13]


Item

Date

Scheduled(Upcoming)

03-Feb-2013

Completed(Previous)

31-Dec-2012

Date

Scheduled(Upcoming)-Earthworks

29-Jan-2013

Completed(Previous)-Electrical

17-Jan-2013

Date

Scheduled(Upcoming)-

Completed(Previous)-Wire Termination

Barzan on shore project - Building works - Package#2

Bldg.Ref:

TBA
02/03-12-12

Planned

Note :

Completed

Balance

Total Trained

147+21

Cumulative

TOM
Bldg.Ref:

Total

Completed

Balance

Total Trained

14

53+49

Planned

Note :

Total

Completed

Balance

Total Trained

38

GCC Craft Training (*) - Dec'2012

Scheduled(Upcoming)

CPY Witnessed

Cumulative

Item

Item

JGC Witnessed

Total

JGC Craft Training (*) -

Completed(Prev.)-Paint/Wire Pull

Remarks

Cumulative

Refresher Discipline Training (*) [Nov'12 to Apr'13]


Item

No

Cumulative
Date
TBA

29-Dec-2012

Total

Completed

Balance

Total Trained

1) Percentage of cancellation :

16

16

228

Rejection[By CTR]-MEP works


nuts/bolts

tracting Co.WLL

nshore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-062

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

19

Total NCR Closed

16

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

14

Total CAR Closed

Total DR Closed

13

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

FCS status (Field Change Sheet)

Total CAR Issued

10

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

FTR status (Field Trouble Request)


13
4

476

Total Issued
Total Open
Total Closed

21

Total Rejected

22

Total cancelled

558
39

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
8

Other S/C SDR

MEP - 9

Nil

Weekly Field Inspection Status (RFI)


Issued

Accepted

Rejected

Cancelled

428

393

32

428

393

32

143

125

18

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

Note : Refer attachment #9 for details.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

Remarks

Note : Refer attachment #9 for details.

QA/QC Highlights
1) Percentage of cancellation : 7.47%
Rejection[By CTR]-MEP works - Wrong item code[welding electrodes] & Rusted
nuts/bolts

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

29-Jan-2013

To:

04-Feb-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

34

Items

As of Today : 34

Plan

Actual

Total NCR Issued

FQCM & FQAM(Bldg./MEP)

Total NCR Closed

DFQC Manager(Bldg.)

Total NCR Open

Lead QCI (Bldg./MEP) & QCE(MEP)

Total NCR Issued (This Week)

QC Inspectors(Bldg.)

QC Inspectors(MEP/Welding)

10

10

CQCC/QC Assistant

Document controller

DFO Team

NC

CPY DR Status
(Deficiency Report
Total DR Issued
Total DR Closed

TOTAL

34

34

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

9th IA : 13-03-13[GCC]

GCC-IA

Status in
brief

Completed(L
ast)

8th IA : 24-12-12[QAIG]

GCC-IA

Issued

24

39

10

Total :

11

Closed

15

32

Balance :

Open

Cumulative : 11
Completed: 08

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

Last External Audit [DFO] = 5 Obs & 6 Rec.


CPY Q & IM Assessment
C/list No.

Assessment Title

Findings

Closed

Open

None

N/A

N/A

None

1
Total No. of
Assessment

Conducted this
Week

42

FCS status (Field Change Sheet

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

42

39

Status of Deliverables

Total Rejected

S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
25
1
8
47

PQP
ITP
QCP
QMP
LTSC

1
25
1
8
47

1
23
1
5
46

Quality Tool Box Talks

Discipline

SDR statu
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR open

N/A

Week
Weekly Site Quality Walk

Score (%)

Total cancelled

Total SDR Closed

Total Condcuted : 6, This week : 0


Description:

Total Issued
Total Open
Total Closed

Score (%)

% Difference

Items
Action Required

Remarks

Issued This Week

Discipline

% Difference

This Period

Last Period

Civil(C300 &
C200)

90.9/90%

94.28/97.5/91.81%

0.5

Civil(C300 &
C200)

92&93.75%

90.9/90%

0.5

Civil(C300 &
B200,C200)

94/89/93%

92&93.75%

0.5

92.8/94.1/96%

94/89/93%

0.5

C300 &
B200/C200

Yes

Quality awareness Training [Nov'12 to Apr'13]


Item

Date

Scheduled(Upcoming)

20-Feb-2013

Completed(Previous)

03-Feb-2012

Date

Scheduled(Upcoming)-Electrical

05-Feb-2013

Completed(Previous)-Concrete

30-Jan-2013

Date

Scheduled(Upcoming)-

Bldg.Ref:

TBA
02/03-12-12

Planned

Note :

Completed

Balance

Total Trained

147+29

Cumulative

TOM
Bldg.Ref:

Total

Completed

Balance

Total Trained

16

53+68

Planned

Note :

Total

Completed

Balance

Total Trained

38

GCC Craft Training (*) - Feb'2013

Cumulative
Date

Scheduled(Upcoming)[G.I.Conduit]

06-Feb-2013

Completed(Previous)-Wire Termination

29-Dec-2012

Barzan on shore project - Building works - Package#2

CPY Witnessed

Cumulative

Item

Item

JGC Witnessed

Total

JGC Craft Training (*) -

Completed(Prev.)-Paint/Wire Pull

Remarks

Cumulative

Refresher Discipline Training (*) [Nov'12 to Apr'13]


Item

No

Total

Completed

Balance

Total Trained

1) Percentage of cancellation :

20

20

228+

Rejection[By CTR]-MEP works


Installation of MCC Panel

tracting Co.WLL

nshore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-063

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

19

Total NCR Closed

16

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

14

Total CAR Closed

Total DR Closed

14

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

FCS status (Field Change Sheet)

Total CAR Issued

10

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

FTR status (Field Trouble Request)


13
4

490

Total Issued
Total Open
Total Closed

21

Total Rejected

22

Total cancelled

589
56

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
18

Other S/C SDR

Nil

14

Weekly Field Inspection Status (RFI)


Issued

Accepted

Rejected

Cancelled

388

367

18

388

367

18

158

143

15

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

Note : Refer attachment #9 for details.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

Remarks

Note : Refer attachment #9 for details.

QA/QC Highlights
1) Percentage of cancellation : 4.64%
Rejection[By CTR]-MEP works - Improper installation of cable gland, Not followed FCS,
Installation of MCC Panel

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

05-Feb-2013

To:

11-Feb-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

34

Items

As of Today : 34

Plan

Actual

Total NCR Issued

FQCM & FQAM(Bldg./MEP)

Total NCR Closed

DFQC Manager(Bldg.)

Total NCR Open

Lead QCI (Bldg./MEP) & QCE(MEP)

Total NCR Issued (This Week)

QC Inspectors(Bldg.)

QC Inspectors(MEP/Welding)

10

10

CQCC/QC Assistant

Document controller

DFO Team

NC

CPY DR Status
(Deficiency Report
Total DR Issued
Total DR Closed

TOTAL

34

34

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

9th IA : 13-03-13[GCC]

GCC-IA

Status in
brief

Completed(L
ast)

8th IA : 24-12-12[QAIG]

GCC-IA

Issued

24

39

10

Total :

11

Closed

15

32

Balance :

Open

Cumulative : 11
Completed: 08

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

Last External Audit [DFO] = 5 Obs & 6 Rec.


CPY Q & IM Assessment
C/list No.

Assessment Title

Findings

Closed

Open

None

N/A

N/A

None

1
Total No. of
Assessment

Conducted this
Week

42

FCS status (Field Change Sheet

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

42

39

Status of Deliverables

Total Rejected

S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
25
1
8
47

PQP
ITP
QCP
QMP
LTSC

1
25
1
8
47

1
21
1
5
47

Quality Tool Box Talks

Discipline

SDR statu
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR open

N/A

Week
Weekly Site Quality Walk

Score (%)

Total cancelled

Total SDR Closed

Total Condcuted : 6, This week : 0


Description:

Total Issued
Total Open
Total Closed

Score (%)

% Difference

Items
Action Required

Remarks

Issued This Week

Discipline

% Difference

This Period

Last Period

Civil(C300 &
C200)

92&93.75%

90.9/90%

0.5

Civil(C300 &
C200)

94/89/93%

92&93.75%

0.5

Civil(C300 &
B200,C200)

92.8/94.1/96%

94/89/93%

0.5

93/93/92.5%

92.8/94.1/96%

0.5

C300 &
B200/C200

Yes

Quality awareness Training [Nov'12 to Apr'13]


Item

Date

Scheduled(Upcoming)

20-Feb-2013

Completed(Previous)

03-Feb-2012

Date

Scheduled(Upcoming)-Electrical

17-Feb-2013

Completed(Previous)-Concrete

30-Jan-2013

Date

Scheduled(Upcoming)-

Bldg.Ref:

Planned

Note :

Completed

Balance

Total Trained

147+29

Cumulative

TOM
Bldg.Ref:

Total

Completed

Balance

Total Trained

16

53+68

Planned

Note :

TBA
02/03-12-12

Total

Completed

Balance

Total Trained

38

GCC Craft Training (*) - Feb'2013

Cumulative
Date

Scheduled(Upcoming)-Duct connections

13-Feb-2013

Completed(Previous)-Grounding/Trunking

11-Feb-2013

Barzan on shore project - Building works - Package#2

CPY Witnessed

Cumulative

Item

Item

JGC Witnessed

Total

JGC Craft Training (*) -

Completed(Prev.)-Paint/Wire Pull

Remarks

Cumulative

Refresher Discipline Training (*) [Nov'12 to Apr'13]


Item

No

Total

Completed

Balance

Total Trained

20

18

228+18

1) Percentage of cancellation :
Rejection[By CTR]-N/A

tracting Co.WLL

nshore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-064

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

20

Total NCR Closed

16

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

14

Total CAR Closed

Total DR Closed

14

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

FCS status (Field Change Sheet)

Total CAR Issued

10

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

FTR status (Field Trouble Request)


13
4

516

Total Issued
Total Open
Total Closed

21

Total Rejected

24

Total cancelled

620
59

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
18

Other S/C SDR

Nil

16

Weekly Field Inspection Status (RFI)


Issued

Accepted

Rejected

Cancelled

408

378

30

408

378

30

190

173

17

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

Note : Refer attachment #9 for details.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

Note : Refer attachment #9 for details.

QA/QC Highlights
1) Percentage of cancellation : 7.35%
Rejection[By CTR]-N/A

Weekly Quality Metrics

Remarks

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

12-Feb-2013

To:

18-Feb-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

34

Items

As of Today : 34

Plan

Actual

Total NCR Issued

FQCM & FQAM(Bldg./MEP)

Total NCR Closed

DFQC Manager(Bldg.)

Total NCR Open

Lead QCI (Bldg./MEP) & QCE(MEP)

Total NCR Issued (This Week)

QC Inspectors(Bldg.)

QC Inspectors(MEP/Welding)

10

10

CQCC/QC Assistant

Document controller

DFO Team

NC

CPY DR Status
(Deficiency Report
Total DR Issued
Total DR Closed

TOTAL

34

34

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

9th IA : 13-03-13[GCC]

GCC-IA

Status in
brief

Completed(L
ast)

8th IA : 24-12-12[QAIG]

GCC-IA

Issued

24

46

12

Total :

11

Closed

15

32

Balance :

Open

14

Cumulative : 11
Completed: 08

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

Last External Audit [Electrical] = 1 CAR, 7 Obs & 1 Rec.


CPY Q & IM Assessment
C/list No.
1

Assessment Title

Findings

Closed

Open

Civil Control [HVAC]

N/A

N/A

None

Total No. of
Assessment

Conducted this
Week

45

FCS status (Field Change Sheet

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

45

42

Status of Deliverables

Total Rejected

S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
24
1
8
47

PQP
ITP
QCP
QMP
LTSC

1
24
1
8
47

1
22
1
8
47

Quality Tool Box Talks

Discipline

SDR statu
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR open

N/A

Week
Weekly Site Quality Walk

Score (%)

Total cancelled

Total SDR Closed

Total Condcuted : 6, This week : 0


Description:

Total Issued
Total Open
Total Closed

Score (%)

% Difference

Items
Action Required

Remarks

Issued This Week

Discipline

% Difference

This Period

Last Period

Civil(C300 &
C200)

94/89/93%

92&93.75%

0.5

Civil(C300 &
C200)

92.8/94.1/96%

94/89/93%

0.5

Civil(C300 &
B200,C200)

93/93/92.5%

92.8/94.1/96%

0.5

93.6/86.3/94.28%

93/93/92.5%

0.5

C300 &
B200/C200

Yes

Quality awareness Training [Nov'12 to Apr'13]


Item

Date

Scheduled(Upcoming)

27-Feb-2013

Completed(Previous)

03-Feb-2012

Date

Scheduled(Upcoming)-Electrical

21-Feb-2013

Completed(Previous)-Concrete

30-Jan-2013

Date

Scheduled(Upcoming)-

Bldg.Ref:

TBA
02/03-12-12

Planned

Note : To be ref

Completed

Balance

Total Trained

147+29

Cumulative

TOM
Bldg.Ref:

Total

Completed

Balance

Total Trained

16

53+68

Planned

Note : To be ref

Total

Completed

Balance

Total Trained

38

GCC Craft Training (*) - Feb'2013

Cumulative
Date

Scheduled(Upcoming)-Cable Tray

20-Feb-2013

Completed(Previous)-Cable dressing

16-Feb-2013

Barzan on shore project - Building works - Package#2

CPY Witnessed

Cumulative

Item

Item

JGC Witnessed

Total

JGC Craft Training (*) -

Completed(Prev.)-Paint/Wire Pull

Remarks

Cumulative

Refresher Discipline Training (*) [Nov'12 to Apr'13]


Item

No

Total

Completed

Balance

Total Trained

1) Percentage of cancellation :

20

16

228+36

Rejection[By CTR]- 1 No - Gro

tracting Co.WLL

nshore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-065

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

22

Total NCR Closed

16

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

14

Total CAR Closed

Total DR Closed

14

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

FCS status (Field Change Sheet)

Total CAR Issued

12

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

FTR status (Field Trouble Request)


14
5

544

Total Issued
Total Open
Total Closed

21

Total Rejected

23

Total cancelled

655
67

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
18

Other S/C SDR

Nil

16

Weekly Field Inspection Status (RFI)


Issued

Accepted

Rejected

Cancelled

375

350

24

375

350

24

137

125

12

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 6.40%
Rejection[By CTR]- 1 No - Grout cube failure [NCR#23 raised]

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

19-Feb-2013

To:

25-Feb-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

34

Items

As of Today : 34

Plan

Actual

Total NCR Issued

FQCM & FQAM(Bldg./MEP)

Total NCR Closed

DFQC Manager(Bldg.)

Total NCR Open

Lead QCI (Bldg./MEP) & QCE(MEP)

Total NCR Issued (This Week)

QC Inspectors(Bldg.)

QC Inspectors(MEP/Welding)

10

10

CQCC/QC Assistant

Document controller

DFO Team

NC

CPY DR Status
(Deficiency Repor
Total DR Issued
Total DR Closed

TOTAL

34

34

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

9th IA : 13-03-13[GCC]

GCC-IA

Status in
brief

Completed(L
ast)

8th IA : 24-12-12[QAIG]

GCC-IA

Issued

24

46

13

Total :

11

Closed

15

33

Balance :

Open

13

Cumulative : 11
Completed: 08

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

Last External Audit [Electrical] = 1 CAR, 7 Obs & 1 Rec.


CPY Q & IM Assessment
Assessment Title

Findings

Closed

Open

Site supervisory/civil control/drawing control

N/A

N/A

None

C/list No.
1

Total No. of
Assessment

Conducted this
Week

49

FCS status (Field Change Sheet

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

49

46

Status of Deliverables

Total Rejected

S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
24
1
8
47

PQP
ITP
QCP
QMP
LTSC

1
24
1
8
47

1
24
1
8
47

Quality Tool Box Talks

Discipline

SDR stat
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR open

N/A

Week
Weekly Site Quality Walk

Score (%)

Total cancelled

Total SDR Closed

Total Condcuted : 6, This week : 0


Description:

Total Issued
Total Open
Total Closed

Score (%)

% Difference

Items
Action Required

Remarks

Issued This Week

Discipline

% Difference

This Period

Last Period

Civil(C300 &
C200)

92.8/94.1/96%

94/89/93%

0.5

Civil(C300 &
C200)

93/93/92.5%

92.8/94.1/96%

0.5

Civil(C300 &
B200,C200)

93.6/86.3/94.28%

93/93/92.5%

0.5

C300 &
B200/C200

93.33/93.6/95.83%

93.6/86.3/94.28%

0.5

Yes

Quality awareness Training [Nov'12 to Apr'13]


Item

Date

Scheduled(Upcoming)

27-Feb-2013

Completed(Previous)

03-Feb-2012

Date

Scheduled(Upcoming)-Electrical

03-Mar-2013

Completed(Previous)-Concrete

30-Jan-2013

Scheduled(Upcoming)-

Completed(Prev.)-Paint/Wire Pull

Bldg.Ref:

Date
TBA
02/03-12-12

Date
26-Feb-2013

Completed(Previous)-Duct connections[Smaller]

25-Feb-2013

Planned

Note : To be re

Balance

Total Trained

147+29

Cumulative

TOM
Bldg.Ref:

Total

Completed

Balance

Total Trained

16

53+68

Planned

Note : To be re

Cumulative

Scheduled(Upcoming)-Duct connections[Bigger]

Barzan on shore project - Building works - Package#2

CPY Witnessed

Completed

Total

Completed

Balance

Total Trained

38

GCC Craft Training (*) - Feb' - Mar'2013


Item

JGC Witnessed

Total

JGC Craft Training (*) Item

Remarks

Cumulative

Refresher Discipline Training (*) [Nov'12 to Apr'13]


Item

No

Cumulative
Total

Completed

Balance

Total Trained

1) Percentage of cancellation

17

11

228+52

Rejection[By CTR - 2No's - Pr

tracting Co.WLL

shore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-066

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

23

Total NCR Closed

16

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

14

Total CAR Closed

Total DR Closed

14

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

FCS status (Field Change Sheet)

Total CAR Issued

13

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

FTR status (Field Trouble Request)


14
5

580

Total Issued
Total Open
Total Closed

23

Total Rejected

24

Total cancelled

663
36

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
18

Other S/C SDR

Nil

16

Weekly Field Inspection Status (RFI)


Issued

Accepted

Rejected

Cancelled

504

481

21

504

481

21

203

194

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 4.16%
Rejection[By CTR - 2No's - Pressure test leak & earth link for cable trays

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

26-Feb-2013

To:

04-Mar-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

34

Items

As of Today : 37

Plan

Actual

Total NCR Issued

FQCM & FQAM(Bldg./MEP)

Total NCR Closed

DFQC Manager(Bldg.)

Total NCR Open

Lead QCI (Bldg./MEP) & QCE(MEP)

Total NCR Issued (This Week)

QC Inspectors(Bldg.)

QC Inspectors(MEP/Welding)

10

10

CQCC/QC Assistant

Document controller

DFO Team

NC

CPY DR Status
(Deficiency Repor
Total DR Issued
Total DR Closed

TOTAL

34

37

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

9th IA : 19-03-13[HUS]

GCC-IA

Status in
brief

Completed(L
ast)

8th IA : 24-12-12[QAIG]

GCC-IA

Issued

24

46

13

Total :

11

Closed

15

33

Balance :

Open

13

Cumulative : 11
Completed: 08

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

Last External Audit [Electrical] = 1 CAR, 7 Obs & 1 Rec.


CPY Q & IM Assessment
Assessment Title

C/list No.

Findings

Closed

Open

N/A

N/A

None

1
Total No. of
Assessment

Conducted this
Week

49

FCS status (Field Change Sheet

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

49

46

Status of Deliverables

Total Rejected

S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
24
1
8
47

PQP
ITP
QCP
QMP
LTSC

1
24
1
8
47

1
24
1
8
47

Quality Tool Box Talks

Discipline

SDR stat
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR open

N/A

Week
Weekly Site Quality Walk

Score (%)

Total cancelled

Total SDR Closed

Total Condcuted : 6, This week : 0


Description:

Total Issued
Total Open
Total Closed

Score (%)

% Difference

Items
Action Required

Remarks

Issued This Week

Discipline

% Difference

This Period

Last Period

Civil(C300 &
C200)

93/93/92.5%

92.8/94.1/96%

0.5

Civil(C300 &
C200)

93.6/86.3/94.28%

93/93/92.5%

0.5

Civil(C300 &
B200,C200)

93.33/93.6/95.83%

93.6/86.3/94.28%

0.5

C300 &
B200/C200

92.5/89.2/92.86%

93.33/93.6/95.83%

0.5

Yes

Quality awareness Training [Nov'12 to Apr'13]


Item

Date

Scheduled(Upcoming)

27-Mar-2013

Completed(Previous)

27-Feb-2013

Date

Scheduled(Upcoming)-Electrical

10-Mar-2013

Completed(Previous)-Concrete

30-Jan-2013

Scheduled(Upcoming)-

Completed(Prev.)-Paint/Wire Pull

Bldg.Ref:

Date
TBA
02/03-12-12

Date
28-Feb-2013

Completed(Previous)-Wire Termination

06-Mar-2013

Planned

Note : To be re

Balance

Total Trained

147+48

Cumulative

TOM
Bldg.Ref:

Total

Completed

Balance

Total Trained

16

53+68

Planned

Note : To be re

Cumulative

Scheduled(Upcoming)-Duct Insulation

Barzan on shore project - Building works - Package#2

CPY Witnessed

Completed

Total

Completed

Balance

Total Trained

38

GCC Craft Training (*) - Feb' - Mar'2013


Item

JGC Witnessed

Total

JGC Craft Training (*) Item

Remarks

Cumulative

Refresher Discipline Training (*) [Nov'12 to Apr'13]


Item

No

Cumulative
Total

Completed

Balance

Total Trained

1) Percentage of cancellation

18

228+78

Rejection[By CTR] :1 No - Pipi

tracting Co.WLL

shore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-067

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

23

Total NCR Closed

16

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

14

Total CAR Closed

Total DR Closed

14

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

FCS status (Field Change Sheet)

Total CAR Issued

13

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

FTR status (Field Trouble Request)


14
5

607

Total Issued
Total Open
Total Closed

25

Total Rejected

25

Total cancelled

697
40

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
18

Other S/C SDR

Nil

16

Weekly Field Inspection Status (RFI)


Issued

Accepted

Rejected

Cancelled

405

388

17

405

388

17

166

157

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 4.19%
Rejection[By CTR] :1 No - Piping [Rough edges]

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

05-Mar-2013

To:

11-Mar-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

34

Items

As of Today : 37

Plan

Actual

Total NCR Issued

FQCM & FQAM(Bldg./MEP)

Total NCR Closed

DFQC Manager(Bldg.)

Total NCR Open

Lead QCI (Bldg./MEP) & QCE(MEP)

Total NCR Issued (This Week)

QC Inspectors(Bldg.)

QC Inspectors(MEP/Welding)

10

10

CQCC/QC Assistant

Document controller

DFO Team

NC

CPY DR Status
(Deficiency Repor
Total DR Issued
Total DR Closed

TOTAL

34

37

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

9th IA : 19-03-13

GCC-IA

Status in
brief

Completed(L
ast)

8th IA : 24-12-12[QAIG]

GCC-IA

Issued

24

46

13

Total :

12

Closed

15

33

Balance :

Open

13

Cumulative : 12
Completed: 08

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

CPY Q & IM Assessment


C/list No.

Assessment Title

Findings

Closed

Open

Electrical

N/A

N/A

None

1
Total No. of
Assessment

Conducted this
Week

50

FCS status (Field Change Sheet

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

50

47

Status of Deliverables

Total Rejected

S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
24
1
8
47

PQP
ITP
QCP
QMP
LTSC

1
24
1
8
47

1
24
1
8
47

Quality Tool Box Talks

Discipline

SDR stat
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR open

N/A

Week
Weekly Site Quality Walk

Score (%)

Total cancelled

Total SDR Closed

Total Condcuted : 6, This week : 0


Description:

Total Issued
Total Open
Total Closed

Score (%)

% Difference

Items
Action Required

Remarks

Issued This Week

Discipline

% Difference

This Period

Last Period

Civil(C300 &
C200)

93.6/86.3/94.28%

93/93/92.5%

0.5

Civil(C300 &
C200)

93.33/93.6/95.83%

93.6/86.3/94.28%

0.5

Civil(C300 &
B200,C200)

92.5/89.2/92.86%

93.33/93.6/95.83%

0.5

91.1/91.8/85%

92.5/89.2/92.86%

0.0

C300 &
B200/C200

Yes

Quality awareness Training [Nov'12 to Apr'13]


Item

Date

Scheduled(Upcoming)

27-Mar-2013

Completed(Previous)

27-Feb-2013

Date

Scheduled(Upcoming)-Drainage/Plumbing

18-Mar-2013

Completed(Previous)-Concrete

30-Jan-2013

Scheduled(Upcoming)-

Completed(Prev.)-Paint/Wire Pull

CPY Witnessed

Bldg.Ref:
Re-walkthrough[Electrical]
on 11/03/13 = 95%

Completed

Balance

Total Trained

147+48

Cumulative
Completed

Balance

Total Trained

16

53+68

TBA
02/03-12-12

Item

Date

Scheduled(Upcoming)-Copper pipe brazing

13-Mar-2013

Completed(Previous)-Wire Pulling

11-Mar-2013

TOM

Planned

Note : To be re

Cumulative
Date

Planned

Note : To be re

Bldg.Ref:

Total

Total

Completed

Balance

Total Trained

38

GCC Craft Training (*) - Feb' - Mar'2013

Barzan on shore project - Building works - Package#2

JGC Witnessed

Total

JGC Craft Training (*) Item

Remarks

Cumulative

Refresher Discipline Training (*) [Nov'12 to Apr'13]


Item

No

Cumulative
Total

Completed

Balance

Total Trained

18

12

228+113

1) Percentage of cancellation

Rejection[By CTR] :1 No - AHU

tracting Co.WLL

shore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-068

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

23

Total NCR Closed

16

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

14

Total CAR Closed

Total DR Closed

14

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

FCS status (Field Change Sheet)

Total CAR Issued

13

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

FTR status (Field Trouble Request)


14
5

621

Total Issued
Total Open
Total Closed

29

Total Rejected

25

Total cancelled

753
78

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
18

Other S/C SDR

Nil

16

Weekly Field Inspection Status (RFI)


Issued

Accepted

Rejected

Cancelled

445

423

21

445

423

21

193

181

11

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 4.72%
Rejection[By CTR] :1 No - AHU Casing Paint repair work

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

12-Mar-2013

To:

18-Mar-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

33

Items

As of Today : 36

Plan

Actual

Total NCR Issued

FQCM & FQAM(Bldg./MEP)

Total NCR Closed

DFQC Manager(Bldg.)

Total NCR Open

Lead QCI (Bldg./MEP) & QCE(MEP)

Total NCR Issued (This Week)

QC Inspectors(Bldg.)

QC Inspectors(MEP/Welding)

10

CQCC/QC Assistant

Document controller

DFO Team

NC

CPY DR Status
(Deficiency Repor
Total DR Issued
Total DR Closed

TOTAL

33

36

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

10th IA : 26-03-13

GCC-IA

Status in
brief

Completed(L
ast)

9th IA : 19-03-13

GCC-IA

Issued

24

46

13

Total :

12

Closed

15

33

Balance :

Open

13

Cumulative : 12
Completed: 09

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

CPY Q & IM Assessment


C/list No.

Assessment Title

Findings

Closed

Open

Civil control [lab]

N/A

N/A

None

1
Total No. of
Assessment

Conducted this
Week

51

FCS status (Field Change Sheet

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

51

48

Status of Deliverables

Total Rejected

S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
24
1
8
47

PQP
ITP
QCP
QMP
LTSC

1
24
1
8
47

1
24
1
7
47

Quality Tool Box Talks

Discipline

SDR stat
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR open

N/A

Week
Weekly Site Quality Walk

Score (%)

Total cancelled

Total SDR Closed

Total Condcuted : 6, This week : 0


Description:

Total Issued
Total Open
Total Closed

Score (%)

% Difference

Items
Action Required

Remarks

Issued This Week

Discipline

% Difference

This Period

Last Period

Civil(C300 &
C200)

93.33/93.6/95.83%

93.6/86.3/94.28%

0.5

Civil(C300 &
C200)

92.5/89.2/92.86%

93.33/93.6/95.83%

0.5

Civil(C300 &
B200,C200)

91.1/91.8/85%

92.5/89.2/92.86%

0.5

93.6/92.7/95/95%

91.1/91.8/85%

0.0

C300 &
B200/C200

Yes

Quality awareness Training [Nov'12 to Apr'13]


Item

Date

Scheduled(Upcoming)

27-Mar-2013

Completed(Previous)

27-Feb-2013

Date

Scheduled(Upcoming)-Plumbing

20-Mar-2013

Completed(Previous) - Electrical

19-Mar-2013

Scheduled(Upcoming)-

Completed(Prev.)-Paint/Wire Pull

Bldg.Ref:

Date
TBA
02/03-12-12

Date
20-Mar-2013

Completed(Previous)-Plumbing/Drainage

18-Mar-2013

Planned

Note : To be re

Balance

Total Trained

147+48

Cumulative

TOM
Bldg.Ref:

Total

Completed

Balance

Total Trained

16

53+85

Planned

Note : To be re

Cumulative

Scheduled(Upcoming)-Flexible conduit

Barzan on shore project - Building works - Package#2

CPY Witnessed

Completed

Total

Completed

Balance

Total Trained

38

GCC Craft Training (*) - Feb' - Mar'2013


Item

JGC Witnessed

Total

JGC Craft Training (*) Item

Remarks

Cumulative

Refresher Discipline Training (*) [Nov'12 to Apr'13]


Item

No

Cumulative
Total

Completed

Balance

Total Trained

18

16

228+185

1) Percentage of cancellation

tracting Co.WLL

shore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-069

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

23

Total NCR Closed

16

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

14

Total CAR Closed

Total DR Closed

14

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

FCS status (Field Change Sheet)

Total CAR Issued

13

Total CAR Closed

Total CAR Open

Total CAR Issued


(This Week)

FTR status (Field Trouble Request)


14
5

662

Total Issued
Total Open
Total Closed

29

Total Rejected

24

Total cancelled

775
60

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
18

Other S/C SDR

Nil

16

Weekly Field Inspection Status (RFI)


Issued

Accepted

Rejected

Cancelled

496

480

16

496

480

16

200

187

13

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 3.22%

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

19-Mar-2013

To:

25-Mar-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

32

Items

As of Today : 35

Plan

Actual

Total NCR Issued

FQCM & FQAM(Bldg./MEP)

Total NCR Closed

DFQC Manager(Bldg.)

Total NCR Open

Lead QCI (Bldg./MEP) & QCE(MEP)

Total NCR Issued (This Week)

QC Inspectors(Bldg.)

QC Inspectors(MEP/Welding)

10

CQCC/QC Assistant

Document controller

DFO Team

NC

CPY DR Status
(Deficiency Repor
Total DR Issued
Total DR Closed

TOTAL

32

35

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

11th IA : 12-06-13

GCC-IA

Status in
brief

Completed(L
ast)

10th IA : 26-03-13

GCC-IA

Issued

24

46

13

Total :

12

Closed

15

41

10

Balance :

Open

Cumulative : 12
Completed: 10

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

CPY Q & IM Assessment


C/list No.
1

Assessment Title

Findings

Closed

Open

Site supervisory control [HVAC]

N/A

N/A

None

Total No. of
Assessment

Conducted this
Week

52

FCS status (Field Change Sheet

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

52

49

Status of Deliverables

Total Rejected

S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
26
1
8
47

PQP
ITP
QCP
QMP
LTSC

1
26
1
8
47

1
26
1
7
47

Quality Tool Box Talks

Discipline

SDR stat
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR open

N/A

Week
Weekly Site Quality Walk

Score (%)

Total cancelled

Total SDR Closed

Total Condcuted : 6, This week : 0


Description:

Total Issued
Total Open
Total Closed

Score (%)

% Difference

Items
Action Required

Remarks

Issued This Week

Discipline

% Difference

This Period

Last Period

Civil(C300 &
C200)

92.5/89.2/92.86%

93.33/93.6/95.83%

0.5

Civil(C300 &
C200)

91.1/91.8/85%

92.5/89.2/92.86%

0.5

Civil(C300 &
B200,C200)

93.6/92.7/95/95%

91.1/91.8/85%

0.5

90/92.5/95%

93.6/92.7/95/95%

0.0

C300 &
B200/C200

Yes

Quality awareness Training [Nov'12 to Apr'13]


Item

Date

Scheduled(Upcoming)

27-Mar-2013

Completed(Previous)

27-Feb-2013

Date

Scheduled(Upcoming)-HVAC,Painting

27-Mar-2013

Completed(Previous) - Plum.&Mech.

20-Mar-2013

Scheduled(Upcoming)-

Completed(Prev.)-Paint/Wire Pull

CPY Witnessed

Bldg.Ref:

Balance

Total Trained

147+48

Cumulative

TBA
02/03-12-12

Date

Total

Completed

Balance

Total Trained

16

10

53+112

Barzan on shore project - Building works - Package#2

23-Mar-2013

Planned

Note : To be re

Total

Completed

Balance

Total Trained

38

Cumulative
Total

Completed

Balance

Total Trained

18

18

228+203

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

TOM
Bldg.Ref:

Cumulative
Date

Planned

Note : To be re

Completed

GCC Craft Training (*) - Feb' - Mar'2013


Item

JGC Witnessed

Total

JGC Craft Training (*) Item

Remarks

Cumulative

Refresher Discipline Training (*) [Nov'12 to Apr'13]


Item

No

1) Percentage of cancellation

tracting Co.WLL

shore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-070

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

23

Total NCR Closed

21

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

14

Total CAR Closed

Total DR Closed

14

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

FCS status (Field Change Sheet)

Total CAR Issued

13

Total CAR Closed

10

Total CAR Open

Total CAR Issued


(This Week)

FTR status (Field Trouble Request)


14
5

691

Total Issued
Total Open
Total Closed

30

Total Rejected

25

Total cancelled

819
73

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
18

Other S/C SDR

Nil

16

Weekly Field Inspection Status (RFI)


Issued

Accepted

Rejected

Cancelled

415

396

23

415

396

23

159

149

10

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 5.54%

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

26-Mar-2013

To:

01-Apr-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

32

Items

As of Today : 33

Plan

Actual

Total NCR Issued

FQCM & FQAM(Bldg./MEP)

Total NCR Closed

DFQC Manager(Bldg.)

Total NCR Open

Lead QCI (Bldg./MEP) & QCE(MEP)

Total NCR Issued (This Week)

QC Inspectors(Bldg.)

QC Inspectors(MEP/Welding)

CQCC/QC Assistant

Document controller

DFO Team

NC

CPY DR Status
(Deficiency Repor
Total DR Issued
Total DR Closed

TOTAL

32

33

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

11th IA : 12-06-13

GCC-IA

Status in
brief

Completed(L
ast)

10th IA : 26-03-13

GCC-IA

Issued

24

46

13

Total :

12

Closed

15

44

11

Balance :

Open

Cumulative : 12
Completed: 10

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

CPY Q & IM Assessment


C/list No.

Assessment Title

Findings

Closed

Open

HVAC-107

N/A

N/A

None

1
Total No. of
Assessment

Conducted this
Week

53

FCS status (Field Change Sheet

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

53

49

Status of Deliverables

Total Rejected

S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
27
1
8
47

PQP
ITP
QCP
QMP
LTSC

1
27
1
8
47

1
25
1
7
47

Quality Tool Box Talks

Discipline

SDR stat
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR open

N/A

Week
Weekly Site Quality Walk

Score (%)

Total cancelled

Total SDR Closed

Total Condcuted : 6, This week : 0


Description:

Total Issued
Total Open
Total Closed

Score (%)

% Difference

Items
Action Required

Remarks

Issued This Week

Discipline

% Difference

This Period

Last Period

Civil(C300 &
C200)

91.1/91.8/85%

92.5/89.2/92.86%

0.5

Civil(C300 &
C200)

93.6/92.7/95/95%

91.1/91.8/85%

0.5

Civil(C300 &
B200,C200)

90/92.5/95%

93.6/92.7/95/95%

0.5

C300 &
B200/C200

95/92.7/95%

90/92.5/95%

0.0

Yes

Quality awareness Training [Nov'12 to Apr'13]


Item

Date

Scheduled(Upcoming)

09-Apr-2013

Completed(Previous)

27-Mar-2013

Date

Scheduled(Upcoming)-Doors & Windows

09-Apr-2013

Completed(Previous) -HVAC,Painting

27-Mar-2013

Scheduled(Upcoming)-

Completed(Prev.)-Paint/Wire Pull

CPY Witnessed

Bldg.Ref:

Balance

Total Trained

195+14

Cumulative

TBA
02/03-12-12

Date

Total

Completed

Balance

Total Trained

16

12

165+23

Total

Completed

Balance

Total Trained

38

Cumulative
Total

Completed

Balance

Total Trained

1) Percentage of cancellation

2) Reason for rejection : Press


18

Barzan on shore project - Building works - Package#2

Planned

Note : To be re

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

TOM
Bldg.Ref:

Cumulative
Date

Planned

Note : To be re

Completed

GCC Craft Training (*) - Feb' - Mar'2013


Item

JGC Witnessed

Total

JGC Craft Training (*) Item

Remarks

Cumulative

Refresher Discipline Training (*) [Nov'12 to Apr'13]


Item

No

23-Mar-2013

18

228+203

tracting Co.WLL

shore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-071

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

23

Total NCR Closed

20

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

14

Total CAR Closed

Total DR Closed

14

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

FCS status (Field Change Sheet)

Total CAR Issued

13

Total CAR Closed

11

Total CAR Open

Total CAR Issued


(This Week)

FTR status (Field Trouble Request)


14
0

710

Total Issued
Total Open
Total Closed

30

Total Rejected

25

Total cancelled

870
105

14

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
18

Other S/C SDR

Nil

16

Weekly Field Inspection Status (RFI)


Issued

Accepted

Rejected

Cancelled

392

376

15

392

376

15

162

157

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 3.82%
2) Reason for rejection : Pressure test failed.

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

02-Apr-2013

To:

08-Apr-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

32

Items

As of Today : 33

Plan

Actual

Total NCR Issued

FQCM & FQAM(Bldg./MEP)

Total NCR Closed

DFQC Manager(Bldg.)

Total NCR Open

Lead QCI (Bldg./MEP) & QCE(MEP)

Total NCR Issued (This Week)

QC Inspectors(Bldg.)

QC Inspectors(MEP/Welding)

CQCC/QC Assistant

Document controller

DFO Team

NC

CPY DR Status
(Deficiency Repor
Total DR Issued
Total DR Closed

TOTAL

32

33

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

11th IA : 12-06-13

GCC-IA

Status in
brief

Completed(L
ast)

10th IA : 26-03-13

GCC-IA

Issued

24

46

13

Total :

13

Closed

15

44

11

Balance :

Open

Cumulative : 13
Completed: 10

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

CPY Q & IM Assessment


Assessment Title

Findings

Closed

Open

HVAC-Civil control, HVAC-109, Site document


control, TOMAS/Completion management

N/A

N/A

None

C/list No.
1

FCS status (Field Change Sheet

Total No. of
Assessment

Conducted this
Week

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

57

57

49

Status of Deliverables
No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
28
1
9
47

PQP
ITP
QCP
QMP
LTSC

1
28
1
9
47

1
27
1
8
47

Total Condcuted : 6, This week : 0


Description:

Total Open
Total Closed
Total Rejected

S.No.

Quality Tool Box Talks

Total Issued

Total cancelled

SDR stat
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR Closed
Total SDR open

N/A

Week
Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

Civil(C300 &
C200)

93.6/92.7/95/95%

91.1/91.8/85%

0.5

Civil(C300 &
C200)

90/92.5/95%

93.6/92.7/95/95%

0.5

Civil(C300 &
B200,C200)

95/92.7/95%

90/92.5/95%

0.5

92.8/94.5/95%

95/92.7/95%

0.0

Discipline

C300 &
B200/C200

% Difference

Action Required
Yes

Quality awareness Training [Nov'12 to Apr'13]


Item

Date

Scheduled(Upcoming)

09-Apr-2013

Completed(Previous)

27-Mar-2013

Date

Scheduled(Upcoming)-Doors & Windows &


Drainage & plumbing

09-04-2013 & 10-04-2013

Completed(Previous) -HVAC,Painting

Scheduled(Upcoming)-

Completed(Prev.)-Paint/Wire Pull

Bldg.Ref:

Balance

Total Trained

195+14

Cumulative
Completed

Balance

Total Trained

16

12

165+23

TBA
02/03-12-12

Date

Total

Completed

Balance

Total Trained

38

Cumulative
Total

Completed

Balance

Total Trained

18

18

228+203

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

Barzan on shore project - Building works - Package#2

23-Mar-2013

Planned

Note : To be re

Cumulative
Date

TOM
Bldg.Ref:

Total

27-Mar-2013

Planned

Note : To be re

Completed

GCC Craft Training (*) - Feb' - Mar'2013


Item

CPY Witnessed

Total

JGC Craft Training (*) Item

JGC Witnessed

Cumulative

Refresher Discipline Training (*) [Nov'12 to Apr'13]


Item

No

Issued This Week

Remarks

1) Percentage of cancellation

tracting Co.WLL

shore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-072

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

23

Total NCR Closed

20

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

14

Total CAR Closed

Total DR Closed

14

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

FCS status (Field Change Sheet)

Total CAR Issued

13

Total CAR Closed

11

Total CAR Open

Total CAR Issued


(This Week)

FTR status (Field Trouble Request)

980

Total Issued

14

100

804

Total Open
Total Closed

14

46

Total Rejected

30

Total cancelled

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
18

Other S/C SDR

Nil

16

Weekly Field Inspection Status (RFI)


Issued

Accepted

Rejected

Cancelled

324

309

15

324

309

15

114

111

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 4.629%

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

09-Apr-2013

To:

15-Apr-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

32

Items

As of Today : 33

Plan

Actual

Total NCR Issued

FQCM & FQAM(Bldg./MEP)

Total NCR Closed

DFQC Manager(Bldg.)

Total NCR Open

Lead QCI (Bldg./MEP) & QCE(MEP)

Total NCR Issued (This Week)

QC Inspectors(Bldg.)

QC Inspectors(MEP/Welding)

CQCC/QC Assistant

Document controller

DFO Team

NC

CPY DR Status
(Deficiency Repor
Total DR Issued
Total DR Closed

TOTAL

32

33

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

11th IA : 12-06-13

GCC-IA

Status in
brief

Completed(L
ast)

10th IA : 26-03-13

GCC-IA

Issued

24

46

13

Total :

13

Closed

24

45

12

Balance :

Open

Cumulative : 13
Completed: 10

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

CPY Q & IM Assessment


Assessment Title

C/list No.

Findings

Closed

Open

N/A

N/A

None

Civil control - concrete works

FCS status (Field Change Sheet

Total No. of
Assessment

Conducted this
Week

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

58

58

55

Status of Deliverables
No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
28
1
9
47

PQP
ITP
QCP
QMP
LTSC

1
28
1
9
47

1
27
1
8
47

Total Condcuted : 6, This week : 0


Description:

Total Open
Total Closed
Total Rejected

S.No.

Quality Tool Box Talks

Total Issued

Total cancelled

SDR stat
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR Closed
Total SDR open

N/A

Week
Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

Civil(C300 &
C200)

90/92.5/95%

93.6/92.7/95/95%

0.5

Civil(C300 &
C200)

95/92.7/95%

90/92.5/95%

0.5

Civil(C300 &
B200,C200)

92.8/94.5/95%

95/92.7/95%

0.5

94.0/94.5/90.0%

92.8/94.5/95%

0.0

Discipline

C300 &
B200/C200

% Difference

Action Required
Yes

Quality awareness Training [Nov'12 to Apr'13]


Item

Date

Scheduled(Upcoming)

----

Completed(Previous)

10-Apr-2013

Date

Completed(Previous) -Doors & Windows &


Drainage & plumbing

Scheduled(Upcoming)-

Completed(Prev.)-Paint/Wire Pull

Total Trained

209+3

Cumulative
Completed

Balance

Total Trained

16

14

188+3
+16

TBA
02/03-12-12

Date

Total

Completed

Balance

Total Trained

38

Cumulative
Total

Completed

Balance

Total Trained

18
Barzan on shore project - Building works - Package#2

1) Percentage of cancellation

2) Reason for rejection : Cable

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

Planned

Note : To be re

Cumulative
Date

TOM
Bldg.Ref:

Total

11-04-2013 & 10-04-2013

Planned

Note : To be re

Balance

GCC Craft Training (*) - Feb' - Mar'2013


Item

Bldg.Ref:

Completed

JGC Craft Training (*) Item

CPY Witnessed

Total

24-Apr-2013

Scheduled(Upcoming)-Sewage works

JGC Witnessed

Cumulative

Refresher Discipline Training (*) [Nov'12 to Apr'13]


Item

No

Issued This Week

Remarks

23-Mar-2013

18

228+203

tracting Co.WLL

shore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-073

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

23

Total NCR Closed

20

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

14

Total CAR Closed

Total DR Closed

14

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

FCS status (Field Change Sheet)

Total CAR Issued

13

Total CAR Closed

12

Total CAR Open

Total CAR Issued


(This Week)

FTR status (Field Trouble Request)

990

Total Issued

14

81

836

Total Open
Total Closed

14

41

Total Rejected

32

Total cancelled

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
19

Other S/C SDR

Nil

18

Weekly Field Inspection Status (RFI)


Issued

Accepted

Rejected

Cancelled

391

366

22

391

366

22

199

184

15

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 5.626%
2) Reason for rejection : Cable tray installation not done properly.

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

16-Apr-2013

To:

22-Apr-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

32

Items

As of Today : 33

Plan

Actual

Total NCR Issued

FQCM & FQAM(Bldg./MEP)

Total NCR Closed

DFQC Manager(Bldg.)

Total NCR Open

Lead QCI (Bldg./MEP) & QCE(MEP)

Total NCR Issued (This Week)

QC Inspectors(Bldg.)

QC Inspectors(MEP/Welding)

CQCC/QC Assistant

Document controller

DFO Team

NC

CPY DR Status
(Deficiency Repor
Total DR Issued
Total DR Closed

TOTAL

32

33

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

11th IA : 12-06-13

GCC-IA

Status in
brief

Completed(L
ast)

10th IA : 26-03-13

GCC-IA

Issued

24

46

13

Total :

13

Closed

24

45

12

Balance :

Open

Cumulative : 13
Completed: 10

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

CPY Q & IM Assessment


Assessment Title

C/list No.

Findings

Closed

Open

N/A

N/A

None

Civil control - Buildings

FCS status (Field Change Sheet

Total No. of
Assessment

Conducted this
Week

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

59

59

26

Status of Deliverables
No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
28
1
9
47

PQP
ITP
QCP
QMP
LTSC

1
28
1
9
47

1
27
1
8
47

Total Condcuted : 6, This week : 0


Description:

Total Open
Total Closed
Total Rejected

S.No.

Quality Tool Box Talks

Total Issued

Total cancelled

SDR stat
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR Closed
Total SDR open

N/A

Week
Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

C300/B200/
B100/C200

95/92.7/95%

90/92.5/95%

0.5

C300/B200/
B100/C200

92.8/94.5/95%

95/92.7/95%

0.5

C300/B200/
B100/C200

94.0/94.5/90.0%

92.8/94.5/95%

0.5

C300/B200/
B100/C200

93.7/96.3/91.6%

94.0/94.5/90.0%

0.0

Discipline

% Difference

Action Required
Yes

Quality awareness Training [May'13 to Oct'13]


Item

Date

Scheduled(Upcoming)

15-May-2013

Completed(Previous)

10-Apr-2013

Date

Completed(Previous) -Doors & Windows &


Drainage & plumbing

Scheduled(Upcoming)-

Completed(Prev.)-Paint/Wire Pull

Balance

Total Trained

TOM
Bldg.Ref:

Total

Completed

Balance

Total Trained

16

14

191+7
+16

23-04-2013 & 10-04-2013

TBA
02/03-12-12

Date

Total

Completed

Balance

Total Trained

38

Cumulative
Total

Completed

Balance

Total Trained

18
Barzan on shore project - Building works - Package#2

1) Percentage of cancellation

2) Reason for rejection : Need

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

Planned

Note : To be re

Cumulative
Date

Planned

Note : To be re

Cumulative

GCC Craft Training (*) - Feb' - Mar'2013


Item

Bldg.Ref:

Completed

JGC Craft Training (*) Item

CPY Witnessed

Total

30-Apr-2013

Scheduled(Upcoming)-Sewage works

JGC Witnessed

Cumulative

Refresher Discipline Training (*) [Nov'12 to Apr'13]


Item

No

Issued This Week

Remarks

23-Mar-2013

18

228+203

tracting Co.WLL

shore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-074

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

23

Total NCR Closed

21

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

17

Total CAR Closed

Total DR Closed

15

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

FCS status (Field Change Sheet)

Total CAR Issued

13

Total CAR Closed

12

Total CAR Open

Total CAR Issued


(This Week)

FTR status (Field Trouble Request)

1014

Total Issued

14

92

841

Total Open
Total Closed

14

49

Total Rejected

32

Total cancelled

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
19

Other S/C SDR

Nil

18

Weekly Field Inspection Status (RFI)


Issued

Accepted

Rejected

Cancelled

313

290

19

313

290

19

125

116

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 6.07%
2) Reason for rejection : Need FCS for HVAC installation.

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

23-Apr-2013

To:

29-Apr-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

32

Items

As of Today : 33

Plan

Actual

Total NCR Issued

FQCM & FQAM(Bldg./MEP)

Total NCR Closed

DFQC Manager(Bldg.)

Total NCR Open

Lead QCI (Bldg./MEP) & QCE(MEP)

Total NCR Issued (This Week)

QC Inspectors(Bldg.)

QC Inspectors(MEP/Welding)

CQCC/QC Assistant

Document controller

DFO Team

NC

CPY DR Status
(Deficiency Repor
Total DR Issued
Total DR Closed

TOTAL

32

33

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

11th IA : 12-06-13

GCC-IA

Status in
brief

Completed(L
ast)

10th IA : 26-03-13

GCC-IA

Issued

24

46

13

Total :

13

Closed

24

45

12

Balance :

Open

Cumulative : 13
Completed: 10

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

CPY Q & IM Assessment


Assessment Title

C/list No.

Findings

Closed

Open

N/A

N/A

None

Civil control - Buildings

FCS status (Field Change Sheet

Total No. of
Assessment

Conducted this
Week

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

59

59

26

Status of Deliverables
No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
28
1
9
47

PQP
ITP
QCP
QMP
LTSC

1
28
1
9
47

1
27
1
8
47

Total Condcuted : 6, This week : 0


Description:

Total Open
Total Closed
Total Rejected

S.No.

Quality Tool Box Talks

Total Issued

Total cancelled

SDR stat
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR Closed
Total SDR open

N/A

Week
Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

C300/B200/
B100/C200

92.8/94.5/95%

95/92.7/95%

0.5

C300/B200/
B100/C200

94.0/94.5/90.0%

92.8/94.5/95%

0.5

C300/B200/
B100/C200

93.7/96.3/91.6%

94.0/94.5/90.0%

0.5

C300/B200/
B100/C200

94.0/95.4/93.3%

93.7/96.3/91.6%

0.0

Discipline

% Difference

Action Required
Yes

Quality awareness Training [May'13 to Oct'13]


Item

Date

Scheduled(Upcoming)

15-May-2013

Completed(Previous)

10-Apr-2013

Date

Scheduled(Upcoming)-Sewage works

01-May-2013

Completed (Previous) - Floor finishes


( Ceramic tiling )

30-Apr-2013

Scheduled(Upcoming)-

Completed(Prev.)-Paint/Wire Pull

Bldg.Ref:

Completed

Balance

Total Trained

TOM
Bldg.Ref:

Total

Completed

Balance

Total Trained

16

15

214+5

TBA
02/03-12-12

Date

Total

Completed

Balance

Total Trained

38

Cumulative
Total

Completed

Balance

Total Trained

Scheduled(Upcoming)-TBA

18
Completed(Previous)-G.I.Conduit

Barzan on shore project - Building works - Package#2

23-Mar-2013

Planned

Note : To be re

Cumulative
Date

Planned

Note : To be re

Cumulative

GCC Craft Training (*) - Feb' - Mar'2013


Item

CPY Witnessed

Total

JGC Craft Training (*) Item

JGC Witnessed

Cumulative

Refresher Discipline Training (*) [Nov'12 to Apr'13]


Item

No

Issued This Week

Remarks

18

228+203

1) Percentage of cancellation
2) Reason for rejection :
followed FCS - 2 nos.
IFC drg - 1 no.

tracting Co.WLL

shore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-075

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

23

Total NCR Closed

21

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

17

Total CAR Closed

Total DR Closed

17

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

FCS status (Field Change Sheet)

Total CAR Issued

13

Total CAR Closed

12

Total CAR Open

Total CAR Issued


(This Week)

FTR status (Field Trouble Request)

1021

Total Issued

14

96

841

Total Open
Total Closed

14

49

Total Rejected

35

Total cancelled

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
19

Other S/C SDR

Nil

18

Weekly Field Inspection Status (RFI)


Issued

Accepted

Rejected

Cancelled

384

365

19

384

365

19

143

132

11

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 4.95%
2) Reason for rejection :
followed FCS - 2 nos.
IFC drg - 1 no.

Not
Not followed

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

30-Apr-2013

To:

06-May-2013

Rep. No.:

"Leading" Indicators

Overall Plan

WQM-GCC-076

"Lagging" Indicators

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)

NCR Status (Non-Conformance Report)

32

Items

As of Today : 33

Plan

Actual

JGC

GCC

LTSC

Total NCR Issued

23

FQCM & FQAM(Bldg./MEP)

Total NCR Closed

21

DFQC Manager(Bldg.)

Total NCR Open

Lead QCI (Bldg./MEP) & QCE(MEP)

Total NCR Issued (This Week)

QC Inspectors(Bldg.)

QC Inspectors(MEP/Welding)

CQCC/QC Assistant

Document controller

DFO Team

TOTAL

32

CPY CAR Status


CPY DR Status
(Deficiency Report)

32

Internal Quality Audits

Audit Findings (*)

Total CAR Issued

Total DR Issued

21

Total CAR Closed

Total DR Closed

17

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

Date

Discipline

Scheduled(N
ext)

11th IA : 12-06-13

GCC-IA

Status in
brief

Completed(L
ast)

10th IA : 26-03-13

GCC-IA

Issued

24

46

13

Total :

13

Closed

24

45

13

Total CAR Issued

13

Balance :

Open

Total CAR Closed

13

Total CAR Open

Total CAR Issued


(This Week)

Cumulative : 13
Completed: 10

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

NCR Status (Non-Conformance Report)

CTR CAR Status


(Corrective Action Request)

CPY Q & IM Assessment


Assessment Title

C/list No.

Findings

Closed

Open

N/A

N/A

None

Civil control - Buildings

1
Total No. of
Assessment

Conducted this
Week

Cumulative to Date

59

59

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

26

Status of Deliverables
S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
28
1
9
47

PQP
ITP
QCP
QMP
LTSC

1
28
1
9
47

1
27
1
8
47

Quality Tool Box Talks

1041

Total Issued

Total Open

111

Total Open

Total Closed

843

Total Closed

14

Total Rejected

52

Total Rejected

Total cancelled

35

Total cancelled

14

SDR status (Specification Deviation Request)


GCC SDR
19

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Total SDR Cancelled

Nil

Total SDR Closed

18

Total SDR open

N/A

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk
Score (%)

This Period

Last Period

C300/B200/
B100/C200

94.0/94.5/90.0%

92.8/94.5/95%

0.5

C300/B200/
B100/C200

93.7/96.3/91.6%

94.0/94.5/90.0%

0.5

C300/B200/
B100/C200

94.0/95.4/93.3%

93.7/96.3/91.6%

0.5

C300/B200/
B100/C200

92.2/96.3/94.3%

94.0/95.4/93.3%

0.0

% Difference

Action Required
Yes

Quality awareness Training [May'13 to Sep'13]


Item

Date

Scheduled(Upcoming)

15-May-2013

Completed(Previous)

10-Apr-2013

Date

Scheduled(Upcoming) - Painting works

26-Jun-2013

Completed (Previous) - Sewage works

01-May-2013

Scheduled(Upcoming)-

Completed(Prev.)-Paint/Wire Pull

TBA
02/03-12-12

Completed

Balance

Date

Completed(Previous)-G.I.Conduit

23-Mar-2013

16

JGC Witnessed

353

326

11

16

CPY Witnessed

146

144

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

TOMAS - NO.OF ITR's [UPLOAD]


Bldg.Ref:

Total

Completed

Balance

Total Trained

Total

Completed

Balance

Total Trained

38

Total

Completed

Balance

Total Trained

18

18

228+203

Planned

Actual

% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

Cumulative

QA/QC Highlights

Scheduled(Upcoming)-TBA

Barzan on shore project - Building works - Package#2

Cancelled

11

Total Trained

Cumulative

GCC Craft Training (*) - Feb' - Mar'2013


Item

Rejected

326

Note : To be referred/discussed in weekly DFO meetings.

Cumulative
Date

Accepted

353

Bldg.Ref:

Total

JGC Craft Training (*) Item

No

Remarks

Cumulative

Refresher Discipline Training (*) [May'13 to Sep'13]


Item

Issued

Issued This Week

Items

Score (%)

Discipline

Total Issued

Items
Total SDR Issued

Total Condcuted : 6, This week : 0


Description:

FTR status (Field Trouble Request)

FCS status (Field Change Sheet)

1) Percentage of cancellation : 4.53%


2) Reason for rejection :
FCS - 6 nos.
provided - 4 nos.
1 no.

Need
Washer not
Pipe sharp edge -

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

07-May-2013

To:

13-May-2013

Rep. No.:

"Leading" Indicators

Overall Plan

WQM-GCC-077

"Lagging" Indicators

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)

NCR Status (Non-Conformance Report)

33

Items

As of Today : 32

Plan

Actual

JGC

GCC

LTSC

Total NCR Issued

23

FQCM & FQAM(Bldg./MEP)

Total NCR Closed

22

DFQC Manager(Bldg.)/FQAE

Total NCR Open

Lead QCI (Bldg./MEP) & QCE(MEP)

Total NCR Issued (This Week)

QC Inspectors(Bldg.)

QC Inspectors(MEP/Welding)

NCR Status (Non-Conformance Report)

10

10

CQCC

Document controller

DFO Team

TOTAL

33

32

Internal Quality Audits

Audit Findings (*)

Total CAR Issued

Total DR Issued

23

Total CAR Closed

Total DR Closed

19

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

Date

Discipline

Scheduled(N
ext)

11th IA : 12-06-13

GCC-IA

Status in
brief

Completed(L
ast)

10th IA : 26-03-13

GCC-IA

Issued

24

46

13

Total :

13

Closed

24

46

13

Total CAR Issued

13

Balance :

Open

Total CAR Closed

13

Total CAR Open

Total CAR Issued


(This Week)

Cumulative : 13
Completed: 10

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

CPY CAR Status


CPY DR Status
(Deficiency Report)

CTR CAR Status


(Corrective Action Request)

CPY Q & IM Assessment


Assessment Title

C/list No.

Findings

Closed

Open

N/A

N/A

None

1
Total No. of
Assessment

Conducted this
Week

Cumulative to Date

59

59

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

56

Status of Deliverables
S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
28
1
9
47

PQP
ITP
QCP
QMP
LTSC

1
28
1
9
47

1
28
1
8
47

Quality Tool Box Talks

1056

Total Issued

Total Open

118

Total Open

Total Closed

850

Total Closed

14

Total Rejected

53

Total Rejected

Total cancelled

35

Total cancelled

14

SDR status (Specification Deviation Request)


GCC SDR
19

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Total SDR Cancelled

Nil

Total SDR Closed

18

Total SDR open

N/A

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk
Score (%)

This Period

Last Period

C300/B200/
B100/C200

93.7/96.3/91.6%

94.0/94.5/90.0%

0.5

C300/B200/
B100/C200

94.0/95.4/93.3%

93.7/96.3/91.6%

0.5

C300/B200/
B100/C200

92.2/96.3/94.3%

94.0/95.4/93.3%

0.0

C300/B200/
B100/C200

94.28/96.3%

92.2/96.3/94.3%

0.0

% Difference

Action Required
Yes

Quality awareness Training [May'13 to Sep'13]


Item

Date

Scheduled(Upcoming)

15-May-2013

Completed(Previous)

10-Apr-2013

Date

Scheduled(Upcoming) - Painting works

26-Jun-2013

Completed (Previous) - Sewage works

01-May-2013

Scheduled(Upcoming)-

Completed(Prev.)-Paint/Wire Pull

TBA
02/03-12-12

Completed

Balance

Date

Cancelled

19

JGC Witnessed

328

309

19

CPY Witnessed

135

125

10

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

TOMAS - NO.OF ITR's [UPLOAD]


Bldg.Ref:

Total

Completed

Balance

Total Trained

Total

Completed

Balance

Total Trained

38

Total

Completed

Balance

Total Trained

18

18

228+203

Planned

Actual

% Prog.

Barzan on shore project - Building works - Package#2

Remarks

Note : To be referred/discussed in weekly DFO meetings.

Cumulative

QA/QC Highlights
1) Percentage of cancellation : 5.79%

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

Remarks

Total Trained

Cumulative

GCC Craft Training (*) - May' - June'2013


Item

Rejected

309

Note : To be referred/discussed in weekly DFO meetings.

Cumulative
Date

Accepted

328

Bldg.Ref:

Total

JGC Craft Training (*) Item

No

Remarks

Cumulative

Refresher Discipline Training (*) [May'13 to Sep'13]


Item

Issued

Issued This Week

Items

Score (%)

Discipline

Total Issued

Items
Total SDR Issued

Total Condcuted : 6, This week : 0


Description:

FTR status (Field Trouble Request)

FCS status (Field Change Sheet)

23-Mar-2013

Weekly Quality Metrics

Gulf Contracting Co.WLL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

14-May-2013

To:

20-May-2013

Rep. No.:

"Leading" Indicators

Overall Plan

WQM-GCC-078

"Lagging" Indicators

Proactive Quality Metrics

Reactive Quality Metrics

Quality Resources(Plan|Actual)

NCR Status (Non-Conformance Report)

32

Items

As of Today : 32

Plan

Actual

JGC

GCC

LTSC

Total NCR Issued

23

FQCM & FQAM(Bldg./MEP)

Total NCR Closed

22

DFQC Manager(Bldg.)/FQAE

Total NCR Open

Lead QCI (Bldg./MEP) & QCE(MEP)

Total NCR Issued (This Week)

QC Inspectors(Bldg.)

QC Inspectors(MEP/Welding)

NCR Status (Non-Conformance Report)

10

10

CQCC

Document controller

DFO Team

TOTAL

32

32

Internal Quality Audits

Audit Findings (*)

Total CAR Issued

Total DR Issued

23

Total CAR Closed

Total DR Closed

22

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

Date

Discipline

Scheduled(N
ext)

11th IA : 19-06-13

GCC-IA

Status in
brief

Completed(L
ast)

10th IA : 26-03-13

GCC-IA

Issued

24

46

14

Total :

13

Closed

24

46

13

Total CAR Issued

13

Balance :

Open

Total CAR Closed

13

Total CAR Open

Total CAR Issued


(This Week)

Cumulative : 13
Completed: 10

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

CPY CAR Status


CPY DR Status
(Deficiency Report)

CTR CAR Status


(Corrective Action Request)

CPY Q & IM Assessment


Assessment Title

C/list No.

Findings

Closed

Open

N/A

N/A

None

Civil control[bldg.] & HVAC Bldg.

1
Total No. of
Assessment

Conducted this
Week

Cumulative to Date

61

61

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

58

Status of Deliverables
S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
28
1
9
48

PQP
ITP
QCP
QMP
LTSC

1
28
1
9
48

1
28
1
8
48

Quality Tool Box Talks

1070

Total Issued

Total Open

115

Total Open

Total Closed

864

Total Closed

14

Total Rejected

56

Total Rejected

Total cancelled

35

Total cancelled

14

SDR status (Specification Deviation Request)


GCC SDR
19

Other S/C SDR

Total SDR Approved

Total SDR Rejected

Total SDR Cancelled

Nil

Total SDR Closed

18

Total SDR open

N/A

Weekly Field Inspection Status (RFI)


Weekly Site Quality Walk
Score (%)

This Period

Last Period

C300/B200/
B100/C200

94.0/95.4/93.3%

93.7/96.3/91.6%

0.5

C300/B200/
B100/C200

92.2/96.3/94.3%

94.0/95.4/93.3%

0.5

C300/B200/
B100/C200

94.28/96.3%

92.2/96.3/94.3%

0.0

C300/B200/
B100/C200

93.54/93.75/96%

94.28/96.3%

0.0

% Difference

Action Required
Yes

Quality awareness Training [May'13 to Sep'13]


Item

Date

Scheduled(Upcoming)

22-May-2013

Completed(Previous)

10-Apr-2013

Date

Scheduled(Upcoming) - Painting works

26-Jun-2013

Completed (Previous) - Sewage works

01-May-2013

Scheduled(Upcoming)-

Completed(Prev.)-Paint/Wire Pull

TBA
02/03-12-12

Completed

Balance

Date

Cancelled

15

JGC Witnessed

348

333

15

CPY Witnessed

126

120

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

TOMAS - NO.OF ITR's [UPLOAD]


Bldg.Ref:

Total

Completed

Balance

Total Trained

Total

Completed

Balance

Total Trained

38

Total

Completed

Balance

Total Trained

18

18

228+203

Planned

Actual

% Prog.

Barzan on shore project - Building works - Package#2

Remarks

Note : To be referred/discussed in weekly DFO meetings.

Cumulative

QA/QC Highlights
1) Percentage of cancellation : 4.31%

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

Remarks

Total Trained

Cumulative

GCC Craft Training (*) - May' - June'2013


Item

Rejected

333

Note : To be referred/discussed in weekly DFO meetings.

Cumulative
Date

Accepted

348

Bldg.Ref:

Total

JGC Craft Training (*) Item

No

Remarks

Cumulative

Refresher Discipline Training (*) [May'13 to Sep'13]


Item

Issued

Issued This Week

Items

Score (%)

Discipline

Total Issued

Items
Total SDR Issued

Total Condcuted : 6, This week : 0


Description:

FTR status (Field Trouble Request)

FCS status (Field Change Sheet)

23-Mar-2013

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

21-May-2013

To:

27-May-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

33

Items

As of Today : 33

Plan

Actual

Total NCR Issued

FQCM & FQAM(Bldg./MEP)

Total NCR Closed

DFQC Manager(Bldg.)/FQAE

Total NCR Open

Lead QCI (Bldg./MEP) & QCE(MEP)

Total NCR Issued (This Week)

QC Inspectors(Bldg.)

11

11

CQCC

Document controller

DFO Team

QC Inspectors(MEP/Welding/painting)

NC

CPY DR Status
(Deficiency Repor
Total DR Issued
Total DR Closed

TOTAL

33

33

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

11th IA : 19-06-13

GCC-IA

Status in
brief

Completed(L
ast)

10th IA : 26-03-13

GCC-IA

Issued

24

46

14

Total :

13

Closed

24

46

13

Balance :

Open

Cumulative : 13
Completed: 10

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

CPY Q & IM Assessment


Assessment Title

C/list No.

Findings

Closed

Open

N/A

N/A

None

Civil control[concrete works/lab]

FCS status (Field Change Sheet

Total No. of
Assessment

Conducted this
Week

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

63

63

60

Status of Deliverables
No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
28
1
9
48

PQP
ITP
QCP
QMP
LTSC

1
28
1
9
48

1
28
1
8
48

Quality Tool Box Talks


Description:

N/A

Total Open
Total Closed
Total Rejected

S.No.

Total Condcuted : 6, This week : 0

Total Issued

Total cancelled

SDR stat
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR Closed
Total SDR open

Week

Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

C300/B200/
B100/C200

92.2/96.3/94.3%

94.0/95.4/93.3%

0.5

C300/B200/
B100/C200

94.28/96.3%

92.2/96.3/94.3%

0.5

C300/B200/
B100/C200

93.54/93.75/96%

94.28/96.3%

0.0

C300/B200/
B100/C200

93.5/94.97/95.15%

93.54/93.75/96%

0.0

Discipline

% Difference

Action Required
Yes

Quality awareness Training [May'13 to Sep'13]


Item

Date

Scheduled(Upcoming)

12-Jun-2013

Completed(Previous)

22-May-2013

Date

Scheduled(Upcoming) - Painting works

26-Jun-2013

Completed (Previous) - Sewage works

01-May-2013

Scheduled(Upcoming)-

Completed(Prev.)-Paint/Wire Pull

CPY Witnessed

Bldg.Ref:

Balance

Total Trained

Cumulative

TBA
02/03-12-12

Date

Total

Completed

Balance

Total Trained

Barzan on shore project - Building works - Package#2

23-Mar-2013

Planned

Note : To be re

Total

Completed

Balance

Total Trained

38

Cumulative
Total

Completed

Balance

Total Trained

18

18

228+203

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

TOM
Bldg.Ref:

Cumulative
Date

Planned

Note : To be re

Completed

GCC Craft Training (*) - May' - June'2013


Item

JGC Witnessed

Total

JGC Craft Training (*) Item

Issued This Week

Remarks

Cumulative

Refresher Discipline Training (*) [May'13 to Sep'13]


Item

No

1) Percentage of cancellation

tracting Co.WLL

shore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-079

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

10

23

Total NCR Closed

22

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

25

Total CAR Closed

Total DR Closed

22

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

FCS status (Field Change Sheet)

Total CAR Issued

14

Total CAR Closed

13

Total CAR Open

Total CAR Issued


(This Week)

FTR status (Field Trouble Request)

1097

Total Issued

15

126
877

Total Open
Total Closed

14

56

Total Rejected

38

Total cancelled

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
24

Other S/C SDR

10

Nil

19

Weekly Field Inspection Status (RFI)

Issued

Accepted

Rejected

Cancelled

317

298

16

317

298

16

123

114

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 5.04%

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

28-May-2013

To:

03-Jun-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

33

Items

As of Today : 33

Plan

Actual

Total NCR Issued

FQCM & FQAM(Bldg./MEP)

Total NCR Closed

DFQC Manager(Bldg.)/FQAE

Total NCR Open

Lead QCI (Bldg./MEP) & QCE(MEP)

Total NCR Issued (This Week)

QC Inspectors(Bldg.)

11

11

CQCC

Document controller

DFO Team

QC Inspectors(MEP/Welding/painting)

NC

CPY DR Status
(Deficiency Repor
Total DR Issued
Total DR Closed

TOTAL

33

33

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

11th IA : 19-06-13

GCC-IA

Status in
brief

Completed(L
ast)

10th IA : 26-03-13

GCC-IA

Issued

24

46

14

Total :

13

Closed

24

46

14

Balance :

Open

Cumulative : 13
Completed: 10

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

CPY Q & IM Assessment


Assessment Title

C/list No.

Findings

Closed

Open

N/A

N/A

None

FCS status (Field Change Sheet

Total No. of
Assessment

Conducted this
Week

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

63

63

60

Status of Deliverables
No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
28
1
9
48

PQP
ITP
QCP
QMP
LTSC

1
28
1
9
48

1
28
1
9
48

Quality Tool Box Talks


Description:

N/A

Total Open
Total Closed
Total Rejected

S.No.

Total Condcuted : 6, This week : 0

Total Issued

Total cancelled

SDR stat
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR Closed
Total SDR open

Week

Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

C300/B200/
B100/C200

94.28/96.3%

92.2/96.3/94.3%

0.5

C300/B200/
B100/C200

93.54/93.75/96%

94.28/96.3%

0.5

C300/B200/
B100/C200

93.5/94.97/95.15%

93.54/93.75/96%

0.0

C300/B200/
B100/C200

95.5/97.6%

93.5/94.97/95.15%

0.0

Discipline

% Difference

Action Required
Yes

Quality awareness Training [May'13 to Sep'13]


Item

Date

Scheduled(Upcoming)

12-Jun-2013

Completed(Previous)

22-May-2013

Date

Scheduled(Upcoming) - Painting works

26-Jun-2013

Completed (Previous) - Sewage works

01-May-2013

Scheduled(Upcoming)-

Completed(Prev.)-Paint/Wire Pull

CPY Witnessed

Bldg.Ref:

Balance

Total Trained

Cumulative

TBA
02/03-12-12

Date

Total

Completed

Balance

Total Trained

Total

Completed

Balance

Total Trained

38

Cumulative
Total

Completed

Balance

Total Trained

1) Percentage of cancellation

2) Reason for Rejection : No F


18

Barzan on shore project - Building works - Package#2

Planned

Note : To be re

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

TOM
Bldg.Ref:

Cumulative
Date

Planned

Note : To be re

Completed

GCC Craft Training (*) - May' - June'2013


Item

JGC Witnessed

Total

JGC Craft Training (*) Item

Issued This Week

Remarks

Cumulative

Refresher Discipline Training (*) [May'13 to Sep'13]


Item

No

23-Mar-2013

18

228+203

tracting Co.WLL

shore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-079

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

10

23

Total NCR Closed

22

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

25

Total CAR Closed

Total DR Closed

25

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

FCS status (Field Change Sheet)

Total CAR Issued

14

Total CAR Closed

14

Total CAR Open

Total CAR Issued


(This Week)

FTR status (Field Trouble Request)

1138

Total Issued

16

148
891

Total Open
Total Closed

14

60

Total Rejected

39

Total cancelled

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
24

Other S/C SDR

10

Nil

19

Weekly Field Inspection Status (RFI)

Issued

Accepted

Rejected

Cancelled

302

285

16

302

285

16

130

114

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 5.29%
2) Reason for Rejection : No FCS [1 No]

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

04-Jun-2013

To:

10-Jun-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

33

Items

As of Today : 33

Plan

Actual

Total NCR Issued

FQCM & FQAM(Bldg./MEP)

Total NCR Closed

DFQC Manager(Bldg.)/FQAE

Total NCR Open

Lead QCI (Bldg./MEP) & QCE(MEP)

Total NCR Issued (This Week)

QC Inspectors(Bldg.)

11

11

CQCC

Document controller

DFO Team

QC Inspectors(MEP/Welding/painting)

NC

CPY DR Status
(Deficiency Repor
Total DR Issued
Total DR Closed

TOTAL

33

33

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

11th IA : 19-06-13

GCC-IA

Status in
brief

Completed(L
ast)

10th IA : 26-03-13

GCC-IA

Issued

24

46

14

Total :

13

Closed

24

46

14

Balance :

Open

Cumulative : 13
Completed: 10

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

CPY Q & IM Assessment


Assessment Title

C/list No.

Findings

Closed

Open

N/A

N/A

None

FCS status (Field Change Sheet

Total No. of
Assessment

Conducted this
Week

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

63

63

60

Status of Deliverables
No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
29
1
9
48

PQP
ITP
QCP
QMP
LTSC

1
29
1
9
48

1
28
1
9
48

Quality Tool Box Talks


Description:

N/A

Total Open
Total Closed
Total Rejected

S.No.

Total Condcuted : 6, This week : 0

Total Issued

Total cancelled

SDR stat
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR Closed
Total SDR open

Week

Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

C300/B200/
B100/C200

93.54/93.75/96%

94.28/96.3%

0.5

C300/B200/
B100/C200

93.5/94.97/95.15%

93.54/93.75/96%

0.5

C300/B200/
B100/C200

95.5/97.6%

93.5/94.97/95.15%

0.0

C300/B200/
B100/C200

93.1/95%

95.5/97.6%

0.0

Discipline

% Difference

Action Required
Yes

Quality awareness Training [May'13 to Sep'13]


Item

Date

Scheduled(Upcoming)

12-Jun-2013

Completed(Previous)

22-May-2013

Date

Scheduled(Upcoming) - Painting works

26-Jun-2013

Completed (Previous) - Sewage works

01-May-2013

Scheduled(Upcoming)-

Completed(Prev.)-Paint/Wire Pull

CPY Witnessed

Bldg.Ref:

Balance

Total Trained

Cumulative

TBA
02/03-12-12

Date

Total

Completed

Balance

Total Trained

Barzan on shore project - Building works - Package#2

23-Mar-2013

Planned

Note : To be re

Total

Completed

Balance

Total Trained

38

Cumulative
Total

Completed

Balance

Total Trained

18

18

228+203

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

TOM
Bldg.Ref:

Cumulative
Date

Planned

Note : To be re

Completed

GCC Craft Training (*) - May' - June'2013


Item

JGC Witnessed

Total

JGC Craft Training (*) Item

Issued This Week

Remarks

Cumulative

Refresher Discipline Training (*) [May'13 to Sep'13]


Item

No

1) Percentage of cancellation

tracting Co.WLL

shore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-080

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

10

23

Total NCR Closed

22

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

26

Total CAR Closed

Total DR Closed

25

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

FCS status (Field Change Sheet)

Total CAR Issued

14

Total CAR Closed

14

Total CAR Open

Total CAR Issued


(This Week)

FTR status (Field Trouble Request)

1159

Total Issued

16

134
923

Total Open
Total Closed

15

63

Total Rejected

39

Total cancelled

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
24

Other S/C SDR

10

Nil

19

Weekly Field Inspection Status (RFI)

Issued

Accepted

Rejected

Cancelled

325

311

14

325

311

14

149

142

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 4.30%

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

11-Jun-2013

To:

17-Jun-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

32

Items

As of Today : 32

Plan

Actual

Total NCR Issued

FQCM & FQAM(Bldg./MEP)

Total NCR Closed

DFQC Manager(Bldg.)/FQAE

Total NCR Open

Lead QCI (Bldg./MEP) & QCE(MEP)

Total NCR Issued (This Week)

QC Inspectors(Bldg.)

10

10

CQCC

Document controller

DFO Team

QC Inspectors(MEP/Welding/painting)

NC

CPY DR Status
(Deficiency Repor
Total DR Issued
Total DR Closed

TOTAL

32

32

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

11th IA : 24-06-13

GCC-IA

Status in
brief

Completed(L
ast)

10th IA : 26-03-13

GCC-IA

Issued

24

46

14

Total :

13

Closed

24

46

14

Balance :

Open

Cumulative : 13
Completed: 10

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

CPY Q & IM Assessment


C/list No.

Assessment Title

Findings

Closed

Open

Building[HVAC]

Yes

TBC

Re-assessment on
19/06/13

1
Total No. of
Assessment

Conducted this
Week

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

64

64

60

Status of Deliverables
No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
29
1
9
48

PQP
ITP
QCP
QMP
LTSC

1
29
1
9
48

1
28
1
9
48

Quality Tool Box Talks


Description:

N/A

Total Issued
Total Open
Total Closed
Total Rejected

S.No.

Total Condcuted : 6, This week : 0

FCS status (Field Change Sheet

Total cancelled

SDR stat
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR Closed
Total SDR open

Week

Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

C300/B200/
B100/C200

93.5/94.97/95.15%

93.54/93.75/96%

0.5

C300/B200/
B100/C200

95.5/97.6%

93.5/94.97/95.15%

0.5

C300/B200/
B100/C200

93.1/95%

95.5/97.6%

0.0

C300/B200/
B100/C200

97.2/93.75/93%

93.1/95%

0.5

Discipline

% Difference

Action Required
Yes

Quality awareness Training [May'13 to Sep'13]


Item

Date

Scheduled(Upcoming)

10-Jul-2013

Completed(Previous)

12-Jun-2013

Date

Scheduled(Upcoming) - Painting works

26-Jun-2013

Completed (Previous) - Sewage works

01-May-2013

Scheduled(Upcoming)-

Completed(Prev.)-Paint/Wire Pull

CPY Witnessed

Bldg.Ref:

Balance

Total Trained

14

Cumulative

TBA
02/03-12-12

Date

Total

Completed

Balance

Total Trained

Barzan on shore project - Building works - Package#2

23-Mar-2013

Planned

Note : To be re

Total

Completed

Balance

Total Trained

38

Cumulative
Total

Completed

Balance

Total Trained

18

18

228+203

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

TOM
Bldg.Ref:

Cumulative
Date

Planned

Note : To be re

Completed

GCC Craft Training (*) - May' - June'2013


Item

JGC Witnessed

Total

JGC Craft Training (*) Item

Issued This Week

Remarks

Cumulative

Refresher Discipline Training (*) [May'13 to Sep'13]


Item

No

1) Percentage of cancellation

tracting Co.WLL

shore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-081

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

10

23

Total NCR Closed

22

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

27

Total CAR Closed

Total DR Closed

26

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

FCS status (Field Change Sheet)

Total CAR Issued

14

Total CAR Closed

14

Total CAR Open

Total CAR Issued


(This Week)

FTR status (Field Trouble Request)

1187

Total Issued

16

133
948

Total Open
Total Closed

16

67

Total Rejected

39

Total cancelled

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
24

Other S/C SDR

10

Nil

19

Weekly Field Inspection Status (RFI)

Issued

Accepted

Rejected

Cancelled

346

328

18

346

328

18

133

133

10

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 5.20%

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

18-Jun-2013

To:

24-Jun-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

35

Items

As of Today : 35

Plan

Actual

Total NCR Issued

FQCM & FQAM(Bldg./MEP)

Total NCR Closed

DFQC Manager(Bldg.)/FQAE

Total NCR Open

Lead QCI (Elec.)

Total NCR Issued (This Week)

QC Inspectors(Bldg.)

12

11

CQCC

Document controller

DFO Team

QC Inspectors(MEP/Welding/painting)

QC Inspectors(FRP) - Call-off Basis

TOTAL

35

35

NC

CPY DR Status
(Deficiency Repor
Total DR Issued
Total DR Closed

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

12th IA : 25-09-13

GCC-IA

Status in
brief

Completed(L
ast)

11th IA : 24-06-13

GCC-IA

Issued

24

59

19

Total :

13

Closed

24

46

14

Balance :

Open

13

Cumulative : 13
Completed: 11

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

Note : Recent Internal audit findings yet to finalize.


CPY Q & IM Assessment
Assessment Title

C/list No.

Findings

Closed

Open

FCS status (Field Change Sheet

Total No. of
Assessment

Conducted this
Week

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

64

64

64

Status of Deliverables
No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
29
1
9
48

PQP
ITP
QCP
QMP
LTSC

1
29
1
9
48

1
28
1
9
48

Quality Tool Box Talks


Description:

N/A

Total Open
Total Closed
Total Rejected

S.No.

Total Condcuted : 6, This week : 0

Total Issued

Total cancelled

SDR stat
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR Closed
Total SDR open

Week

Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

C300/B200/
B100/C200

95.5/97.6%

93.5/94.97/95.15%

0.5

C300/B200/
B100/C200

93.1/95%

95.5/97.6%

0.5

C300/B200/
B100/C200

97.2/93.75/93%

93.1/95%

0.0

C300/B200/
B100/C200

93.7/96./92.2%

97.2/93.75/93%

0.5

Discipline

% Difference

Action Required
Yes

Quality awareness Training [May'13 to Sep'13]


Item

Date

Scheduled(Upcoming)

10-Jul-2013

Completed(Previous)

12-Jun-2013

Date

Scheduled(Upcoming) - Painting works

30-Jun-2013

Completed (Previous) - Sewage works

01-May-2013

Scheduled(Upcoming)-

Completed(Prev.)-Paint/Wire Pull

CPY Witnessed

Bldg.Ref:

Balance

Total Trained

14

Cumulative

TBA
02/03-12-12

Date

Total

Completed

Balance

Total Trained

Total

Completed

Balance

Total Trained

38

Cumulative
Total

Completed

Balance

Total Trained

1) Percentage of cancellation

2)Reason for rejection : 2 No's


18

Barzan on shore project - Building works - Package#2

Planned

Note : To be re

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

TOM
Bldg.Ref:

Cumulative
Date

Planned

Note : To be re

Completed

GCC Craft Training (*) - May' - June'2013


Item

JGC Witnessed

Total

JGC Craft Training (*) Item

Issued This Week

Remarks

Cumulative

Refresher Discipline Training (*) [May'13 to Sep'13]


Item

No

23-Mar-2013

18

228+203

tracting Co.WLL

shore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-082

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

10

23

Total NCR Closed

22

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

27

Total CAR Closed

Total DR Closed

27

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

FCS status (Field Change Sheet)

Total CAR Issued

19

Total CAR Closed

14

Total CAR Open

Total CAR Issued


(This Week)

FTR status (Field Trouble Request)

1216

Total Issued

16

123
980

Total Open
Total Closed

16

73

Total Rejected

40

Total cancelled

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
24

Other S/C SDR

10

Nil

19

Weekly Field Inspection Status (RFI)

Issued

Accepted

Rejected

Cancelled

351

332

17

351

332

17

141

134

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 4.84%
2)Reason for rejection : 2 No's [MEP] - Material is not as per FCS.

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

25-Jun-2013

To:

01-Jul-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

34

Items

As of Today : 33

Plan

Actual

Total NCR Issued

FQCM

Total NCR Closed

DFQC Manager(Bldg.)/FQAE

Total NCR Open

Lead QCI (Elec.)

Total NCR Issued (This Week)

QC Inspectors(Bldg.)

13

13

CQCC

Document controller

DFO Team

QC Inspectors(MEP/Welding/painting)

QC Inspectors(FRP) - Call-off Basis

TOTAL

34

33

NC

CPY DR Status
(Deficiency Repor
Total DR Issued
Total DR Closed

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

12th IA : 25-07-13

GCC-IA

Status in
brief

Completed(L
ast)

11th IA : 24-06-13

GCC-IA

Issued

30

60

19

Total :

16

Closed

24

46

14

Balance :

Open

14

Cumulative : 16
Completed: 11

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

CPY Q & IM Assessment


Assessment Title

C/list No.

Findings

Closed

Open

FCS status (Field Change Sheet

Total No. of
Assessment

Conducted this
Week

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

64

64

64

Status of Deliverables
No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
32
1
9
49

PQP
ITP
QCP
QMP
LTSC

1
32
1
9
49

1
28
1
9
48

Quality Tool Box Talks


Description:

N/A

Total Open
Total Closed
Total Rejected

S.No.

Total Condcuted : 6, This week : 0

Total Issued

Total cancelled

SDR stat
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR Closed
Total SDR open

Week

Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

C300/B200/
B100/C200

93.1/95%

95.5/97.6%

0.5

C300/B200/
B100/C200

97.2/93.75/93%

93.1/95%

0.5

C300/B200/
B100/C200

93.7/96./92.2%

97.2/93.75/93%

0.0

C300/B200/
B100/C200

95/95/91.66%

93.7/96./92.2%

0.5

Discipline

% Difference

Action Required
Yes

Quality awareness Training [May'13 to Sep'13]


Item

Date

Scheduled(Upcoming)

10-Jul-2013

Completed(Previous)

12-Jun-2013

Date

Scheduled(Upcoming) - Floor finishes

31-Jul-2013

Completed (Previous) - Painting works

30-Jun-2013

Scheduled(Upcoming)-

Completed(Prev.)-Paint/Wire Pull

CPY Witnessed

Bldg.Ref:

Balance

Total Trained

14

Cumulative

TBA
02/03-12-12

Date

Total

Completed

Balance

Total Trained

11

Total

Completed

Balance

Total Trained

38

Cumulative
Total

Completed

Balance

Total Trained

1) Percentage of cancellation
2)Reason for rejection : N/A

18
Barzan on shore project - Building works - Package#2

Planned

Note : To be re

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

TOM
Bldg.Ref:

Cumulative
Date

Planned

Note : To be re

Completed

GCC Craft Training (*) - May' - June'2013


Item

JGC Witnessed

Total

JGC Craft Training (*) Item

Issued This Week

Remarks

Cumulative

Refresher Discipline Training (*) [May'13 to Sep'13]


Item

No

23-Mar-2013

18

228+203

tracting Co.WLL

shore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-083

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

10

23

Total NCR Closed

22

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

27

Total CAR Closed

Total DR Closed

27

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

FCS status (Field Change Sheet)

Total CAR Issued

19

Total CAR Closed

14

Total CAR Open

Total CAR Issued


(This Week)

FTR status (Field Trouble Request)

1247

Total Issued

16

131
980

Total Open
Total Closed

16

75

Total Rejected

43

Total cancelled

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
24

Other S/C SDR

10

Nil

19

Weekly Field Inspection Status (RFI)

Issued

Accepted

Rejected

Cancelled

293

272

21

293

272

21

128

114

14

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 7.16%
2)Reason for rejection : N/A

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

02-Jul-2013

To:

08-Jul-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

34

Items

As of Today : 33

Plan

Actual

Total NCR Issued

FQCM

Total NCR Closed

DFQC Manager(Bldg.)/FQAE

Total NCR Open

Lead QCI (Elec.)

Total NCR Issued (This Week)

QC Inspectors(Bldg.)

13

13

CQCC

Document controller

DFO Team

QC Inspectors(MEP/Welding/painting)

QC Inspectors(FRP) - Call-off Basis

TOTAL

34

33

NC

CPY DR Status
(Deficiency Repor
Total DR Issued
Total DR Closed

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

12th IA : 25-07-13

GCC-IA

Status in
brief

Completed(L
ast)

11th IA : 24-06-13

GCC-IA

Issued

30

60

19

Total :

16

Closed

24

46

14

Balance :

Open

14

Cumulative : 16
Completed: 11

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

CPY Q & IM Assessment


Assessment Title

C/list No.

Findings

Closed

Open

FCS status (Field Change Sheet

Total No. of
Assessment

Conducted this
Week

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

64

64

64

Status of Deliverables
No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
32
1
9
50

PQP
ITP
QCP
QMP
LTSC

1
32
1
9
50

1
28
1
9
49

Quality Tool Box Talks


Description:

N/A

Total Open
Total Closed
Total Rejected

S.No.

Total Condcuted : 6, This week : 0

Total Issued

Total cancelled

SDR stat
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR Closed
Total SDR open

Week

Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

C300/B200/
B100/C200

97.2/93.75/93%

93.1/95%

0.5

C300/B200/
B100/C200

93.7/96./92.2%

97.2/93.75/93%

0.5

C300/B200/
B100/C200

95/95/91.66%

93.7/96./92.2%

0.0

C300/B200/
B100/C200

93.6/93.75/94

95/95/91.66%

0.5

Discipline

% Difference

Action Required
Yes

Quality awareness Training [May'13 to Sep'13]


Item

Date

Scheduled(Upcoming)

10-Jul-2013

Completed(Previous)

12-Jun-2013

Date

Scheduled(Upcoming) - Floor finishes

31-Jul-2013

Completed (Previous) - Painting works

30-Jun-2013

Scheduled(Upcoming)-

Completed(Prev.)-Paint/Wire Pull

CPY Witnessed

Bldg.Ref:

Balance

Total Trained

14

Cumulative

TBA
02/03-12-12

Date

Total

Completed

Balance

Total Trained

11

Total

Completed

Balance

Total Trained

38

Cumulative
Total

Completed

Balance

Total Trained

1) Percentage of cancellation
2)Reason for rejection : N/A

18
Barzan on shore project - Building works - Package#2

Planned

Note : To be re

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

TOM
Bldg.Ref:

Cumulative
Date

Planned

Note : To be re

Completed

GCC Craft Training (*) - May' - June'2013


Item

JGC Witnessed

Total

JGC Craft Training (*) Item

Issued This Week

Remarks

Cumulative

Refresher Discipline Training (*) [May'13 to Sep'13]


Item

No

23-Mar-2013

18

228+203

tracting Co.WLL

shore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-084

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

10

23

Total NCR Closed

22

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

29

Total CAR Closed

Total DR Closed

27

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

FCS status (Field Change Sheet)

Total CAR Issued

19

Total CAR Closed

14

Total CAR Open

Total CAR Issued


(This Week)

FTR status (Field Trouble Request)

1265

Total Issued

17

130

Total Open
Total Closed

16

81

Total Rejected

43

Total cancelled

1011

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
24

Other S/C SDR

10

Nil

19

Weekly Field Inspection Status (RFI)

Issued

Accepted

Rejected

Cancelled

335

310

25

335

310

25

155

141

14

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 7.46%
2)Reason for rejection : N/A

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

09-Jul-2013

To:

15-Jul-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

34

Items

As of Today : 33

Plan

Actual

Total NCR Issued

FQCM

Total NCR Closed

DFQC Manager(Bldg.)/FQAE

Total NCR Open

Lead QCI (Elec.)

Total NCR Issued (This Week)

QC Inspectors(Bldg.)

13

13

CQCC

Document controller

DFO Team

QC Inspectors(MEP/Welding/painting)

QC Inspectors(FRP) - Call-off Basis

TOTAL

34

33

NC

CPY DR Status
(Deficiency Repor
Total DR Issued
Total DR Closed

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

12th IA : 25-07-13

GCC-IA

Status in
brief

Completed(L
ast)

11th IA : 24-06-13

GCC-IA

Issued

30

60

19

Total :

16

Closed

24

48

14

Balance :

Open

12

Cumulative : 16
Completed: 11

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

CPY Q & IM Assessment


Assessment Title

C/list No.
1

Findings

Closed

Open

PMC-HVAC

FCS status (Field Change Sheet

Total No. of
Assessment

Conducted this
Week

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

65

65

65

Status of Deliverables
No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
33
1
9
50

PQP
ITP
QCP
QMP
LTSC

1
33
1
9
50

1
31
1
9
49

Quality Tool Box Talks


Description:

N/A

Total Open
Total Closed
Total Rejected

S.No.

Total Condcuted : 6, This week : 0

Total Issued

Total cancelled

SDR stat
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR Closed
Total SDR open

Week

Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

C300/B200/
B100/C200

93.7/96./92.2%

97.2/93.75/93%

0.0

C300/B200/
B100/C200

95/95/91.66%

93.7/96./92.2%

0.5

C300/B200/
B100/C200

93.6/93.75/94

95/95/91.66%

0.0

C300/B200/
B100/C200

93.6/93.75/94%

93.6/93.75/94

0.5

Discipline

% Difference

Action Required
Yes

Quality awareness Training [May'13 to Sep'13]


Item

Date

Scheduled(Upcoming)

14-Aug-2013

Completed(Previous)

10-Jul-2013

Date

Scheduled(Upcoming) - Floor finishes

31-Jul-2013

Completed (Previous) - Painting works

30-Jun-2013

Scheduled(Upcoming)-

Completed(Prev.)-Paint/Wire Pull

CPY Witnessed

Bldg.Ref:

Balance

Total Trained

17

Cumulative

TBA
02/03-12-12

Date

Total

Completed

Balance

Total Trained

11

Total

Completed

Balance

Total Trained

38

Cumulative
Total

18
Barzan on shore project - Building works - Package#2

23-Mar-2013

Planned

Note : To be re

Completed

Balance

Total Trained

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

TOM
Bldg.Ref:

Cumulative
Date

Planned

Note : To be re

Completed

GCC Craft Training (*) - May' - June'2013


Item

JGC Witnessed

Total

JGC Craft Training (*) Item

Issued This Week

Remarks

Cumulative

Refresher Discipline Training (*) [May'13 to Sep'13]


Item

No

18

228+203

1) Percentage of cancellation

2)Reason for rejection : Incorr


per FCS (2 No's)

tracting Co.WLL

shore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-085

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

10

23

Total NCR Closed

22

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

29

Total CAR Closed

Total DR Closed

27

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

FCS status (Field Change Sheet)

Total CAR Issued

19

Total CAR Closed

14

Total CAR Open

Total CAR Issued


(This Week)

FTR status (Field Trouble Request)

1284

Total Issued

17

134

Total Open
Total Closed

16

81

Total Rejected

43

Total cancelled

1026

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
24

Other S/C SDR

10

Nil

19

Weekly Field Inspection Status (RFI)

Issued

Accepted

Rejected

Cancelled

296

275

17

296

275

17

130

121

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 5.74%
2)Reason for rejection : Incorrect description on RFI's (2 No's) & Installations are not as
per FCS (2 No's)

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

15-Jul-2013

To:

21-Jul-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

34

Items

As of Today : 33

Plan

Actual

Total NCR Issued

FQCM

Total NCR Closed

DFQC Manager(Bldg.)/FQAE

Total NCR Open

Lead QCI (Elec.)

Total NCR Issued (This Week)

QC Inspectors(Bldg.)

13

13

CQCC

Document controller

DFO Team

QC Inspectors(MEP/Welding/painting)

QC Inspectors(FRP) - Call-off Basis

TOTAL

34

33

NC

CPY DR Status
(Deficiency Repor
Total DR Issued
Total DR Closed

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

12th IA : 25-07-13

GCC-IA

Status in
brief

Completed(L
ast)

11th IA : 24-06-13

GCC-IA

Issued

30

60

19

Total :

16

Closed

30

48

14

Balance :

Open

12

Cumulative : 16
Completed: 11

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

CPY Q & IM Assessment


Assessment Title

C/list No.
1

Findings

Closed

Open

PMC-ELECTRICAL(100%)

FCS status (Field Change Sheet

Total No. of
Assessment

Conducted this
Week

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

66

66

66

Status of Deliverables
No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
33
1
9
50

PQP
ITP
QCP
QMP
LTSC

1
33
1
9
50

1
31
1
9
49

Quality Tool Box Talks


Description:

N/A

Total Open
Total Closed
Total Rejected

S.No.

Total Condcuted : 6, This week : 0

Total Issued

Total cancelled

SDR stat
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR Closed
Total SDR open

Week

Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

C300/B200/
B100/C200

95/95/91.66%

93.7/96./92.2%

0.0

C300/B200/
B100/C200

93.6/93.75/94

95/95/91.66%

0.5

C300/B200/
B100/C200

93.6/93.75/94%

93.6/93.75/94

0.0

C300/B200/
B100/C200

95.8/97/94.28%

93.6/93.75/94%

0.5

Discipline

% Difference

Action Required
Yes

Quality awareness Training [May'13 to Sep'13]


Item

Date

Scheduled(Upcoming)

14-Aug-2013

Completed(Previous)

10-Jul-2013

Date

Scheduled(Upcoming) - Floor finishes

31-Jul-2013

Completed (Previous) - Painting works

30-Jun-2013

Scheduled(Upcoming)-

Completed(Prev.)-Paint/Wire Pull

CPY Witnessed

Bldg.Ref:

Balance

Total Trained

17

Cumulative

TBA
02/03-12-12

Date

Total

Completed

Balance

Total Trained

11

Total

Completed

Balance

Total Trained

38

Cumulative
Total

Completed

Balance

Total Trained

1) Percentage of cancellation
2)Reason for rejection : Refer

18
Barzan on shore project - Building works - Package#2

Planned

Note : To be re

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

TOM
Bldg.Ref:

Cumulative
Date

Planned

Note : To be re

Completed

GCC Craft Training (*) - May' - June'2013


Item

JGC Witnessed

Total

JGC Craft Training (*) Item

Issued This Week

Remarks

Cumulative

Refresher Discipline Training (*) [May'13 to Sep'13]


Item

No

23-Mar-2013

18

228+203

tracting Co.WLL

shore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-086

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

12

23

Total NCR Closed

22

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

29

Total CAR Closed

Total DR Closed

29

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

FCS status (Field Change Sheet)

Total CAR Issued

19

Total CAR Closed

14

Total CAR Open

Total CAR Issued


(This Week)

FTR status (Field Trouble Request)

1298

Total Issued

17

121

Total Open
Total Closed

16

81

Total Rejected

43

Total cancelled

1053

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
24

Other S/C SDR

10

Nil

19

Weekly Field Inspection Status (RFI)

Issued

Accepted

Rejected

Cancelled

256

224

24

256

224

24

124

100

24

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 9.37%
2)Reason for rejection : Refer attachment#07

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

22-Jul-2013

To:

28-Jul-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

33

Items

As of Today : 32

Plan

Actual

Total NCR Issued

FQCM

Total NCR Closed

DFQC Manager(Bldg.)/FQAE

Total NCR Open

Lead QCI (Elec.)

Total NCR Issued (This Week)

QC Inspectors(Bldg.)

13

13

CQCC

Document controller

DFO Team

QC Inspectors(MEP/Welding/painting)

QC Inspectors(FRP) - Call-off Basis

TOTAL

33

32

NC

CPY DR Status
(Deficiency Repor
Total DR Issued
Total DR Closed

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

12th IA : 31-07-13

GCC-IA

Status in
brief

Completed(L
ast)

11th IA : 24-06-13

GCC-IA

Issued

30

60

19

Total :

16

Closed

24

50

14

Balance :

Open

10

Cumulative : 16
Completed: 11

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

CPY Q & IM Assessment


Assessment Title

C/list No.
1

Findings

Closed

Open

PMC-Field Electrical Testing/Commissioning(100%)

FCS status (Field Change Sheet

Total No. of
Assessment

Conducted this
Week

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

67

67

67

Status of Deliverables
No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
33
1
9
50

PQP
ITP
QCP
QMP
LTSC

1
33
1
9
50

1
31
1
9
50

Quality Tool Box Talks


Description:

N/A

Total Open
Total Closed
Total Rejected

S.No.

Total Condcuted : 6, This week : 0

Total Issued

Total cancelled

SDR stat
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR Closed
Total SDR open

Week

Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

C300/B200/
B100/C200

93.6/93.75/94

95/95/91.66%

0.0

C300/B200/
B100/C200

93.6/93.75/94%

93.6/93.75/94

0.5

C300/B200/
B100/C200

95.8/97/94.28%

93.6/93.75/94%

0.0

C300/B200/
B100/C200

92.3/95.83/94%

95.8/97/94.28%

0.5

Discipline

% Difference

Action Required
Yes

Quality awareness Training [May'13 to Sep'13]


Item

Date

Scheduled(Upcoming)

04-Aug-2013

Completed(Previous)

23-Jul-2013

Date

Scheduled(Upcoming) - Floor finishes

31-Jul-2013

Completed (Previous) - Painting works

30-Jun-2013

Scheduled(Upcoming)-

Completed(Prev.)-Paint/Wire Pull

CPY Witnessed

Bldg.Ref:

Balance

Total Trained

11

45

Cumulative

TBA
02/03-12-12

Date

Total

Completed

Balance

Total Trained

11

Total

Completed

Balance

Total Trained

38

Cumulative
Total

Completed

Balance

Total Trained

1) Percentage of cancellation
2)Reason for rejection : Refer

18
Barzan on shore project - Building works - Package#2

Planned

Note : To be re

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

TOM
Bldg.Ref:

Cumulative
Date

Planned

Note : To be re

Completed

GCC Craft Training (*) - May' - June'2013


Item

JGC Witnessed

Total

JGC Craft Training (*) Item

Issued This Week

Remarks

Cumulative

Refresher Discipline Training (*) [May'13 to Sep'13]


Item

No

23-Mar-2013

18

228+203

tracting Co.WLL

shore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-087

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

12

23

Total NCR Closed

22

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

30

Total CAR Closed

Total DR Closed

29

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

FCS status (Field Change Sheet)

Total CAR Issued

19

Total CAR Closed

14

Total CAR Open

Total CAR Issued


(This Week)

FTR status (Field Trouble Request)

1312

Total Issued

17

121

Total Open
Total Closed

16

85

Total Rejected

44

Total cancelled

1062

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
24

Other S/C SDR

10

Nil

19

Weekly Field Inspection Status (RFI)

Issued

Accepted

Rejected

Cancelled

281

263

13

281

263

13

84

80

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 4.62%
2)Reason for rejection : Refer attachment#07

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

29-Jul-2013

To:

04-Aug-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

33

Items

As of Today : 32

Plan

Actual

Total NCR Issued

FQCM

Total NCR Closed

DFQC Manager(Bldg.)/FQAE

Total NCR Open

Lead QCI (Elec.)

Total NCR Issued (This Week)

QC Inspectors(Bldg.)

13

13

CQCC

Document controller

DFO Team

QC Inspectors(MEP/Welding/painting)

QC Inspectors(FRP) - Call-off Basis

TOTAL

33

32

NC

CPY DR Status
(Deficiency Repor
Total DR Issued
Total DR Closed

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

13th IA : 15-08-13

GCC-IA

Status in
brief

Completed(L
ast)

12th IA : 31-07-13

GCC-IA

Issued

30

60

19

Total :

16

Closed

24

53

14

Balance :

Open

Cumulative : 16
Completed: 12

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

CPY Q & IM Assessment


Assessment Title

C/list No.

Findings

Closed

Open

FCS status (Field Change Sheet


Total No. of
Assessment

Conducted this
Week

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

67

67

67

Status of Deliverables
No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
33
1
9
50

PQP
ITP
QCP
QMP
LTSC

1
33
1
9
50

1
32
1
9
50

Quality Tool Box Talks


Description:

N/A

Total Open
Total Closed
Total Rejected

S.No.

Total Condcuted : 6, This week : 0

Total Issued

Total cancelled

SDR stat
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR Closed
Total SDR open

Week

Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

C300/B200/
B100/C200

93.6/93.75/94%

93.6/93.75/94

0.0

C300/B200/
B100/C200

95.8/97/94.28%

93.6/93.75/94%

0.5

C300/B200/
B100/C200

92.3/95.83/94%

95.8/97/94.28%

0.0

C300/B200/
B100/C200

94.4/95.38/91.25%

92.3/95.83/94%

0.5

Discipline

% Difference

Action Required
Yes

Quality awareness Training [May'13 to Sep'13]


Item

Date

Scheduled(Upcoming)

05-Aug-2013

Completed(Previous)

23-Jul-2013

Date

Scheduled(Upcoming) - Electrical works

06-Aug-2013

Completed (Previous) - Floor finishes

31-Jul-2013

Scheduled(Upcoming)-

Completed(Prev.)-Paint/Wire Pull

CPY Witnessed

Bldg.Ref:

Balance

Total Trained

11

45

Cumulative

TBA
02/03-12-12

Date

Total

Completed

Balance

Total Trained

15

Total

Completed

Balance

Total Trained

38

Cumulative
Total

Completed

Balance

Total Trained

1) Percentage of cancellation
2)Reason for rejection : None

18
Barzan on shore project - Building works - Package#2

Planned

Note : To be re

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

TOM
Bldg.Ref:

Cumulative
Date

Planned

Note : To be re

Completed

GCC Craft Training (*) - May' - June'2013


Item

JGC Witnessed

Total

JGC Craft Training (*) Item

Issued This Week

Remarks

Cumulative

Refresher Discipline Training (*) [May'13 to Sep'13]


Item

No

23-Mar-2013

18

228+203

tracting Co.WLL

shore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-088

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

12

24

Total NCR Closed

22

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

33

Total CAR Closed

Total DR Closed

29

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

FCS status (Field Change Sheet)

Total CAR Issued

19

Total CAR Closed

14

Total CAR Open

Total CAR Issued


(This Week)

FTR status (Field Trouble Request)

1327

Total Issued

17

114

Total Open
Total Closed

17

84

Total Rejected

44

Total cancelled

1085

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
24

Other S/C SDR

10

Nil

19

Weekly Field Inspection Status (RFI)

Issued

Accepted

Rejected

Cancelled

238

228

10

238

228

10

94

88

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 4.2%
2)Reason for rejection : None

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

05-Aug-2013

To:

11-Aug-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

31

Items

As of Today : 30

Plan

Actual

Total NCR Issued

FQCM

Total NCR Closed

DFQCM

Total NCR Open

QA

Total NCR Issued (This Week)

QCI (Building)

13

13

CQCC

Document controller

DFO Team

QC Team(MEP works)

QC Inspectors(FRP/Painting/Welding) - Call-off Basis

TOTAL

31

30

NC

CPY DR Status
(Deficiency Repor
Total DR Issued
Total DR Closed

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

13th IA : 15-08-13

GCC-IA

Status in
brief

Completed(L
ast)

12th IA : 31-07-13

GCC-IA

Issued

35

60

19

Total :

16

Closed

24

53

14

Balance :

Open

11

Cumulative : 16
Completed: 12

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

CPY Q & IM Assessment


Assessment Title

C/list No.
1

Findings

Closed

Open

Document and Data control(100%)

FCS status (Field Change Sheet

Total No. of
Assessment

Conducted this
Week

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

68

68

68

Status of Deliverables
No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
33
1
9
50

PQP
ITP
QCP
QMP
LTSC

1
33
1
9
50

1
32
1
9
50

Quality Tool Box Talks


Description:

N/A

Total Open
Total Closed
Total Rejected

S.No.

Total Condcuted : 6, This week : 0

Total Issued

Total cancelled

SDR stat
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR Closed
Total SDR open

Week

Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

C300/B200/
B100/C200

95.8/97/94.28%

93.6/93.75/94%

0.0

C300/B200/
B100/C200

92.3/95.83/94%

95.8/97/94.28%

0.5

C300/B200/
B100/C200

94.4/95.38/91.25%

92.3/95.83/94%

0.0

C300/B200/
B100/C200

95/91.40/95.4%

94.4/95.38/91.25%

0.5

Discipline

% Difference

Action Required
Yes

Quality awareness Training [May'13 to Sep'13]


Item

Date

Scheduled(Upcoming)

19-Aug-2013

Completed(Previous)

13-Aug-2013

Date

Scheduled(Upcoming) - Electrical works

18-Aug-2013

Completed (Previous) - Floor finishes

31-Jul-2013

Scheduled(Upcoming) - TBA
Completed(Prev.)-Welding(Hindi)

CPY Witnessed

Bldg.Ref:

Balance

Total Trained

13

11

89

Cumulative

TBA
12/13-08-13

Date

Total

Completed

Balance

Total Trained

15

Total

Completed

Balance

Total Trained

40

Cumulative
Total

Completed

Balance

Total Trained

1) Percentage of cancellation
2)Reason for rejection : Refer

18
Barzan on shore project - Building works - Package#2

Planned

Note : To be re

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

TOM
Bldg.Ref:

Cumulative
Date

Planned

Note : To be re

Completed

GCC Craft Training (*) - May' - June'2013


Item

JGC Witnessed

Total

JGC Craft Training (*) Item

Issued This Week

Remarks

Cumulative

Refresher Discipline Training (*) [May'13 to Sep'13]


Item

No

23-Mar-2013

18

228+203

tracting Co.WLL

shore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-089

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

15

24

Total NCR Closed

22

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

38

Total CAR Closed

Total DR Closed

32

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

FCS status (Field Change Sheet)

Total CAR Issued

19

Total CAR Closed

14

Total CAR Open

Total CAR Issued


(This Week)

FTR status (Field Trouble Request)

1338

Total Issued

17

106

Total Open
Total Closed

17

86

Total Rejected

44

Total cancelled

1102

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
25

Other S/C SDR

11

Nil

20

Weekly Field Inspection Status (RFI)

Issued

Accepted

Rejected

Cancelled

157

144

12

157

144

12

52

48

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 7.64%
2)Reason for rejection : Refer attachment#7

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

12-Aug-2013

To:

18-Aug-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

31

Items

As of Today : 30

Plan

Actual

Total NCR Issued

FQCM

Total NCR Closed

DFQCM

Total NCR Open

QA

Total NCR Issued (This Week)

QCI (Building)

13

13

CQCC

Document controller

DFO Team

QC Team(MEP works)

QC Inspectors(FRP/Painting/Welding) - Call-off Basis

TOTAL

31

30

NC

CPY DR Status
(Deficiency Repor
Total DR Issued
Total DR Closed

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

14th IA : 29-08-13

GCC-IA

Status in
brief

Completed(L
ast)

13th IA : 15-08-13

GCC-IA

Issued

35

60

19

Total :

16

Closed

30

53

14

Balance :

Open

Cumulative : 16
Completed: 13

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

CPY Q & IM Assessment


Assessment Title

C/list No.

Findings

Closed

Open

FCS status (Field Change Sheet

Total No. of
Assessment

Conducted this
Week

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

68

68

68

Status of Deliverables
No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
33
1
9
50

PQP
ITP
QCP
QMP
LTSC

1
33
1
9
50

1
33
1
9
50

Quality Tool Box Talks


Description:

N/A

Total Open
Total Closed
Total Rejected

S.No.

Total Condcuted : 6, This week : 0

Total Issued

Total cancelled

SDR stat
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR Closed
Total SDR open

Week

Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

C300/B200/
B100/C200

92.3/95.83/94%

95.8/97/94.28%

0.0

C300/B200/
B100/C200

94.4/95.38/91.25%

92.3/95.83/94%

0.5

C300/B200/
B100/C200

95/91.40/95.4%

94.4/95.38/91.25%

0.0

C300/B200/
B100/C200

91.42/95.88/96.92

95/91.40/95.4%

0.5

Area

% Difference

Action Required
Yes

Quality awareness Training [May'13 to Sep'13]


Item

Date

Scheduled(Upcoming)

11-Sep-2013

Completed(Previous)

19-Aug-2013

Date

Scheduled(Upcoming) - Electrical works

28-Aug-2013

Completed (Previous) - Floor finishes

18-Aug-2013

Scheduled(Upcoming) - TBA
Completed(Prev.)-Welding(Hindi)

CPY Witnessed

Bldg.Ref:

Balance

Total Trained

13

12

103

Cumulative

TBA
12/13-08-13

Date

Total

Completed

Balance

Total Trained

22

Barzan on shore project - Building works - Package#2

Planned

Note : To be re

Total

Completed

Balance

Total Trained

40

Cumulative
Total

Completed

Balance

Total Trained

18

18

228+203

1) Percentage of cancellation
2)Reason for rejection : Refer

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

TOM
Bldg.Ref:

Cumulative
Date

Planned

Note : To be re

Completed

GCC Craft Training (*) - May' - June'2013


Item

JGC Witnessed

Total

JGC Craft Training (*) Item

Issued This Week

Remarks

Cumulative

Refresher Discipline Training (*) [May'13 to Sep'13]


Item

No

23-Mar-2013

3) Cancellations due to red fla

tracting Co.WLL

shore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-090

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

15

24

Total NCR Closed

22

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

38

Total CAR Closed

Total DR Closed

33

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

FCS status (Field Change Sheet)

Total CAR Issued

19

Total CAR Closed

14

Total CAR Open

Total CAR Issued


(This Week)

FTR status (Field Trouble Request)

1356

Total Issued

17

107

Total Open
Total Closed

17

91

Total Rejected

44

Total cancelled

1114

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
25

Other S/C SDR

11

Nil

20

Weekly Field Inspection Status (RFI)

Issued

Accepted

Rejected

Cancelled

279

259

18

279

259

18

132

126

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 6.45%
2)Reason for rejection : Refer attachment#7
3) Cancellations due to red flag not counted in metrics.

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

20-Aug-2013

To:

26-Aug-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

31

Items

As of Today : 31

Plan

Actual

Total NCR Issued

FQAM

Total NCR Closed

DFQCM

Total NCR Open

FQCM(Mech.)

Total NCR Issued (This Week)

QCI (Building)

13

13

CQCC

Document controller

DFO Team

QC Team(MEP works)

QC Inspectors(FRP/Painting/Welding) - Call-off Basis

TOTAL

31

31

NC

CPY DR Status
(Deficiency Repor
Total DR Issued
Total DR Closed

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

14th IA : 29-08-13

GCC-IA

Status in
brief

Completed(L
ast)

13th IA : 15-08-13

GCC-IA

Issued

35

60

19

Total :

16

Closed

32

59

15

Balance :

Open

Cumulative : 16
Completed: 13

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

CPY Q & IM Assessment


Assessment Title

C/list No.
1

Findings

Closed

Open

HVAC - PMC

FCS status (Field Change Sheet

Total No. of
Assessment

Conducted this
Week

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

69

69

69

Status of Deliverables
No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
33
1
9
50

PQP
ITP
QCP
QMP
LTSC

1
33
1
9
50

1
33
1
9
50

Quality Tool Box Talks


Description:

N/A

Total Open
Total Closed
Total Rejected

S.No.

Total Condcuted : 6, This week : 0

Total Issued

Total cancelled

SDR stat
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR Closed
Total SDR open

Week

Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

C300/B200/
B100/C200

94.4/95.38/91.25%

92.3/95.83/94%

0.0

C300/B200/
B100/C200

95/91.40/95.4%

94.4/95.38/91.25%

0.5

C300/B200/
B100/C200

91.42/95.88/96.92

95/91.40/95.4%

0.0

C300/B200/
B100/C200

95.38/95%

91.42/95.88/96.92

0.5

Area

% Difference

Action Required
Yes

Quality awareness Training [May'13 to Sep'13]


Item

Date

Scheduled(Upcoming)

11-Sep-2013

Completed(Previous)

19-Aug-2013

Date

Scheduled(Upcoming) - Doors/Windows

28-Aug-2013

Completed (Previous) - Electrical

18-Aug-2013

Scheduled(Upcoming) - TBA
Completed(Prev.)-Welding(Hindi)

CPY Witnessed

Bldg.Ref:
C300-CANCELLED DUE TO
NO POWER

Completed

Balance

Total Trained

13

12

103

Cumulative
Completed

Balance

Total Trained

42

TBA
12/13-08-13

Date

Total

Completed

Balance

Total Trained

40

Barzan on shore project - Building works - Package#2

Planned

Cumulative
Total

Completed

Balance

Total Trained

18

18

228+203

1) Percentage of cancellation
2)Reason for rejection : Refer

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

TOM

Note : To be re

Cumulative
Date

Planned

Note : To be re

Bldg.Ref:

Total

GCC Craft Training (*) - May' - June'2013


Item

JGC Witnessed

Total

JGC Craft Training (*) Item

Issued This Week

Remarks

Cumulative

Refresher Discipline Training (*) [May'13 to Sep'13]


Item

No

23-Mar-2013

3) Cancellations due to red fla

tracting Co.WLL

shore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-090

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

17

24

Total NCR Closed

22

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

38

Total CAR Closed

Total DR Closed

37

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

FCS status (Field Change Sheet)

Total CAR Issued

19

Total CAR Closed

15

Total CAR Open

Total CAR Issued


(This Week)

FTR status (Field Trouble Request)

1375

Total Issued

17

115

Total Open
Total Closed

17

91

Total Rejected

44

Total cancelled

1125

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
25

Other S/C SDR

11

Nil

20

Weekly Field Inspection Status (RFI)

Issued

Accepted

Rejected

Cancelled

211

187

15

211

187

15

88

79

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 7.10%
2)Reason for rejection : Refer attachment#7
3) Cancellations due to red flag not counted in metrics.

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

27-Aug-2013

To:

02-Sep-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

32

Items

As of Today : 32

Plan

Actual

Total NCR Issued

FQAM

Total NCR Closed

DFQCM

Total NCR Open

FQCM(Mech.)

Total NCR Issued (This Week)

QCI (Building)

13

13

CQCC

Document controller

DFO Team

QC Team(MEP works)

QC Inspectors(FRP/Painting/Welding) - Call-off Basis

TOTAL

32

32

NC

CPY DR Status
(Deficiency Repor
Total DR Issued
Total DR Closed

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

14th IA : 26-09-13

GCC-IA

Status in
brief

Completed(L
ast)

14th IA : 29-08-13

GCC-IA

Issued

41

60

19

Total :

16

Closed

30

59

15

Balance :

Open

11

Cumulative : 16
Completed: 14

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

CPY Q & IM Assessment


Assessment Title

C/list No.

Findings

Closed

Open

FCS status (Field Change Sheet

Total No. of
Assessment

Conducted this
Week

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

69

69

69

Status of Deliverables
No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
33
1
9
50

PQP
ITP
QCP
QMP
LTSC

1
33
1
9
50

1
33
1
9
50

Quality Tool Box Talks


Description:

N/A

Total Open
Total Closed
Total Rejected

S.No.

Total Condcuted : 6, This week : 0

Total Issued

Total cancelled

SDR stat
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR Closed
Total SDR open

Week

Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

C300/B200/
B100/C200

95/91.40/95.4%

94.4/95.38/91.25%

0.0

C300/B200/
B100/C200

91.42/95.88/96.92

95/91.40/95.4%

0.5

C300/B200/
B100/C200

95.38/95%

91.42/95.88/96.92

0.0

C300/B200/
B100/C200

92.85/90/95.45%

95.38/95%

0.5

Area

% Difference

Action Required
Yes

Quality awareness Training [May'13 to Sep'13]


Item

Date

Scheduled(Upcoming)

11-Sep-2013

Completed(Previous)

19-Aug-2013

Date

Scheduled(Upcoming) - Plumb./Mech.

04-Sep-2013

Completed (Previous) - Doors/Windows

28-Aug-2013

Scheduled(Upcoming) - TBA
Completed(Prev.)-Welding(Hindi)

CPY Witnessed

Bldg.Ref:

Balance

Total Trained

13

12

103

Cumulative

TBA
12/13-08-13

Date

Total

Completed

Balance

Total Trained

46

Barzan on shore project - Building works - Package#2

Planned

Note : To be re

Total

Completed

Balance

Total Trained

40

Cumulative
Total

Completed

Balance

Total Trained

18

18

228+203

1) Percentage of cancellation
2)Reason for rejection : Refer

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

TOM
Bldg.Ref:

Cumulative
Date

Planned

Note : To be re

Completed

GCC Craft Training (*) - May' - June'2013


Item

JGC Witnessed

Total

JGC Craft Training (*) Item

Issued This Week

Remarks

Cumulative

Refresher Discipline Training (*) [May'13 to Sep'13]


Item

No

23-Mar-2013

3) Cancellations due to red fla

tracting Co.WLL

shore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-091

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

17

24

Total NCR Closed

11

22

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

38

Total CAR Closed

Total DR Closed

38

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

FCS status (Field Change Sheet)

Total CAR Issued

19

Total CAR Closed

15

Total CAR Open

Total CAR Issued


(This Week)

FTR status (Field Trouble Request)

1382

Total Issued

18

107

Total Open
Total Closed

17

92

Total Rejected

46

Total cancelled

1137

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
25

Other S/C SDR

11

Nil

20

Weekly Field Inspection Status (RFI)

Issued

Accepted

Rejected

Cancelled

233

220

12

233

220

12

73

67

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 5.15%
2)Reason for rejection : Refer attachment#7
3) Cancellations due to red flag not counted in metrics.

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

03-Sep-2013

To:

09-Sep-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

32

Items

As of Today : 32

Plan

Actual

Total NCR Issued

FQAM

Total NCR Closed

DFQCM

Total NCR Open

FQCM(Mech.)

Total NCR Issued (This Week)

QCI (Building)

13

13

CQCC

Document controller

DFO Team

QC Team(MEP works)

QC Inspectors(FRP/Painting/Welding) - Call-off Basis

TOTAL

32

32

NC

CPY DR Status
(Deficiency Repor
Total DR Issued
Total DR Closed

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

15th IA : 26-09-13

GCC-IA

Status in
brief

Completed(L
ast)

14th IA : 29-08-13

GCC-IA

Issued

41

60

19

Total :

16

Closed

31

60

17

Balance :

Open

10

Cumulative : 16
Completed: 14

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

CPY Q & IM Assessment


Assessment Title

C/list No.

Findings

Closed

Open

FCS status (Field Change Sheet

Total No. of
Assessment

Conducted this
Week

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

69

69

69

Status of Deliverables
No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
33
1
9
50

PQP
ITP
QCP
QMP
LTSC

1
33
1
9
50

1
33
1
9
50

Quality Tool Box Talks


Description:

N/A

Total Open
Total Closed
Total Rejected

S.No.

Total Condcuted : 6, This week : 0

Total Issued

Total cancelled

SDR stat
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR Closed
Total SDR open

Week

Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

C300/B200/
B100/C200

91.42/95.88/96.92

95/91.40/95.4%

0.0

C300/B200/
B100/C200

95.38/95%

91.42/95.88/96.92

0.5

C300/B200/
B100/C200

92.85/90/95.45%

95.38/95%

0.0

C300/B200/
B100/C200

93.75/87.64/95.38

92.85/90/95.45%

0.5

Area

% Difference

Action Required
Yes

Quality awareness Training [May'13 to Sep'13]


Item

Date

Scheduled(Upcoming)

11-Sep-2013

Completed(Previous)

19-Aug-2013

Date

Scheduled(Upcoming) - HVAC

18-Sep-2013

Completed (Previous) - Plumb/Mech.

04-Sep-2013

Scheduled(Upcoming) - TBA
Completed(Prev.)-Welding(Hindi)

CPY Witnessed

Bldg.Ref:

Balance

Total Trained

13

12

103

Cumulative

TBA
12/13-08-13

Date

Total

Completed

Balance

Total Trained

58

Barzan on shore project - Building works - Package#2

Planned

Note : To be re

Total

Completed

Balance

Total Trained

40

Cumulative
Total

Completed

Balance

Total Trained

18

18

228+203

1) Percentage of cancellation
2)Reason for rejection : Refer

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

TOM
Bldg.Ref:

Cumulative
Date

Planned

Note : To be re

Completed

GCC Craft Training (*) - May' - June'2013


Item

JGC Witnessed

Total

JGC Craft Training (*) Item

Issued This Week

Remarks

Cumulative

Refresher Discipline Training (*) [May'13 to Sep'13]


Item

No

23-Mar-2013

3) Cancellations due to red fla

tracting Co.WLL

shore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-092

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

17

24

Total NCR Closed

11

22

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

38

Total CAR Closed

Total DR Closed

38

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

FCS status (Field Change Sheet)

Total CAR Issued

19

Total CAR Closed

17

Total CAR Open

Total CAR Issued


(This Week)

FTR status (Field Trouble Request)

1382

Total Issued

18

107

Total Open
Total Closed

17

92

Total Rejected

46

Total cancelled

1137

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
25

Other S/C SDR

11

Nil

20

Weekly Field Inspection Status (RFI)

Issued

Accepted

Rejected

Cancelled

233

220

12

233

220

12

73

67

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 5.15%
2)Reason for rejection : Refer attachment#7
3) Cancellations due to red flag not counted in metrics.

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

10-Sep-2013

To:

16-Sep-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

31

Items

As of Today : 31

Plan

Actual

Total NCR Issued

FQAM

Total NCR Closed

DFQCM

Total NCR Open

FQCM(Mech.)

Total NCR Issued (This Week)

QCI (Civil/arch.)

12

12

CQCC

Document controller

DFO Team

QCI Team(MEP works)

QC Inspectors(FRP/Painting/Welding) - Call-off Basis

TOTAL

31

31

NC

CPY DR Status
(Deficiency Repor
Total DR Issued
Total DR Closed

Discipline

15th IA : 26-09-13

GCC-IA

Status in
brief

Completed(L
ast)

14th IA : 29-08-13

GCC-IA

Issued

41

60

19

Total :

16

Closed

33

60

17

Balance :

Open

Cumulative : 16
Completed: 14

JGC
CAR

OBS

CAR

GCC/LTSC

SCTR QCI DEMOBILIZ


Nov'13

Date

Scheduled(N
ext)

OBS

Item

Total DR Issued
(This Week)

Audit Findings (*)

Oct'13

Internal Quality Audits

Total DR Open

QCI (Civil/Arch.)

QCI (Mech.)
CPY Q & IM Assessment
Assessment Title

C/list No.

Findings

QCI(Elec.)
Closed

Open

Note : Above program is tentative only


GCC Management decision.

FCS status (Field Change Sheet

Total No. of
Assessment

Conducted this
Week

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

69

69

69

Status of Deliverables
No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
33
1
9
51

PQP
ITP
QCP
QMP
LTSC

1
33
1
9
51

1
33
1
9
51

Quality Tool Box Talks


Description:

N/A

Total Open
Total Closed
Total Rejected

S.No.

Total Condcuted : 6, This week : 0

Total Issued

Total cancelled

SDR stat
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR Closed
Total SDR open

Week

Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

C300/B200/
B100/C200

95.38/95%

91.42/95.88/96.92

0.9

C300/B200/
B100/C200

92.85/90/95.45%

95.38/95%

3.0

C300/B200/
B100/C200

93.75/87.64/95.38

92.85/90/95.45%

0.5

C300/B200/
B100/C200

92.5/77.69/93.84%

93.75/87.64/95.38

4.0

Area

% Difference

Action Required
Yes

Date

Scheduled(Upcoming)

TBA

Completed(Previous)

11-Sep-2013

Date

Scheduled(Upcoming) - HVAC

18-Sep-2013

Completed (Previous) - Plumb/Mech.

04-Sep-2013

Scheduled(Upcoming) - TBA
Completed(Prev.)-Welding(Hindi)

Bldg.Ref:

Balance

Total Trained

13

13

116

Cumulative

TBA
12/13-08-13

Date

Total

Completed

Balance

Total Trained

58

Barzan on shore project - Building works - Package#2

Planned

Note : To be re

Total

Completed

Balance

Total Trained

40

Cumulative
Total

Completed

Balance

Total Trained

18

18

228+203

1) Percentage of cancellation
2)Reason for rejection : Refer

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

TOM
Bldg.Ref:

Cumulative
Date

Planned

Note : To be re

Completed

GCC Craft Training (*) - May' - June'2013


Item

CPY Witnessed

Total

JGC Craft Training (*) Item

JGC Witnessed

Cumulative

Refresher Discipline Training (*) [May'13 to Sep'13]


Item

Issued This Week

Remarks

Quality awareness Training [May'13 to Sep'13]


Item

No

23-Mar-2013

3) Cancellations due to red fla

tracting Co.WLL

shore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-093

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

19

24

Total NCR Closed

11

22

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

43

Total CAR Closed

Total DR Closed

40

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

Mar'14

Feb'14

Jan'14

Dec'13

SCTR QCI DEMOBILIZATION

Note : Above program is tentative only and subject to


GCC Management decision.

FCS status (Field Change Sheet)

Total CAR Issued

19

Total CAR Closed

17

Total CAR Open

Total CAR Issued


(This Week)

FTR status (Field Trouble Request)

1418

Total Issued

18

121

Total Open
Total Closed

17

92

Total Rejected

49

Total cancelled

1156

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
25

Other S/C SDR

11

Nil

20

Weekly Field Inspection Status (RFI)

Issued

Accepted

Rejected

Cancelled

299

283

16

299

283

16

96

87

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 5.35%
2)Reason for rejection : Refer attachment#7
3) Cancellations due to red flag not counted in metrics.

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

17-Sep-2013

To:

23-Sep-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

30

Items

As of Today : 28

Plan

Actual

Total NCR Issued

FQAM

Total NCR Closed

DFQCM

Total NCR Open

FQCM(Mech.)

Total NCR Issued (This Week)

QCI (Civil/arch.)

12

10

CQCC

Document controller

DFO Team

QCI Team(MEP works)

QC Inspectors(FRP/Painting/Welding) - Call-off Basis

TOTAL

30

28

NC

CPY DR Status
(Deficiency Repor
Total DR Issued
Total DR Closed

Discipline

15th IA : 28-09-13

GCC-IA

Status in
brief

Completed(L
ast)

14th IA : 29-08-13

GCC-IA

Issued

41

60

19

Total :

16

Closed

39

60

18

Balance :

Open

Cumulative : 16
Completed: 14

JGC
CAR

OBS

CAR

GCC/LTSC

SCTR QCI DEMOBILIZ


Nov'13

Date

Scheduled(N
ext)

OBS

Item

Total DR Issued
(This Week)

Audit Findings (*)

Oct'13

Internal Quality Audits

Total DR Open

QCI (Civil/Arch.)

QCI (Mech.)
CPY Q & IM Assessment
Assessment Title

C/list No.

Findings

QCI(Elec.)
Closed

Open

Note : Above program is tentative only


GCC Management decision.

FCS status (Field Change Sheet

Total No. of
Assessment

Conducted this
Week

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

69

69

69

Status of Deliverables
No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
33
1
9
51

PQP
ITP
QCP
QMP
LTSC

1
33
1
9
51

1
33
1
9
51

Quality Tool Box Talks


Description:

N/A

Total Open
Total Closed
Total Rejected

S.No.

Total Condcuted : 6, This week : 0

Total Issued

Total cancelled

SDR stat
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR Closed
Total SDR open

Week

Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

C300/B200/
B100/C200

92.85/90/95.45%

95.38/95%

0.9

C300/B200/
B100/C200

93.75/87.64/95.38

92.85/90/95.45%

3.0

C300/B200/
B100/C200

92.5/77.69/93.84%

93.75/87.64/95.38

0.5

C300/B200/
B100/C200

95/91.4/93.84%

92.5/77.69/93.84%

4.0

Area

% Difference

Action Required
Yes

Quality awareness Training [May'13 to Sep'13]


Item

Date

Scheduled(Upcoming)

TBC

Completed(Previous)

11-Sep-2013

Scheduled(Upcoming) - HVAC
Completed (Previous) - Plumb/Mech.

Date

Scheduled(Upcoming) - TBA
Completed(Prev.)-Welding(Hindi)

CPY Witnessed

Bldg.Ref:

Balance

Total Trained

13

13

116

Cumulative
Completed

Balance

Total Trained

93

18-Sep-2013

TBA
12/13-08-13

Date

Total

Completed

Balance

Total Trained

40

Cumulative
Total

Completed

Balance

Total Trained

18

18

228+203

Barzan on shore project - Building works - Package#2

1) Percentage of cancellation
2)Reason for rejection : Refer

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

Planned

Note : To be re

Cumulative
Date

TOM
Bldg.Ref:

Total

TBC

Planned

Note : To be re

Completed

GCC Craft Training (*) - May' - June'2013


Item

JGC Witnessed

Total

JGC Craft Training (*) Item

Issued This Week

Remarks

Cumulative

Refresher Discipline Training (*) [May'13 to Sep'13]


Item

No

23-Mar-2013

3) Cancellations due to red fla

tracting Co.WLL

shore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-094

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

19

24

Total NCR Closed

12

22

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

44

Total CAR Closed

Total DR Closed

43

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

Mar'14

Feb'14

Jan'14

Dec'13

SCTR QCI DEMOBILIZATION

Note : Above program is tentative only and subject to


GCC Management decision.

FCS status (Field Change Sheet)

Total CAR Issued

19

Total CAR Closed

18

Total CAR Open

Total CAR Issued


(This Week)

FTR status (Field Trouble Request)

1434

Total Issued

19

104

Total Open
Total Closed

17

92

Total Rejected

49

Total cancelled

1189

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
26

Other S/C SDR

14

Nil

23

Weekly Field Inspection Status (RFI)

Issued

Accepted

Rejected

Cancelled

293

269

24

293

269

24

101

90

11

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 8.1%
2)Reason for rejection : Refer attachment#7
3) Cancellations due to red flag not counted in metrics.

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

24-Sep-2013

To:

30-Sep-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

29

Items

As of Today : 29

Plan

Actual

Total NCR Issued

FQAM

Total NCR Closed

FQCM(Civil/Arch.)

Total NCR Open

FQCM(Mech.)

Total NCR Issued (This Week)

QCI (Civil/arch.)

11

11

CQCC

Document controller

DFO Team

QC Team(MEP works)(Lead + QCI's)

QC Inspectors(FRP/Painting/Welding) - Call-off Basis

TOTAL

29

29

NC

CPY DR Status
(Deficiency Repor
Total DR Issued
Total DR Closed

Discipline

TBC

GCC-IA

Status in
brief

Completed(L
ast)

16th IA : 29-09-13

GCC-IA

Issued

47

60

19

Total :

16

Closed

40

60

18

Balance :

Open

Cumulative : 16
Completed : 16

JGC
CAR

OBS

CAR

GCC/LTSC

CPY Q & IM Assessment


Assessment Title

C/list No.

Findings

Closed

Open

SCTR QCI DEMOBILIZ


Oct'13

Date

Scheduled(N
ext)

OBS

Item

Total DR Issued
(This Week)

Audit Findings (*)

Sep'13

Internal Quality Audits

Total DR Open

QCI (Civil/Arch.)

QCI (Mech.)

QCI(Elec.)

Note : Above program is tentative only


GCC Management decision.

FCS status (Field Change Sheet

Total No. of
Assessment

Conducted this
Week

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

69

69

69

Status of Deliverables
No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
33
1
9
51

PQP
ITP
QCP
QMP
LTSC

1
33
1
9
51

1
33
1
9
51

Quality Tool Box Talks


Description:

N/A

Total Open
Total Closed
Total Rejected

S.No.

Total Condcuted : 6, This week : 0

Total Issued

Total cancelled

SDR stat
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR Closed
Total SDR open

Week

Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

C300/B200/
B100/C200

93.75/87.64/95.38

92.85/90/95.45%

0.9

C300/B200/
B100/C200

92.5/77.69/93.84%

93.75/87.64/95.38

3.0

C300/B200/
B100/C200

95/91.4/93.84%

92.5/77.69/93.84%

0.5

C300/B200/
B100/C200

95/91.4/93.84%

95/91.4/93.84%

4.0

Area

% Difference

Action Required
Yes

Quality awareness Training [May'13 to Sep'13]


Item

Date

Scheduled(Upcoming)

TBC

Completed(Previous)

11-Sep-2013

Scheduled(Upcoming) - HVAC
Completed (Previous) - Plumb/Mech.

Date

Scheduled(Upcoming) - TBA
Completed(Prev.)-Welding(Hindi)

CPY Witnessed

Bldg.Ref:

Balance

Total Trained

13

13

116

Cumulative
Completed

Balance

Total Trained

93

18-Sep-2013

TBA
12/13-08-13

Date

Total

Completed

Balance

Total Trained

40

Cumulative
Total

Completed

Balance

Total Trained

18

18

228+203

Barzan on shore project - Building works - Package#2

1) Percentage of cancellation
2)Reason for rejection : N/A

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

Planned

Note : To be re

Cumulative
Date

TOM
Bldg.Ref:

Total

TBC

Planned

Note : To be re

Completed

GCC Craft Training (*) - May' - June'2013


Item

JGC Witnessed

Total

JGC Craft Training (*) Item

Issued This Week

Remarks

Cumulative

Refresher Discipline Training (*) [May'13 to Sep'13]


Item

No

23-Mar-2013

3) Cancellations due to red fla

tracting Co.WLL

shore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-095

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

19

24

Total NCR Closed

12

23

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

44

Total CAR Closed

Total DR Closed

43

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

Feb'14

Jan'14

Dec'13

Nov'13

SCTR QCI DEMOBILIZATION

Total CAR Issued

19

Total CAR Closed

18

Total CAR Open

Total CAR Issued


(This Week)

Note : Above program is tentative only and subject to


GCC Management decision.

FCS status (Field Change Sheet)

FTR status (Field Trouble Request)

1449

Total Issued

19

116

Total Open
Total Closed

17

94

Total Rejected

50

Total cancelled

1187

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
27

Other S/C SDR

14

Nil

23

Weekly Field Inspection Status (RFI)

Issued

Accepted

Rejected

Cancelled

245

234

11

245

234

11

79

77

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 4.9%
2)Reason for rejection : N/A
3) Cancellations due to red flag not counted in metrics.(If any).

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

01-Oct-2013

To:

07-Oct-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

28

Items

As of Today : 24

Plan

Actual

Total NCR Issued

FQAM

Total NCR Closed

Lead(Civil/Arch.)

Total NCR Open

FQCM(Mech.)

Total NCR Issued (This Week)

QCI (Civil/arch.)

11

CQCC

Document controller

DFO Team

QC Team(MEP works)

QC Inspectors(FRP) - Call-off Basis

TOTAL

28

24

NC

CPY DR Status
(Deficiency Repor
Total DR Issued
Total DR Closed

Discipline

17th IA : 20-10-13

GCC-IA

Status in
brief

Completed(L
ast)

16th IA : 29-09-13

GCC-IA

Issued

47

60

19

Total :

16

Closed

40

60

19

Balance :

Open

Cumulative : 19
Completed : 16

JGC
CAR

OBS

CAR

GCC/LTSC

CPY Q & IM Assessment


Assessment Title

C/list No.

Findings

Closed

Open

SCTR QCI DEMOBILIZ


Oct'13

Date

Scheduled(N
ext)

OBS

Item

Total DR Issued
(This Week)

Audit Findings (*)

Sep'13

Internal Quality Audits

Total DR Open

QCI (Civil/Arch.)

QCI (Mech.)

QCI(Elec.)

Note : Above program is tentative only


GCC Management decision.

FCS status (Field Change Sheet

Total No. of
Assessment

Conducted this
Week

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

69

69

69

Status of Deliverables
No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
33
1
9
51

PQP
ITP
QCP
QMP
LTSC

1
33
1
9
51

1
33
1
9
51

Quality Tool Box Talks


Description:

N/A

Total Open
Total Closed
Total Rejected

S.No.

Total Condcuted : 6, This week : 0

Total Issued

Total cancelled

SDR stat
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR Closed
Total SDR open

Week

Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

C300/B200/
B100/C200

92.5/77.69/93.84%

93.75/87.64/95.38

3.0

C300/B200/
B100/C200

95/91.4/93.84%

92.5/77.69/93.84%

0.5

C300/B200/
B100/C200

95/91.4/93.84%

95/91.4/93.84%

4.0

C300/B200/
B100/C200

90/96/93.33%

95/91.4/93.84%

1.0

Area

% Difference

Action Required
Yes

Quality awareness Training [Oct'13 to Dec'13]


Item

Date

Scheduled(Upcoming)

24-Oct-2013

Completed(Previous)

06-Oct-2013

Date

Scheduled(Upcoming) - Electrical works

12-Oct-2013

Completed (Previous) - Plumb/Mech.

18-Sep-2013

Scheduled(Upcoming) - TBA
Completed(Prev.)-Welding(Hindi)

CPY Witnessed

Bldg.Ref:

Balance

Total Trained

10

Cumulative

TBA
12/13-08-13

Date

Total

Completed

Balance

Total Trained

Barzan on shore project - Building works - Package#2

Planned

Note : To be re

Total

Completed

Balance

Total Trained

40

Cumulative
Total

Completed

Balance

Total Trained

18

18

228+203

1) Percentage of cancellation
2)Reason for rejection : N/A

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

TOM
Bldg.Ref:

Cumulative
Date

Planned

Note : To be re

Completed

GCC Craft Training (*) - May' - June'2013


Item

JGC Witnessed

Total

JGC Craft Training (*) Item

Issued This Week

Remarks

Cumulative

Discipline(+Refresher) Training (*) [Oct'13 to Dec'13]


Item

No

23-Mar-2013

3) Cancellations due to red fla

tracting Co.WLL

shore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-096

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

19

24

Total NCR Closed

14

23

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

49

Total CAR Closed

Total DR Closed

43

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

Feb'14

Jan'14

Dec'13

Nov'13

SCTR QCI DEMOBILIZATION

Total CAR Issued

19

Total CAR Closed

19

Total CAR Open

Total CAR Issued


(This Week)

Note : Above program is tentative only and subject to


GCC Management decision.

FCS status (Field Change Sheet)

FTR status (Field Trouble Request)

1470

Total Issued

19

158
1161

Total Open
Total Closed

17

100

Total Rejected

51

Total cancelled

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
27

Other S/C SDR

14

Nil

23

Weekly Field Inspection Status (RFI)

Issued

Accepted

Rejected

Cancelled

211

194

17

211

194

17

67

62

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 8.05%
2)Reason for rejection : N/A
3) Cancellations due to red flag not counted in metrics.(If any).

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

15-Oct-2013

To:

22-Oct-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

27

Items

As of Today : 24

Plan

Actual

Total NCR Issued

FQAM

Total NCR Closed

Lead(Civil/Arch.)

Total NCR Open

FQCM(Mech.)

Total NCR Issued (This Week)

QCI (Civil/arch.)

10

CQCC

Document controller

DFO Team

QC Team(MEP works)

QC Inspectors(FRP) - Call-off Basis

TOTAL

27

26

NC

CPY DR Status
(Deficiency Repor
Total DR Issued
Total DR Closed

Discipline

18th IA : 09-11-13

GCC-IA

Status in
brief

Completed(L
ast)

17th IA : 20-10-13

GCC-IA

Issued

55

60

19

Total :

21

Closed

46

60

19

Balance :

Open

Cumulative : 21
Completed : 17

JGC
CAR

OBS

CAR

GCC/LTSC

SCTR QCI DEMOBILIZ


Oct'13

Date

Scheduled(N
ext)

OBS

Item

Total DR Issued
(This Week)

Audit Findings (*)

Sep'13

Internal Quality Audits

Total DR Open

QCI (Civil/Arch.)

QCI (Mech.)
CPY Q & IM Assessment
Assessment Title

C/list No.

Findings

QCI(Elec.)
Closed

Open

Note : Above program is tentative only


GCC Management decision.

FCS status (Field Change Sheet

Total No. of
Assessment

Conducted this
Week

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

69

69

69

Status of Deliverables
No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
33
1
9
51

PQP
ITP
QCP
QMP
LTSC

1
33
1
9
51

1
33
1
9
51

Quality Tool Box Talks


Description:

N/A

Total Open
Total Closed
Total Rejected

S.No.

Total Condcuted : 6, This week : 0

Total Issued

Total cancelled

SDR stat
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR Closed
Total SDR open

Week

Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

C300/B200/
B100/C200

95/91.4/93.84%

92.5/77.69/93.84%

0.5

C300/B200/
B100/C200

95/91.4/93.84%

95/91.4/93.84%

4.0

C300/B200/
B100/C200

90/96/93.33%

95/91.4/93.84%

1.0

C300/B200/
B100/C200

95/93.64%

90/96/93.33%

1.0

Area

% Difference

Action Required
Yes

Quality awareness Training [Oct'13 to Dec'13]


Item

Date

Scheduled(Upcoming)

24-Oct-2013

Completed(Previous)

06-Oct-2013

Date

Completed (Previous) - Plumb/Draiange

Scheduled(Upcoming) - TBA
Completed(Prev.)-Welding(Hindi)

Bldg.Ref:

Note : To be re
Total Trained

10

Cumulative
Completed

Balance

Total Trained

26

TBA
12/13-08-13

Date

Total

Completed

Balance

Total Trained

40

Cumulative
Total

Completed

Balance

Total Trained

18

18

228+203

Barzan on shore project - Building works - Package#2

1) Percentage of cancellation
2)Reason for rejection : N/A

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

Planned

Note : To be re

Cumulative
Date

TOM
Bldg.Ref:

Total

22-Oct-2013

Planned

B100-Cancelled due to no
Electrical QCI.

Balance

GCC Craft Training (*) - May' - June'2013


Item

CPY Witnessed

Completed

JGC Craft Training (*) Item

JGC Witnessed

Total

TBA

Scheduled(Upcoming)

Issued This Week

Remarks

Cumulative

Discipline(+Refresher) Training (*) [Oct'13 to Dec'13]


Item

No

23-Mar-2013

tracting Co.WLL

shore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-097

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

21

26

Total NCR Closed

14

23

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

50

Total CAR Closed

Total DR Closed

47

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

Feb'14

CTR CAR Status


(Corrective Action Request)

Jan'14

Dec'13

Nov'13

SCTR QCI DEMOBILIZATION

Total CAR Issued

19

Total CAR Closed

19

Total CAR Open

Total CAR Issued


(This Week)

Note : Above program is tentative only and subject to


GCC Management decision.

FCS status (Field Change Sheet)

FTR status (Field Trouble Request)

1474

Total Issued

19

102

Total Open
Total Closed

17

99

Total Rejected

51

Total cancelled

1222

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
27

Other S/C SDR

14

Nil

23

Weekly Field Inspection Status (RFI)

Issued

Accepted

Rejected

Cancelled

89

82

89

82

31

29

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 8.53%
2)Reason for rejection : N/A

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

22-Oct-2013

To:

28-Oct-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

26

Items

As of Today : 26

Plan

Actual

Total NCR Issued

FQAM

Total NCR Closed

Lead(Civil/Arch.)

Total NCR Open

FQCM(Mech.)

Total NCR Issued (This Week)

QCI (Civil/arch.)

CQCC

Document controller

DFO Team

QC Team(MEP works)

QC Inspectors(FRP) - Call-off Basis

TOTAL

26

26

NC

CPY DR Status
(Deficiency Repor
Total DR Issued
Total DR Closed

Discipline

18th IA : 09-11-13

GCC-IA

Status in
brief

Completed(L
ast)

17th IA : 20-10-13

GCC-IA

Issued

55

60

19

Total :

21

Closed

46

60

19

Balance :

Open

Cumulative : 21
Completed : 17

JGC
CAR

OBS

CAR

GCC/LTSC

SCTR QCI DEMOBILIZ


Oct'13

Date

Scheduled(N
ext)

OBS

Item

Total DR Issued
(This Week)

Audit Findings (*)

Sep'13

Internal Quality Audits

Total DR Open

QCI (Civil/Arch.)

QCI (Mech.)
CPY Q & IM Assessment
Assessment Title

C/list No.

Findings

QCI(Elec.)
Closed

Open

Note : Above program is tentative only


GCC Management decision.

FCS status (Field Change Sheet

Total No. of
Assessment

Conducted this
Week

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

69

69

69

Status of Deliverables
No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
33
1
9
51

PQP
ITP
QCP
QMP
LTSC

1
33
1
9
51

1
33
1
9
51

Quality Tool Box Talks


Description:

N/A

Total Open
Total Closed
Total Rejected

S.No.

Total Condcuted : 6, This week : 0

Total Issued

Total cancelled

SDR stat
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR Closed
Total SDR open

Week

Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

C300/B200/
B100/C200

95/91.4/93.84%

92.5/77.69/93.84%

0.5

C300/B200/
B100/C200

90/96/93.33%

95/91.4/93.84%

4.0

C300/B200/
B100/C200

95/93.64%

90/96/93.33%

1.0

C300/B200/
B100/C200

98.3/92.3%

95/93.64%

1.0

Area

% Difference

Action Required
Yes

Quality awareness Training [Oct'13 to Dec'13]


Item

Date

Scheduled(Upcoming)

21-Nov-2013

Completed(Previous)

24-Oct-2013

Date

Completed (Previous) - Plumb/Draiange

Scheduled(Upcoming) - TBA
Completed(Prev.)-Welding(Hindi)

Bldg.Ref:

Total Trained

17

Cumulative
Completed

Balance

Total Trained

26

TBA
12/13-08-13

Date

Total

Completed

Balance

Total Trained

40

Cumulative
Total

Completed

Balance

Total Trained

18

18

228+203

Barzan on shore project - Building works - Package#2

1) Percentage of cancellation
2)Reason for rejection : N/A

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

Planned

Note : To be re

Cumulative
Date

TOM
Bldg.Ref:

Total

22-Oct-2013

Planned

Note : To be re

Balance

GCC Craft Training (*) - May' - June'2013


Item

CPY Witnessed

Completed

JGC Craft Training (*) Item

JGC Witnessed

Total

TBA

Scheduled(Upcoming)

Issued This Week

Remarks

Cumulative

Discipline(+Refresher) Training (*) [Oct'13 to Dec'13]


Item

No

23-Mar-2013

tracting Co.WLL

shore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-098

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

22

27

Total NCR Closed

14

23

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

50

Total CAR Closed

Total DR Closed

49

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

Feb'14

CTR CAR Status


(Corrective Action Request)

Jan'14

Dec'13

Nov'13

SCTR QCI DEMOBILIZATION

Total CAR Issued

19

Total CAR Closed

19

Total CAR Open

Total CAR Issued


(This Week)

Note : Above program is tentative only and subject to


GCC Management decision.

FCS status (Field Change Sheet)

FTR status (Field Trouble Request)

1490

Total Issued

19

134

Total Open
Total Closed

17

99

Total Rejected

52

Total cancelled

1205

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
27

Other S/C SDR

14

Nil

23

Weekly Field Inspection Status (RFI)

Issued

Accepted

Rejected

Cancelled

105

102

105

102

52

50

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 2.85%
2)Reason for rejection : N/A

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

29-Oct-2013

To:

04-Nov-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

26

Items

As of Today : 26

Plan

Actual

Total NCR Issued

FQAM

Total NCR Closed

Lead(Civil/Arch.)

Total NCR Open

FQCM(Mech.)

Total NCR Issued (This Week)

QCI (Civil/arch.)

CQCC

Document controller

DFO Team

QC Team(MEP works)

QC Inspectors(FRP) - Call-off Basis

TOTAL

26

26

NC

CPY DR Status
(Deficiency Repor
Total DR Issued
Total DR Closed

Discipline

18th IA : 09-11-13

GCC-IA

Status in
brief

Completed(L
ast)

17th IA : 20-10-13

GCC-IA

Issued

55

60

19

Total :

21

Closed

46

60

19

Balance :

Open

Cumulative : 21
Completed : 17

JGC
CAR

OBS

CAR

GCC/LTSC

SCTR QCI DEMOBILIZ


Oct'13

Date

Scheduled(N
ext)

OBS

Item

Total DR Issued
(This Week)

Audit Findings (*)

Sep'13

Internal Quality Audits

Total DR Open

QCI (Civil/Arch.)

QCI (Mech.)
CPY Q & IM Assessment
Assessment Title

C/list No.

Findings

QCI(Elec.)
Closed

Open

Note : Above program is tentative only


GCC Management decision.

FCS status (Field Change Sheet

Total No. of
Assessment

Conducted this
Week

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

69

69

69

Status of Deliverables
No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
33
1
9
51

PQP
ITP
QCP
QMP
LTSC

1
33
1
9
51

1
33
1
9
51

Quality Tool Box Talks


Description:

N/A

Total Open
Total Closed
Total Rejected

S.No.

Total Condcuted : 6, This week : 0

Total Issued

Total cancelled

SDR stat
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR Closed
Total SDR open

Week

Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

C300/B200/
B100/C200

90/96/93.33%

95/91.4/93.84%

4.0

C300/B200/
B100/C200

95/93.64%

90/96/93.33%

1.0

C300/B200/
B100/C200

98.3/92.3%

95/93.64%

1.0

C300/B200/
B100/C200

93.75/92.7/91.5%

98.3/92.3%

0.5

Area

% Difference

Action Required
Yes

Quality awareness Training [Oct'13 to Dec'13]


Item

Date

Scheduled(Upcoming)

21-Nov-2013

Completed(Previous)

24-Oct-2013

Date

Completed (Previous) - Plumb/Draiange

Scheduled(Upcoming) - TBA
Completed(Prev.)-Welding(Hindi)

Bldg.Ref:

Total Trained

17

Cumulative
Completed

Balance

Total Trained

26

TBA
12/13-08-13

Date

Total

Completed

Balance

Total Trained

40

Cumulative
Total

Completed

Balance

Total Trained

18

18

228+203

Barzan on shore project - Building works - Package#2

1) Percentage of cancellation

2)Reason for rejection : 2 No's

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

Planned

Note : To be re

Cumulative
Date

TOM
Bldg.Ref:

Total

22-Oct-2013

Planned

Note : To be re

Balance

GCC Craft Training (*) - May' - June'2013


Item

CPY Witnessed

Completed

JGC Craft Training (*) Item

JGC Witnessed

Total

TBA

Scheduled(Upcoming)

Issued This Week

Remarks

Cumulative

Discipline(+Refresher) Training (*) [Oct'13 to Dec'13]


Item

No

23-Mar-2013

tracting Co.WLL

shore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-099

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

22

27

Total NCR Closed

14

23

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

50

Total CAR Closed

Total DR Closed

49

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

Feb'14

CTR CAR Status


(Corrective Action Request)

Jan'14

Dec'13

Nov'13

SCTR QCI DEMOBILIZATION

Total CAR Issued

19

Total CAR Closed

19

Total CAR Open

Total CAR Issued


(This Week)

Note : Above program is tentative only and subject to


GCC Management decision.

FCS status (Field Change Sheet)

FTR status (Field Trouble Request)

1503

Total Issued

19

146
1204

Total Open
Total Closed

19

100

Total Rejected

53

Total cancelled

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
27

Other S/C SDR

14

Nil

23

Weekly Field Inspection Status (RFI)

Issued

Accepted

Rejected

Cancelled

185

167

16

185

167

16

97

89

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 8.64%
2)Reason for rejection : 2 No's, Delivered material is not as per IFC Dwg.

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

05-Nov-2013

To:

11-Nov-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

20

Items

As of Today : 20

Plan

Actual

Total NCR Issued

FQAM

Total NCR Closed

Lead(Civil/Arch.)

Total NCR Open

FQCM(Mech.)

Total NCR Issued (This Week)

QCI (Civil/arch.)

CQCC

Document controller

QC Team(MEP works)

QC Inspectors(FRP) - Call-off Basis

NC

CPY DR Status
(Deficiency Repor
Total DR Issued
Total DR Closed

20

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

19th IA : 23-11-13

GCC-IA

Status in
brief

Completed(L
ast)

18th IA : 09-11-13

GCC-IA

Issued

61

60

19

Total :

21

Closed

46

60

19

Balance :

Open

15

Cumulative : 21
Completed : 18

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

SCTR QCI DEMOBILIZ


Oct'13

20

Sep'13

TOTAL

QCI (Civil/Arch.)

QCI (Mech.)
CPY Q & IM Assessment
Assessment Title

C/list No.

Findings

QCI(Elec.)
Closed

Open

Note : Above program is tentative only


GCC Management decision.

FCS status (Field Change Sheet

Total No. of
Assessment

Conducted this
Week

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

69

69

69

Status of Deliverables
No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
35
1
9
52

PQP
ITP
QCP
QMP
LTSC

1
35
1
9
52

1
35
1
9
52

Quality Tool Box Talks


Description:

N/A

Total Open
Total Closed
Total Rejected

S.No.

Total Condcuted : 6, This week : 0

Total Issued

Total cancelled

SDR stat
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR Closed
Total SDR open

Week

Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

C300/B200/
B100/C200

95/93.64%

90/96/93.33%

4.0

C300/B200/
B100/C200

98.3/92.3%

95/93.64%

1.0

C300/B200/
B100/C200

93.75/92.7/91.5%

98.3/92.3%

1.0

C300/B200/
B100/C200

86/93.7/91.54%

93.75/92.7/91.5%

0.5

Area

% Difference

Action Required
Yes

Quality awareness Training [Oct'13 to Dec'13]


Item

Date

Scheduled(Upcoming)

21-Nov-2013

Completed(Previous)

24-Oct-2013

Date

Completed (Previous) - Plumb/Draiange

Scheduled(Upcoming) - TBA
Completed(Prev.)-Welding(Hindi)

Bldg.Ref:

Total Trained

17

Cumulative
Completed

Balance

Total Trained

26

TBA
12/13-08-13

Date

Total

Completed

Balance

Total Trained

40

Cumulative
Total

Completed

Balance

Total Trained

18

18

228+203

Barzan on shore project - Building works - Package#2

1) Percentage of cancellation
2)Reason for rejection : N/A

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

Planned

Note : To be re

Cumulative
Date

TOM
Bldg.Ref:

Total

22-Oct-2013

Planned

Note : To be re

Balance

GCC Craft Training (*) - May' - June'2013


Item

CPY Witnessed

Completed

JGC Craft Training (*) Item

JGC Witnessed

Total

TBA

Scheduled(Upcoming)

Issued This Week

Remarks

Cumulative

Discipline(+Refresher) Training (*) [Oct'13 to Dec'13]


Item

No

23-Mar-2013

tracting Co.WLL

shore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-100

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

22

27

Total NCR Closed

14

23

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

50

Total CAR Closed

Total DR Closed

49

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

Feb'14

CTR CAR Status


(Corrective Action Request)

Jan'14

Dec'13

Nov'13

SCTR QCI DEMOBILIZATION

Total CAR Issued

19

Total CAR Closed

19

Total CAR Open

Total CAR Issued


(This Week)

Note : Above program is tentative only and subject to


GCC Management decision.

FCS status (Field Change Sheet)

FTR status (Field Trouble Request)

1517

Total Issued

19

142
1219

Total Open
Total Closed

19

102

Total Rejected

54

Total cancelled

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
27

Other S/C SDR

14

Nil

23

Weekly Field Inspection Status (RFI)

Issued

Accepted

Rejected

Cancelled

167

159

167

159

87

83

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 4.79%
2)Reason for rejection : N/A

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

12-Nov-2013

To:

18-Nov-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

19

Items

As of Today : 19

Plan

Actual

Total NCR Issued

FQAM

Total NCR Closed

Lead(Civil/Arch.)

Total NCR Open

FQCM(Mech.)

Total NCR Issued (This Week)

QCI (Civil/arch.)

CQCC

Document controller

QC Team(MEP works)

QC Inspectors(FRP) - Call-off Basis

NC

CPY DR Status
(Deficiency Repor
Total DR Issued
Total DR Closed

19

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

19th IA : 23-11-13

GCC-IA

Status in
brief

Completed(L
ast)

18th IA : 09-11-13

GCC-IA

Issued

61

60

19

Total :

21

Closed

52

60

19

Balance :

Open

Cumulative : 21
Completed : 18

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

SCTR QCI DEMOBILIZ


Oct'13

19

Sep'13

TOTAL

QCI (Civil/Arch.)

QCI (Mech.)
CPY Q & IM Assessment
Assessment Title

C/list No.

Findings

QCI(Elec.)
Closed

Open

Note : Above program is tentative only


GCC Management decision.

FCS status (Field Change Sheet

Total No. of
Assessment

Conducted this
Week

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

69

69

69

Status of Deliverables
No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
35
1
9
53

PQP
ITP
QCP
QMP
LTSC

1
35
1
9
53

1
35
1
9
52

Quality Tool Box Talks


Description:

N/A

Total Open
Total Closed
Total Rejected

S.No.

Total Condcuted : 6, This week : 0

Total Issued

Total cancelled

SDR stat
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR Closed
Total SDR open

Week

Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

C300/B200/
B100/C200

98.3/92.3%

95/93.64%

4.0

C300/B200/
B100/C200

93.75/92.7/91.5%

98.3/92.3%

1.0

C300/B200/
B100/C200

86/93.7/91.54%

93.75/92.7/91.5%

1.0

C300/B200/
B100/C200

96.6/92.3/94.5%

86/93.7/91.54%

0.5

Area

% Difference

Action Required
Yes

Quality awareness Training [Oct'13 to Dec'13]


Item

Date

Scheduled(Upcoming)

21-Nov-2013

Completed(Previous)

24-Oct-2013

Date

Scheduled(Upcoming)

20-Nov-2013

Completed (Previous) - Plumb/Draiange

22-Oct-2013

Scheduled(Upcoming) - TBA
Completed(Prev.)-Welding(Hindi)

CPY Witnessed

Bldg.Ref:

Balance

Total Trained

17

Cumulative

TBA
12/13-08-13

Date

Total

Completed

Balance

Total Trained

26

Barzan on shore project - Building works - Package#2

Planned

Note : To be re

Total

Completed

Balance

Total Trained

40

Cumulative
Total

Completed

Balance

Total Trained

18

18

228+203

1) Percentage of cancellation
2)Reason for rejection : Refer

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

TOM
Bldg.Ref:

Cumulative
Date

Planned

Note : To be re

Completed

GCC Craft Training (*) - May' - June'2013


Item

JGC Witnessed

Total

JGC Craft Training (*) Item

Issued This Week

Remarks

Cumulative

Discipline(+Refresher) Training (*) [Oct'13 to Dec'13]


Item

No

23-Mar-2013

tracting Co.WLL

shore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-101

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

22

27

Total NCR Closed

14

23

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

50

Total CAR Closed

Total DR Closed

49

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

Feb'14

CTR CAR Status


(Corrective Action Request)

Jan'14

Dec'13

Nov'13

SCTR QCI DEMOBILIZATION

Total CAR Issued

19

Total CAR Closed

19

Total CAR Open

Total CAR Issued


(This Week)

Note : Above program is tentative only and subject to


GCC Management decision.

FCS status (Field Change Sheet)

FTR status (Field Trouble Request)

1532

Total Issued

20

138
1238

Total Open
Total Closed

19

102

Total Rejected

54

Total cancelled

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
27

Other S/C SDR

14

Nil

23

Weekly Field Inspection Status (RFI)

Issued

Accepted

Rejected

Cancelled

161

152

161

152

98

96

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 4.97%
2)Reason for rejection : Refer attachment # 7

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

19-Nov-2013

To:

25-Nov-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

19

Items

As of Today : 19

Plan

Actual

Total NCR Issued

FQAM

Total NCR Closed

Lead(Civil/Arch.)

Total NCR Open

FQCM(Mech.)

Total NCR Issued (This Week)

QCI (Civil/arch.)

CQCC

Document controller

QC Team(MEP works)

QC Inspectors(FRP) - Call-off Basis

NC

CPY DR Status
(Deficiency Repor
Total DR Issued
Total DR Closed

19

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

20th IA : 21-12-13

GCC-IA

Status in
brief

Completed(L
ast)

19th IA : 23-11-13

GCC-IA

Issued

69

60

19

Total :

20

Closed

52

60

19

Balance :

Open

17

Cumulative : 20
Completed : 19

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

SCTR QCI DEMOBILIZ


Oct'13

19

Sep'13

TOTAL

QCI (Civil/Arch.)

QCI (Mech.)
CPY Q & IM Assessment
Assessment Title

C/list No.

Findings

QCI(Elec.)
Closed

Open

Note : Above program is tentative only


GCC Management decision.

FCS status (Field Change Sheet

Total No. of
Assessment

Conducted this
Week

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

69

69

69

Status of Deliverables
No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
35
1
9
53

PQP
ITP
QCP
QMP
LTSC

1
35
1
9
53

1
35
1
9
52

Quality Tool Box Talks


Description:

N/A

Total Open
Total Closed
Total Rejected

S.No.

Total Condcuted : 6, This week : 0

Total Issued

Total cancelled

SDR stat
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR Closed
Total SDR open

Week

Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

C300/B200/
B100/C200

93.75/92.7/91.5%

98.3/92.3%

1.0

C300/B200/
B100/C200

86/93.7/91.54%

93.75/92.7/91.5%

1.0

C300/B200/
B100/C200

96.6/92.3/94.5%

86/93.7/91.54%

1.0

C300/B200/
B100/C200

95.5/91.5/93.3%

96.6/92.3/94.5%

0.5

Area

% Difference

Action Required
Yes

Quality awareness Training [Oct'13 to Dec'13]


Item

Date

Scheduled(Upcoming)

16-Dec-2013

Completed(Previous)

21-Nov-2013

Scheduled(Upcoming) -TBA
Completed (Previous) - Electrical

Date

Scheduled(Upcoming) - TBA
Completed(Prev.)-Welding(Hindi)

CPY Witnessed

Bldg.Ref:

Balance

Total Trained

18

Cumulative
Completed

Balance

Total Trained

30

21-Nov-2013

TBA
12/13-08-13

Date

Total

Completed

Balance

Total Trained

40

Cumulative
Total

Completed

Balance

Total Trained

18

18

228+203

Barzan on shore project - Building works - Package#2

1) Percentage of cancellation
2)Reason for rejection : N/A

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

Planned

Note : To be re

Cumulative
Date

TOM
Bldg.Ref:

Total

TBA

Planned

Note : To be re

Completed

GCC Craft Training (*) - May' - June'2013


Item

JGC Witnessed

Total

JGC Craft Training (*) Item

Issued This Week

Remarks

Cumulative

Discipline(+Refresher) Training (*) [Oct'13 to Dec'13]


Item

No

23-Mar-2013

tracting Co.WLL

shore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-102

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

22

27

Total NCR Closed

14

23

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

50

Total CAR Closed

Total DR Closed

49

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

Feb'14

CTR CAR Status


(Corrective Action Request)

Jan'14

Dec'13

Nov'13

SCTR QCI DEMOBILIZATION

Total CAR Issued

19

Total CAR Closed

19

Total CAR Open

Total CAR Issued


(This Week)

Note : Above program is tentative only and subject to


GCC Management decision.

FCS status (Field Change Sheet)

FTR status (Field Trouble Request)

1551

Total Issued

20

137
1255

Total Open
Total Closed

19

105

Total Rejected

54

Total cancelled

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
27

Other S/C SDR

14

Nil

23

Weekly Field Inspection Status (RFI)

Issued

Accepted

Rejected

Cancelled

165

134

165

134

88

85

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

TOMAS - NO.OF ITR's [UPLOAD]


Planned

Actual

% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 4.84%
2)Reason for rejection : N/A

Weekly Quality Metrics

Gulf Contracting Co.WL


Barzan Onshore Project, Package#2
Site Weekly QA/QC Metrics
Period :

From:

26-Nov-2013

To:

02-Dec-2013

"Leading" Indicators
Proactive Quality Metrics

Quality Resources(Plan|Actual)
Overall Plan

NCR S

19

Items

As of Today : 19

Plan

Actual

Total NCR Issued

FQAM

Total NCR Closed

Lead(Civil/Arch.)

Total NCR Open

FQCM(Mech.)

Total NCR Issued (This Week)

QCI (Civil/arch.)

CQCC

Document controller

QC Team(MEP works)

QC Inspectors(FRP) - Call-off Basis

NC

CPY DR Status
(Deficiency Repor
Total DR Issued
Total DR Closed

19

Internal Quality Audits

Total DR Issued
(This Week)

Audit Findings (*)

Date

Discipline

Scheduled(N
ext)

20th IA : 21-12-13

GCC-IA

Status in
brief

Completed(L
ast)

19th IA : 23-11-13

GCC-IA

Issued

69

60

19

Total :

20

Closed

52

60

19

Balance :

Open

17

Cumulative : 20
Completed : 19

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR Open

SCTR QCI DEMOBILIZ


Oct'13

19

Sep'13

TOTAL

QCI (Civil/Arch.)

QCI (Mech.)
CPY Q & IM Assessment
Assessment Title

C/list No.

Findings

QCI(Elec.)
Closed

Open

Note : Above program is tentative only


GCC Management decision.

FCS status (Field Change Sheet

Total No. of
Assessment

Conducted this
Week

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

69

69

69

Status of Deliverables
No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
35
1
9
53

PQP
ITP
QCP
QMP
LTSC

1
35
1
9
53

1
35
1
9
53

Quality Tool Box Talks


Description:

N/A

Total Open
Total Closed
Total Rejected

S.No.

Total Condcuted : 6, This week : 0

Total Issued

Total cancelled

SDR stat
Items
Total SDR Issued
Total SDR Approved
Total SDR Rejected
Total SDR Cancelled
Total SDR Closed
Total SDR open

Week

Weekly Site Quality Walk

Items

Score (%)

Score (%)

This Period

Last Period

C300/B200/
B100/C200

86/93.7/91.54%

93.75/92.7/91.5%

1.0

C300/B200/
B100/C200

96.6/92.3/94.5%

86/93.7/91.54%

1.0

C300/B200/
B100/C200

95.5/91.5/93.3%

96.6/92.3/94.5%

1.0

C300/B200/
B100/C200

95.5/90/92.38%

Area

% Difference

Action Required
Yes

No

Issued This Week

Remarks

JGC Witnessed
CPY Witnessed

Bldg.Ref:

Planned

Total No.of Binder


0.5

95.5/91.5/93.3%

Quality awareness Training [Oct'13 to Dec'13]


Item

Date

Scheduled(Upcoming)

16-Dec-2013

Completed(Previous)

21-Nov-2013

Cumulative
Total

Completed

Balance

Total Trained

18

Discipline(+Refresher) Training (*) [Oct'13 to Dec'13]


Item
Scheduled(Upcoming) -TBA
Completed (Previous) - Electrical

Date

Cumulative
Completed

Balance

Total Trained

30

TBA
21-Nov-2013

Scheduled(Upcoming) - TBA
Completed(Prev.)-Welding(Hindi)

TBA
12/13-08-13

Total

Completed

Balance

Total Trained

40

GCC Craft Training (*) - May' - June'2013


Item

Date

Barzan on shore project - Building works - Package#2

TOM

Planned

Cumulative
Total

Completed

Balance

Total Trained

18

18

228+203

1) Percentage of cancellation
2)Reason for rejection : N/A

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

Note : To be referred/discusse

Note : To be re

Cumulative
Date

Total No.of Binder


Total No.of Binder

Bldg.Ref:

Total

JGC Craft Training (*) Item

Total No.of Binder

23-Mar-2013

tracting Co.WLL

shore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-103

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
Items

JGC

GCC

LTSC

Total NCR Issued

22

27

Total NCR Closed

15

16

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

50

Total CAR Closed

Total DR Closed

50

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

Feb'14

CTR CAR Status


(Corrective Action Request)

Jan'14

Dec'13

Nov'13

SCTR QCI DEMOBILIZATION

Total CAR Issued

19

Total CAR Closed

19

Total CAR Open

Total CAR Issued


(This Week)

Note : Above program is tentative only and subject to


GCC Management decision.

FCS status (Field Change Sheet)

FTR status (Field Trouble Request)

1568

Total Issued

20

152
1254

Total Open
Total Closed

20

106

Total Rejected

56

Total cancelled

SDR status (Specification Deviation Request)


Items

Total SDR Cancelled

GCC SDR
28

Other S/C SDR

14

Nil

23

Weekly Field Inspection Status (RFI)

Issued

Accepted

Rejected

Cancelled

211

183

28

211

183

28

114

110

Planned

DFO - NO.OF BOOK'S


Actual
% Prog.

Remarks

Total No.of Binders Identified = 1000 No's


Total No.of Binders Submitted = 42 No's
Total No.of Binders Approved by CTR = 31 No's
Total No.of Binders Approved by CPY = 21 No's
Note : To be referred/discussed in weekly DFO meetings.
TOMAS - NO.OF ITR's [UPLOAD]
Planned

Actual

% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 13.27% (4.26%)
2)Reason for rejection : N/A

Weekly Quality Metrics

Gulf Contracting C

Barzan Onshore Project, Packag


Site Weekly QA/QC Metrics
Period :

From:

03-Dec-2013

To:

09-Dec-2013

"Leading" Indicators
Proactive Quality Metrics
Quality Resources(Plan|Actual)
Overall Plan

19

As of Today : 19

Plan

Actual

Total NCR Issue

FQAM

Total NCR Clos

Lead(Civil/Arch.)

Total NCR Ope

FQCM(Mech.)

Total NCR Issue

QCI (Civil/arch.)

CQCC

Document controller

QC Team(MEP works)

QC Inspectors(FRP) - Call-off Basis

Total DR

Total DR
TOTAL

19

19

Internal Quality Audits

Total DR
(This We

Audit Findings (*)

Date

Discipline

Scheduled(Next)

20th IA : 21-12-13

GCC-IA

Status in
brief

Completed(Last)

19th IA : 23-11-13

GCC-IA

Issued

69

60

19

Total :

20

Closed

52

60

19

Balance :

Open

17

Cumulative :

20

Completed : 19

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR

QCI (Civil/Arch

QCI (Mech.)
CPY Q & IM Assessment
C/list No.

Assessment Title

Findings

QCI(Elec.)
Closed

Note : Above pro


Management de

Open

FCS status (F

Total No. of
Assessment

Conducted this Week

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

69

69

69

Total Rejecte

S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
35
1
9
53

PQP
ITP
QCP
QMP
LTSC

1
35
1
9
53

1
35
1
9
53

N/A

Total Open

Total Closed

Status of Deliverables

Description:

Total Issued

Total cancell

Total SD

Total SD

Total SD
Total SDR

Quality Tool Box Talks

Total SD

Total Condcuted : 6, This week : 0

Total SD

Weekly Site Quality Walk


Building Ref.

Score (%)

Score (%)

This Period

Last Period

HVAC(BXK-02)/Civil(BXK02)/Elec.(BXK-02)

96.6/92.3/94.5%

HVAC(BXK-01)/Civil(BXK02)/Elec.(BCCB)

95.55/93.33/91.54%

HVAC(BXK-01)/Civil(BXK02)/Elec.(BCCB)

95.55/92.38/90%

HVAC(BXK-04)/Civil(BXK02)/Elec.(BSIH-103)

93.33/92.5/75.2%

% Difference

93.75/91.54/86%

I
Action Required
Yes

Remarks

No

4.0

96.6/92.3/94.5%

1.0

95.55/93.33/91.54%

1.0

Issued This W

JGC Witness

Elect(BSS-203)/Civil(BXK02)/HVAC(BSS-901)

CPY Witness

Bldg.Ref

Total
95.55/92.38/90%

5.0

Elec(BSIH-103) - Re walkthough
shall be done.

Quality awareness Training [Oct'13 to Dec'13]


Item

Date

Scheduled(Upcoming)

16-Dec-2013

Completed(Previous)

21-Nov-2013

Item

Date

Total

Completed

Balance

Total Trained

18

Cumulative

Completed (Previous) - Electrical

Completed

Balance

Total Trained

30

21-Nov-2013

JGC Craft Training (*) Date


TBA

Scheduled(Upcoming) - TBA

12/13-08-13

Total

Completed

Balance

Total Trained

40

GCC Craft Training (*) - May' - June'2013


Item

Cumulative
Date

Total

Completed

Balance

Total Trained

18

18

228+203

Barzan on shore project - Building works - Package#2

1) Percentag

2)Reason for

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

Note : To be

Cumulative

Item

Completed(Prev.)-Welding(Hindi)

Total

Bldg.Ref

Total

TBA

Scheduled(Upcoming) -TBA

Total

Cumulative

Discipline(+Refresher) Training (*) [Oct'13 to Dec'13]

Total

23-Mar-2013

ntracting Co.WLL

nshore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-104

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
JGC

GCC

LTSC

Total NCR Issued

Items

22

27

Total NCR Closed

15

16

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

50

Total CAR Closed

Total DR Closed

50

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

Total CAR Issued

19

Total CAR Closed

19

QCI (Mech.)

Total CAR Open

QCI(Elec.)

Total CAR Issued


(This Week)

Oct'13

Feb'14

CTR CAR Status


(Corrective Action Request)

Jan'14

Dec'13

Nov'13

Sep'13

SCTR QCI DEMOBILIZATION

QCI (Civil/Arch.)

Note : Above program is tentative only and subject to GCC


Management decision.

FTR status (Field Trouble Request)

FCS status (Field Change Sheet)

Total Issued

1584

Total Issued

20

Total Open

155

Total Open

Total Closed

1254

Total Closed

20

118

Total Rejected

57

Total cancelled

Total Rejected
Total cancelled

SDR status (Specification Deviation Request)


Items
Total SDR Issued

GCC SDR
28

Other S/C SDR

Total SDR Approved

14

Total SDR Rejected

Total SDR Cancelled

Nil

Total SDR Closed

23

Total SDR open

Weekly Field Inspection Status (RFI)

Issued

Accepted

Rejected

Cancelled

Issued This Week

245

232

12

JGC Witnessed

245

232

12

CPY Witnessed

115

104

11

Items

Bldg.Ref:

Planned

DFO - NO.OF BOOK'S


Actual

% Prog.

Remarks

Total No.of Binders Identified = 1000 No's


Total No.of Binders Submitted = 42 No's
Total No.of Binders Approved by CTR = 31 No's
Total No.of Binders Approved by CPY = 25 No's
Note : To be referred/discussed in weekly DFO meetings.
TOMAS - NO.OF ITR's [UPLOAD]
Bldg.Ref:

Planned

Actual

% Prog.

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 5.31%
2)Reason for rejection : Wrong Labeling (1 No.)

Weekly Quality Metrics

Remarks

Gulf Contracting C

Barzan Onshore Project, Packag


Site Weekly QA/QC Metrics
Period :

From:

10-Dec-2013

To:

16-Dec-2013

"Leading" Indicators
Proactive Quality Metrics
Quality Resources(Plan|Actual)
Overall Plan

19

As of Today : 19

Plan

Actual

Total NCR Issue

FQAM

Total NCR Clos

Lead(Civil/Arch.)

Total NCR Ope

FQCM(Mech.)

Total NCR Issue

QCI (Civil/arch.)

CQCC

Document controller

QC Team(MEP works)

QC Inspectors(FRP) - Call-off Basis

Total DR

Total DR
TOTAL

19

19

Internal Quality Audits

Total DR
(This We

Audit Findings (*)

Date

Discipline

Scheduled(Next)

20th IA : 21-12-13

GCC-IA

Status in
brief

Completed(Last)

19th IA : 23-11-13

GCC-IA

Issued

69

60

19

Total :

20

Closed

52

60

19

Balance :

Open

17

Cumulative :

20

Completed : 19

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR

QCI (Civil/Arch

QCI (Mech.)
CPY Q & IM Assessment
C/list No.

Assessment Title

Findings

QCI(Elec.)
Closed

Note : Above pro


Management de

Open

FCS status (F

Total No. of
Assessment

Conducted this Week

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

69

69

69

Total Rejecte

S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
35
1
9
53

PQP
ITP
QCP
QMP
LTSC

1
35
1
9
53

1
35
1
9
53

N/A

Total Open

Total Closed

Status of Deliverables

Description:

Total Issued

Total cancell

Total SD

Total SD

Total SD
Total SDR

Quality Tool Box Talks

Total SD

Total Condcuted : 6, This week : 0

Total SD

Weekly Site Quality Walk


Building Ref.

Score (%)

Score (%)

This Period

Last Period

HVAC(BXK-01)/Civil(BXK02)/Elec.(BCCB)

95.55/93.33/91.54%

HVAC(BXK-01)/Civil(BXK02)/Elec.(BCCB)

95.55/92.38/90%

HVAC(BXK-04)/Civil(BXK02)/Elec.(BSIH-103)

93.33/92.5/75.2%

HVAC(BCCB)/Civil(BXK02&06)/Elec.(BXK-04)

93.7/93.08/90%

% Difference

96.6/92.3/94.5%

I
Action Required
Yes

95.55/93.33/91.54%

1.0

95.55/92.38/90%

5.0

93.33/92.5/75.2%

5.0

Date

Scheduled(Upcoming)

TBA

Completed(Previous)

21-Nov-2013

Elec(BSIH-103) - Re walkthough shall be


done.

Elec(BSIH-103) - Re walkthough
shall be done.

Date

Total

Completed

Balance

Total Trained

18

Cumulative

Completed (Previous) - Electrical

Completed

Balance

Total Trained

30

21-Nov-2013

JGC Craft Training (*) Date


TBA

Scheduled(Upcoming) - TBA

12/13-08-13

Total

Completed

Balance

Total Trained

40

GCC Craft Training (*) - May' - June'2013


Item

Barzan on shore project - Building works - Package#2

Total

Total
Note : To be

Cumulative
Date

Total

Completed

Balance

Total Trained

18

18

228+203

1) Percentag

2)Reason for

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

Total

Cumulative

Item

Completed(Prev.)-Welding(Hindi)

Bldg.Ref

Bldg.Ref

Total

TBA

Scheduled(Upcoming) -TBA

CPY Witness

Total

Cumulative

Discipline(+Refresher) Training (*) [Oct'13 to Dec'13]


Item

JGC Witness

HVAC(BXK-02)/Civil(BXK-02)/Elec.
(BXK-02)

Quality awareness Training [Oct'13 to Dec'13]


Item

Remarks

No

1.0

Issued This W

23-Mar-2013

ntracting Co.WLL

nshore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-105

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
JGC

GCC

LTSC

Total NCR Issued

Items

22

27

Total NCR Closed

15

16

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

50

Total CAR Closed

Total DR Closed

50

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

Total CAR Issued

19

Total CAR Closed

19

QCI (Mech.)

Total CAR Open

QCI(Elec.)

Total CAR Issued


(This Week)

Oct'13

Feb'14

CTR CAR Status


(Corrective Action Request)

Jan'14

Dec'13

Nov'13

Sep'13

SCTR QCI DEMOBILIZATION

QCI (Civil/Arch.)

Note : Above program is tentative only and subject to GCC


Management decision.

FTR status (Field Trouble Request)

FCS status (Field Change Sheet)

Total Issued

1620

Total Issued

20

Total Open

172

Total Open

Total Closed

1273

Total Closed

20

118

Total Rejected

57

Total cancelled

Total Rejected
Total cancelled

SDR status (Specification Deviation Request)


Items
Total SDR Issued

GCC SDR
28

Other S/C SDR

Total SDR Approved

14

Total SDR Rejected

Total SDR Cancelled

Nil

Total SDR Closed

23

Total SDR open

Weekly Field Inspection Status (RFI)

Issued

Accepted

Rejected

Cancelled

Issued This Week

247

227

20

JGC Witnessed

247

227

20

CPY Witnessed

130

121

Items

Bldg.Ref:

Planned

DFO - NO.OF BOOK'S


Actual

% Prog.

Remarks

Total No.of Binders Identified = 1000 No's (Approx.)


Total No.of Binders Submitted = 60 No's
Total No.of Binders Approved by CTR = 31 No's
Total No.of Binders Approved by CPY = 25 No's
Note : To be referred/discussed in weekly DFO meetings.
TOMAS - NO.OF ITR's [UPLOAD]
Bldg.Ref:

Planned

Actual

% Prog.

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 8.16%
2)Reason for rejection : None

Weekly Quality Metrics

Remarks

Gulf Contracting C

Barzan Onshore Project, Packag


Site Weekly QA/QC Metrics
Period :

From:

17-Dec-2013

To:

23-Dec-2013

"Leading" Indicators
Proactive Quality Metrics
Quality Resources(Plan|Actual)
Overall Plan

19

As of Today : 19

Plan

Actual

Total NCR Issue

FQAM

Total NCR Clos

Lead(Civil/Arch.)

Total NCR Ope

FQCM(Mech.)

Total NCR Issue

QCI (Civil/arch.)

CQCC

Document controller

QC Team(MEP works)

QC Inspectors(FRP) - Call-off Basis

Total DR

Total DR
TOTAL

19

19

Internal Quality Audits

Total DR
(This We

Audit Findings (*)

Date

Discipline

Scheduled(Next)

TBA

GCC-IA

Status in
brief

Completed(Last)

20th IA : 21-12-13

GCC-IA

Issued

69

60

19

Total :

20

Closed

52

60

19

Balance :

Open

17

Cumulative :

20

Completed : 20

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR

QCI (Civil/Arch

QCI (Mech.)
CPY Q & IM Assessment
C/list No.

Assessment Title

Findings

QCI(Elec.)
Closed

Note : Above pro


Management de

Open

FCS status (F

Total No. of
Assessment

Conducted this Week

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

69

69

69

Total Rejecte

S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
35
1
9
53

PQP
ITP
QCP
QMP
LTSC

1
35
1
9
53

1
35
1
9
53

N/A

Total Open

Total Closed

Status of Deliverables

Description:

Total Issued

Total cancell

Total SD

Total SD

Total SD
Total SDR

Quality Tool Box Talks

Total SD

Total Condcuted : 6, This week : 0

Total SD

Weekly Site Quality Walk


Building Ref.

Score (%)

Score (%)

This Period

Last Period

HVAC(BXK-01)/Civil(BXK02)/Elec.(BCCB)

95.55/93.33/91.54%

HVAC(BXK-01)/Civil(BXK02)/Elec.(BCCB)

95.55/92.38/90%

HVAC(BXK-04)/Civil(BXK02)/Elec.(BSIH-103)

93.33/92.5/75.2%

HVAC(BCCB)/Civil(BXK02&06)/Elec.(BXK-04)

93.7/93.08/90%

% Difference

96.6/92.3/94.5%

I
Action Required
Yes

95.55/93.33/91.54%

1.0

95.55/92.38/90%

5.0

93.33/92.5/75.2%

5.0

Date

Scheduled(Upcoming)

TBA

Completed(Previous)

21-Nov-2013

Elec(BSIH-103) - Re walkthough shall be


done.

Elec(BSIH-103) - Re walkthrough
scheduled on 25/12/2013

Date

Total

Completed

Balance

Total Trained

18

Cumulative

Completed (Previous) - Electrical

Completed

Balance

Total Trained

30

21-Nov-2013

JGC Craft Training (*) Date


TBA

Scheduled(Upcoming) - TBA

12/13-08-13

Total

Completed

Balance

Total Trained

40

GCC Craft Training (*) - May' - June'2013


Item

Barzan on shore project - Building works - Package#2

Total

Total
Note : To be

Cumulative
Date

Total

Completed

Balance

Total Trained

18

18

228+203

1) Percentag

2)Reason for

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

Total

Cumulative

Item

Completed(Prev.)-Welding(Hindi)

Bldg.Ref

Bldg.Ref

Total

TBA

Scheduled(Upcoming) -TBA

CPY Witness

Total

Cumulative

Discipline(+Refresher) Training (*) [Oct'13 to Dec'13]


Item

JGC Witness

HVAC(BXK-02)/Civil(BXK-02)/Elec.
(BXK-02)

Quality awareness Training [Oct'13 to Dec'13]


Item

Remarks

No

1.0

Issued This W

23-Mar-2013

ntracting Co.WLL

nshore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-105

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
JGC

GCC

LTSC

Total NCR Issued

Items

22

27

Total NCR Closed

15

16

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

50

Total CAR Closed

Total DR Closed

50

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

Total CAR Issued

19

Total CAR Closed

19

QCI (Mech.)

Total CAR Open

QCI(Elec.)

Total CAR Issued


(This Week)

Oct'13

Feb'14

CTR CAR Status


(Corrective Action Request)

Jan'14

Dec'13

Nov'13

Sep'13

SCTR QCI DEMOBILIZATION

QCI (Civil/Arch.)

Note : Above program is tentative only and subject to GCC


Management decision.

FTR status (Field Trouble Request)

FCS status (Field Change Sheet)

Total Issued

1633

Total Issued

20

Total Open

168

Total Open

Total Closed

1290

Total Closed

20

118

Total Rejected

57

Total cancelled

Total Rejected
Total cancelled

SDR status (Specification Deviation Request)


Items
Total SDR Issued

GCC SDR
28

Other S/C SDR

Total SDR Approved

14

Total SDR Rejected

Total SDR Cancelled

Nil

Total SDR Closed

23

Total SDR open

Weekly Field Inspection Status (RFI)

Issued

Accepted

Rejected

Cancelled

Issued This Week

258

236

22

JGC Witnessed

258

236

22

CPY Witnessed

137

123

14

Items

Bldg.Ref:

Planned

DFO - NO.OF BOOK'S


Actual

% Prog.

Remarks

Total No.of Binders Identified = 1000 No's (Approx.)


Total No.of Binders Submitted = 64 No's
Total No.of Binders Approved by CTR = 31 No's
Total No.of Binders Approved by CPY = 25 No's
Note : To be referred/discussed in weekly DFO meetings.
TOMAS - NO.OF ITR's [UPLOAD]
Bldg.Ref:

Planned

Actual

% Prog.

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 8.52%
2)Reason for rejection : None

Weekly Quality Metrics

Remarks

Gulf Contracting C

Barzan Onshore Project, Packag


Site Weekly QA/QC Metrics
Period :

From:

24-Dec-2013

To:

30-Dec-2013

"Leading" Indicators
Proactive Quality Metrics
Quality Resources(Plan|Actual)
Overall Plan

19

As of Today : 19

Plan

Actual

Total NCR Issue

FQAM

Total NCR Clos

Lead(Civil/Arch.)

Total NCR Ope

FQCM(Mech.)

Total NCR Issue

QCI (Civil/arch.)

CQCC

Document controller

QC Team(MEP works)

QC Inspectors(FRP) - Call-off Basis

Total DR

Total DR
TOTAL

19

19

Internal Quality Audits

Total DR
(This We

Audit Findings (*)

Date

Discipline

Scheduled(Next)

TBA

GCC-IA

Status in
brief

Completed(Last)

20th IA : 21-12-13

GCC-IA

Issued

69

60

19

Total :

20

Closed

63

60

19

Balance :

Open

Cumulative :

20

Completed : 20

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR

QCI (Civil/Arch

QCI (Mech.)
CPY Q & IM Assessment
C/list No.

Assessment Title

Findings

QCI(Elec.)
Closed

Note : Above pro


Management de

Open

FCS status (F

Total No. of
Assessment

Conducted this Week

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

69

69

69

Total Rejecte

S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
35
1
9
53

PQP
ITP
QCP
QMP
LTSC

1
35
1
9
53

1
35
1
9
53

N/A

Total Open

Total Closed

Status of Deliverables

Description:

Total Issued

Total cancell

Total SD

Total SD

Total SD
Total SDR

Quality Tool Box Talks

Total SD

Total Condcuted : 6, This week : 0

Total SD

Weekly Site Quality Walk


Building Ref.

Score (%)

Score (%)

This Period

Last Period

% Difference

I
Action Required
Yes

95.55/92.38/90%

95.55/93.33/91.54%

1.0

HVAC(BXK-04)/Civil(BXK02)/Elec.(BSIH-103)

93.33/92.5/75.2%

95.55/92.38/90%

1.0

93.7/93.08/90%

93.33/92.5/75.2%

5.0

HVAC(BCCB)/Civil(BXK02&06)/Elec.(BXK-04)

HVAC(BXK-02)/Civil(BXK02)/Elec.(BXK-02)

96/93/94%

93.7/93.08/90%

Elec(BSIH-103) - Re walkthough shall be


done.

Scheduled(Upcoming)

TBA

Completed(Previous)

21-Nov-2013

Item

Date

Total

Completed

Balance

Total Trained

18

Cumulative

Completed (Previous) - Electrical

Completed

Balance

Total Trained

30

21-Nov-2013

JGC Craft Training (*) Date


TBA

Scheduled(Upcoming) - TBA

12/13-08-13

Total

Completed

Balance

Total Trained

40

GCC Craft Training (*) - May' - June'2013


Item

Barzan on shore project - Building works - Package#2

Note : To be

Cumulative
Date

Total

Completed

Balance

Total Trained

18

18

228+203

1) Percentag

2)Reason for

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

Total

Cumulative

Item

Completed(Prev.)-Welding(Hindi)

Total

Bldg.Ref

Total

TBA

Scheduled(Upcoming) -TBA

Bldg.Ref

Total

Cumulative

Discipline(+Refresher) Training (*) [Oct'13 to Dec'13]

CPY Witness

Total

Quality awareness Training [Oct'13 to Dec'13]


Date

JGC Witness

HVAC(BXK-01)/Civil(BXK-02)/Elec.
(BCCB)

3.0

Item

Remarks

No

HVAC(BXK-01)/Civil(BXK02)/Elec.(BCCB)

Issued This W

23-Mar-2013

ntracting Co.WLL

nshore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-106

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
JGC

GCC

LTSC

Total NCR Issued

Items

22

27

Total NCR Closed

15

16

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

51

Total CAR Closed

Total DR Closed

50

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

Total CAR Issued

19

Total CAR Closed

19

QCI (Mech.)

Total CAR Open

QCI(Elec.)

Total CAR Issued


(This Week)

Oct'13

Feb'14

CTR CAR Status


(Corrective Action Request)

Jan'14

Dec'13

Nov'13

Sep'13

SCTR QCI DEMOBILIZATION

QCI (Civil/Arch.)

Note : Above program is tentative only and subject to GCC


Management decision.

FTR status (Field Trouble Request)

FCS status (Field Change Sheet)

Total Issued

1646

Total Issued

20

Total Open

149

Total Open

Total Closed

1319

Total Closed

20

Total Rejected

121

Total Rejected

57

Total cancelled

Total cancelled

SDR status (Specification Deviation Request)


Items
Total SDR Issued

GCC SDR
28

Other S/C SDR

Total SDR Approved

14

Total SDR Rejected

Total SDR Cancelled

Nil

Total SDR Closed

23

Total SDR open

Weekly Field Inspection Status (RFI)

Issued

Accepted

Rejected

Cancelled

Issued This Week

228

215

13

JGC Witnessed

228

215

13

CPY Witnessed

134

127

Items

Bldg.Ref:

Planned

DFO - NO.OF BOOK'S


Actual

% Prog.

Remarks

Total No.of Binders Identified = 1000 No's (Approx.)


Total No.of Binders Submitted = 70 No's
Total No.of Binders Approved by CTR = 31 No's
Total No.of Binders Approved by CPY = 31 No's
Note : To be referred/discussed in weekly DFO meetings.
TOMAS - NO.OF ITR's [UPLOAD]
Bldg.Ref:

Planned

Actual

% Prog.

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 5.71%
2)Reason for rejection : None

Weekly Quality Metrics

Remarks

Gulf Contracting C

Barzan Onshore Project, Packag


Site Weekly QA/QC Metrics
Period :

From:

31-Dec-2013

To:

06-Jan-2014

"Leading" Indicators
Proactive Quality Metrics
Quality Resources(Plan|Actual)
Overall Plan

19

As of Today : 19

Plan

Actual

Total NCR Issue

FQAM

Total NCR Clos

Lead(Civil/Arch.)

Total NCR Ope

FQCM(Mech.)

Total NCR Issue

QCI (Civil/arch.)

CQCC

Document controller

QC Team(MEP works)

QC Inspectors(FRP) - Call-off Basis

Total DR

Total DR
TOTAL

19

19

Internal Quality Audits

Total DR
(This We

Audit Findings (*)

Date

Discipline

Scheduled(Next)

TBA

GCC-IA

Status in
brief

Completed(Last)

20th IA : 21-12-13

GCC-IA

Issued

69

60

19

Total :

20

Closed

68

60

19

Balance :

Open

Cumulative :

20

Completed : 20

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR

QCI (Civil/Arch

QCI (Mech.)
CPY Q & IM Assessment
C/list No.

Assessment Title

Findings

QCI(Elec.)
Closed

Note : Above pro


Management de

Open

FCS status (F

Total No. of
Assessment

Conducted this Week

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

69

69

69

Total Rejecte

S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
35
1
9
53

PQP
ITP
QCP
QMP
LTSC

1
35
1
9
53

1
35
1
9
53

N/A

Total Open

Total Closed

Status of Deliverables

Description:

Total Issued

Total cancell

Total SD

Total SD

Total SD
Total SDR

Quality Tool Box Talks

Total SD

Total Condcuted : 6, This week : 0

Total SD

Weekly Site Quality Walk


Building Ref.
HVAC(BXK-04)/Civil(BXK02)/Elec.(BSIH-103)

Score (%)

Score (%)

This Period

Last Period

93.33/92.5/75.2%

HVAC(BCCB)/Civil(BXK02&06)/Elec.(BXK-04)

% Difference

95.55/92.38/90%

I
Action Required
Yes

Issued This W

Remarks

No

JGC Witness

1.0

HVAC(BXK-01)/Civil(BXK-02)/Elec.
(BCCB)

Elec(BSIH-103) - Re walkthough
done, score is 97%

93.7/93.08/90%

93.33/92.5/75.2%

5.0

HVAC(BXK-02)/Civil(BXK02)/Elec.(BXK-02)

96/93/94%

93.7/93.08/90%

3.0

HVAC(BSIH 103)/Civil(BXK02/06)/Elec.(BSIH-103)

95/93/97%

CPY Witness

Bldg.Ref

Total
96/93/94%

1.0

Quality awareness Training [Oct'13 to Dec'13]


Item

Date

Scheduled(Upcoming)

TBA

Completed(Previous)

21-Nov-2013

Date

Total

Completed

Balance

Total Trained

18

Cumulative

Completed (Previous) - Electrical

Completed

Balance

Total Trained

30

21-Nov-2013

JGC Craft Training (*) Date


TBA

Scheduled(Upcoming) - TBA

12/13-08-13

Total

Completed

Balance

Total Trained

40

GCC Craft Training (*) - May' - June'2013


Item

Cumulative
Date

Total

Completed

Balance

Total Trained

18

18

228+203

Barzan on shore project - Building works - Package#2

1) Percentag

2)Reason for

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

Note : To be

Cumulative

Item

Completed(Prev.)-Welding(Hindi)

Total

Bldg.Ref

Total

TBA

Scheduled(Upcoming) -TBA

Total

Cumulative

Discipline(+Refresher) Training (*) [Oct'13 to Dec'13]


Item

Total

23-Mar-2013

ntracting Co.WLL

nshore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-107

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
JGC

GCC

LTSC

Total NCR Issued

Items

22

27

Total NCR Closed

15

16

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

51

Total CAR Closed

Total DR Closed

50

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

Total CAR Issued

19

Total CAR Closed

19

QCI (Mech.)

Total CAR Open

QCI(Elec.)

Total CAR Issued


(This Week)

Oct'13

Feb'14

CTR CAR Status


(Corrective Action Request)

Jan'14

Dec'13

Nov'13

Sep'13

SCTR QCI DEMOBILIZATION

QCI (Civil/Arch.)

Note : Above program is tentative only and subject to GCC


Management decision.

FTR status (Field Trouble Request)

FCS status (Field Change Sheet)

Total Issued

1646

Total Issued

20

Total Open

149

Total Open

Total Closed

1319

Total Closed

20

Total Rejected

121

Total Rejected

57

Total cancelled

Total cancelled

SDR status (Specification Deviation Request)


Items
Total SDR Issued

GCC SDR
28

Other S/C SDR

Total SDR Approved

14

Total SDR Rejected

Total SDR Cancelled

Nil

Total SDR Closed

23

Total SDR open

Weekly Field Inspection Status (RFI)

Issued

Accepted

Rejected

Cancelled

Issued This Week

220

208

12

JGC Witnessed

220

208

12

CPY Witnessed

123

118

Items

Bldg.Ref:

Planned

DFO - NO.OF BOOK'S


Actual

% Prog.

Remarks

Total No.of Binders Identified = 1000 No's (Approx.)


Total No.of Binders Submitted = 70 No's
Total No.of Binders Approved by CTR = 31 No's
Total No.of Binders Approved by CPY = 31 No's
Note : To be referred/discussed in weekly DFO meetings.
TOMAS - NO.OF ITR's [UPLOAD]
Bldg.Ref:

Planned

Actual

% Prog.

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 5.45%
2)Reason for rejection : None

Weekly Quality Metrics

Remarks

Gulf Contracting C

Barzan Onshore Project, Packag


Site Weekly QA/QC Metrics
Period :

From:

07-Jan-2014

To:

13-Jan-2014

"Leading" Indicators
Proactive Quality Metrics
Quality Resources(Plan|Actual)
Overall Plan

19

As of Today : 19

Plan

Actual

Total NCR Issue

FQAM

Total NCR Clos

Lead(Civil/Arch.)

Total NCR Ope

FQCM(Mech.)

Total NCR Issue

QCI (Civil/arch.)

CQCC

Document controller

QC Team(MEP works)

QC Inspectors(FRP) - Call-off Basis

Total DR

Total DR
TOTAL

19

19

Internal Quality Audits

Total DR
(This We

Audit Findings (*)

Date

Discipline

Scheduled(Next)

TBA

GCC-IA

Status in
brief

Completed(Last)

20th IA : 21-12-13

GCC-IA

Issued

69

60

19

Total :

20

Closed

68

60

19

Balance :

Open

Cumulative :

20

Completed : 20

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR

QCI (Civil/Arch

QCI (Mech.)
CPY Q & IM Assessment
C/list No.

Assessment Title

Findings

QCI(Elec.)
Closed

Note : Above pro


Management de

Open

FCS status (F

Total No. of
Assessment

Conducted this Week

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

69

69

69

Total Rejecte

S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
35
1
9
53

PQP
ITP
QCP
QMP
LTSC

1
35
1
9
53

1
35
1
9
53

N/A

Total Open

Total Closed

Status of Deliverables

Description:

Total Issued

Total cancell

Total SD

Total SD

Total SD
Total SDR

Quality Tool Box Talks

Total SD

Total Condcuted : 6, This week : 0

Total SD

Weekly Site Quality Walk


Building Ref.
HVAC(BCCB)/Civil(BXK02&06)/Elec.(BXK-04)

Score (%)

Score (%)

This Period

Last Period

93.7/93.08/90%

% Difference

93.33/92.5/97

I
Action Required
Yes

HVAC(BXK-02)/Civil(BXK02)/Elec.(BXK-02)

96/93/94%

93.7/93.08/90%

3.0

HVAC(BSIH 103)/Civil(BXK02/06)/Elec.(BSIH-103)

95/93/97%

96/93/94%

1.0

Elec.(BCCB)/Civil(BXK02/06)/HVAC(BXK-06)

Remarks

No

3.0

Issued This W

JGC Witness

HVAC(BXK-04)/Civil(BXK-02)/Elec.
(BSIH-103)

CPY Witness

Bldg.Ref

Total
90.5/92.3/92.79%

95/93/97%

5.0

Quality awareness Training [Oct'13 to Dec'13]


Item

Date

Scheduled(Upcoming)

TBA

Completed(Previous)

21-Nov-2013

Date

Total

Completed

Balance

Total Trained

18

Cumulative

Completed (Previous) - Electrical

Completed

Balance

Total Trained

30

21-Nov-2013

JGC Craft Training (*) Date


TBA

Scheduled(Upcoming) - TBA

12/13-08-13

Total

Completed

Balance

Total Trained

40

GCC Craft Training (*) - May' - June'2013


Item

Cumulative
Date

Total

Completed

Balance

Total Trained

18

18

228+203

Barzan on shore project - Building works - Package#2

1) Percentag

2)Reason for

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

Note : To be

Cumulative

Item

Completed(Prev.)-Welding(Hindi)

Total

Bldg.Ref

Total

TBA

Scheduled(Upcoming) -TBA

Total

Cumulative

Discipline(+Refresher) Training (*) [Oct'13 to Dec'13]


Item

Total

23-Mar-2013

ntracting Co.WLL

nshore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-108

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
JGC

GCC

LTSC

Total NCR Issued

Items

22

27

Total NCR Closed

17

25

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status
CPY DR Status
(Deficiency Report)
Total CAR Issued

Total DR Issued

52

Total CAR Closed

Total DR Closed

50

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

Total CAR Issued

19

Total CAR Closed

19

QCI (Mech.)

Total CAR Open

QCI(Elec.)

Total CAR Issued


(This Week)

Oct'13

Feb'14

CTR CAR Status


(Corrective Action Request)

Jan'14

Dec'13

Nov'13

Sep'13

SCTR QCI DEMOBILIZATION

QCI (Civil/Arch.)

Note : Above program is tentative only and subject to GCC


Management decision.

FTR status (Field Trouble Request)

FCS status (Field Change Sheet)

Total Issued

1680

Total Issued

20

Total Open

136

Total Open

Total Closed

1362

Total Closed

20

Total Rejected

125

Total Rejected

57

Total cancelled

Total cancelled

SDR status (Specification Deviation Request)


Items
Total SDR Issued

GCC SDR
30

Other S/C SDR

Total SDR Approved

21

Total SDR Rejected

Total SDR Cancelled

Nil

Total SDR Closed

30

Total SDR open

Weekly Field Inspection Status (RFI)

Issued

Accepted

Rejected

Cancelled

Issued This Week

228

198

16

JGC Witnessed

228

198

16

CPY Witnessed

138

128

10

Items

Bldg.Ref:

Planned

DFO - NO.OF BOOK'S


Actual

% Prog.

Note : 14
RFI's
cancelled due
to rain.

Remarks

Total No.of Binders Identified = 950 No's (Approx.)


Total No.of Binders Submitted = 84 No's
Total No.of Binders Approved by CTR = 34 No's
Total No.of Binders Approved by CPY = 31 No's
Note : To be referred/discussed in weekly DFO meetings.
TOMAS - NO.OF ITR's [UPLOAD]
Bldg.Ref:

Planned

Actual

% Prog.

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 7.05%
2)Reason for rejection : None

Weekly Quality Metrics

Remarks

Gulf Contracting C

Barzan Onshore Project, Packag


Site Weekly QA/QC Metrics
Period :

From:

14-Jan-2014

To:

20-Jan-2014

"Leading" Indicators
Proactive Quality Metrics
Quality Resources(Plan|Actual)
Overall Plan

19

As of Today : 19

Plan

Actual

Total NCR Issue

FQAM

Total NCR Clos

Lead(Civil/Arch.)

Total NCR Ope

FQCM(Mech.)

Total NCR Issue

QCI (Civil/arch.)

CQCC

Document controller

QC Team(MEP works)

QC Inspectors(FRP) - Call-off Basis

Total DR

Total DR
TOTAL

19

19

Internal Quality Audits

Total DR
(This We

Audit Findings (*)

Date

Discipline

Scheduled(Next)

TBA

GCC-IA

Status in
brief

Completed(Last)

20th IA : 21-12-13

GCC-IA

Issued

69

60

19

Total :

20

Closed

68

60

19

Balance :

Open

Cumulative :

20

Completed : 20

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR

QCI (Civil/Arch

QCI (Mech.)
CPY Q & IM Assessment
Assessment Title

Findings

SITE DOCUMENT & DRAWING CONTROL(ELECTRICAL)

Note : SCORE : 100%

C/list No.
1

QCI(Elec.)
Closed

Note : Above pro


Management de

Open

FCS status (F

Total No. of
Assessment

Conducted this Week

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

70

70

70

Total Rejecte

S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
35
1
9
53

PQP
ITP
QCP
QMP
LTSC

1
35
1
9
53

1
35
1
9
53

N/A

Total Open

Total Closed

Status of Deliverables

Description:

Total Issued

Total cancell

Total SD

Total SD

Total SD
Total SDR

Quality Tool Box Talks

Total SD

Total Condcuted : 6, This week : 0

Total SD

Weekly Site Quality Walk


Building Ref.

Score (%)

Score (%)

This Period

Last Period

HVAC(BXK-02)/Civil(BXK02)/Elec.(BXK-02)

96/93/94%

HVAC(BSIH 103)/Civil(BXK02/06)/Elec.(BSIH-103)

95/93/97%

90.5/92.3/92.79%

% Difference

93.7/93.08/90%

I
Action Required
Yes

Remarks

No

3.0

96/93/94%

3.0

95/93/97%

1.0

Issued This W

JGC Witness

HVAC(BCCB)/Civil(BXK-02&06)/Elec.
(BXK-04)

CPY Witness

Bldg.Ref

Elec.(BCCB)/Civil(BXK02/06)/HVAC(BXK-06)

Total

Elec.(BXK-02)/HVAC(BXK02/06)/CIVIL(BXK-02)

CANCELLED

90.5/92.3/92.79%

Quality awareness Training [Oct'13 to Dec'13]


Item

Date

Scheduled(Upcoming)

TBA

Completed(Previous)

21-Nov-2013

Date

Total

Completed

Balance

Total Trained

18

Cumulative

Completed (Previous) - Electrical

Completed

Balance

Total Trained

30

21-Nov-2013

JGC Craft Training (*) Date


TBA

Scheduled(Upcoming) - TBA

12/13-08-13

Total

Completed

Balance

Total Trained

40

GCC Craft Training (*) - May' - June'2013


Item

Cumulative
Date

Total

Completed

Balance

Total Trained

18

18

228+203

Barzan on shore project - Building works - Package#2

1) Percentag

2)Reason for

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

Note : To be

Cumulative

Item

Completed(Prev.)-Welding(Hindi)

Total

Bldg.Ref

Total

TBA

Scheduled(Upcoming) -TBA

Total

Cumulative

Discipline(+Refresher) Training (*) [Oct'13 to Dec'13]


Item

Total

CPY ISSUED DR-702

23-Mar-2013

3) RFI Cance

ntracting Co.WLL

nshore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-109

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
JGC

GCC

LTSC

Total NCR Issued

Items

22

27

Total NCR Closed

17

25

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status

CPY DR Status
(Deficiency Report)

Total CAR Issued

Total DR Issued

53

Total CAR Closed

Total DR Closed

51

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

Total CAR Issued

19

Total CAR Closed

19

QCI (Mech.)

Total CAR Open

QCI(Elec.)

Total CAR Issued


(This Week)

Oct'13

Feb'14

CTR CAR Status


(Corrective Action Request)

Jan'14

Dec'13

Nov'13

Sep'13

SCTR QCI DEMOBILIZATION

QCI (Civil/Arch.)

Note : Above program is tentative only and subject to GCC


Management decision.

FTR status (Field Trouble Request)

FCS status (Field Change Sheet)

Total Issued

1697

Total Issued

22

Total Open

141

Total Open

Total Closed

1374

Total Closed

20

Total Rejected

125

Total Rejected

57

Total cancelled

Total cancelled

SDR status (Specification Deviation Request)


Items
Total SDR Issued

GCC SDR
30

Other S/C SDR

Total SDR Approved

21

Total SDR Rejected

Total SDR Cancelled

Nil

Total SDR Closed

30

Total SDR open

Weekly Field Inspection Status (RFI)

Issued

Accepted

Rejected

Cancelled

Issued This Week

293

272

20

JGC Witnessed

293

272

20

CPY Witnessed

191

128

15

Items

Bldg.Ref:

Planned

DFO - NO.OF BOOK'S


Actual

% Prog.

Note : 16
RFI's
cancelled due
to rain.

Remarks

Total No.of Binders Identified = 950 No's (Approx.)


Total No.of Binders Submitted = 84 No's
Total No.of Binders Approved by CTR = 34 No's
Total No.of Binders Approved by CPY = 31 No's
Note : To be referred/discussed in weekly DFO meetings.
TOMAS - NO.OF ITR's [UPLOAD]
Bldg.Ref:

Planned

Actual

% Prog.

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 7.16%
2)Reason for rejection : BXK-02, FM 200 PRESSURE TEST, due to no access.
3) RFI Cancellation due to the rain not counted in metrics.

Weekly Quality Metrics

Remarks

Gulf Contracting C

Barzan Onshore Project, Packag


Site Weekly QA/QC Metrics
Period :

From:

21-Jan-2014

To:

27-Jan-2014

"Leading" Indicators
Proactive Quality Metrics
Quality Resources(Plan|Actual)
Overall Plan

22

As of Today : 22

Plan

Actual

Total NCR Issue

FQAM

Total NCR Clos

Lead(Civil/Arch.)

Total NCR Ope

FQCM(Mech.)

Total NCR Issue

QCI (Civil/arch.)

CQCC

Document controller

QC Team(MEP works)

QC Inspectors(FRP) - Call-off Basis

Total DR

Total DR
TOTAL

22

22

Internal Quality Audits

Total DR
(This We

Audit Findings (*)

Date

Discipline

Scheduled(Next)

21st IA : 15-02-14[DFO]

GCC-IA

Status in
brief

Completed(Last)

20th IA : 21-12-13

GCC-IA

Issued

69

60

19

Total :

22

Closed

69

60

19

Balance :

Open

Cumulative :

22

Completed : 20

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR

QCI (Civil/Arch

QCI (Mech.)
CPY Q & IM Assessment
C/list No.

Assessment Title

Findings

QCI(Elec.)
Closed

Note : Above pro


Management de
above schedule.

Open

FCS status (F

Total No. of
Assessment

Conducted this Week

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

70

70

70

Total Rejecte

S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
35
1
9
53

PQP
ITP
QCP
QMP
LTSC

1
35
1
9
53

1
35
1
9
53

N/A

Total Open

Total Closed

Status of Deliverables

Description:

Total Issued

Total cancell

Total SD

Total SD

Total SD
Total SDR

Quality Tool Box Talks

Total SD

Total Condcuted : 6, This week : 0

Total SD

Weekly Site Quality Walk


Score (%)

This Period

Last Period

95/93/97%

96/93/94%

3.0

90.5/92.3/92.79%

95/93/97%

3.0

CANCELLED

90.5/92.3/92.79%

Building Ref.
HVAC(BSIH 103)/Civil(BXK02/06)/Elec.(BSIH-103)

Elec.(BCCB)/Civil(BXK02/06)/HVAC(BXK-06)

Score (%)

% Difference

Action Required
Yes

Remarks

No

JGC Witness

HVAC(BXK-02)/Civil(BXK-02)/Elec.
(BXK-02)

CPY Witness

Bldg.Ref

Elec.(BXK-02)/HVAC(BXK02/06)/CIVIL(BXK-02)

CPY ISSUED DR-702,REWALKTHROUGH CONDUCTED.

a
Elec.(BXK-04)/HVAC(BXK06)/CIVIL(BXK-02)

Issued This W

87.8/92.3/95.45%

CANCELLED

Quality awareness Training [Oct'13 to Dec'13]


Item

Date

Scheduled(Upcoming)-DFO

06-Mar-2014

Completed(Previous)

21-Nov-2013

Item

Date

Scheduled(Upcoming) -BXK-02 Access Issues

02-Feb-2014

Completed (Previous) - Hydrotest

26-Jan-2014

Total

Completed

Balance

Total Trained

Cumulative

Date
TBA

Scheduled(Upcoming) - TBA

Completed

Balance

Total Trained

12/13-08-13

Total

Completed

Balance

Total Trained

40

GCC Craft Training (*) - May' - June'2013


Item

Cumulative
Date

Total

Completed

Balance

Total Trained

Scheduled(Upcoming)-TBA

18
Completed(Previous)-G.I.Conduit

Barzan on shore project - Building works - Package#2

Note : To be

Cumulative

Item

Completed(Prev.)-Welding(Hindi)

Total

Bldg.Ref

Total

JGC Craft Training (*) -

Total
Total

Cumulative

Discipline(+Refresher) Training (*) [Jan'14 to Mar'14]

Total

23-Mar-2013

18

228+203

1) Percentag

2)Reason for
incompletion

ntracting Co.WLL

nshore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-110

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
JGC

GCC

LTSC

Total NCR Issued

Items

22

27

Total NCR Closed

17

25

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status

CPY DR Status
(Deficiency Report)

Total CAR Issued

Total DR Issued

53

Total CAR Closed

Total DR Closed

51

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

Jun'14

May'14

Apr'14

Mar'14

Feb'14

Jan'14

SCTR QCI DEMOBILIZATION

QCI (Civil/Arch.)

Total CAR Issued

19

Total CAR Closed

19

QCI (Mech.)

Total CAR Open

QCI(Elec.)

Total CAR Issued


(This Week)

Note : Above program is tentative only and subject to GCC


Management decision. Call-off basis QCI's are not considered in
above schedule.

FTR status (Field Trouble Request)

FCS status (Field Change Sheet)

Total Issued

1736

Total Issued

22

Total Open

157

Total Open

Total Closed

1397

Total Closed

21

Total Rejected

125

Total Rejected

57

Total cancelled

Total cancelled

SDR status (Specification Deviation Request)


Items
Total SDR Issued

GCC SDR
30

Other S/C SDR

Total SDR Approved

21

Total SDR Rejected

Total SDR Cancelled

Nil

Total SDR Closed

30

Total SDR open

Weekly Field Inspection Status (RFI)

Issued

Accepted

Rejected

Cancelled

Issued This Week

273

250

21

JGC Witnessed

273

250

21

CPY Witnessed

185

174

11

Items

Remarks

DFO - NO.OF BOOK'S


Bldg.Ref:

Planned

Actual

% Prog.

Remarks

Total No.of Binders Identified = 880 No's (Approx.)


Total No.of Binders Submitted = 99 No's
Total No.of Binders Approved by CTR = 34 No's
Total No.of Binders Approved by CPY = 31 No's
Note : To be referred/discussed in weekly DFO meetings.
TOMAS - NO.OF ITR's [UPLOAD]
Bldg.Ref:

Planned

Actual

% Prog.

Remarks

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 7.69%
2)Reason for rejection : BSS-108,2 RFI's - Installation of Earthpit, due to the Backfill activities
incompletion.

Weekly Quality Metrics

Gulf Contracting C

Barzan Onshore Project, Packag


Site Weekly QA/QC Metrics
Period :

From:

28-Jan-2014

To:

03-Feb-2014

"Leading" Indicators
Proactive Quality Metrics
Quality Resources(Plan|Actual)
Overall Plan

22

As of Today : 22

Plan

Actual

Total NCR Issue

FQAM

Total NCR Clos

Lead(Civil/Arch.)

Total NCR Ope

FQCM(Mech.)

Total NCR Issue

QCI (Civil/arch.)

CQCC

Document controller

QC Team(MEP works)

QC Inspectors(FRP/MEP) - Call-off Basis

Total DR

Total DR
TOTAL

22

22

Internal Quality Audits

Total DR
(This We

Audit Findings (*)

Date

Discipline

Scheduled(Next)

21st IA : 15-02-14[DFO]

GCC-IA

Status in
brief

Completed(Last)

20th IA : 21-12-13

GCC-IA

Issued

69

60

19

Total :

22

Closed

69

60

19

Balance :

Open

Cumulative :

22

Completed : 20

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR

QCI (Civil/Arch

QCI (Mech.)
CPY Q & IM Assessment
C/list No.

Assessment Title

Findings

QCI(Elec.)
Closed

Note : Above pro


Management de
above schedule.

Open

FCS status (F

Total No. of
Assessment

Conducted this Week

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

70

70

70

Total Rejecte

S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
35
1
9
53

PQP
ITP
QCP
QMP
LTSC

1
35
1
9
53

1
35
1
9
53

N/A

Total Open

Total Closed

Status of Deliverables

Description:

Total Issued

Total cancell

Total SD

Total SD

Total SD
Total SDR

Quality Tool Box Talks

Total SD

Total Condcuted : 6, This week : 0

Total SD

Weekly Site Quality Walk


Score (%)

Score (%)

This Period

Last Period

90.5/92.3/92.79%

95/93/97%

3.0

CANCELLED

90.5/92.3/92.79%

Building Ref.
Elec.(BCCB)/Civil(BXK02/06)/HVAC(BXK-06)

Elec.(BXK-02)/HVAC(BXK02/06)/CIVIL(BXK-02)

% Difference

I
Action Required
Yes

Remarks

No

87.8/92.3/95.45%

CANCELLED

JGC Witness

HVAC(BSIH 103)/Civil(BXK02/06)/Elec.(BSIH-103)

CPY Witness

CPY ISSUED DR-702,REWALKTHROUGH CONDUCTED.

a
Elec.(BXK-04)/HVAC(BXK06)/CIVIL(BXK-02)

Issued This W

Bldg.Ref

Total

Elect.(BSS-106)/HVAC(BXK06)/CIVIL(C300)

92.5/92.3/95%

87.8/92.3/95.45%

2.0

Quality awareness Training [Oct'13 to Dec'13]


Item

Date

Scheduled(Upcoming)-DFO

06-Mar-2014

Completed(Previous)

21-Nov-2013

Date

Total

Completed

Balance

Total Trained

Cumulative

Completed (Previous) - BXK-02 Access Issues

Completed

Balance

Total Trained

12

03-Feb-2014

JGC Craft Training (*) Date


TBA

Scheduled(Upcoming) - TBA

12/13-08-13

Total

Completed

Balance

Total Trained

40

GCC Craft Training (*) - May' - June'2013


Item

Cumulative
Date

Total

Completed

Balance

Total Trained

18

18

228+203

Barzan on shore project - Building works - Package#2

1) Percentag

2)Reason for

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

Note : To be

Cumulative

Item

Completed(Prev.)-Welding(Hindi)

Total

Bldg.Ref

Total

TBA

Scheduled(Upcoming) - TBA

Total

Cumulative

Discipline(+Refresher) Training (*) [Jan'14 to Mar'14]


Item

Total

23-Mar-2013

ntracting Co.WLL

nshore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-111

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
JGC

GCC

LTSC

Total NCR Issued

Items

22

27

Total NCR Closed

17

25

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status

CPY DR Status
(Deficiency Report)

Total CAR Issued

Total DR Issued

53

Total CAR Closed

Total DR Closed

51

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

Jun'14

May'14

Apr'14

Mar'14

Feb'14

Jan'14

SCTR QCI DEMOBILIZATION

QCI (Civil/Arch.)

Total CAR Issued

19

Total CAR Closed

19

QCI (Mech.)

Total CAR Open

QCI(Elec.)

Total CAR Issued


(This Week)

Note : Above program is tentative only and subject to GCC


Management decision. Call-off basis QCI's are not considered in
above schedule.

FTR status (Field Trouble Request)

FCS status (Field Change Sheet)

Total Issued

1755

Total Issued

23

Total Open

168

Total Open

Total Closed

1405

Total Closed

21

Total Rejected

125

Total Rejected

57

Total cancelled

Total cancelled

SDR status (Specification Deviation Request)


Items
Total SDR Issued

GCC SDR
30

Other S/C SDR

Total SDR Approved

21

Total SDR Rejected

Total SDR Cancelled

Nil

Total SDR Closed

30

Total SDR open

Weekly Field Inspection Status (RFI)

Issued

Accepted

Rejected

Cancelled

Issued This Week

215

200

15

JGC Witnessed

215

200

15

CPY Witnessed

137

133

Items

Remarks

DFO - NO.OF BOOK'S


Bldg.Ref:

Planned

Actual

% Prog.

Remarks

Total No.of Binders Identified = 880 No's (Approx.)


Total No.of Binders Submitted = 120 No's
Total No.of Binders Approved by CTR = 31 No's
Total No.of Binders Approved by CPY = 31 No's
Note : To be referred/discussed in weekly DFO meetings.
TOMAS - NO.OF ITR's [UPLOAD]
Bldg.Ref:

Planned

Actual

% Prog.

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 6.97%
2)Reason for rejection : None

Weekly Quality Metrics

Remarks

Gulf Contracting C

Barzan Onshore Project, Packag


Site Weekly QA/QC Metrics
Period :

From:

04-Feb-2014

To:

10-Feb-2014

"Leading" Indicators
Proactive Quality Metrics
Quality Resources(Plan|Actual)
Overall Plan

22

As of Today : 22

Plan

Actual

Total NCR Issue

FQAM

Total NCR Clos

Lead(Civil/Arch.)

Total NCR Ope

FQCM(Mech.)

Total NCR Issue

QCI (Civil/arch.)

CQCC

Document controller

QC Team(MEP works)

QC Inspectors(FRP/MEP) - Call-off Basis

Total DR

Total DR
TOTAL

22

22

Internal Quality Audits

Total DR
(This We

Audit Findings (*)

Date

Discipline

Scheduled(Next)

21st IA : 15-02-14[DFO]

GCC-IA

Status in
brief

Completed(Last)

20th IA : 21-12-13

GCC-IA

Issued

69

60

19

Total :

23

Closed

69

60

19

Balance :

Open

Cumulative :

23

Completed : 20

JGC
CAR

OBS

CAR

GCC/LTSC

OBS

Item

Total DR

QCI (Civil/Arch

QCI (Mech.)
CPY Q & IM Assessment
C/list No.

Assessment Title

Findings

QCI(Elec.)
Closed

Note : Above pro


Management de
above schedule.

Open

FCS status (F

Total No. of
Assessment

Conducted this Week

Cumulative to Date

Deficient (Red)

Concern (Amber)

Satisfactory (Green)

70

70

70

Total Rejecte

S.No.

No. of
Deliverables

Documents

Submitted

Approved/w
comments

1
2
3
4
5

1
35
1
9
53

PQP
ITP
QCP
QMP
LTSC

1
35
1
9
53

1
35
1
9
53

N/A

Total Open

Total Closed

Status of Deliverables

Description:

Total Issued

Total cancell

Total SD

Total SD

Total SD
Total SDR

Quality Tool Box Talks

Total SD

Total Condcuted : 6, This week : 0

Total SD

Weekly Site Quality Walk


Score (%)

Score (%)

This Period

Last Period

Elec.(BXK-02)/HVAC(BXK02/06)/CIVIL(BXK-02)

CANCELLED

90.5/92.3/92.79%

Elec.(BXK-04)/HVAC(BXK06)/CIVIL(BXK-02)

87.8/92.3/95.45%

CANCELLED

Building Ref.

Elect.(BSS-106)/HVAC(BXK06)/CIVIL(C300)

% Difference

92.5/92.3/95%

87.8/92.3/95.45%

2.0

95/93/96%

92.5/92.3/95%

1.0

I
Action Required
Yes

Issued This W

Remarks

No

JGC Witness

Elec.(BCCB)/Civil(BXK02/06)/HVAC(BXK-06)

CPY ISSUED DR-702,REWALKTHROUGH


CONDUCTED.SURVEY REPORT
SUBMITTED.

CPY Witness

Bldg.Ref

Tota

Tota

Elect.(BCCB)/HVAC(BXK02)/CIVIL(BXK-02)

Quality awareness Training [Oct'13 to Dec'13]


Item

Date

Scheduled(Upcoming)-DFO

06-Mar-2014

Completed(Previous)

21-Nov-2013

Cumulative

Date

Completed

Balance

Total Trained

Cumulative

Completed (Previous) - BXK-02 Access Issues

Completed

Balance

Total Trained

12

03-Feb-2014

JGC Craft Training (*) -

Cumulative

Item

Date
TBA

Scheduled(Upcoming) - TBA
Completed(Prev.)-Welding(Hindi)

12/13-08-13

Total

Completed

Balance

Total Trained

40

GCC Craft Training (*) - May' - June'2013


Item

Cumulative
Date

Total

Completed

Balance

Total Trained

18

18

228+203

Barzan on shore project - Building works - Package#2

1) Percentag

2)Reason for

Scheduled(Upcoming)-TBA
Completed(Previous)-G.I.Conduit

Note : To be

Bldg.Ref

Total

TBA

Scheduled(Upcoming) - TBA

Tota

Total

Discipline(+Refresher) Training (*) [Jan'14 to Mar'14]


Item

Tota

23-Mar-2013

ntracting Co.WLL

nshore Project, Package#2

Weekly QA/QC Metrics


Rep. No.:

WQM-GCC-112

"Lagging" Indicators
Reactive Quality Metrics
NCR Status (Non-Conformance Report)
JGC

GCC

LTSC

Total NCR Issued

Items

22

27

Total NCR Closed

19

26

Total NCR Open

Total NCR Issued (This Week)

NCR Status (Non-Conformance Report)


CPY CAR Status

CPY DR Status
(Deficiency Report)

Total CAR Issued

Total DR Issued

53

Total CAR Closed

Total DR Closed

52

Total CAR Open

Total DR Open

Total DR Issued
(This Week)

Total CAR Issued (This


Week)

CTR CAR Status


(Corrective Action Request)

Jun'14

May'14

Apr'14

Mar'14

Feb'14

Jan'14

SCTR QCI DEMOBILIZATION

QCI (Civil/Arch.)

Total CAR Issued

19

Total CAR Closed

19

QCI (Mech.)

Total CAR Open

QCI(Elec.)

Total CAR Issued


(This Week)

Note : Above program is tentative only and subject to GCC


Management decision. Call-off basis QCI's are not considered in
above schedule.

FTR status (Field Trouble Request)

FCS status (Field Change Sheet)

Total Issued

1769

Total Issued

23

Total Open

148

Total Open

Total Closed

1437

Total Closed

21

Total Rejected

127

Total Rejected

57

Total cancelled

Total cancelled

SDR status (Specification Deviation Request)


Items
Total SDR Issued

GCC SDR
30

Other S/C SDR

Total SDR Approved

21

Total SDR Rejected

Total SDR Cancelled

Nil

Total SDR Closed

30

Total SDR open

Weekly Field Inspection Status (RFI)

Issued

Accepted

Rejected

Cancelled

Issued This Week

228

210

18

JGC Witnessed

228

210

18

CPY Witnessed

97

89

Items

Remarks

DFO - NO.OF BOOK'S


Bldg.Ref:

Planned

Actual

% Prog.

Remarks

Total No.of Binders Identified = 880 No's (Approx.)


Total No.of Binders Submitted = 122 No's
Total No.of Binders Approved by CTR = 34 No's
Total No.of Binders Approved by CPY = 34 No's
Note : To be referred/discussed in weekly DFO meetings for more details.
TOMAS - NO.OF ITR's [UPLOAD]
Bldg.Ref:

Planned

Actual

% Prog.

Note : To be referred/discussed in weekly DFO meetings.

QA/QC Highlights
1) Percentage of cancellation : 7.89%
2)Reason for rejection : Pressurization Fan Misalignment ( 1 No.)

Weekly Quality Metrics

Remarks

You might also like